CN207878518U - A kind of anti-settling well lid - Google Patents

A kind of anti-settling well lid Download PDF

Info

Publication number
CN207878518U
CN207878518U CN201721929468.4U CN201721929468U CN207878518U CN 207878518 U CN207878518 U CN 207878518U CN 201721929468 U CN201721929468 U CN 201721929468U CN 207878518 U CN207878518 U CN 207878518U
Authority
CN
China
Prior art keywords
lid
hole
well lid
wedge
crib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721929468.4U
Other languages
Chinese (zh)
Inventor
甘建波
彭宏
俞湛然
陈百荣
孙洪伟
连双斌
陈志恒
钟仰俊
李明斌
邵天聪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhuhai Huafa New Construction Holdings Ltd
Original Assignee
Zhuhai Huafa New Construction Holdings Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhuhai Huafa New Construction Holdings Ltd filed Critical Zhuhai Huafa New Construction Holdings Ltd
Priority to CN201721929468.4U priority Critical patent/CN207878518U/en
Application granted granted Critical
Publication of CN207878518U publication Critical patent/CN207878518U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model is related to a kind of anti-settling well lids, including crib and well lid, crib includes supporting rack, well lid is mounted on supporting rack, extension board is equipped on the outside of support frame bottom, supporting rack inner wall is equipped with location hole, well lid includes the first lid and the second lid being slidably connected, support spring is equipped between first lid and the second lid, through-hole is equipped in the middle part of first lid, wedged hole is equipped in the middle part of second lid, supporting rod is equipped in through-hole, the lower end of supporting rod is fixedly connected with wedge block, fixed frame is equipped in wedged hole, multiple strip-shaped holes are equipped in second lid, strip-shaped hole is connected to wedged hole, wedge-shaped bar is slidably connected in strip-shaped hole, the medial end of wedge-shaped bar is located in wedged hole, the outboard end of wedge-shaped bar is oppositely arranged with location hole, wedge-shaped bar is equipped with fixinig plate, resetting spring is connected between fixinig plate and fixed frame.Periphery pavement cracking, crib well lid sink caused by present application addresses not led to the problem of closely due to shaking because of well lid and crib cooperation.

Description

A kind of anti-settling well lid
Technical field
The utility model is related to common techniques fields, and in particular to a kind of anti-settling well lid.
Background technology
Well lid is for covering road or family's middle-deep well, the lid for preventing people or object from falling.It can be divided into gold by material Belong to well lid, high strength fibre cement concrete well lid, Resin man-hole cover etc..It is general using round, can be used for greenbelt, pavement, Car lane, harbour etc..
Pipe network interlocks below urban road, and the inspection shafts such as rainwater, sewage inspection well are often arranged in road table.Traditional inspection shaft It separately constructs with bituminous paving, is not an entirety in structure.After bitumen pavement construction completion, open to traffic soon, works as vehicle When pressing through well lid, the cooperation of well lid and crib does not lead to the opposite crib shaking of well lid closely, in the course of time, causes asphalt surface course gradual Cracking, damaged, crib well lid sink, stick up and winnow with a dustpan, is crooked, and when vehicle pass-through, which generates, jumps vehicle and strenuous vibration.This phenomenon has become A kind of FAQs of bituminous paving.
Utility model content
The utility model is intended to provide a kind of anti-settling well lid, to solve inspection shaft because well lid and crib cooperation do not generate closely Shake and caused by periphery pavement cracking, crib well lid sink the problem of.
In order to achieve the above objectives, the technical solution of the utility model is as follows:A kind of anti-settling well lid, including crib and well lid, The diameter of well lid is less than the diameter of crib, and crib includes supporting rack, and well lid is mounted on supporting rack, is equipped on the outside of support frame bottom Extension board, extension board are integrally formed with supporting rack, and supporting rack inner wall is equipped with location hole, and well lid includes the first lid and the second lid Body, the first lid are slidably connected with the second lid, support spring are equipped between the first lid and the second lid, in the first lid Portion is equipped with through-hole, and the middle part of the second lid is equipped with wedged hole, supporting rod, the lower end of supporting rod are equipped in the through-hole of the first lid It is fixedly connected with the wedge block coordinated with wedged hole, fixed frame is equipped in wedged hole, multiple strip-shaped holes, item are equipped in the second lid Shape hole is connected to wedged hole, and wedge-shaped bar is slidably connected in strip-shaped hole, and the medial end of wedge-shaped bar is located in wedged hole, wedge shape The outboard end of item is oppositely arranged with location hole, and wedge-shaped bar is equipped with fixinig plate, and reset is connected between fixinig plate and fixed frame Spring.
Using a kind of anti-settling well lid of above-mentioned technical proposal, when practical application, after the completion of roadbed, crib is placed in inspection shaft Top, then pave pitch and concrete, and the extension board of crib is embedded in below pitch and concrete, extension board and road are made Pitch, the concrete in face become an entirety, and supporting rack plays the role of that well lid and fixed well lid position, well lid is supported to play screening The effect of lid inspection shaft.After bitumen pavement construction completion, after open to traffic, after downward pressure of the well lid by wheel, support Spring, which pushes wheel, has certain cushioning effect, reduces pressure of the wheel to well lid, since lower pressure is more than support spring Elastic force, and the first lid and the second lid are slidably connected, and the first lid is moved downward with respect to the second lid, drive supporting rod and Wedge block moves down, and after wedge block is caught in wedged hole, wedge block continues to move downward the wedge-shaped bar that can be squeezed in wedged hole, Since wedge-shaped bar is slidably connected in strip-shaped hole, wedge-shaped bar be squeezed after along strip-shaped hole to outside the second lid Slideslip, due to The outboard end of wedge-shaped bar is oppositely arranged with location hole, and wedge-shaped bar can be caught in location hole, prevent well lid from sinking, and also can avoid well Lid acutely shaken with respect to crib due to by lower pressure and caused by periphery pavement cracking the problem of;When well lid is not by wheel Lower pressure when, from skidding off and being slided into strip-shaped hole in location hole under the pulling force of resetting spring, the first lid exists wedge-shaped bar Original position is moved upwards up under the action of support spring.
The advantageous effect of the technical program is:
1. the present apparatus is by the way that the extension board of crib to be embedded in below pitch and concrete, when well lid is by wheel pressure When, since crib and road surface become an entirety so that the lower pressure suffered by crib and well lid is shared on road surface, avoid crib and Well lid sinks after being under pressure.
2. supporting rod and wedge block is arranged in the present apparatus at the top of the first lid, when wheel pushes the first lid, wedge block Wedge-shaped bar is pushed to slide and be stuck in the location hole of supporting rack, the position of well lid and crib, which is fixed, keeps crib tight with well lid Close fit avoids under wheel after pressure cover for manhole, generated because of the relative motion of well lid and crib shaking and caused by periphery road surface open The problem of splitting.
The second lid relatively moves downward after 3. present apparatus support spring can not only make the first lid be under pressure, in addition, Support spring has certain cushioning effect, can also be shared part by lower pressure rear support spring in the first lid and be pushed Power reduces the load-bearing of the first lid and crib, plays the role of protecting crib.
Preferably, as an improvement, the bottom of supporting rack is equipped with beam.The pressure under the first lid is by wheel Afterwards, the bottom of the second lid pushes against beam, and beam has the function of certain damping and buffering, avoids the second lid bottom The rigid contact between supporting rack, while reducing the generation of noise.
Preferably, as an improvement, the first lid upper surface is rotatably connected to handheld ring, and the first lid upper surface is also set There is the annular groove for accommodating the handheld ring.When to go into the well check when, can be replaced by hand and lift well lid, it is easy to operate, when not needing , can be hyperphoric in annular groove by mobile phone when lifting well lid, save space.
Preferably, as an improvement, crib inner wall is equipped with groove, and the side wall of the first lid is equipped with and fit depressions Protrusion.When security protection well lid, protrusion glides along groove, and is stuck in groove, and cooperation between the first lid and crib can be made close, into One step prevent from coordinating between well lid and crib do not lead to the problem of closely shaking and caused by periphery pavement cracking.
Preferably, as an improvement, the top periphery of supporting rack is equipped with fillet.Phase is arranged in supporting rack top periphery fillet It is safer compared with traditional right angle setting, be not easy to scratch tire, and tire on crib when driving, rounding off is not likely to produce It jolts.
Preferably, as an improvement, the first lid is equipped with collector nozzle, and support spring and resetting spring are coated with waterproof Layer.When raining or when surface gathered water, water can be by collector nozzle Quick drainage, and the waterproof layer of support spring and resetting spring can avoid Support spring and resetting spring are rusted, and extend the service life of equipment.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model embodiment.
Fig. 2 is the vertical view of the utility model well lid.
Specific implementation mode
The utility model is described in further detail below by specific implementation mode:
Reference numeral in Figure of description includes:Crib 1, supporting rack 2, extension board 3, location hole 4, the first lid 5, Two lids 6, support spring 7, supporting rod 8, wedge block 9, wedged hole 10, wedge-shaped bar 11, fixed column 12, resetting spring 13, lower water Mouth 14, beam 15, handheld ring 16, protrusion 17, fixinig plate 18.
As shown in Figure 1 and Figure 2:A kind of anti-settling well lid, including crib 1 and well lid, the diameter of well lid are less than the diameter of crib 1, Crib 1 includes supporting rack 2, and the bottom of supporting rack 2 is equipped with beam 15, and beam 15 is rubber pad, and well lid is mounted on supporting rack 2 On, 2 bottom outside of supporting rack is equipped with extension board 3, and extension board 3 is integrally formed with supporting rack 2, and 2 side wall of supporting rack is equipped with location hole 4, the top periphery of supporting rack 2 is equipped with fillet;Well lid includes the first lid 5 and the second lid 6, the first lid 5 and the second lid 6 It is slidably connected, support spring 7 is equipped between the first lid 5 and the second lid 6,5 upper surface of the first lid is rotatably connected to portable Ring 16,5 upper surface of the first lid are additionally provided with the annular groove for accommodating handheld ring 16, and the first lid 5 is equipped with collector nozzle 14, the first lid 5 middle part is equipped with through-hole, and the middle part of the second lid 6 is equipped with wedged hole 10, is equipped with supporting rod 8 in the through-hole of the first lid 5, props up The lower end of strut 8 is fixedly connected with the wedge block 9 coordinated with wedged hole 10, is equipped with fixed frame in wedged hole 10, fixed frame be with Four fixed columns 12 that second lid 6 is fixedly connected, and four fixed columns 12 are distributed in the periphery of wedged hole, in the second lid 6 If there are four the strip-shaped holes being arranged radially centered on wedged hole 10, and strip-shaped hole is connected to wedged hole, in strip-shaped hole Slidably connect wedge-shaped bar 11, the medial end of wedge-shaped bar 11 is respectively positioned in wedged hole 10, and the outboard end of wedge-shaped bar 11 with Location hole 4 is oppositely arranged, and fixinig plate 18 is provided in wedge-shaped bar 11, resetting spring is connected between fixinig plate 18 and fixed column 12 13, support spring 7 and resetting spring 13 are coated with waterproof layer, and the supporting rack inner wall of crib 1 is equipped with groove, the side of the first lid 5 Wall is equipped with the protrusion 17 with fit depressions.
In the present embodiment, when practical application, after the completion of roadbed, crib 1 is placed in the top of inspection shaft, then pave drip The extension board 3 of crib 1 is embedded in below pitch and concrete, makes pitch, the coagulation of extension board 3 and road surface by green and concrete Soil becomes an entirety, and the protrusion 17 on the first lid 5 makes the first lid 5 and the second lid 6 along the groove downslide of 1 inner wall of crib In place, supporting rack 2 supports the first lid 5 and the second lid 6, after bitumen pavement construction completion, after open to traffic, when vehicle is from well The side of covering crosses, and after pressure of first lid 5 by the wheel travelled, first, support spring 7, which pushes wheel, to be had centainly Cushioning effect, reduces the pressure of the first lid of wheel pair 5, while can reduce the amplitude of jolting of vehicle;Since pressure is big under wheel In the elastic force of support spring 7, and the first lid 5 and the second lid 6 are slidably connected, and the first lid 5 is by phase after downward pressure Second lid 6 is moved downward, and then the through-hole of supporting rod 8 and wedge block 9 in the first lid 5 is driven to move down, works as wedge After shape block 9 is caught in wedged hole 10, wedge block 9 is continued to move downward by pressure under wheel, due to the medial end of wedge-shaped bar 11 In wedged hole 10, wedge block 9, which continues to move downward, can squeeze wedge-shaped bar 11, since wedge-shaped bar 11 is slidably connected at strip-shaped hole It is interior, and the outboard end of wedge-shaped bar 11 and location hole 4 are opposite, wedge-shaped bar 11 be squeezed after along the outside Slideslip of strip-shaped hole, and It is caught in the location hole 4 of 2 inner wall of supporting rack, prevents the side of well lid from sinking or being upturned, keep the steady of well lid, meanwhile, Wedge-shaped bar 11 fixes the position of the first lid 5 and the second lid 6, and the first lid 5, the second lid 6 is made closely to connect with crib 1 Connect, can avoid well lid due to by lower pressure with respect to crib 1 acutely shake and caused by periphery pavement cracking the problem of.
When wheel pushes the first lid 5, since there are rubber pads, rubber pad to have between the second lid 6 and supporting rack 2 Certain cushioning effect avoids generating rigid contact between 6 lower part of the second lid and supporting rack 2, while reducing because of rigid contact The noise of generation.When well lid is not when by the lower pressure of wheel, the first lid 5 restores upwards under the elastic force of support spring 7 To original position, wedge block 9 moves up therewith, and wedge block 9 no longer squeezes wedge-shaped bar 11 after moving up, at this point, due to resetting bullet One end of spring 13 is connected with fixed column 12, and wedge-shaped bar 11 slides back strip-shaped hole under the pulling force of resetting spring 13 out of location hole 4 It is interior.
Above-described is only the embodiments of the present invention, well known specific technical solution and/or characteristic etc. in scheme Common sense does not describe excessively herein.It should be pointed out that for those skilled in the art, not departing from the utility model technology Under the premise of scheme, several modifications and improvements can also be made, these should also be considered as the scope of protection of the utility model, these The effect and patent practicability of the utility model implementation are not all interfered with.This application claims protection domain should be with its right It is required that content subject to, the records such as specific implementation mode in specification can be used for explain claim content.

Claims (6)

1. a kind of anti-settling well lid, including crib and well lid, the diameter of the well lid is less than the diameter of crib, and the crib includes branch Support, the well lid are mounted on supporting rack, it is characterised in that:Support frame as described above bottom outside is equipped with extension board, the extension Plate is integrally formed with supporting rack, and support frame as described above inner wall is equipped with location hole, and the well lid includes the first lid and the second lid, institute It states the first lid to be slidably connected with the second lid, support spring is equipped between the first lid and the second lid, in the first lid Portion is equipped with through-hole, and the middle part of the second lid is equipped with wedged hole, supporting rod, the lower end of supporting rod are equipped in the through-hole of the first lid It is fixedly connected with the wedge block coordinated with wedged hole, fixed frame is equipped in wedged hole, multiple strip-shaped holes, institute are equipped in the second lid It states strip-shaped hole to be connected to wedged hole, wedge-shaped bar is slidably connected in strip-shaped hole, the medial end of the wedge-shaped bar is located at wedge shape In hole, the outboard end of wedge-shaped bar is oppositely arranged with the location hole, and wedge-shaped bar is equipped with fixinig plate, the fixinig plate and fixation Resetting spring is connected between frame.
2. a kind of anti-settling well lid according to claim 1, it is characterised in that:The bottom of support frame as described above is equipped with beam.
3. a kind of anti-settling well lid according to claim 2, it is characterised in that:First lid upper surface is rotatably connected to Ring handheld ring, the first lid upper surface are additionally provided with the annular groove for accommodating the handheld ring.
4. a kind of anti-settling well lid according to claim 3, it is characterised in that:The crib inner wall is equipped with groove, and described the One covered body wall is equipped with the protrusion with fit depressions.
5. a kind of anti-settling well lid according to claim 4, it is characterised in that:The top periphery of support frame as described above is equipped with circle Angle.
6. a kind of anti-settling well lid according to claim 5, it is characterised in that:First lid is equipped with collector nozzle, institute It states support spring and resetting spring is coated with waterproof layer.
CN201721929468.4U 2017-12-30 2017-12-30 A kind of anti-settling well lid Active CN207878518U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721929468.4U CN207878518U (en) 2017-12-30 2017-12-30 A kind of anti-settling well lid

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721929468.4U CN207878518U (en) 2017-12-30 2017-12-30 A kind of anti-settling well lid

Publications (1)

Publication Number Publication Date
CN207878518U true CN207878518U (en) 2018-09-18

Family

ID=63505571

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721929468.4U Active CN207878518U (en) 2017-12-30 2017-12-30 A kind of anti-settling well lid

Country Status (1)

Country Link
CN (1) CN207878518U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110373969A (en) * 2019-07-19 2019-10-25 郭斯羽 A kind of anti-jump vehicle transition plates for road rail intersection region

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110373969A (en) * 2019-07-19 2019-10-25 郭斯羽 A kind of anti-jump vehicle transition plates for road rail intersection region

Similar Documents

Publication Publication Date Title
CN207878518U (en) A kind of anti-settling well lid
KR101355803B1 (en) Protecting device of tree by the road side for rainwater supply eco-friendly
CN207904977U (en) A kind of town road well lid facilitating tilting
CN108265579B (en) Roadbed leveling device for asphalt road
CN207469033U (en) Ecological footpath
CN209652688U (en) A kind of suspension assembled floor-board of sponge urban pavement water-permeable water storage
CN104499397A (en) Asphalt pavement structure based on coordination of deformation of subgrade and pavement
CN209243648U (en) Cement pavement Accrete clearing device in hydraulic engineering
CN207760680U (en) A kind of asphalt pavement structure
CN204266137U (en) A kind of novel municipal porous pavement road drainage structure
CN108193717B (en) Inspection well lid capable of automatically lifting and lowering with damping function
CN204781005U (en) Inspection shaft lid with adjustable height
CN206396632U (en) A kind of elevated bridge road surface drainage structure
CN211285929U (en) Prefabricated sewer well cover
CN211080508U (en) Shock attenuation flood discharge scour protection rotatory well lid device
CN208009176U (en) A kind of water penetration urban roadbed
CN209493780U (en) A kind of asphalt paving
CN109083035B (en) Automatically extensible road construction indicating plate applicable to sand blown areas
CN211285126U (en) Environment-friendly garden permeable road structure with rainwater collection function
CN216809430U (en) Town road prevention of seepage project organization
KR200444169Y1 (en) An artificial turf
CN207210889U (en) A kind of double-decker water-permeable brick
CN106836308B (en) A kind of inspection well cover of the anti-tilting of damping
RU75398U1 (en) COVERING OF RAILWAY AND TRAMWAY TRANSFERS
CN110578365A (en) shock attenuation flood discharge scour protection rotatory well lid device

Legal Events