CN207920141U CN201820110456.7U CN201820110456U CN207920141U CN 207920141 U CN207920141 U CN 207920141U CN 201820110456 U CN201820110456 U CN 201820110456U CN 207920141 U CN207920141 U CN 207920141U
Authority
CN
China
Prior art keywords
pin
high ductility
ductility concrete
strand wires
steel strand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820110456.7U
Other languages
Chinese (zh)
Inventor
邓明科
张凡
卜新星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xi'an Wuhe New Material Technology Group Co ltd
Original Assignee
Xian University of Architecture and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Architecture and Technology filed Critical Xian University of Architecture and Technology
Priority to CN201820110456.7U priority Critical patent/CN207920141U/en
Application granted granted Critical
Publication of CN207920141U publication Critical patent/CN207920141U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The utility model provides a kind of high ductility concrete wrapping wire pin ruggedized construction, including pin, and helical form is tied with steel strand wires to pin outside from top to bottom, and pin and steel strand wires are coated with high ductility concrete topping.The utility model is reinforced pin by the way of high ductility concrete using twining steel wire outside and press to smear.Steel strand wires can form pin hoop effect, prevent wooden cracking, improve the anti-crack ability of pin.High ductility concrete has high tenacity, high cracking resistance and high damnification resistant ability, can keep certain cooperative transformation with pin flexible, improve the globality and load-bearing capacity of pin, to meet the requirement of pin reinforcing.Material is easier to obtain, and solves pin and replaces raw material problems faced, highly practical.Operation is simple, construction personnel is required low, is not necessarily to highly professional technical staff, meanwhile, high ductility concrete has fabulous anti-permeability performance, can be formed and be protected to internal steel strand wires, prevent steel corrosion.

Description

A kind of high ductility concrete-wrapping wire pin ruggedized construction
Technical field
The utility model belongs to building structure aseismatic and reinforcement technique field, and in particular to a kind of high ductility concrete-around Silk pin ruggedized construction.
Background technology
Structure is prevalent in as a kind of common structure type in south China local-style dwelling houses and historic site and relic.Due to The particularity of house main material, with the growth of service life, often there are the diseases such as crack, is rotten, damaging by worms in wood pillar, lead to nothing Method is continuing with, wherein common local-style dwelling houses is particularly acute.
To ensure the normal use of structure, need the maintenance measures such as to be replaced the pillar for disease occur, reinforce.It is limited to The raw material acquisition difficulty of the requirement of environmental protection policy, timber structure is larger, and the alternative costs of pin are larger.It is more to the repair of timber structure By the way of being reinforced to the wooden component.Existing reinforcement technique mostly use the special materials such as carbon cloth, chemical preservation medicament Material, acquisition is constant and complicated for operation, and the popularization difficulty in local-style dwelling houses reinforcing is larger.
Utility model content
The purpose of the utility model is to overcome the above problem of the existing technology, provide that a kind of consolidation effect is good, construction It simply can large-scale popularization and pin ruggedized construction at low cost.
The technical scheme that the utility model is provided is as follows:
A kind of high ductility concrete-wrapping wire pin ruggedized construction, including pin, helical form twines the pin outside from top to bottom There are steel strand wires, the pin and steel strand wires to be coated with high ductility concrete topping.
The high ductility concrete surface layer thickness 10-40cm.
The steel strand wires are equidistantly wound.
The a diameter of 8.6-21.6mm of steel strand wires.
Steel strand wires interval 30-150mm described in two adjacent rings.
The utility model has the beneficial effects that:
This pin ruggedized construction provided by the utility model, by the way of twining steel wire outside and pressing and smear high ductility concrete Pin is reinforced.Steel strand wires can form pin hoop effect, prevent wooden cracking, improve the anti-crack ability of pin.It is high Ductility concrete has high tenacity, high cracking resistance and high damnification resistant ability, can keep certain cooperative transformation with pin flexible, The globality and load-bearing capacity for improving pin, to meet the requirement of pin reinforcing.
Compared with prior art, the utility model has the characteristics that as follows:
(1)Used material is steel strand wires and high ductility concrete, more previous material(Fiber cloth, chemical agent etc.) It more easily obtains, while solving pin and replacing raw material problems faced, it is highly practical.
(2)Operation is simple, and steel strands wound and high ductility concrete topping construction technology are simple, and construction personnel is required Low, common plasterer can be completed, and be not necessarily to highly professional technical staff.(3)High ductility concrete has fabulous resist Performance is oozed, internal steel strand wires can be formed and be protected, prevent steel corrosion.
It is described in further details below in conjunction with attached drawing.
Description of the drawings
Fig. 1 is the front view of the utility model;
Fig. 2 is the vertical view of the utility model.
In figure:1, steel strand wires;2, high ductility concrete topping;3, pin.
Specific implementation mode
Embodiment 1:
Present embodiments provide a kind of high ductility concrete-wrapping wire pin ruggedized construction as shown in Figure 1 and Figure 2, including wood Column 3, helical form is tied with steel strand wires 1 to the pin 3 outside from top to bottom, and the pin and steel strand wires 1 are coated with high ductility coagulation Native face layer 2.
Work progress is as follows:
Step 1:There is interval between 3 surrounding spiral wound steel strand wires 1 of pin, each circle steel strand wires 1;
Step 2:In 3 border of pin, pressure smears high ductility concrete topping 2, and steel strand wires 1 and pin 3 are fully wrapped around.
Wherein, the group of high elongation fiber concrete is divided into cement, flyash, silicon ash, sand, PVA fibers, water-reducing agent and water, By mass percentage, cement:Flyash:Silicon ash:Sand:Water=1:0.9 :0.1 :0.76 :0.58 ;With cement, flyash, The total volume of silicon ash, Sha Heshui after mixing is radix, and the volume volume of PVA fibers is 1.5%;The additive amount of water-reducing agent For cement, flyash and silicon ash gross mass 0.8%.
In the component of high elongation fiber concrete, the maximum particle diameter of sand is 1.26mm;PVA fibers are Shanghai Luo Yang sections The PA600 fiber types of skill Co., Ltd production, length 8mm, a diameter of 26 μm, tensile strength 1200MPa, elasticity modulus For 30GPa;Cement is P.O.52.5R portland cements;Flyash is I grade of flyash;The loss on ignition of silicon ash used is 5%, Dioxide-containing silica is 88%, specific surface area 18000m2/kg ;Water-reducing agent is that water-reducing rate is efficient in 30% or more polycarboxylic acids Water-reducing agent, polycarboxylate water-reducer are the PCA of Jiangsu Botexin Materials Co., Ltd's production®- I type high performance water reducing agent of polyocarboxy acid.
3 ruggedized construction of this pin provided by the utility model smears the side of high ductility concrete using twining steel wire outside and pressing Formula reinforces pin 3.Steel strand wires 1 can form pin 3 hoop effect, prevent wooden cracking, improve the cracking resistance energy of pin 3 Power.High ductility concrete has high tenacity, high cracking resistance and high damnification resistant ability, can keep certain association with pin 3 flexible With deformation, the globality and load-bearing capacity of pin 3 are improved, to meet the requirement of the reinforcing of pin 3.
Embodiment 2:
On the basis of embodiment 1, a kind of high ductility concrete-wrapping wire pin ruggedized construction, institute are present embodiments provided Steel strand wires 1 are stated equidistantly to wind.
As shown in Figure 1, in the present embodiment, it is 30-150mm that steel strand wires 1 described in two adjacent rings, which are spaced S,.Wherein, the height 2 thickness of ductility concrete topping is 10-40cm.
Embodiment 3:
On the basis of the above embodiments, the pin 3 of the present embodiment 600mm a diameter of to certain wooden frame structure adds Gu Vertical Cracks occurs in the pin, can not be continuing with.
Step 1:Between between the steel strand wires 1 of the 3 a diameter of 8.6mm of surrounding spiral wound of pin, each circle steel strand wires 1 Every S=50mm.
Step 2:In 3 border of pin, pressure smears high ductility concrete topping 2, surface thickness 20mm, by steel strand wires 1 and pin 3 It is fully wrapped around.
In conclusion compared with prior art, the utility model has the following advantages that:
(1)Used material is steel strand wires 1 and high ductility concrete, more previous material(Fiber cloth, chemical agent Deng)It more easily obtains, while solving pin 3 and replacing raw material problems faced, it is highly practical.
(2)Operation is simple, and the winding of steel strand wires 1 and high 2 construction technology of ductility concrete topping are simple, and construction personnel is wanted Ask low, common plasterer can be completed, and be not necessarily to highly professional technical staff.
(3)High ductility concrete has fabulous anti-permeability performance, can be formed and be protected to internal steel strand wires 1, prevent steel from becoming rusty Erosion.
The part that the present embodiment does not specifically describe belongs to the common knowledge and known technology of the art, herein not Another one is described in detail.

Claims (5)

1. a kind of high ductility concrete-wrapping wire pin ruggedized construction, including pin(3), it is characterised in that:The pin(3)From It is tied with steel strand wires outside lower helical form(1), the pin(3)And steel strand wires(1)It is coated with high ductility concrete topping (2).
2. a kind of high ductility concrete-wrapping wire pin ruggedized construction according to claim 1, it is characterised in that:The height Ductility concrete topping(2)Thickness is 10-40cm.
3. a kind of high ductility concrete-wrapping wire pin ruggedized construction according to claim 1, it is characterised in that:The steel Twisted wire(1)Equidistantly winding.
4. according to a kind of high ductility concrete-wrapping wire pin ruggedized construction of claim 1-3 any one of them, feature exists In:The steel strand wires(1)Nominal diameter is 8.6-21.6mm.
5. according to a kind of high ductility concrete-wrapping wire pin ruggedized construction of claim 1-3 any one of them, feature exists In:Steel strand wires described in two adjacent rings(1)It is spaced 30-150mm.
CN201820110456.7U 2018-01-23 2018-01-23 A kind of high ductility concrete-wrapping wire pin ruggedized construction Active CN207920141U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820110456.7U CN207920141U (en) 2018-01-23 2018-01-23 A kind of high ductility concrete-wrapping wire pin ruggedized construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820110456.7U CN207920141U (en) 2018-01-23 2018-01-23 A kind of high ductility concrete-wrapping wire pin ruggedized construction

Publications (1)

Publication Number Publication Date
CN207920141U true CN207920141U (en) 2018-09-28

Family

ID=63605253

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820110456.7U Active CN207920141U (en) 2018-01-23 2018-01-23 A kind of high ductility concrete-wrapping wire pin ruggedized construction

Country Status (1)

Country Link
CN (1) CN207920141U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111608415A (en) * 2020-05-13 2020-09-01 武汉大学 Square steel tube concrete column reinforcing method based on high-ductility cement-based material
CN114808767A (en) * 2022-05-19 2022-07-29 安徽省交通控股集团有限公司 Steel wire rope hoop prestress construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111608415A (en) * 2020-05-13 2020-09-01 武汉大学 Square steel tube concrete column reinforcing method based on high-ductility cement-based material
CN111608415B (en) * 2020-05-13 2021-07-06 武汉大学 Square steel tube concrete column reinforcing method based on high-ductility cement-based material
CN114808767A (en) * 2022-05-19 2022-07-29 安徽省交通控股集团有限公司 Steel wire rope hoop prestress construction method

Similar Documents

Publication Publication Date Title
CN202117165U (en) Composite structure with fibre compound material barrel confining concrete-filled steel tube
CN202519664U (en) High tensile reinforcement reinforced prestressed UHPC (Ultra High Performance Concrete) thin-wall tubular pile component
CN107447646B (en) Preparation method of steel-continuous fiber composite bar ECC-concrete composite column/pier
CN211851012U (en) Shear-resistant reinforcing device for reinforced concrete member
CN207920141U (en) A kind of high ductility concrete-wrapping wire pin ruggedized construction
CN107327078A (en) A kind of Novel steel continuous fiber composite reinforcing ECC concrete composite beams and preparation method thereof
CN109403205A (en) Hollow sandwich multi-cavity steel tube concrete component and preparation method thereof
CN108894432A (en) A kind of very-high performance steel fiber concrete pipe constraint regeneration monolith column
CN108894328A (en) A kind of novel combined column and assemble method
CN104005407A (en) Partially prestressed concrete structure foundation pile
CN103132654B (en) FRP reinforcement material end nut and manufacturing method thereof
CN101979774A (en) Partial external prestressed and fine-grain reinforcing steel bar fiber reinforced cementitious composite (FRCC) railway box girder
CN107311571A (en) The preparation method of nanometer enhancing TRC composites
CN208857720U (en) A kind of prestressing force metal composite muscle reinforcement bridge structure
CN207364466U (en) Polymer strengthens Prestressed concrete cylinder pipe road
CN200943329Y (en) High intensity prestressed concrete pole
CN103510738A (en) High-durability large-bending-moment concrete electric pole
CN105174857A (en) Fiber concrete prefabrication member
CN207920143U (en) A kind of high ductility concrete-brick column encloses set pin ruggedized construction
CN201943186U (en) FRP pipe-RPC-steel pipe combined member
CN208379423U (en) A kind of concrete column
CN207920142U (en) A kind of brick masonry wall ruggedized construction
CN211114427U (en) Natural fiber composite pipe restraint recycled concrete post
CN208105668U (en) A kind of support construction
CN207405621U (en) A kind of high-strength construction stake

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190828

Address after: 710055 North Gateway, 17th Floor, Jianke Building, No. 13 Yanta Road, Beilin District, Xi'an City, Shaanxi Province

Patentee after: XI'AN WUHE CIVIL ENGINEERING NEW MATERIAL CO.,LTD.

Address before: 710055 Shaanxi province Xi'an Beilin District Yanta Road No. 13

Patentee before: XIAN University OF ARCHITECTURE AND TECHNOLOG

TR01 Transfer of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A high ductility reinforced concrete wire wrapped timber column structure

Effective date of registration: 20221013

Granted publication date: 20180928

Pledgee: Pudong Development Bank of Shanghai Limited by Share Ltd. Xi'an branch

Pledgor: XI'AN WUHE CIVIL ENGINEERING NEW MATERIAL CO.,LTD.

Registration number: Y2022610000653

PE01 Entry into force of the registration of the contract for pledge of patent right
CP03 Change of name, title or address

Address after: 710075 Room A-115-37, iChuangtu Maker Park, No. 14, Gaoxin 2nd Road, High-tech Zone, Xi'an City, Shaanxi Province

Patentee after: Xi'an Wuhe New Material Technology Group Co.,Ltd.

Address before: 710055 north house, 17th floor, Jianke building, 13 Yanta Road, Beilin District, Xi'an City, Shaanxi Province

Patentee before: XI'AN WUHE CIVIL ENGINEERING NEW MATERIAL CO.,LTD.

CP03 Change of name, title or address
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20231107

Granted publication date: 20180928

Pledgee: Pudong Development Bank of Shanghai Limited by Share Ltd. Xi'an branch

Pledgor: XI'AN WUHE CIVIL ENGINEERING NEW MATERIAL CO.,LTD.

Registration number: Y2022610000653

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A High Ductility Concrete Wire Wound Wood Column Reinforcement Structure

Effective date of registration: 20231127

Granted publication date: 20180928

Pledgee: Pudong Development Bank of Shanghai Limited by Share Ltd. Xi'an branch

Pledgor: Xi'an Wuhe New Material Technology Group Co.,Ltd.

Registration number: Y2023980067686

PE01 Entry into force of the registration of the contract for pledge of patent right