CN207829891U - A kind of preventing mean of Tunnel Base deformation - Google Patents

A kind of preventing mean of Tunnel Base deformation Download PDF

Info

Publication number
CN207829891U
CN207829891U CN201820251002.1U CN201820251002U CN207829891U CN 207829891 U CN207829891 U CN 207829891U CN 201820251002 U CN201820251002 U CN 201820251002U CN 207829891 U CN207829891 U CN 207829891U
Authority
CN
China
Prior art keywords
tunnel
horizontal drilling
preventing mean
horizontal
base deformation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820251002.1U
Other languages
Chinese (zh)
Inventor
陶伟明
王磊
余大龙
宋洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201820251002.1U priority Critical patent/CN207829891U/en
Application granted granted Critical
Publication of CN207829891U publication Critical patent/CN207829891U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses a kind of preventing means of Tunnel Base deformation, including the bore operation cavity in tunnel one or both sides is arranged, and the horizontal drilling being drilled with from the operation cavity along tunnel lateral direction direction, and the inner wall of the horizontal drilling is equipped with branch pillar.Bore operation cavity is arranged in tunnel one or both sides in the present apparatus, then is drilled with horizontal drilling by operation cavity, convenient for construction and maintenance;The horizontal drilling of the present apparatus is arranged along tunnel longitudinal direction, pass through the shrinkage deformation of horizontal drilling, to provide deformation space to the tunnel bottom country rock in entire tunnel longitudinal extent, so as to reduce the country rock dilatation caused by surrouding rock stress adjusts, achieve the purpose that eliminate tunnel arching of bottom, the deformation of control tunnel bottom;Horizontal drilling that the present apparatus is equipped with while stress release is played, the effect that Tunnel Base load destroys tunnel inverted arch during reducing operation is effectively controlled the construction and operations risks that complicated geological Tunnel Base arches up.

Description

A kind of preventing mean of Tunnel Base deformation
Technical field
The utility model is related to Environment in Railway Engineering Construction technical field, especially a kind of preventing mean of Tunnel Base deformation.
Background technology
High-speed railway is high to Track regularity requirement, if orbital forcing is bad, will cause rolling stock high vibration, Wheel-rail dynamic interaction increases exponentially, and seriously endangers track and rolling stock component, influences the raising of train speed, or even be easy to draw It plays train derailing to topple, jeopardizes traffic safety.Currently, China express railway all uses non-fragment orbit pattern, non-fragment orbit to be laid with At tunnel, the excavation in tunnel destroys the original original stress equilibrium state of tunnel bottom country rock, and tunnel bottom country rock needs new by a wheel After the Stress relief phase, original stress equilibrium state can be just reentered.During at tunnel bottom, country rock carries out Stress relief, surrouding rock stress Adjustment expansive rock can be caused to expand, to country rock volume generate Partial Incremental, cause non-fragment orbit tunnel bottom generate it is upwardly-deformed (on Arch), seriously affect the ride comfort of high speed railway track.
The ride comfort of existing track circuit is mainly adjusted by fastener, but the maximum adjustment amount of fastener is limited.When When the arch deflection at track tunnel bottom is more than fastener maximum adjustment amount, the ride comfort of circuit can not be ensured, railway will be influenced Transport order, or even jeopardize traffic safety.It what technical measures to avoid or eliminate tunnel arching of bottom using, realize the deformation control of tunnel bottom System is a significant technology issues of urgent need to resolve.
Utility model content
The goal of the invention of the utility model is:For it is of the existing technology be adjusted by fastener when, work as track When the arch deflection at tunnel bottom is more than fastener maximum adjustment amount, the problem of ride comfort of circuit can not be ensured, one kind is provided The preventing mean of Tunnel Base deformation.
To achieve the goals above, the technical solution adopted in the utility model is:
A kind of preventing mean of Tunnel Base deformation, including the bore operation cavity in tunnel one or both sides is set, with And the horizontal drilling being drilled with from the operation cavity along tunnel lateral direction direction, the horizontal drilling are horizontally disposed, and The inner wall of the horizontal drilling is equipped with branch pillar.
Bore operation cavity is arranged in tunnel one or both sides in the present apparatus, then is drilled with horizontal drilling by operation cavity, just In construction and maintenance.All horizontal drillings of the present apparatus are arranged along tunnel longitudinal direction, by the shrinkage deformation of horizontal drilling, come Enough deformation spaces are provided to the tunnel bottom country rock in entire tunnel longitudinal extent, so as to reduce because surrouding rock stress adjustment causes Country rock dilatation, achieve the purpose that eliminate tunnel arching of bottom, the deformation of control tunnel bottom.It horizontal drilling that the present apparatus is equipped with while rising Stress release is arrived, the effect that Tunnel Base load destroys tunnel inverted arch during reducing operation is effectively controlled intricately The construction of matter Tunnel Base arch and operations risks, are greatly saved the regulation maintenance cost of later stage tunnel inverted arch arch, are anti- Only complicated geological Tunnel Base arch design provides scientific basis, ensure that the safety of constructing tunnel and operation, makes tunnel Design is more reasonable, safe and reliable.
As the preferred embodiment of the utility model, the direction of all horizontal drilling settings is each perpendicular to tunnel longitudinal direction side To being arranged on the cross section in tunnel.
As the preferred embodiment of the utility model, the underface of the horizontal drilling setting supporting in the early stage, and the water The length in flat drill hole is more than the lateral length in the tunnel, empty with the deformation for providing tunnel bottom country rock within the scope of entire tunnel lateral direction Between.
As the preferred embodiment of the utility model, several water are equipped on the different height of the same cross section in tunnel Flat drill hole.By the way that more horizontal drillings are arranged, the deformation space of bigger can be provided for tunnel bottom country rock, reach elimination tunnel arching of bottom, Control the purpose of tunnel bottom deformation.
As the preferred embodiment of the utility model, the direction of a part of horizontal drilling setting is perpendicular to tunnel longitudinal direction side To the direction that horizontal drilling described in another part is arranged favours tunnel longitudinal direction, that is, favours the cross section setting in tunnel.
As the preferred embodiment of the utility model, all horizontal drillings are uniformly arranged along tunnel longitudinal direction.
As the preferred embodiment of the utility model, the operation cavity is equipped with openable and closable door with tunnel junction, convenient Detect the stress result of stress section, the work such as easy access.
As the preferred embodiment of the utility model, several foil gauges are equipped in the branch pillar, to answer branch pillar Power situation is detected, and when the stress of branch pillar stress section tends towards stability, illustrates that the deformation at tunnel bottom is smaller, and tunnel bottom country rock is completed The Stress relief of a new round, has reentered original stress equilibrium state, it is contemplated that close to horizontal drilling.
As the preferred embodiment of the utility model, a diameter of 10cm-30cm of the horizontal drilling.
As the preferred embodiment of the utility model, the branch pillar is pvc pipe or steel pipe.
In conclusion by adopting the above-described technical solution, the utility model has the beneficial effects that:
Bore operation cavity is arranged in tunnel one or both sides in the present apparatus, then is drilled with horizontal drilling by operation cavity, just In construction and maintenance.All horizontal drillings of the present apparatus are arranged along tunnel longitudinal direction, by the shrinkage deformation of horizontal drilling, come Enough deformation spaces are provided to the tunnel bottom country rock in entire tunnel longitudinal extent, so as to reduce because surrouding rock stress adjustment causes Country rock dilatation, achieve the purpose that eliminate tunnel arching of bottom, the deformation of control tunnel bottom.It horizontal drilling that the present apparatus is equipped with while rising Stress release is arrived, the effect that Tunnel Base load destroys tunnel inverted arch during reducing operation is effectively controlled intricately The construction of matter Tunnel Base arch and operations risks, are greatly saved the regulation maintenance cost of later stage tunnel inverted arch arch, are anti- Only complicated geological Tunnel Base arch design provides scientific basis, ensure that the safety of constructing tunnel and operation, makes tunnel Design is more reasonable, safe and reliable.
Description of the drawings
Fig. 1 is the structural schematic diagram of the preventing mean of Tunnel Base deformation described in the utility model.
It is marked in figure:1- tunnels bottom country rock, 2- preliminary bracings, 3- secondary linings, 4- inverted arch filled layers, 5- road bed boards, 6- rails Pillow, 7- non-fragment orbits, 8- operation cavitys, 9- horizontal drillings.
Specific implementation mode
Below in conjunction with the accompanying drawings, the utility model is described in detail.
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and implementation Example, the present invention will be further described in detail.It should be appreciated that specific embodiment described herein is only explaining this Utility model is not used to limit the utility model.
As shown in Figure 1, non-fragment orbit tunnel bottom point includes mainly tunnel bottom country rock 1, set successively above tunnel bottom country rock 1 There are preliminary bracing 2, secondary lining 3, inverted arch filled layer 4, then be laid with road bed board 5 on the inverted arch filled layer 4, in the railway roadbed Plate 5 is equipped with sleeper 6, and non-fragment orbit 7 is equipped on the sleeper 6.
The preventing mean of a kind of Tunnel Base deformation, including the bore operation cavity 8 in tunnel side is set, and from institute State the horizontal drilling 9 for a diameter of 10cm-30cm that operation cavity 8 is drilled with along tunnel lateral direction direction, all horizontal brills Hole 9 is uniformly arranged along tunnel longitudinal direction, and the inner wall of the horizontal drilling 9 be equipped with branch pillar, the branch pillar be pvc pipe or Steel pipe, the branch pillar is interior to be equipped with several foil gauges.The operation cavity 8 is equipped with openable and closable door with tunnel junction, convenient Detect the stress result of stress section, the work such as easy access.
The underface of supporting in the early stage 2 is arranged in the horizontal drilling 9, and the direction of all horizontal drillings 9 setting is equal Perpendicular to tunnel longitudinal direction, the length of the horizontal drilling 9 is more than the lateral length in the tunnel, in the same cross section in tunnel Different height be equipped with several horizontal drillings 9.
Bore operation cavity is arranged in tunnel side in the present apparatus, then is drilled with horizontal drilling by operation cavity, convenient for construction And maintenance.The horizontal drilling of the present apparatus is uniformly arranged along tunnel longitudinal direction, by the shrinkage deformation of horizontal drilling, to entire Tunnel bottom country rock in tunnel longitudinal extent provides enough deformation spaces, so as to reduce the country rock caused by surrouding rock stress adjusts Dilatation achievees the purpose that eliminate tunnel arching of bottom, the deformation of control tunnel bottom.Horizontal drilling that the present apparatus is equipped with while playing is answered Power discharges, and the effect that Tunnel Base load destroys tunnel inverted arch during reducing operation is effectively controlled complicated geological tunnel The construction of substrate arch and operations risks, are greatly saved the regulation maintenance cost of later stage tunnel inverted arch arch, to prevent complexity The arch design of geology Tunnel Base provides scientific basis, ensure that the safety of constructing tunnel and operation, makes Tunnel Design more Adduction is managed, is safe and reliable.
The above is only the preferred embodiment of the utility model only, is not intended to limit the utility model, all at this All any modification, equivalent and improvement etc., should be included in the utility model made by within the spirit and principle of utility model Protection domain within.

Claims (10)

1. a kind of preventing mean of Tunnel Base deformation, which is characterized in that including the drilling work in tunnel one or both sides is arranged Industry cavity (8), and the horizontal drilling (9) that is drilled with from the operation cavity (8) along tunnel lateral direction direction, and the level The inner wall of drilling (9) is equipped with branch pillar.
2. a kind of preventing mean of Tunnel Base deformation according to claim 1, which is characterized in that all horizontal brills The direction of hole (9) setting is each perpendicular to tunnel longitudinal direction.
3. a kind of preventing mean of Tunnel Base deformation according to claim 2, which is characterized in that the horizontal drilling (9) underface of setting supporting in the early stage (2), and the length of the horizontal drilling (9) is more than the lateral length in the tunnel.
4. a kind of preventing mean of Tunnel Base deformation according to claim 2, which is characterized in that same transversal in tunnel The different height in face is equipped with several horizontal drillings (9).
5. a kind of preventing mean of Tunnel Base deformation according to claim 1, which is characterized in that a part of level Drill (9) setting direction perpendicular to tunnel longitudinal direction, the direction of horizontal drilling (9) setting described in another part favours tunnel Road longitudinal direction.
6. a kind of preventing mean of Tunnel Base deformation according to claim 1, which is characterized in that all horizontal brills Hole (9) is uniformly arranged along tunnel longitudinal direction.
7. a kind of preventing mean of Tunnel Base deformation according to claim 1, which is characterized in that the operation cavity (8) it is equipped with openable and closable door with tunnel junction.
8. a kind of preventing mean of Tunnel Base deformation according to claim 1, which is characterized in that set in the branch pillar There are several foil gauges.
9. a kind of preventing mean of Tunnel Base deformation according to claim 1, which is characterized in that the horizontal drilling (9) a diameter of 10cm-30cm.
10. according to a kind of preventing mean of any Tunnel Base deformations of claim 1-9, which is characterized in that the branch Pillar is pvc pipe or steel pipe.
CN201820251002.1U 2018-02-11 2018-02-11 A kind of preventing mean of Tunnel Base deformation Active CN207829891U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820251002.1U CN207829891U (en) 2018-02-11 2018-02-11 A kind of preventing mean of Tunnel Base deformation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820251002.1U CN207829891U (en) 2018-02-11 2018-02-11 A kind of preventing mean of Tunnel Base deformation

Publications (1)

Publication Number Publication Date
CN207829891U true CN207829891U (en) 2018-09-07

Family

ID=63397829

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820251002.1U Active CN207829891U (en) 2018-02-11 2018-02-11 A kind of preventing mean of Tunnel Base deformation

Country Status (1)

Country Link
CN (1) CN207829891U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110617077A (en) * 2019-09-20 2019-12-27 中铁十八局集团有限公司 Construction method for preventing floor heave of tunnel bottom inverted arch

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110617077A (en) * 2019-09-20 2019-12-27 中铁十八局集团有限公司 Construction method for preventing floor heave of tunnel bottom inverted arch

Similar Documents

Publication Publication Date Title
CN103757993B (en) High-speed railway subgrade sedimentation repair system and method
CN207829891U (en) A kind of preventing mean of Tunnel Base deformation
CN106089258A (en) Tunnel device and construction method
US20140314502A1 (en) Polymer grouting method for uplifting ballastless track of high-speed rail
CN111502706B (en) Tunnel inverted arch structure and method suitable for bottom heave deformation control
CN108316062A (en) A kind of control device and its construction method of non-fragment orbit tunnel arching of bottom
CN207998754U (en) A kind of preventing mean and ballastless track system that prevent non-fragment orbit from arching up
CN204703922U (en) A kind ofly process the construction corollary equipment that Tunnel invades limit
CN108286443B (en) A kind of construction method of the prevention and control device of non-fragment orbit tunnel bottom deformation
CN108316943B (en) A kind of construction method for the device preventing the deformation of non-fragment orbit tunnel bottom
CN103670438A (en) Novel high-strength and high-deformation piston type inverted arch
CN105926383B (en) A kind of track plates lifting translating device and construction method
CN110983996A (en) Beam body jacking and deviation rectifying method for high-speed railway bridge
CN108331593A (en) A kind of cavity type preventing mean and construction method for the deformation of non-fragment orbit tunnel bottom
CN104652299A (en) Electrified railway existing bridge and culvert whole-hole moving-out construction method
CN107916936A (en) A kind of major diameter one-tunnel two-tracks subway tunnel and its construction method
CN105236265B (en) Reinforcing method and reinforcing structure for rail of portal crane
CN212404647U (en) Tunnel bottom structure with track structure and tunnel lining separated
CN208831009U (en) A kind of cavity type preventing mean for Tunnel Base deformation
CN105256667A (en) Framework flat prefabricated track plate
CN105821729A (en) Track board lifting device and method
CN215443921U (en) Tunnel drain hole synchronous operation vehicle constructed by TBM method
CN206769925U (en) A kind of hard rock large cross-section tunnel construction supporting structure
CN206539363U (en) A kind of antiflushing type mine roadway support device
CN206127747U (en) Auxiliary device of fixed guard rail pillow

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant