CN207904783U - Rotary body device in the middle part of the pier shaft of high-altitude - Google Patents
Rotary body device in the middle part of the pier shaft of high-altitude Download PDFInfo
- Publication number
- CN207904783U CN207904783U CN201820207484.0U CN201820207484U CN207904783U CN 207904783 U CN207904783 U CN 207904783U CN 201820207484 U CN201820207484 U CN 201820207484U CN 207904783 U CN207904783 U CN 207904783U
- Authority
- CN
- China
- Prior art keywords
- pier
- pier shaft
- construction
- swivel
- altitude
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses rotary body devices in the middle part of a kind of high-altitude pier shaft, including construction rotor system device, lower wall pier shaft and upper disk pier shaft, are installed on high pier middle and upper part position, and construction rotor system device is set between lower wall pier shaft and upper disk pier shaft;It is excessive excessively high with center of gravity can to solve pier bottom swivel transfer body weight, leads to crank, the excessive problem of swivel process tilting moment;It is complicated big with construction technology control difficulty that pier top swivel stress system conversion can be solved simultaneously, especially body member and the installation of pier top bearing and continuous beam 0# segmental constructions interfere with each other larger, complicated problem, the construction methods such as the utility model is turned compared to pier bottom, pier top turns, there is larger breakthrough in the structure feature of swivel and the technical difficulty of swivel, it is not only more ripe in technology, so that swivel spanning existing railway, highway are safer, and optimized on the duration, reduce corresponding economic cost.
Description
Technical field
The present utility model is related to railway, highway communication engineering, specifically swivel dress in the middle part of a kind of high-altitude pier shaft
It sets.
Background technology
With China's expanding economy, railway and freeway net preliminarily form and constantly improve, from now on railway,
In highway construction, newly-built railway is inevitably encountered, highway needs asking across existing railway and busy highway
Topic, at this moment will be considered as the construction method small to existing line Influence to operation, and rotator construction is a kind of preferable method, but
It is when pier height is higher, will appear swivel in pier bottom swivel, weight is excessive and center of gravity is excessively high, and crank, swivel process is caused to incline
Cover the excessive problem of torque;It then will appear stress system conversion complexity in pier top swivel and construction technology control difficulty be big, especially
It is that body member and the installation of pier top bearing and continuous beam 0# segmental constructions interfere with each other larger, complicated problem.Therefore
Studying a kind of not only economic but also safety construction is very important.
When newly-built railway, highway are needed across existing railway and busy highway, generally use pushing tow or swivel are applied
Work should be selected according to field condition.Rotator construction generally use pier bottom or pier top setting rotor system carry out rotator construction,
But when pier height is higher, will appear swivel in pier bottom swivel, weight is excessive and center of gravity is excessively high, leads to crank, turns process
The excessive problem of tilting moment;It then will appear stress system conversion complexity in pier top swivel and construction technology control difficulty be big, it is special
It is not that body member and the installation of pier top bearing and continuous beam 0# segmental constructions interfere with each other larger, complicated problem.
Invention content
The purpose of this utility model is that in view of the above-mentioned deficiencies in the prior art, providing the higher iron of bridge pier
Road, highway bridge cross over existing railway and busy highway when using rotator construction settling mode.When the higher iron of bridge pier
When road, highway continuous beam, Continuous Rigid-Frame Bridge are needed using rotator construction, since bridge pier is higher, it should not be turned using pier bottom
Body construction, and pier top rotator construction is also more complex, it is contemplated that the safety of structure, the safety of construction save cost, and have invented height
Rotary body device in the middle part of empty pier shaft.
To solve the above problems, the utility model is achieved using following technical scheme:Swivel dress in the middle part of the pier shaft of high-altitude
It sets, including construction rotor system device, lower wall pier shaft and upper disk pier shaft, is installed on high pier middle and upper part position, construction swivel system
Bulk cargo, which installs, to be placed between lower wall pier shaft and upper disk pier shaft.
Pier shaft is respectively set on the lower wall pier shaft and upper disk pier shaft and widens steel construction.
Steel construction rotator construction platform is set up to construction rotor system setting position along high pier.
The upper disk pier shaft, lower wall pier shaft use armored concrete, and the pier shaft widens steel construction and steel construction swivel is applied
Work platform uses steel construction.
The construction rotor system device be it is existing it is a full set of turn facility, including flexural pivot, top rotary table, lower rotary table, slideway,
Spike and trailer system.
It needs to apply using swivel across existing railway, highway in railway, the big span continuous beam of highway, continuous rigid frame bridge
Work, and pier shaft is higher(30m~60m)When, rotary body device in the middle part of the high-altitude pier shaft of the utility model is set, pier bottom can be solved and turned
Body transfer body weight is excessive and center of gravity is excessively high, leads to crank, the excessive problem of swivel process tilting moment;It can solve simultaneously
Certainly the conversion of pier top swivel stress system is complicated and construction technology control difficulty is big, especially body member and the installation of pier top bearing with
And continuous beam 0# segmental constructions interfere with each other larger, complicated problem.
The construction methods such as the utility model is turned compared to pier bottom, pier top turns, in structure feature and the swivel of swivel
Technical difficulty has larger breakthrough, not only more ripe in technology so that swivel spanning existing railway, highway are more
For safety, therefore it is to solve the high pier swivel most economical and feasible scheme of bridge using rotary body device in the middle part of the pier shaft of high-altitude, is one
The novel processing mode of kind.
Rotary body device has the following advantages in the middle part of the pier shaft of the utility model high-altitude:
(1)Rotary body device can effectively solve the higher railway of bridge pier, highway continuous beam, continuous steel in the middle part of the pier shaft of high-altitude
The rotator construction problem of structure bridge.
(2)Widen steel construction dismounting after the completion of construction, bridge pier globality is coordinated, and appearance is preferable.
(3)Engineering can be safely performed more, short time limit, save engineering cost, economical rationality, technological innovation.
Description of the drawings
Fig. 1 bridge piers front layout drawing;
Fig. 2 bridge pier side arrangement figures;
Fig. 3 steel constructions widen figure;
Fig. 4 rotator construction steel platform structure layout drawings.
Specific implementation mode
The utility model is further described in 1-4 and embodiment below in conjunction with the accompanying drawings, and embodiment is not constituted to this reality
With novel limitation:
As shown in Figs 1-4, high-altitude pier is arranged using the suitable position in 6 middle and upper part of high pier in rotary body device in the middle part of the pier shaft of high-altitude
Rotary body device in the middle part of body, 2 thickness h 1 of lower wall pier shaft and 3 thickness h 2 of upper disk pier shaft can be adjusted according to load situation, when pier shaft width
Setting pier shaft widens steel construction 4 when cannot meet rotor system setting, and swivel is completed, and cutting away pier shaft after closing turning hinge widens steel
Structure 4, steel construction rotator construction platform 5 can be set up to rotary body device position along bridge pier by turning platform and staff's workbench
It sets, is removed after the completion of swivel.Rotor system device 1, which includes that flexural pivot, upper lower rotary table, slideway and spike, trailer system etc. are a full set of, to be turned
Body facility, upper disk pier shaft 3, lower wall pier shaft 2 use armored concrete, pier shaft to widen steel construction 4 and steel construction rotator construction platform 5
Using steel construction.
The rotor system device 1 of 6 middle part rotary body device of high-altitude pier shaft is located in pier, is with the position that rack platform can be accomplished
Preferably, and consider preferably to control beam body, the thickness of upper lower burrs pier shaft is adjusted according to stressing conditions, and pier shaft is widened
Steel construction 4 determines whether to be arranged according to pier shaft and 1 size of rotor system device, steel construction rotator construction platform 5 using bridge pier as
Supplementary structure is configured, and scantling is determined according to Force Calculation.
The main construction procedure and method of the utility model are as follows:
1, construction bridges pile foundation and suspended deck structure.Steel construction rotator construction platform 5 of constructing is basic.
2,2 or less bridge pier part of construction lower wall pier shaft.
3, construction lower wall pier shaft 2, while the pier shaft for lower wall pier shaft 2 of constructing widens steel construction 4.
4, construction construction steel construction rotator construction platform 5.
5, construction rotor system device 1.
6, disk pier shaft 6 in construction, while the pier shaft for upper disk pier shaft 6 of constructing widens steel construction 4.
7, construction bridges other structures.
Basic principles, main features, and advantages of the present invention has been shown and described above.Ability
The technical staff in domain should be recognized that the present utility model is not limited to the above embodiments, described in the above embodiment and specification
Only illustrate the principles of the present invention, on the premise of not departing from the spirit and scope of the utility model, the utility model can also
There are various changes and modifications, these changes and improvements are both fallen in claimed range.
Claims (5)
1. rotary body device in the middle part of a kind of high-altitude pier shaft, which is characterized in that including rotor system device of constructing(1), lower wall pier shaft(2)
And upper disk pier shaft(3), it is installed on high pier(6)Middle and upper part position, rotor system device of constructing(1)It is set to lower wall pier shaft(2)
With upper disk pier shaft(3)Between.
2. rotary body device in the middle part of high-altitude pier shaft according to claim 1, which is characterized in that the lower wall pier shaft(2)On and
Disk pier shaft(3)On pier shaft be respectively set widen steel construction(4).
3. rotary body device in the middle part of the high-altitude pier shaft according to claim 1-2 any one, which is characterized in that along high pier
(6)Set up steel construction rotator construction platform(5)To construction rotor system device(1)Position.
4. rotary body device in the middle part of high-altitude pier shaft according to claim 3, which is characterized in that the upper disk pier shaft(3), lower wall
Pier shaft(2)Using armored concrete, the pier shaft widens steel construction(4)And steel construction rotator construction platform(5)Using steel construction.
5. rotary body device in the middle part of high-altitude pier shaft according to claim 1, which is characterized in that the construction rotor system device
(1)For existing a full set of swivel facility, including flexural pivot, top rotary table, lower rotary table, slideway, spike and trailer system.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820207484.0U CN207904783U (en) | 2018-02-06 | 2018-02-06 | Rotary body device in the middle part of the pier shaft of high-altitude |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820207484.0U CN207904783U (en) | 2018-02-06 | 2018-02-06 | Rotary body device in the middle part of the pier shaft of high-altitude |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207904783U true CN207904783U (en) | 2018-09-25 |
Family
ID=63562224
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820207484.0U Active CN207904783U (en) | 2018-02-06 | 2018-02-06 | Rotary body device in the middle part of the pier shaft of high-altitude |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207904783U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111305039A (en) * | 2020-01-22 | 2020-06-19 | 长沙理工大学 | Device for improving stress distribution of swivel cable-stayed bridge and installation method thereof |
CN113882277A (en) * | 2021-11-12 | 2022-01-04 | 中铁三局集团第五工程有限公司 | Rotary bridge construction structure in high pier |
CN114016439A (en) * | 2021-11-12 | 2022-02-08 | 中铁三局集团第五工程有限公司 | Construction method for upper pier body and No. 0 block bracket of rotating bridge in high pier |
-
2018
- 2018-02-06 CN CN201820207484.0U patent/CN207904783U/en active Active
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111305039A (en) * | 2020-01-22 | 2020-06-19 | 长沙理工大学 | Device for improving stress distribution of swivel cable-stayed bridge and installation method thereof |
CN111305039B (en) * | 2020-01-22 | 2021-06-01 | 长沙理工大学 | Device for improving stress distribution of swivel cable-stayed bridge and installation method thereof |
CN113882277A (en) * | 2021-11-12 | 2022-01-04 | 中铁三局集团第五工程有限公司 | Rotary bridge construction structure in high pier |
CN114016439A (en) * | 2021-11-12 | 2022-02-08 | 中铁三局集团第五工程有限公司 | Construction method for upper pier body and No. 0 block bracket of rotating bridge in high pier |
CN114016439B (en) * | 2021-11-12 | 2024-06-04 | 中铁三局集团有限公司 | Construction method for upper pier body and No. 0 block support of middle-rotation body bridge of high pier |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207904783U (en) | Rotary body device in the middle part of the pier shaft of high-altitude | |
CN204662279U (en) | Tumbling-type concrete box girder bridge rotator construction with protection system closes up hanger device | |
CN103882812B (en) | Across the construction method of girder in stayed-cable bridge | |
CN104328745B (en) | Across the rotary body device of the little bridge beam of high ferro and construction method thereof on a kind of low-angle | |
CN104947604B (en) | A kind of fast quick change frame construction method of high-speed railway 900t concrete box girders | |
CN102953343A (en) | Descending bracket self-mobile model framework bridge fabrication machine | |
CN103669217B (en) | A kind of rear-support hanging basket and its entirety change width method for traversing | |
CN103541300B (en) | Based on the construction method of the railway concrete continuous beam that flat stacking is implemented | |
CN107201719A (en) | Overpass anti-collision wall formwork hoisting conveyance and anti-collision wall construction method | |
CN106381814A (en) | Cast-in-cantilever structure of movable crane formwork of zigzag-form steel web continuous box beam and construction method of cast-in-cantilever structure | |
CN103388305A (en) | Railway T-beam cast-in-site bridge deck forming machine | |
CN202380403U (en) | Integral hoisting system of arch rib of arch bridge | |
CN105401525B (en) | Cast-in-situ construction method of beam flange plates of acoustic barriers through movable mold base vehicles | |
CN204112239U (en) | Across the rotary body device of the little bridge beam of high ferro on a kind of low-angle | |
CN207582948U (en) | A kind of morning tears formula superimposed sheet temporary supporting system open | |
CN105648912A (en) | Construction method for integrally transferring and splicing movable formwork | |
CN203498743U (en) | Railway concrete continuous beam implemented on basis of flat pushing method | |
CN206571502U (en) | A kind of constructing tunnel telescoping steel form turns mobile device | |
CN206887771U (en) | A kind of small across footpath plate-beam construction platform structure | |
CN106957012A (en) | A kind of intelligent weighing Lift-on/Lift-off System | |
CN206233122U (en) | For bridge cantilever construction with Hanging Basket movable tower crane | |
CN205116036U (en) | Permanent support of continuous bridge system of turning conversion slide system of sliding | |
CN106284088A (en) | Prefabricated arch bar lifting method of temporarily fixing | |
CN108677751A (en) | A kind of Bridge Rotation Construction Technique beam body lifting system | |