- CN207862991U CN207862991U CN201820132240.0U CN201820132240U CN207862991U CN 207862991 U CN207862991 U CN 207862991U CN 201820132240 U CN201820132240 U CN 201820132240U CN 207862991 U CN207862991 U CN 207862991U
- Authority
- CN
- China
- Prior art keywords
- groove
- basement
- waterproof
- concrete structure
- waterproof layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Floor Finish (AREA)
Abstract
The utility model is related to a kind of basement groove waterproof constructions, belong to hypogee waterproof field, it is set in groove opening up in the concrete structure of floor, the trench wall is provided with waterproof layer, it is provided with filler on the inside of the waterproof layer, it is provided with pipeline architecture in the filler, the waterproof layer includes the sidewall film being arranged in groove two side walls and is arranged counterdie in trench bottom surfaces, the sidewall film upper end is stretched out groove and is fitted in the floor concrete structure of side, the sidewall film lower end is fitted in along trenched side-wall on the bottom surface of groove, the both ends of the counterdie and the lower end of sidewall film overlap.The utility model solves the problems, such as that ground lower groove water suction collapses, and using groove waterproof construction, basement groove is done waterproofing protection, is effectively prevented backfill in groove and sink, protects ground structure.
Description
Technical field
The utility model is related to hypogee waterproof field, more particularly to a kind of basement groove waterproof construction.
Background technology
With the improvement of living standards, the basement structure of urban architecture is more and more, such as underground garage, equipment room,
These Large Underground Structures must carry out water proof structure.Especially some underground pipeline layouts when, need underground room floor dig
If groove, in the trench by pipe installation, in order to protect pipeline, need to carry out water-proofing treatment to pipeline.The prior art
In when carrying out water-proofing treatment, first in the trench by pipe installation, then backfill in the trench, until backfill surface layer and groove
Both sides flush, and then spread waterproof layer on ground, and using this waterproof construction, backfill is easy to absorb the moisture of underground, and occurs
It sink, waterproof layer is caused to sink, room floor cracking in underground destroys ground overall structure.
Utility model content
The purpose of this utility model is to provide a kind of basement groove waterproof constructions, using groove waterproof construction, by ground
Lower room groove does waterproofing protection, is effectively prevented backfill in groove and sink, protects ground structure.
The above-mentioned purpose of the utility model technical scheme is that:
A kind of basement groove waterproof construction is set in groove opening up in the concrete structure of floor, in the groove
Wall is provided with waterproof layer, is provided with filler on the inside of the waterproof layer, pipeline architecture, the waterproof are provided in the filler
Layer includes that the sidewall film in groove two side walls is arranged and the counterdie in trench bottom surfaces is arranged, and the sidewall film upper end is stretched out
Groove is simultaneously fitted in the floor concrete structure of side, and the sidewall film lower end is fitted in along trenched side-wall on the bottom surface of groove,
The both ends of the counterdie and the lower end of sidewall film overlap.
By using above-mentioned technical proposal, wall setting waterproof layer, waterproof layer use two side forms and a bottom in the trench
The three-stage structure of film protects in three faces of groove using waterproof layer, avoids filler from softening because of water suction and sink,
Ensure the stable and firm of ground waterproof structure and other structures;Waterproof layer is turned round using three sections of overlapped connection types in groove
Place carries out the double-deck overlap joint, the case where avoiding a piece of waterproof layer from being laid on corner easy fracture and destroy waterproof layer, corner into
Row Double-protection strengthens waterproof layer structure.
Preferably, separation layer is provided between the waterproof layer and trench wall, the upper end and floor of the separation layer
Concrete structure flushes.
By using above-mentioned technical proposal, separation layer is set, waterproof layer can be protected not press against bad, separation layer by floor concrete structure
Upper end is flushed with floor concrete structure, keeps waterproof layer lap-joint more smooth, reduces the relief height of waterproof layer lap-joint, ground is made to tie
Structure is more smooth.
Preferably, the groove is provided with opening up C-shaped supporting rack, the upper end of the C-shaped supporting rack and face with
Floor concrete structure flushes.
By using above-mentioned technical proposal, waterproof layer is supported by C-shaped supporting rack, waterproof layer is made preferably to be bonded
On the trench walls, C-shaped supporting rack upper end opening facilitates the laying of pipeline, C-shaped supporting rack upper end to be flushed with floor concrete structure, no
Influence the laying of floor concrete structure.
Preferably, the filler and C-shaped supporting rack are contour.
By using above-mentioned technical proposal, ensures that groove is flushed with floor concrete structure, keep the ground structure of laying more smooth.
Preferably, being provided with groove flat film above the C-shaped supporting rack and filler.
The water resistance of groove is further promoted to progress water-proofing treatment above groove by using above-mentioned technical proposal,
Protect the ground structure in the pipeline architecture and groove in groove.
Preferably, the sidewall film upper end is overlapped with the planar film being fitted in the concrete structure of floor.
By using above-mentioned technical proposal, the integral waterproofing ability on groove and its both sides ground is promoted, promotes basement ditch
The water proofing property and fastness of slot structure.
Preferably, the planar film and groove flat film upper surface flush.
By using above-mentioned technical proposal, ground waterproof layer is more smooth, is laid with after superstructure, and superstructure is also more
Add smooth, improves the construction quality of basement.
Preferably, being provided with bed course on the planar film and groove flat film, ground floor is provided on the bed course.
By using above-mentioned technical proposal, bed course is provided on planar film and groove flat film later can be more preferable by waterproof layer
Ground protects, and waterproof layer is avoided to be in direct contact with ground floor, extends the usage time of waterproof layer, preferably improves basement ditch
Waterproof ability at slot.
In conclusion the utility model has the advantages that:
1, the utility model protects in three faces of groove using waterproof layer, and it is soft because of water suction to avoid filler
Change and sink, ensures that the stable and firm of ground waterproof structure and other structures, water resistance improve, extend basement groove structure
Usage time.
2, waterproof layer is carried out the double-deck overlap joint in groove corner, is avoided a piece of waterproof using three sections of overlapped connection types
The case where layer is laid on corner easy fracture and destroys waterproof layer carries out Double-protection in corner, strengthens waterproof layer structure.
3, the upper end of separation layer, C-shaped supporting rack and filler are flushed with floor concrete structure, ensure that in the concrete structure of ground
Smooth with the ground structure on groove, thickness is uniform.
Description of the drawings
Fig. 1 is the schematic diagram of the utility model groove waterproof construction.
In figure, 1, groove;100, floor concrete structure;2, waterproof layer;21, sidewall film;22, counterdie;23, groove flat film;
24, planar film;3, separation layer;4, C-shaped supporting rack;5, filler;6, pipeline architecture;7, bed course;8, ground floor.
Specific implementation mode
The utility model is described in further detail below in conjunction with attached drawing.
The utility model create description in, it is to be understood that term "center", "upper", "lower", "front", "rear",
The orientation or positional relationship of the instructions such as "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside" is based on attached drawing institute
The orientation or positional relationship shown is merely for convenience of description the utility model and creates and simplify description, rather than indicates or imply
Signified device or element must have a particular orientation, with specific azimuth configuration and operation, therefore should not be understood as to this
The limitation of utility model.
A kind of basement groove waterproof construction, as shown in Fig. 1, the waterproof construction are arranged in groove 1, and groove 1 is to dig
The U-shaped structure slot being located in ground concrete structure 100, corner are arc-shaped transition angle.1 inner wall of groove is provided with separation layer
3, separation layer 3 is internally provided with waterproof layer 2, and 2 inside of waterproof layer is filled with the filler 5 for burying groove 1, is buried in filler 5
There are pipeline architecture 6, waterproof layer 2 that filler 5 and pipeline architecture 6 are fully enclosed in the inside of groove 1, better waterproof can be played
Effect prevents trench fill structure from sinking, pipeline architecture 6 is protected not to be corroded.
Specifically, separation layer 3 is fitted on the inner wall of groove 1, both ends, which are stretched out out of groove 1 and bent to both sides, to be bonded
The upper surface of concrete structure 100 on ground, and the upper side of 3 bending part of separation layer and the upper surface of ground concrete structure 100 are neat
It is flat.Waterproof layer 2 includes that fitting is fixed on the sidewall film 21 in 1 two side walls of groove and the counterdie 22 positioned at 1 bottom surface of groove, side wall
The upper end of film 21 is stretched out from 1 opening of groove, is fitted in 100 upper surface of ground concrete structure to side bending, is specifically fitted in
On the upper surface of separation layer 3, the lower end of sidewall film 21 corner of 1 inner wall and is fitted on the bottom surface of groove 1 along groove,
It is specifically fitted on separation layer 3, counterdie 22 is fitted on the bottom surface of groove 1, and both ends are overlapped on along the inner wall of separation layer 3
The lower end of sidewall film 21, and connect with 21 lower end of sidewall film by gluing.
As shown in Fig. 1, after separation layer 3 and waterproof layer 2 install, the inside that groove 1 is located in waterproof layer 2 is installed
There is opening up C-shaped supporting rack 4, C-shaped supporting rack 4 and ground concrete structure 100 are contour, and C-shaped supporting rack 4 is along 1 length of groove
Direction interval, which is arranged and is bonded, to be pressed on waterproof layer 2, for fixing waterproof layer 2.The fillers 5 such as sandstone are filled in groove 1,
The pipeline installation structure 6 in filler 5, filler 5 are tamped after burying pipeline architecture 6 simultaneously, and height reaches and ground
Face concrete structure 100 flushes.
Waterproof layer 2 further includes groove flat film 23 and planar film 24, after structure is laid in groove 1, is supported in C-shaped
The top of frame 4 and filler 5 is laid with groove flat film 23 and covers groove 1, and the splicing of 23 both ends of groove flat film has fitting to fix
Planar film 24 in ground concrete structure 100, planar film 24 and 23 upper surface of groove flat film flush, and planar film 24 overlaps
In the upper end of sidewall film 21, closed waterproof construction is formed in groove 1.
Planar film 24 and 23 top of groove flat film are laid with the bed course 7 to shield, and 7 top of bed course is laid with ground floor 8.
Waterproof layer 2 uses nano modification coiled water-proof polyolefine material, separation layer 3 and bed course 7 to use rubber pad, ground floor 8 in the present embodiment
For concrete layer, C-shaped supporting rack 4 is metal framework.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability
Field technique personnel can as needed make the present embodiment the modification of not creative contribution after reading this specification, but
As long as all being protected by Patent Law in the right of the utility model.
Claims (8)
1. a kind of basement groove waterproof construction, is characterized in that:It is set to floor concrete structure(100)Upper opening up groove
(1)It is interior, the groove(1)Inner wall is provided with waterproof layer(2), the waterproof layer(2)Inside is provided with filler(5), described to fill out
Fill object(5)Inside it is provided with pipeline architecture(6), the waterproof layer(2)Including being arranged in groove(1)Sidewall film in two side walls
(21)And it is arranged in groove(1)The counterdie of bottom surface(22), the sidewall film(21)Groove is stretched out in upper end(1)And it is fitted in side
Floor concrete structure(100)On, the sidewall film(21)Lower end is along groove(1)Side wall is fitted in groove(1)Bottom surface on, institute
State counterdie(22)Both ends and sidewall film(21)Lower end overlap joint.
2. basement groove waterproof construction according to claim 1, it is characterised in that:The waterproof layer(2)With groove(1)
Separation layer is provided between inner wall(3), the separation layer(3)Upper end and floor concrete structure(100)It flushes.
3. basement groove waterproof construction according to claim 1, it is characterised in that:The groove(1)It is provided with opening
C-shaped supporting rack upward(4), the C-shaped supporting rack(4)Upper end and face and floor concrete structure(100)It flushes.
4. basement groove waterproof construction according to claim 3, it is characterised in that:The filler(5)It is supported with C-shaped
Frame(4)It is contour.
5. basement groove waterproof construction according to claim 4, it is characterised in that:The C-shaped supporting rack(4)With filling
Object(5)Top is provided with groove flat film(23).
6. basement groove waterproof construction according to claim 5, it is characterised in that:The sidewall film(21)Upper end overlaps
It is fitted in floor concrete structure(100)On planar film(24).
7. basement groove waterproof construction according to claim 6, it is characterised in that:The planar film(24)It is flat with groove
Facial mask(23)Upper surface flushes.
8. basement groove waterproof construction according to claim 7, it is characterised in that:The planar film(24)It is flat with groove
Facial mask(23)On be provided with bed course(7), the bed course(7)On be provided with ground floor(8).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820132240.0U CN207862991U (en) | 2018-01-25 | 2018-01-25 | Basement groove waterproof construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820132240.0U CN207862991U (en) | 2018-01-25 | 2018-01-25 | Basement groove waterproof construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207862991U true CN207862991U (en) | 2018-09-14 |
Family
ID=63458859
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820132240.0U Active CN207862991U (en) | 2018-01-25 | 2018-01-25 | Basement groove waterproof construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207862991U (en) |
-
2018
- 2018-01-25 CN CN201820132240.0U patent/CN207862991U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103758221B (en) | Roof deformation joint structure of automobile ramp | |
CN214696174U (en) | Waterproof structure of assembled external wall panel joint | |
CN107386298A (en) | A kind of depth hole composite supporting construction and its construction method with water-proof function | |
CN207862991U (en) | Basement groove waterproof construction | |
CN212001285U (en) | Waterproof structure for deformation joint of underground overlong structure | |
CN209873490U (en) | Maintenance device of tunnel road surface percolating water | |
CN212224826U (en) | Vertical shock insulation ditch and outdoor open ditch connected node structure | |
CN211950224U (en) | Heat preservation engineering window node | |
CN208009239U (en) | A kind of type that falls Ω bridge floor longitudinal seam telescopic device | |
TW201226687A (en) | Leak-proof window framework and construction method thereof | |
CN207919877U (en) | A kind of prefabricated GRC assembled wall boards | |
CN112281860A (en) | Lining wall structure and construction method thereof | |
CN206143818U (en) | Novel anticorrosive room build basis | |
CN206986904U (en) | A kind of depth hole composite supporting construction with water-proof function | |
CN219219784U (en) | Underground garage roof expansion joint moldiness construction system | |
CN209873894U (en) | Basement waterproof structure | |
CN213392262U (en) | Tunnel secondary lining water seepage treatment structure | |
CN109140046B (en) | Method for plugging end of pipe jacking pipe curtain | |
CN213418357U (en) | Floor waterproof structure of interlayer drainage toilet | |
CN210395458U (en) | Connection structure of cut-off wall and hydraulic structure | |
CN217128308U (en) | A cut-off wall for loess abrupt slope long distance pipeline | |
CN215292535U (en) | Simple device for preventing water seepage of tunnel settlement joint | |
CN220953934U (en) | Waterproof building | |
CN217782410U (en) | Outer window antiseep edge frame water stop structure | |
CN211037298U (en) | Waterproof type prefabricated building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |