CN207848612U CN201820129833.1U CN201820129833U CN207848612U CN 207848612 U CN207848612 U CN 207848612U CN 201820129833 U CN201820129833 U CN 201820129833U CN 207848612 U CN207848612 U CN 207848612U
Authority
CN
China
Prior art keywords
arc panel
transverse slat
pipeline
antidetonation suspension
sliding block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820129833.1U
Other languages
Chinese (zh)
Inventor
富志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Xasheng Jun Peng Building Engineering Co Ltd
Original Assignee
Shenzhen Xasheng Jun Peng Building Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Xasheng Jun Peng Building Engineering Co Ltd filed Critical Shenzhen Xasheng Jun Peng Building Engineering Co Ltd
Priority to CN201820129833.1U priority Critical patent/CN207848612U/en
Application granted granted Critical
Publication of CN207848612U publication Critical patent/CN207848612U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The utility model is related to a kind of antidetonation suspension and support, drip irrigation devices:It include the hanger on roof;Transverse slat on the hanger for carrying pipeline;Sliding is connected to multigroup sliding block on the transverse slat;Several groups are used to be clamped the arc panel of pipeline on the sliding block;For driving the opposite sliding of the arc panel the first spring of pipeline is clamped on the transverse slat;And for limiting the locating part of the arc panel on the transverse slat, the one end of the arc panel far from the transverse slat is equipped with the fixing piece for the symmetrical arc panel of stationary phase.The antidetonation suspension and support of the utility model when in use, can be adapted to the pipeline of different tube diameters, while can also play the role of certain buffering and damping to the pipeline of clamping, can also reduce certain noise.

Description

A kind of antidetonation suspension and support
Technical field
The utility model is related to technical field of building construction more particularly to a kind of antidetonation suspension and supports.
Background technology
Pipeline is that for conveying, one kind of gas, liquid or the fluid with solid particle is indispensable to be set in the modern life It applies, it is widely used.
In pipe installation process, people would generally be added for pipeline antidetonation suspension and support come when reducing earthquake to the shadow of pipeline It rings, on antidetonation suspension and support, multiple clips can be provided with, be generally first fixed on the wall hanger, then pass through clip high-ranking military officer Road is fixed on antidetonation suspension and support.
But during actual installation pipeline, it will usually which there are the different pipelines of various calibers, need construction personnel It goes to be adapted to these pipelines using the clip of different model, this mounting means process is comparatively laborious, can not only increase workload, also The cost of project installation can be increased.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of antidetonation suspension and support, Neng Goushi Pipeline with different tube diameters, it is cost-effective so as to reduce the amount of labour of staff.
The above-mentioned purpose of the utility model technical scheme is that:
A kind of antidetonation suspension and support, including:Hanger on roof;Cross on the hanger for carrying pipeline Plate;Sliding is connected to multigroup sliding block on the transverse slat;Several groups are used to be clamped the arc panel of pipeline on the sliding block; For driving the opposite sliding of the arc panel the first spring of pipeline is clamped on the transverse slat;And it is set to the cross Locating part on plate for limiting the arc panel, the one end of the arc panel far from the transverse slat are equipped with symmetrical for fixing The arc panel fixing piece.
Using above-mentioned technical proposal, when needing pipe laying, limitation of the locating part to arc panel can be released, at this point, First spring will automatically drive arc panel relative motion, to which pipeline be clamped, and the fixing piece being arranged, it can be in arc It is further together by two arc board lockings, more secured so as to which pipeline to be clamped after shape plate clamps pipeline, By this scheme, it can be adapted to the pipeline of different tube diameters, eliminate this link for installing multiple and different model clips, then Reduce the amount of labour of staff.
The utility model is further arranged:The locating part includes:It is hinged on hooked scarf L-shaped on the transverse slat;With And it is fixed on the shackle to match with the hooked scarf on the sliding block.
Hooked scarf can be rotated, keeps it mutual with shackle when needing to release the limitation to sliding block using above-mentioned technical proposal Separation, the first spring automatically will drive sliding block to move.
The utility model is further arranged:The locating part is the screw rod being interspersed on the transverse slat side, the sliding block Corresponding position offer the jack to match with the screw rod.
Using above-mentioned technical proposal, rotary screw so that the top of screw rod is rotated out of out of sliding block jack, so as to Release the limitation to sliding block.
The utility model is further arranged:The fixing piece includes:The arc panel is fixed on far from transverse slat end Convex block;The inserted link being interspersed between the convex block;And it is threaded in the stop nut of the plunger end.
Using above-mentioned technical proposal, after pipeline is clamped symmetrical arc panel, inserted link can be inserted into symmetrical Between convex block, then rotary stopper nut plays further reinforcing to be fixed together two arc panels to pipeline again Effect.
The utility model is further arranged:The arc panel inner wall opens up fluted, and the groove activity is equipped with and manages The fixture block that road matches, the interior second spring being equipped with for driving the fixture block to be slided along the groove inner wall of the groove.
Using above-mentioned technical proposal, after pipeline is clamped arc panel, the second spring of setting can drive fixture block recessed It freely stretches in slot, further such that arc panel can be adapted to the pipeline of different tube diameters, meanwhile, second spring driving fixture block is stretched Contracting, also have the function of certain buffering and damping to pipeline, can further protective conduit, to extend pipeline use the longevity Life.
The utility model is further arranged:The transverse slat between the symmetrical arc panel is equipped with and arc Shape face.
Using above-mentioned technical proposal, the arcwall face being recessed inwardly is set, the contact area with pipeline can be increased so that pipe Road can be consolidated more between being placed in arc panel.
The utility model is further arranged:Being sticked on the arcwall face has buffer layer.
Using above-mentioned technical proposal, the buffer layer of setting can play further cushioning effect to pipeline, meanwhile, delay Layer is rushed to reduce pipeline with protective conduit and damage there is a situation where friction with transverse slat contact position.
In conclusion the utility model has the advantages that:
By the way that slidable arc panel and locating part is arranged, locating part is released, the first spring can drive arc panel pair Pipeline is clamped, and the fixing piece being arranged, and can further reinforce symmetrical arc panel so that pipeline is clamped more Securely;
By the way that second spring, fixture block and arcwall face is arranged, second spring driving fixture block can play pipeline certain Buffering and cushioning effect, can further be adapted to the pipeline of different tube diameters;And the buffer layer on arcwall face can be together with fixture block It cooperates, it is further to pipeline to be limited so that pipeline is fixed more securely.
Description of the drawings
Fig. 1 is the overall structure diagram of the utility model embodiment 1;
Fig. 2 is the enlarged drawing at A in Fig. 1;
Fig. 3 is the position view of screw rod in the utility model embodiment 2.
Reference numeral:1, hanger;2, transverse slat;21, sliding block;22, the first spring;3, arc panel;31, groove;32, fixture block; 33, second spring;4, hooked scarf;41, shackle;5, screw rod;6, convex block;61, inserted link;62, stop nut;7, arcwall face;8, it buffers Layer.
Specific implementation mode
The utility model is described in further detail below in conjunction with attached drawing.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability Field technique personnel can as needed make the present embodiment the modification for not creating contribution after reading this specification, but only It all to be protected by Patent Law in the right of the utility model.
Embodiment 1:A kind of antidetonation suspension and support includes as depicted in figs. 1 and 2 the hanger 1 on roof or wall; And it is fixed on the transverse slat 2 on hanger 1, transverse slat 2 is used for carrying various pipelines, is slid on transverse slat 2 and is connected at least two groups cunning Block 21, every group of sliding block 21 are symmetrical two, are respectively and fixedly provided with arc panel 3 on each sliding block 21, the arc panel 3 in every group is used for Pipeline is clamped, and sliding block 21 is in the sliding slot opened up on transverse slat 2, and the first spring is further fixed on the inner wall of end of sliding slot 22, the other end and 21 phase of sliding block of the first spring 22 are fixed.
Wherein, it is provided with the locating part for limiting arc panel 3 on transverse slat 2, and is provided on arc panel 3 for fixing The fixing piece of symmetrical arc panel 3, in the present embodiment, locating part includes:End is hinged on hooked scarf L-shaped on transverse slat 2 4;And it is fixed on the shackle 41 to match with hooked scarf 4 on sliding block 21.
Fixing piece includes:Arc panel 3 is fixed on far from the convex block 6 on 2 end of transverse slat;Be interspersed in symmetrical convex block 6 it Between inserted link 61;And it is threaded in the stop nut 62 of 61 end of inserted link.
When needing that pipeline is fixed, pipeline can be made to be between symmetrical arc panel 3, then by hooked scarf 4 from It is taken away in shackle 41, releases the limitation to sliding block 21, at this point, the first spring 22 will utilize the restoring force of itself, automatically driven Movable slider 21 drives arc panel 3 to slide so that arc panel 3 clamps pipeline;Then, inserted link 61 is inserted into symmetrical convex block Between 6, in the end turn-knob upper limit nut 62 of inserted link 61, you can two arc panels 3 are fixed together, thus very by pipeline Firmly be clamped between arc panel 3, through the above scheme, can so that arc panel 3 be adapted to different tube diameters pipeline, to Process when Pipe installing can be simplified, further decrease the workload of staff.
It is further opened with groove 31 in the inner wall of arc panel 3, it is movable in groove 31 to be equipped with the fixture block to match with pipeline 32, and the inner wall of groove 31 is fixed with second spring 33, the inner end phase of the one end of second spring 33 far from groove 31 and fixture block 32 It is fixed.After pipeline is clamped arc panel 3, second spring 33 can drive fixture block 32 freely to stretch in groove 1, further Arc panel 3 is allow to be adapted to the pipeline of different tube diameters;Meanwhile second spring 33 drives fixture block 32 flexible, also has to pipeline The effect of certain buffering and damping, can further protective conduit, to extend the service life of pipeline.
Wherein, be equipped with the arcwall face 7 that is recessed inwardly on 2 loading end of transverse slat between arc panel 3, arcwall face 7 with pipe When road is in contact, the contact area with pipeline can be increased so that pipeline can be consolidated more between being placed in arc panel 3;Separately Outside, being also sticked on arcwall face 7 has buffer layer 8, and in the present embodiment, buffer layer 8 is flexible sheet rubber, sheet rubber pair Pipeline can play further cushioning effect, be protected at the same time it can also the outer wall to pipeline, to reduce pipeline and cross The case where contact position of plate 2 is damaged due to friction.
Embodiment 2:As shown in figure 3, difference from example 1 is that the difference of locating part limits in the present embodiment Position part be the screw rod 5 being interspersed on 2 side of transverse slat, and on the corresponding position of sliding block 21, offer with screw rod 5 match insert Hole.
It, can be with rotary screw 5 when needing using arc panel 3 so that the end of screw rod 5 and the jack phase on sliding block 21 point From so that the first spring 22 driving sliding block 21 slides.

Claims (7)

1. a kind of antidetonation suspension and support, which is characterized in that including:Hanger on roof(1);
Set on the hanger(1)On transverse slat for carrying pipeline(2);
Sliding is connected to the transverse slat(2)On multigroup sliding block(21);
Mounted on the sliding block(21)Upper several groups are used to be clamped the arc panel of pipeline(3);
Set on the transverse slat(2)On for driving the arc panel(3)Opposite sliding is to be clamped the first spring of pipeline(22);With And it is set to the transverse slat(2)On for limiting the arc panel(3)Locating part, the arc panel(3)Far from the transverse slat (2)One end be equipped with for the symmetrical arc panel of stationary phase(3)Fixing piece.
2. a kind of antidetonation suspension and support according to claim 1, which is characterized in that the locating part includes:It is hinged on described Transverse slat(2)Upper L-shaped hooked scarf(4);And it is fixed on the sliding block(21)The upper and hooked scarf(4)The shackle to match (41).
3. a kind of antidetonation suspension and support according to claim 1, which is characterized in that the locating part is to be interspersed in the transverse slat (2)Screw rod on side(5), the sliding block(21)Corresponding position offer and the screw rod(5)The jack to match.
4. a kind of antidetonation suspension and support according to claim 1, which is characterized in that the fixing piece includes:It is fixed on described Arc panel(3)Far from transverse slat(2)Convex block on end(6);It is interspersed in the convex block(6)Between inserted link(61);And screw thread It is connected to the inserted link(61)The stop nut of end(62).
5. a kind of antidetonation suspension and support according to claim 1, which is characterized in that the arc panel(3)Inner wall offers recessed Slot(31), the groove(31)Activity is equipped with the fixture block to match with pipeline(32), the groove(31)It is interior to be equipped with for driving Move the fixture block(32)Along the groove(31)The second spring of inner wall sliding(33).
6. a kind of antidetonation suspension and support according to claim 1, which is characterized in that be located at the symmetrical arc panel(3) Between the transverse slat(2)It is equipped with and arcwall face(7).
7. a kind of antidetonation suspension and support according to claim 6, which is characterized in that the arcwall face(7)On be sticked and have buffering Layer(8).
CN201820129833.1U 2018-01-24 2018-01-24 A kind of antidetonation suspension and support Expired - Fee Related CN207848612U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820129833.1U CN207848612U (en) 2018-01-24 2018-01-24 A kind of antidetonation suspension and support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820129833.1U CN207848612U (en) 2018-01-24 2018-01-24 A kind of antidetonation suspension and support

Publications (1)

Publication Number Publication Date
CN207848612U true CN207848612U (en) 2018-09-11

Family

ID=63412411

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820129833.1U Expired - Fee Related CN207848612U (en) 2018-01-24 2018-01-24 A kind of antidetonation suspension and support

Country Status (1)

Country Link
CN (1) CN207848612U (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109659854A (en) * 2018-11-09 2019-04-19 国网浙江杭州市余杭区供电有限公司 A kind of fixed device of drainage thread for distribution line live working
CN110131483A (en) * 2019-04-18 2019-08-16 江苏唯斯安建筑科技有限公司 A kind of antidetonation suspension and support
CN110486534A (en) * 2019-08-16 2019-11-22 镇江市云鹏电器有限公司 A kind of locking suspension and support of convenient disassembly
CN111503378A (en) * 2020-04-14 2020-08-07 江苏奇佩建筑装配科技有限公司 Adjustable pipeline support hanger
CN111853150A (en) * 2020-07-08 2020-10-30 合肥元康环境科技有限公司 Bridge lateral rigid anti-seismic support system
CN112755430A (en) * 2019-10-21 2021-05-07 江苏固泰建筑材料科技有限公司 Anti-seismic finished product support and hanger for fire sprinkler pipe
CN113819304A (en) * 2021-08-22 2021-12-21 芜湖中燃城市燃气发展有限公司 Liquefied gas conveying pipeline supporting device and method
CN114440007A (en) * 2022-04-11 2022-05-06 河南工学院 A prop up and hang device for electromechanical device installation
CN114593275A (en) * 2022-03-25 2022-06-07 安徽英标新材料科技有限公司 Corrosion-resistant drain pipe and using method thereof

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109659854A (en) * 2018-11-09 2019-04-19 国网浙江杭州市余杭区供电有限公司 A kind of fixed device of drainage thread for distribution line live working
CN109659854B (en) * 2018-11-09 2020-10-27 国网浙江杭州市余杭区供电有限公司 A drainage line fixing device for distribution lines live working
CN110131483A (en) * 2019-04-18 2019-08-16 江苏唯斯安建筑科技有限公司 A kind of antidetonation suspension and support
CN110486534A (en) * 2019-08-16 2019-11-22 镇江市云鹏电器有限公司 A kind of locking suspension and support of convenient disassembly
CN112755430A (en) * 2019-10-21 2021-05-07 江苏固泰建筑材料科技有限公司 Anti-seismic finished product support and hanger for fire sprinkler pipe
CN112755430B (en) * 2019-10-21 2022-01-18 江苏固泰建筑材料科技有限公司 Anti-seismic finished product support and hanger for fire sprinkler pipe
CN111503378A (en) * 2020-04-14 2020-08-07 江苏奇佩建筑装配科技有限公司 Adjustable pipeline support hanger
CN111853150A (en) * 2020-07-08 2020-10-30 合肥元康环境科技有限公司 Bridge lateral rigid anti-seismic support system
CN113819304A (en) * 2021-08-22 2021-12-21 芜湖中燃城市燃气发展有限公司 Liquefied gas conveying pipeline supporting device and method
CN114593275A (en) * 2022-03-25 2022-06-07 安徽英标新材料科技有限公司 Corrosion-resistant drain pipe and using method thereof
CN114440007A (en) * 2022-04-11 2022-05-06 河南工学院 A prop up and hang device for electromechanical device installation
CN114440007B (en) * 2022-04-11 2022-08-09 河南工学院 A prop up and hang device for electromechanical device installation

Similar Documents

Publication Publication Date Title
CN207848612U (en) A kind of antidetonation suspension and support
EP2060468A3 (en) Overhead conveyer system with side buffer storage fixed on the guiding rails, and method for fixing said storage buffer
CN207504492U (en) A kind of telescopic cable testing bridge
ATE242379T1 (en) ROOF AND CEILING SYSTEM FOR FLAT ROOF BUILDINGS
CN209041771U (en) A kind of comprehensive suspension and support of gate antidetonation
CN207582782U (en) A kind of keel installation structure
CN214368233U (en) Heating pipe clamping device with adjustable tension force
CN208474666U (en) A kind of suspension and support being easily installed
WO2008113915A3 (en) System for attaching a non perfectly stretched suspended partition
CN217927526U (en) Pipeline vibration damper
CN208263393U (en) Anti-deviation device for PVC pipe production line
CN207406919U (en) A kind of pipe clamp type sunpender hanger
CN208202293U (en) A kind of indoor decoration ceiling mounting structure
CN105571016B (en) Connecting pipe assembly and air conditioning system
CN210950223U (en) Adjustable anti-seismic support
CN207569356U (en) A kind of utility unit of the shockproof pipe clamp of Level tune
CN108089672A (en) One kind is based on hard disc of computer clamping structure
CN210980980U (en) Do benefit to pipe case cleaning equipment of installation space optimization
CN210599979U (en) Rubber shock absorber for front shock absorber
CN208417768U (en) Building pipe ruggedized construction
CN211080397U (en) Anti-condensation structure of building water supply and drainage pipeline
CN202484011U (en) Detachable pipe clip
CN208901487U (en) A kind of smoking cover with supporting and locating functions
CN208864190U (en) Robot security's system for cleaning glass window window
CN112923143A (en) Can be according to chain clamp of construction size automatic change fastening size

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180911

Termination date: 20220124