CN207933956U - Portable construction dedusting heat sink - Google Patents

Portable construction dedusting heat sink Download PDF

Info

Publication number
CN207933956U
CN207933956U CN201720851368.8U CN201720851368U CN207933956U CN 207933956 U CN207933956 U CN 207933956U CN 201720851368 U CN201720851368 U CN 201720851368U CN 207933956 U CN207933956 U CN 207933956U
Authority
CN
China
Prior art keywords
dust
cylinder
collecting
collecting cylinder
wind
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720851368.8U
Other languages
Chinese (zh)
Inventor
何霁耀
张来安
于文生
杨汝贤
黎粤桥
徐成贤
杨树平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Construction Investment & Construction Co Ltd
Original Assignee
Gansu Construction Investment & Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Construction Investment & Construction Co Ltd filed Critical Gansu Construction Investment & Construction Co Ltd
Priority to CN201720851368.8U priority Critical patent/CN207933956U/en
Application granted granted Critical
Publication of CN207933956U publication Critical patent/CN207933956U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Separation Of Particles Using Liquids (AREA)

Abstract

The utility model is related to construction ancillary equipment fields, propose portable construction dedusting heat sink, including fixed bottom plate, dust removal component, cooling element, it is characterised in that:The fixed bottom plate is equipped with dust removal component and cooling element, the dust removal component is from top to bottom successively by dust-collecting cylinder, defeated dirt channel and telescopic supporting rod composition, several wind-collecting covers in its dust-collecting cylinder, and one end of wind-collecting cover protrudes dust-collecting cylinder, the other end is located in dust-collecting cylinder and port is equipped with exhaust fan, its defeated dirt beneath galleries side connects deduster, and the deduster other end is equipped with exhaust duct, the cooling element is from outside to inside by thermal insulation layer, outer wall cylinder and water-supply-pipe composition, its water-supply-pipe one end is pierced by outer wall cylinder side wall connection water inlet pipe, the other end is divided into several delivery pipe branches, its delivery pipe branch protrudes outer wall cylinder, delivery pipe branch outstanding is equipped with several atomizers.The utility model has the beneficial effects that:Comprehensive dedusting cooling and efficient can be achieved, it is simple in structure and easy to use.

Description

Portable construction dedusting heat sink
Technical field
The utility model is related to construction ancillary equipment fields, and in particular to portable construction is cooled down with dedusting to be filled It sets.
Background technology
With the continuous development of urban construction, to establish good living environment, builds construction in kind and never stopped, And scale is increasing.Currently, when architectural engineering main structure construction, it is open work scene, is exposed under burning sun, it is scorching Hot summer, temperature is very high, even more than 40 DEG C, this temperature is that people is difficult to restrain oneself.And construction operation usually will produce greatly The dust of amount, since dust is small, light weight, it is easy to which large area raises, and is very easy to by construction personnel's suction body.On Stating phenomenon causes the working environment of construction personnel to dislike very much summary, is unfavorable for worker's work.So need to construction environment into Row dedusting and cooling processing, improve working environment.On how to avoid dust from injuring, way typically now is to allow construction worker Mask is worn, but mask needs to frequently replace, dust can also be assembled on mask quickly, it is difficult to play protection effect.About drop Temperature just takes the mode of watering, but time-consuming and laborious ineffective.In order to preferably improve this situation, there have been some to build Build working dedusting heat sink.
In existing public technology, as in patent CN 205496243U by for sap cavity using outlet tube to construction ring Border cools down;The dust pollution of construction site is reduced using deduster and sweep-up pipe.But still remain following some lack Point:(1) setting of outlet tube and sweep-up pipe makes water spray and dust suction range be confined to a direction, and range is too small to cause dedusting to be dropped Temp effect is poor;(2) device is complicated, and troublesome in poeration, victory inconvenient for use.
Utility model content
The purpose of this utility model is to be directed to problems of the prior art described above, proposes a kind of achievable full side The dedusting of position cools down and efficient, portable construction dedusting heat sink simple in structure and easy to use.
To achieve the above object, the technical solution that the utility model is taken is as follows:
Portable construction dedusting heat sink, including fixed bottom plate, dust removal component, cooling element, feature exist In:The fixed bottom plate left and right ends are respectively equipped with dust removal component and cooling element, and edge is equipped with fixed hole, described to remove Dirt component is made of dust-collecting cylinder, defeated dirt channel and telescopic supporting rod successively from top to bottom, and dust-collecting cylinder annular arranges several ladders The wind-collecting cover of physique structure, and one end of wind-collecting cover protrudes dust-collecting cylinder, the other end is located in dust-collecting cylinder and port is equipped with exhaust fan, Its defeated dirt channel interior is equipped with pipeline fan, and lower side connects deduster by dust outlet tube, and the deduster other end is equipped with row Air hose, the cooling element are made of thermal insulation layer, outer wall cylinder and water-supply-pipe from outside to inside, and water-supply-pipe one end is pierced by outer wall cylinder side Wall connects water inlet pipe, and the other end is divided into several delivery pipe branches, and water inlet pipe is equipped with blower pump for pipeline and control valve, delivery pipe branch It is close to the arrangement of outer wall cylinder and prominent outer wall cylinder, delivery pipe branch outstanding is in truncated cone-shaped structural arrangement and is equipped with several atomizers.
The other end of the water inlet pipe is equipped with buffer tank, and buffer tank is located at the centre of fixed bottom plate, and spare Water purifier is equipped in water tank, top is equipped with filler.
The wind-collecting cover of three to five prismatoid structures is equipped in the dust-collecting cylinder, and one end of wind-collecting cover protrusion dust-collecting cylinder is set There is strainer.
The dust-collecting cylinder and deduster are equipped with protective cover.
Compared with prior art, the utility model has the beneficial effects that:
(1) using the dust removal component being made of dust-collecting cylinder, defeated dirt channel and retractable support, several collection wind in dust-collecting cylinder Under the action of cover, pipeline fan and telescopic supporting rod in defeated dirt channel can efficient quick the comprehensive dedusting of realization;Using The cooling element being made of thermal insulation layer, outer wall cylinder and water-supply-pipe, the protrusion outer wall cylinder of truncated cone-shaped structure delivery pipe branch it is auxiliary Help effect is lower to realize comprehensive cooling.Moreover, the thermal insulation layer of outer wall drum outer wall cladding can effectively avoid heat exchange, so tie Structure designs so that the efficiency of dedusting cooling is very high.In addition, dust removal component and cooling element are to be independently arranged and simple in structure, because It can work independently so that changeable use and easy to operate.
(2) buffer tank in fixed bottom plate center is also that device plays a balance work while realization stores for future use water With, for avoiding device lodging auxiliary is provided.And the setting of its internal water purifier can also be realized after wastewater purification dropping Temperature, preferably to utilize resource.
(3) wind-collecting cover on dust-collecting cylinder one end setting strainer can avoid larger impurity enter wind-collecting cover with play protection The effect of dust-collecting cylinder.And protective cover is respectively provided with also for protective device to dust-collecting cylinder and deduster, it avoids in dust-collecting cylinder Exhaust fan and deduster make moist and influence to work normally.
Description of the drawings
Fig. 1 is the main structure diagram of the utility model.
Fig. 2 is the overlooking structure diagram of the utility model.
In figure:Fixed bottom plate 1, dust removal component 2, cooling element 3, dust-collecting cylinder 4, defeated dirt channel 5, telescopic supporting rod 6, collection wind Cover 7, exhaust fan 8, dust outlet tube 9, deduster 10, exhaust duct 11, outer wall cylinder 12, water-supply-pipe 13, water inlet pipe 14, delivery pipe branch 15, Blower pump for pipeline 16, control valve 17, atomizer 18, buffer tank 19, water purifier 20, thermal insulation layer 21, pipeline fan 22.
Specific implementation mode
To enable those skilled in the art to be better understood from the utility model, below in conjunction with drawings and examples Further description is carried out to the technical solution of the utility model.
As illustrated in fig. 1 and 2, in the embodiments of the present invention, portable construction dedusting heat sink, including Fixed bottom plate 1, dust removal component 2, cooling element 3,1 left and right ends of fixed bottom plate are respectively equipped with dust removal component 2 and cooling portion Part 3, edge are equipped with fixed hole, and the dust removal component 2 is from top to bottom successively by dust-collecting cylinder 4, defeated dirt channel 5 and flexible branch Strut 6 forms, and 4 annular of dust-collecting cylinder arranges the wind-collecting cover 7 of several prismatoid structures, and one end of wind-collecting cover 7 protrudes dust Cylinder 4, the other end is located in dust-collecting cylinder 4 and port is equipped with exhaust fan 8, and defeated dirt channel 5 is internally provided with pipeline fan 22, lower part Side by dust outlet tube 9 connect deduster 10, and 10 other end of deduster be equipped with exhaust duct 11, the cooling element 3 from outside to In be made of thermal insulation layer 21, outer wall cylinder 12 and water-supply-pipe 13,13 one end of water-supply-pipe be pierced by 12 side wall of outer wall cylinder connection water inlet pipe 14, the other end is divided into several delivery pipe branches 15, and water inlet pipe 14 is equipped with blower pump for pipeline 16 and control valve 17, delivery pipe branch 15 are close to the arrangement of outer wall cylinder 12 and prominent outer wall cylinder 12, if delivery pipe branch outstanding 15 is in truncated cone-shaped structural arrangement and is equipped with dry fog Change nozzle 18.
The other end of the water inlet pipe 14 is equipped with buffer tank 19, and buffer tank 19 is located at the center of fixed bottom plate 1 Place, and water purifier 20 is equipped in buffer tank 19, top is equipped with filler.
The wind-collecting cover 7 of three to five prismatoid structures is equipped in the dust-collecting cylinder 4, and wind-collecting cover 7 protrudes the one of dust-collecting cylinder 4 End is equipped with strainer.
The dust-collecting cylinder 4 and deduster 10 are equipped with protective cover.
The specific implementation process of the utility model is as follows:
About dedusting.Under the action of exhaust fan 8 in the wind-collecting cover 7 of dust-collecting cylinder 4, the airborne dust of construction site with wind into Enter dust-collecting cylinder 4, because the top of dust-collecting cylinder 4 is closed, airborne dust is arranged with wind by exhaust fan 8 and from the air outlet of exhaust fan 8 Go out, subsequently enter the defeated dirt channel 5 of 4 bottom of dust-collecting cylinder connection, under the auxiliary of the pipeline fan 22 in defeated dirt channel 5 quickly into Enter dust outlet tube 9, then is discharged using exhaust duct 11 after the separating treatment of deduster 10.In this process due in dust-collecting cylinder 4 Three to five prismatoid structures wind-collecting cover 7 along 4 barrel annular of dust-collecting cylinder be arranged, along with stretching for 2 bottom of dust removal component The scalability of contracting supporting rod 6, also the auxiliary conveying of pipeline fan 22 so that can efficient quick the comprehensive airborne dust of realization Collection is handled.
About cooling.Water is discharged into buffer tank 19 by filler, enters back into water inlet pipe 14, in blower pump for pipeline 16 The water of effect lower band pressure enters water-supply-pipe 13, then be diverted to each delivery pipe branch 15, if finally by delivery pipe branch 15 Dry nebulization nozzle 18 is sprayed onto in the air, realizes cooling.In this process since the delivery pipe branch 15 for protruding from outer wall cylinder 12 is in Truncated cone-shaped structure effectively realize comprehensive spray cooling.And construction site temperature is high, and outer wall cylinder 12 is sudden and violent for a long time Dew can make the temperature of its barrel higher, be increased so as to cause the temperature of water in delivery pipe branch 15.So in 12 outer wall of outer wall cylinder Thermal insulation layer 21 is coated to avoid the generation of heat exchange, and then improves cooling-down effect.Specifically select GD vertical about blower pump for pipeline 16 Formula single-stage pipe type centrifugal pump.
To sum up, the setting of dust removal component 2 and cooling element 3 so that can efficiently realize comprehensive dedusting and cooling and And efficiency is very high.In addition, dust removal component 3 and cooling element 3 are to be independently arranged and simple in structure, because that can work independently, make can Switching use and it is easy to operate.
Also need to having for explanation:First, strainer is arranged in one end of the wind-collecting cover 7 on dust-collecting cylinder 4, since construction site is deposited Impurity it is more, when dust removal component 2 works, so that it may larger, lighter impurity be avoided to enter wind-collecting cover 7 and influence exhaust fan 8 work is exactly to play the role of protecting dust-collecting cylinder 4.Second is that it is respectively provided with protective cover to dust-collecting cylinder 4 and deduster 10, When cooling element 3 works, exhaust fan 8 and deduster 10 in dust-collecting cylinder 4 can be avoided to make moist and influence to work normally, that is, be also Play the role of protective device.Third, the buffer tank 19 in 1 center of fixed bottom plate is also dress while realization stores for future use water It sets and plays a balanced action, booster action is provided for avoiding device lodging.And in order to realize the efficient utilization of water resource, Water purifier 20 is arranged in the inside of buffer tank 19, can also realize after wastewater purification cooling down.Such as it is not in cooling Waste water, i.e. water purifier 20 do not have to work.
It is that portable construction provided by the utility model is described in detail with dedusting heat sink above, tool Body embodiment is served only for helping to understand the technical solution of the utility model and core concept.It should be pointed out that for this technology For the technical staff in field, without departing from the principle of this utility model, if dry finishing can be carried out to the utility model Decorations and improvement, these modifications and improvement will also fall into the scope of protection of the utility model.

Claims (4)

1. portable construction dedusting heat sink, including fixed bottom plate (1), dust removal component (2), cooling element (3), It is characterized in that:Fixed bottom plate (1) left and right ends are respectively equipped with dust removal component (2) and cooling element (3), and edge is equipped with Fixed hole, the dust removal component (2) is from top to bottom successively by dust-collecting cylinder (4), defeated dirt channel (5) and telescopic supporting rod (6) group At dust-collecting cylinder (4) annular arranges the wind-collecting cover (7) of several prismatoid structures, and one end of wind-collecting cover (7) protrudes dust-collecting cylinder (4), the other end is located in dust-collecting cylinder (4) and port is equipped with exhaust fan (8), and defeated dirt channel (5) is internally provided with pipeline fan (22), lower side connects deduster (10) by dust outlet tube (9), and deduster (10) other end is equipped with exhaust duct (11), institute It states cooling element (3) to be formed by covering thermal insulation layer (21), outer wall cylinder (12) and water-supply-pipe (13) from outside to inside, water-supply-pipe (13) one End is pierced by outer wall cylinder (12) side wall connection water inlet pipe (14), and the other end is divided into several delivery pipe branches (15), and water inlet pipe (14) is set There are blower pump for pipeline (16) and control valve (17), delivery pipe branch (15) to be close to outer wall cylinder (12) arrangement and prominent outer wall cylinder (12), delivery pipe branch (15) outstanding in truncated cone-shaped structural arrangement and is equipped with several atomizers (18).
2. portable construction dedusting heat sink according to claim 1, it is characterised in that:The water inlet pipe (14) the other end is equipped with buffer tank (19), and buffer tank (19) is located at the centre of fixed bottom plate (1), and buffer tank (19) water purifier (20) is equipped in, top is equipped with filler.
3. portable construction dedusting heat sink according to claim 1, it is characterised in that:The dust-collecting cylinder (4) wind-collecting cover (7) of three to five prismatoid structures is equipped in, and one end of the prominent dust-collecting cylinder (4) of wind-collecting cover (7) is equipped with filter Net.
4. portable construction dedusting heat sink according to claim 1, it is characterised in that:The dust-collecting cylinder (4) and deduster (10) is equipped with protective cover.
CN201720851368.8U 2017-07-13 2017-07-13 Portable construction dedusting heat sink Expired - Fee Related CN207933956U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720851368.8U CN207933956U (en) 2017-07-13 2017-07-13 Portable construction dedusting heat sink

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720851368.8U CN207933956U (en) 2017-07-13 2017-07-13 Portable construction dedusting heat sink

Publications (1)

Publication Number Publication Date
CN207933956U true CN207933956U (en) 2018-10-02

Family

ID=63644307

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720851368.8U Expired - Fee Related CN207933956U (en) 2017-07-13 2017-07-13 Portable construction dedusting heat sink

Country Status (1)

Country Link
CN (1) CN207933956U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112856155A (en) * 2021-01-28 2021-05-28 甘肃建投建设有限公司 Building construction supervision method based on BIM

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112856155A (en) * 2021-01-28 2021-05-28 甘肃建投建设有限公司 Building construction supervision method based on BIM
CN112856155B (en) * 2021-01-28 2022-08-19 甘肃建投建设有限公司 Building construction supervision method based on BIM

Similar Documents

Publication Publication Date Title
CN205549934U (en) Dust collection device for building engineering construction
CN110375393A (en) A kind of intelligence spinning workshop dust pelletizing system
CN106194242A (en) A kind of tunnel dust pelletizing system
CN213668482U (en) Building construction working face sprays dust fall heat sink
CN207933956U (en) Portable construction dedusting heat sink
CN206104234U (en) Multi -functional water curtain paint spray booth
CN108691563A (en) A kind of bidirectional ventilated device for reducing dust of tunnel exploitation
CN209386841U (en) A kind of cooling tower facilitating auxiliary heat dissipation
CN105920955B (en) A kind of blowing and drawing type dust pelletizing system of the underground space
CN107036206B (en) A kind of unpowered type Evaporative Cooling Air-conditioning System suitable for crow
CN206730705U (en) Multi-functional spraying exhausting-dusting device
CN207635585U (en) Condensate water recovery device of air conditioner
CN110476819A (en) A kind of air optimization room structure for outside scale livestock or poultry house
CN207062862U (en) A kind of device for reducing dust of construction road
CN209105755U (en) Flower planting greenhouse
CN209609488U (en) A kind of fresh air system of farm adjustable wind direction and removable odor function
CN208885557U (en) A kind of purification fan
CN207769555U (en) Water paint exhaust gas energy conservation and environmental protection processing system based on UV photochemical catalytic oxidations
CN207357462U (en) A kind of water rotation type circulates paint spray booth
CN208704067U (en) A kind of centralized hot and cold air exchange system removing haze for whole city
CN205832915U (en) Low temperature plasma waste gas treatment equipment
CN206566660U (en) Intelligent climbing frame spraying and dust-removing system
CN206008263U (en) A kind of filtrating equipment of flue gas
CN107238151A (en) It is a kind of to be used for centralized air's exchange system except haze
CN104712153A (en) Green energy-saving public building waterscape system based on evaporative cooling principle

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181002