CN207835019U - A kind of interim cover board - Google Patents
A kind of interim cover board Download PDFInfo
- Publication number
- CN207835019U CN207835019U CN201721858717.5U CN201721858717U CN207835019U CN 207835019 U CN207835019 U CN 207835019U CN 201721858717 U CN201721858717 U CN 201721858717U CN 207835019 U CN207835019 U CN 207835019U
- Authority
- CN
- China
- Prior art keywords
- inserted link
- sub
- assembly
- slot
- connecting bracket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Details Of Indoor Wiring (AREA)
Abstract
The utility model discloses a kind of interim cover boards, including the first sub-assembly and the second sub-assembly, wherein the first sub-assembly includes the first connecting bracket and the inserted link for being connected to the first connecting bracket, which can be arranged one, can also be arranged multiple;Second sub-assembly includes the second connecting bracket and the counterpart for being connected to the second connecting bracket, the slot for coordinating with inserted link is formed on counterpart, inserted link coordinates with slot combines the first sub-assembly with the second sub-assembly, slot can be corresponded with inserted link to be coordinated, also can a slot correspond to multiple inserted links, inserted link be only capable of from slot it is open-ended from pass in and out so as to which stable loading end can be formed after inserted link and counterpart cooperation;It can be seen that above-mentioned interim cover board, simple in structure, at low cost for monoblock steel plate convenient for making, light-weight, easy to carry and use, and the cable duct of different in width can be adapted to by adjusting the insertion depth of inserted link, it is versatile.
Description
Technical field
The utility model is related to construction of transformer substation technical field, more particularly to a kind of interim cover board.
Background technology
To prevent construction worker from accidentally falling into cable duct, it is necessary in the construction process to cable duct be capped interim cover board with
Carry out hole protection.
Currently, mostly cable duct is protected using monoblock steel plate as interim cover board, however since cable duct is longer and each
Function house cable ditch size is different, and higher using monoblock steel plate as interim cover board cost, weight is big, is not easy to carry, and
It cannot be adjusted, poor universality according to cable duct change in size.
Therefore, how to improve covering plate structure, keep its of low cost, versatility is good, is easy to use, becomes people in the art
Member's important technological problems urgently to be resolved hurrily.
Utility model content
In view of this, the purpose of this utility model is to provide a kind of interim cover boards, so that its is of low cost, versatility
It is good, it is easy to use.
To achieve the above object, the utility model provides the following technical solutions:
A kind of interim cover board, including:
First sub-assembly, including the first connecting bracket and the inserted link for being connected to first connecting bracket;
Second sub-assembly, including the second connecting bracket and the counterpart for being connected to second connecting bracket, it is described to match
Be formed with the slot for coordinating with the inserted link on component, the inserted link and slot cooperation will first sub-assembly and
Second sub-assembly combination, and the inserted link be only capable of from the slot it is open-ended from pass in and out.
Preferably, the inserted link is provided with a plurality of, spaced and parallel be abreast connected to first connecting bracket.
Preferably, the counterpart includes multiple sleeves, and the inner cavity of the sleeve is the slot coordinated with the inserted link, more
A sleeve is spaced and parallel is abreast connected to second connecting bracket.
Preferably, second sub-assembly further include reinforce rib, the reinforcement rib across multiple sleeves and with
Multiple sleeves are all connected with.
Preferably, the end of the inserted link is formed with guide frame.
To achieve the above object, interim cover board provided by the utility model, including the first sub-assembly and the second sub-assembly,
Wherein, the first sub-assembly includes the first connecting bracket and the inserted link for being connected to the first connecting bracket, which can be arranged one
It is a, it can also be arranged multiple;Second sub-assembly includes the second connecting bracket and the counterpart for being connected to the second connecting bracket, is matched
The slot for coordinating with inserted link is formed on component, inserted link coordinates with slot combines the first sub-assembly with the second sub-assembly,
Slot can be corresponded with inserted link to be coordinated, also can a slot correspond to multiple inserted links, inserted link be only capable of from slot it is open-ended from
It passes in and out so as to which stable loading end can be formed after inserted link and counterpart cooperation;It can be seen that above-mentioned interim cover board, structure letter
It is single, at low cost for monoblock steel plate convenient for making, light-weight, easy to carry and use, and can be by adjusting slotting
The insertion depth of bar is versatile to adapt to the cable duct of different in width.
Description of the drawings
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment
Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only
It is some embodiments of the utility model, for those of ordinary skill in the art, in the premise not made the creative labor
Under, other drawings may also be obtained based on these drawings.
Fig. 1 is the structural schematic diagram for the first sub-assembly that the utility model embodiment provides;
Fig. 2 is the structural schematic diagram for the second sub-assembly that the utility model embodiment provides;
Fig. 3 is the structural schematic diagram for the interim cover board that the utility model embodiment provides.
In figure:
1 is the first sub-assembly;101 be the first connecting bracket;102 be inserted link;2 be the second sub-assembly;201 be the second connection
Holder;202 be counterpart;202a is slot;203 be reinforcement rib.
Specific implementation mode
The purpose of this utility model is to provide a kind of interim cover board, the structure design of the interim cover board can reduce cable
With cable by position contact friction, for both protection is provided, improve unfolding efficiency.
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
The every other embodiment obtained, shall fall within the protection scope of the present invention.
- Fig. 3 is please referred to Fig.1, Fig. 1 is the structural schematic diagram for the first sub-assembly that the utility model embodiment provides, and Fig. 2 is
The structural schematic diagram for the second sub-assembly that the utility model embodiment provides, Fig. 3 provide interim for the utility model embodiment
The structural schematic diagram of cover board.
A kind of interim cover board that the utility model embodiment provides, including the first sub-assembly 1 and the second sub-assembly 2.
Wherein, the first sub-assembly 1 includes the first connecting bracket 101 and the inserted link for being connected to the first connecting bracket 101
102, which can be arranged one, can also be arranged multiple;Second sub-assembly 2 includes the second connecting bracket 201 and connects
It is connected to the counterpart 202 of the second connecting bracket 201, the slot 202a for coordinating with inserted link 102 is formed on counterpart 202,
Inserted link 102 combines the first sub-assembly 1 with the second sub-assembly 2 with slot 202a cooperations, and slot 202a can be a pair of with inserted link 102 1
Should coordinate, also can a slot 202a correspond to multiple inserted links 102, inserted link 102 be only capable of from slot 202a it is open-ended from pass in and out
So that inserted link 102 can form stable loading end after coordinating with counterpart 202.
Compared with prior art, interim cover board provided by the utility model, it is simple in structure, convenient for making, relative to monoblock
It is at low cost for steel plate, light-weight, easy to carry and use, in use, can be by adjusting the insertion depth of inserted link 102
It is versatile to adapt to the cable duct of different in width.
As described above, 102 quantity of inserted link can be arranged one, can also be arranged it is a plurality of, in the utility model embodiment,
As shown in Figure 1-Figure 3, inserted link 102 is provided with a plurality of, spaced and parallel be abreast connected to the first connecting bracket 101.
With above structure correspondingly, in the utility model embodiment, counterpart 202 include multiple sleeves, sleeve with
Inserted link 102 corresponds, and the inner cavity of sleeve is the slot 202a coordinated with inserted link 102, multiple sleeves it is spaced and it is parallel simultaneously
It is connected to the second connecting bracket 201 to row.
Specifically, in the utility model embodiment, the first connecting bracket 101 and the second connecting bracket 201 are angle
Iron, inserted link 102 are reinforcing bar, and sleeve is steel pipe.
In actual use, interim cover board can be only made of first sub-assembly 1 and second sub-assembly 2,
It can be constituted with first sub-assembly 1 and two the second sub-assemblies 2 or second sub-assembly 2 and two the first sub-assemblies 1
It constitutes.
Above-mentioned technical proposal is advanced optimized, in the utility model embodiment, the second sub-assembly 2 further includes reinforcing rib
203, reinforce rib 203 and be all connected with across multiple sleeves and with multiple sleeves, to improve the bearing capacity of interim cover board.
Preferably, in the utility model embodiment, the end of inserted link 102 is formed with guide frame.
Each embodiment is described by the way of progressive in this specification, the highlights of each of the examples are with other
The difference of embodiment, just to refer each other for identical similar portion between each embodiment.
The foregoing description of the disclosed embodiments enables professional and technical personnel in the field to realize or use this practicality new
Type.Various modifications to these embodiments will be apparent to those skilled in the art, and determine herein
The General Principle of justice can be realized in other embodiments without departing from the spirit or scope of the present utility model.Cause
This, the utility model is not intended to be limited to the embodiments shown herein, and is to fit to and principles disclosed herein
The widest range consistent with features of novelty.
Claims (5)
1. a kind of interim cover board, which is characterized in that including:
First sub-assembly, including the first connecting bracket and the inserted link for being connected to first connecting bracket;
Second sub-assembly, including the second connecting bracket and the counterpart for being connected to second connecting bracket, the counterpart
On be formed with slot for coordinating with the inserted link, the inserted link and the slot coordinate by first sub-assembly with it is described
Second sub-assembly combine, and the inserted link be only capable of from the slot it is open-ended from pass in and out.
2. interim cover board according to claim 1, which is characterized in that the inserted link be provided with it is a plurality of, it is spaced and flat
Row is abreast connected to first connecting bracket.
3. interim cover board according to claim 2, which is characterized in that the counterpart includes multiple sleeves, the sleeve
Inner cavity be the slot coordinated with the inserted link, multiple sleeves are spaced and parallel be abreast connected to described second and connect
Connect holder.
4. interim cover board according to claim 3, which is characterized in that second sub-assembly further includes reinforcing rib, institute
Reinforcement rib is stated to be all connected with across multiple sleeves and with multiple sleeves.
5. interim cover board according to any one of claims 1-4, which is characterized in that the end of the inserted link, which is formed with, leads
To structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721858717.5U CN207835019U (en) | 2017-12-27 | 2017-12-27 | A kind of interim cover board |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721858717.5U CN207835019U (en) | 2017-12-27 | 2017-12-27 | A kind of interim cover board |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207835019U true CN207835019U (en) | 2018-09-07 |
Family
ID=63389920
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721858717.5U Expired - Fee Related CN207835019U (en) | 2017-12-27 | 2017-12-27 | A kind of interim cover board |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207835019U (en) |
-
2017
- 2017-12-27 CN CN201721858717.5U patent/CN207835019U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207835019U (en) | A kind of interim cover board | |
CN204071054U (en) | A kind of free splicing work in combination platform | |
CN204793913U (en) | Multi -purpose cable equipment fixing device | |
CN205006309U (en) | Wardrobe main part | |
CN201289927Y (en) | Combined connector connected through clip connection mode | |
CN105071016B (en) | A kind of antenna holder | |
CN208325110U (en) | A kind of novel ceiling cabling bracket | |
CN103618236B (en) | A kind of secondary wiring flattening device | |
CN204551887U (en) | A kind of lightweight section structure spandrel girder | |
CN207999852U (en) | Gas-cooker | |
CN207225397U (en) | A kind of logistics roll container | |
CN206813556U (en) | One kind is laid bricks storage device | |
CN207339218U (en) | A kind of U-shaped card fitting | |
CN207053098U (en) | A kind of cruciate flower cable tray connector | |
CN206912544U (en) | A kind of H profile steel guide conveying appliance for bonding machine | |
CN204676840U (en) | A kind of Novel wrapped edge | |
CN103671369A (en) | Right angle connector for aluminum alloy framework | |
CN205155660U (en) | Combination formula fluorescent tube and cap structure thereof | |
CN207053097U (en) | A kind of cable tray connector | |
CN215491715U (en) | Follow-on engineering survey pay-off | |
CN104944279B (en) | Hook gear for crane | |
CN203205634U (en) | Fixing structure of USB port | |
CN209876226U (en) | Rotary joint extension structure | |
CN203292514U (en) | Stepped lathe tool padding blade for lathe | |
CN218050938U (en) | Positioning mechanism and truss-like welding robot |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180907 Termination date: 20181227 |
|
CF01 | Termination of patent right due to non-payment of annual fee |