CN207792805U - The integrated liftable modular support of sewage disposal - Google Patents

The integrated liftable modular support of sewage disposal Download PDF

Info

Publication number
CN207792805U
CN207792805U CN201721897787.1U CN201721897787U CN207792805U CN 207792805 U CN207792805 U CN 207792805U CN 201721897787 U CN201721897787 U CN 201721897787U CN 207792805 U CN207792805 U CN 207792805U
Authority
CN
China
Prior art keywords
water
sewage disposal
column
module
filler
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721897787.1U
Other languages
Chinese (zh)
Inventor
彭朝华
刘宏雁
王秋玲
蔡明�
尹丽玲
张晓赛
彭飞
孙卫东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong shunshi Environmental Protection Technology Co.,Ltd.
Original Assignee
Shijiazhuang Shun Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shijiazhuang Shun Technology Co Ltd filed Critical Shijiazhuang Shun Technology Co Ltd
Priority to CN201721897787.1U priority Critical patent/CN207792805U/en
Application granted granted Critical
Publication of CN207792805U publication Critical patent/CN207792805U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02WCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO WASTEWATER TREATMENT OR WASTE MANAGEMENT
    • Y02W10/00Technologies for wastewater treatment
    • Y02W10/10Biological treatment of water, waste water, or sewage

Abstract

The utility model provides a kind of integrated liftable modular support of sewage disposal, it is to be assembled by hanging beam and filler lower hanging beam on four hollow columns, filler and formed cube frame, it is provided at least one of water distribution module, aeration module, filler module or receipts water module on it, the lifting lug to hang out this sewage disposal from sewage disposal device bottom with integrated liftable modular support is provided on each hollow column.The integrated liftable modular support good integrity of the utility model, it is versatile, water distribution, aeration, filler can be achieved at the same time and/or receive water function, save material utilization amount, reduce cost, in the state of not interrupting sewage disposal operation, which can integrally hang out, easily to overhaul inner components, or integral replacing is carried out to module therein, it multigroup in sewage disposal device can be used in combination simultaneously, make sewage disposal device Effec-tive Function in life cycle, ensure stable effluent quality.

Description

The integrated liftable modular support of sewage disposal
Technical field
The utility model is related to a kind of sewage disposal device attachmentes, and concretely relating to sewage disposal integration can rise Modular support drops.
Background technology
It is water distribution, aeration, filler in the critical component of biofilm sewage disposal and receives water, in existing cesspool or tank body Sectional elevation be followed successively by from bottom to top cloth water-bound, aeration module, filler module and receive water-bound equipment in, these components are being tied Structure arrangement is upper mutual indepedent.Due to that independently of each other, when exception or failure occur in level members instantly, must be removed between each component The structure or component of one level could be overhauled.
In sewage disposal device, the failure rate for being aerated module and filler group is higher.When being aerated module appearance exception, expose Gas is uneven, and water process efficiency reduces, and need to be overhauled or be repaired in time.It, will be in tank when maintenance is aerated module(In pond)It is dirty Water is vented, remove layer disposed thereon, large area covering filler group and receive water-bound.Simultaneously as the self structure of filler, strong The reasons such as degree, operating mode or life cycle, between possible filler can gradual breakdown or disturbance winding or formed block, if being filled out The replacement of material also needs to stop production, will be in tank(In pond)Sewage is vented, and dismantles the water supplement structure of layer disposed thereon, and filler group is whole Body removes, and finds out and replaces the corrupted filler to go wrong, time-consuming and laborious, inefficiency.In actual sewage processing procedure, it is Do not influence other component operation, corrupted filler can only be cut, and can not polishing, this can influence the attachment and breeding of biology, So that biodegradable efficiency reduces.
It, will be in tank in crucial attachment in overhauling or repairing sewage disposal device such as aeration module and filler group(In pond)It is dirty Water is vented, on the one hand, sewage disposal device is in run-stopping status, no sewage treatment capacity;On the other hand, it is vented crucial work The sewage of skill section such as hydrolysis section and aerobic section also abandons original microorganism species tamed and be in equilibrium quantity. Sewage disposal device is reactivated again, microorganism species are restored to equilibrium quantity, needs the culture and domestication of long period, ability Restore sewage treatment capacity.
The above problem is unresolved at present, and sewage treatment plant can only passively endure local fault and exception, inefficient in spite of illness It can operation;Forced arrestment operation, is forced to concentrate maintenance, then spends a period of time culture microorganism species Wait-to-Restore Sewage treatment capacity.Such processing mode so that sewage treatment plant is unable to standard operation whithin a period of time, this is also such Sewage treatment plant is unable to the hidden danger the very crux of stable operation.In addition, in existing biofilms method sewage disposal device, water distribution, exposure Gas, filler and receipts water are independent support system, and each system does not borrow mutually, causes the waste of material.
In conclusion how to realize that reasonable water distribution, optimization aeration, the operation of filler persistent high efficiency, receipts water avoid the formation of dead zone, To ensure the operation of sewage treatment plant efficient stable, on-line maintenance and replacement are realized, be carrying of facing of current sewage treatment plant Upshift time realizes that there is an urgent need for one of technical barriers captured in standardization operational process.
Utility model content
The purpose of this utility model is to provide a kind of integrated liftable modular support of sewage disposal, existing to solve Each structure is independently arranged in sewage disposal device, wastes material and space, the time-consuming and laborious problem of stop production to overhaul.
What the purpose of this utility model was realized in:
The integrated liftable modular support of a kind of sewage disposal, by hanging beam and filler on four hollow columns, filler Lower hanging beam assembles to form cube frame, be provided on the cube frame water distribution module, aeration module, filler module and At least one of water module is received, it is vertical that the hollow column is divided into the first column, the second column, third in the direction of the clock Column and the 4th column, four hollow columns set up the corner location set in quadrangle separately, are provided on each hollow column to incite somebody to action The lifting lug that this sewage disposal is hung out with integrated liftable modular support from sewage disposal device.
It is provided in the water distribution module into water water distribution module comprising water inlet pipe and cloth water distribution pipe, described first Column connects through the water inlet pipe with the water inlet on sewage disposal device as water inlet down-comer, the upper end, lower end and institute Cloth water distribution pipe is stated to connect.
Reflux water distribution module is additionally provided in the water distribution module comprising reflux water inlet pipe and reflux water distribution distribution Pipe, the third column is as water down-comer is flowed back into, and the upper end is through the reflux water inlet pipe and returning on sewage disposal device It flows into the mouth of a river to connect, lower end connects with the reflux cloth water distribution pipe.
The aeration module includes air inlet pipe, the first air inlet distribution pipe, the second air inlet distribution pipe and is aerated distribution pipe, described Second column and the 4th column are as air induction conduit, one end of the air inlet pipe and the air inlet phase on sewage disposal device It connects, the other end connects with first air inlet pipe and second air inlet pipe respectively, the upper end of the second column and described first Air inlet distribution pipe connects, and the upper end of the 4th column connects with second air inlet pipe, under the lower end of the second column, the 4th column End connects with the aeration distribution pipe.
The aeration module further includes aeration head, and the aeration head is arranged in the aeration distribution pipe, for uniformly exposing Gas.
The filler module is arranged on by the filler between hanging beam and the filler lower hanging beam.
The filler module further includes filler auxiliary hanging beam, is arranged outside cube frame, is hung under the filler Beam is located in same level and connects, and is used for Auxiliary support hanging filler.
The receipts water module includes water receiving tank and water receiving tank support, water receiving tank support setting in first column and On the third column, it is used to support the water receiving tank;It is provided with water receiving tank outlet in the water receiving tank, is used for water receiving tank Interior water outlet is exported to next technique unit.
The water receiving tank is that symmetrical inequilateral is I-shaped, is pushed up with being formed with the third column using first column Hold in the palm dual-gripper.
On the outer surface that hanging beam and filler lower hanging beam assemble the cube frame formed on by four hollow columns, filler It is provided with diagonal brace.
Four hollow columns connect knot with hanging beam on the filler and the filler lower hanging beam through connecting bracket or flange etc. Structure connects.
Preferably, water distribution module, filler module are provided with in integrated liftable modular support in this sewage disposal With receipts water module;It is highly preferred that this sewage disposal be provided with simultaneously in integrated liftable modular support water distribution module, It is aerated module, filler module and receives water module.
The utility model assembles by using four steel pipes and filler hanging beam as column and to form cube frame, at this At least one of water distribution module, aeration module, filler module or receipts water module are optionally provided on cube frame, It realizes water distribution, aeration, filler and receives water integrated integrated layout, and layout design is optimized to the structure on holder, make each It is independent of each other between module, forms the liftable modular support of integration.
Column in the integrated module formula holder not only circulation duct as water distribution module and aeration module, but also as receipts The support system of sink weir plate, each system borrow mutually, using supporting each other, save the material in biofilm sewage technique Dosage reduces the project installation amount and construction cost of sewage disposal device, saves each module in sewage treatment pot/interior occupied Space, the performance of enhanced sewage processing equipment are conducive to improve sewage treatment capacity.
In the state of not interrupting sewage disposal operation, which can integrally hang out, efficiently and easily to overhaul, Its inner components is replaced, or integral replacing is carried out to wherein set function module, after maintenance or replacement parts, by mould Block formula holder is put back in sewage disposal device in time, accomplishes the parts for overhauling, occurring exception or failure immediately, solves because stopping Water overhauls once in a blue moon, which concentrates the problem of changing and material equipment is caused to waste without exception, displaces The module maintenance come is intact spare again later, not only shortens the repair time, but also reduces maintenance difficulty, also improves repair quality, To realize repair and maintenance normalization, critical process section is not out of service, and microorganism ownership is suffered a loss small, it is ensured that sewage factory and office Reason ability is stablized, and the supportability of effluent quality improves.
The integrated liftable modular support good integrity of the utility model, it is versatile, batch production batch can be formed Amount production, fine manufacture, raising modularization standardization is horizontal, meanwhile, it multigroup in sewage disposal device can be used in combination, accomplish sequentially to take turns It repaiies, so that each process section of sewage disposal and the integral device efficient stable in life cycle is run, be sewage disposal device or factory Standardization operation lay the foundation.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model.
Fig. 2 is the side view of Fig. 1.
Fig. 3 is the structural schematic diagram of cube frame in the utility model.
Fig. 4 is the structural schematic diagram into water water distribution module.
Fig. 5 is the structural schematic diagram of reflux water distribution module.
Fig. 6 is the structural schematic diagram for being aerated module.
Fig. 7 is the arrangement schematic diagram for being aerated aeration head in module.
Fig. 8 is the vertical view of filler module.
Fig. 9 is the structural schematic diagram for receiving water module.
In figure, 1, sewage disposal device, the 2, first column, the 3, second column, 4, third column, the 5, the 4th column, 6, fill out Hanging beam on material, 7, filler lower hanging beam, 8, lifting lug, 9, connecting bracket, 10, diagonal brace, 11, water inlet, 12, water supply connector, 13, water inlet Pipe, 14, water distribution pipe, 15, reflux water inlet, 16, reflux water inlet pipe, 17, reflux water distributor, 21, air inlet, 22, air inlet Pipe, the 23, first air inlet gas-distribution pipe, the 24, second air inlet gas-distribution pipe, 25, aeration distribution tracheae, 26, aeration head, 31, filler auxiliary Hanging beam, 32, filler, 41, water receiving tank, 42, water receiving tank support, 43, water receiving tank outlet.
Specific implementation mode
As shown in Fig. 1 ~ 3, the integrated liftable modular support of the utility model is stood as hollow by four steel pipes Column assembles to form cube frame with as the filler hanging beam of planar support, and be provided on cube frame water distribution module, At least one of be aerated module, filler module or receive water module.It is arranged in integrated liftable modular support in Fig. 1 There are water distribution module, aeration module, filler module and receipts water module that can the holder be placed on sewage in sewage disposal process In processing equipment 1, realizes water distribution, aeration, filler and receive the structure-integrated of water module.Certainly, it can also be set according to sewage disposal At least one module is arranged in liftable modular support in standby needs.
Hollow column of four steel pipes as holder is used in the present embodiment, it is preferred to use the identical steel of equal strength, size Pipe.Four hollow columns set up the corner location in square separately, be followed successively by the direction of the clock the first column 2, the second column 3, Third column 4 and the 4th column 5.It is provided with lifting lug 8 on the excircle of each hollow column, is used for integrated liftable module Formula holder is hung out from the bottom of sewage disposal device.Preferably, each lifting lug 8 is located at the upper end of the column, and in same level, In order to lift by crane.Each hollow column with as hanging beam 6, filler lower hanging beam 7 on the filler of planar support through connecting bracket 9 or endoporus It is lined with the connection structures such as the flange of reinforced pipe to be connected, is convenient for assembly and disassembly.It can be arranged on the outer surface of cube frame There is diagonal brace 10, to form firm cube structure.
According to the technological process of sewage disposal, water distribution module includes water inlet water distribution module and/or reflux water distribution module.Such as figure Shown in 4, water inlet water distribution module be using the first column 2 as down-comer of intaking, the upper end of the water inlet down-comer through water inlet pipe 13, Water supply connector 12 connects with water inlet 11, the lower end for down-comer of intaking with above 1 bottom of sewage disposal device into water cloth Water pipe 14 connects, to realize the water distribution uniformity of the water inlet from water inlet 11.The setting of water supply connector 12 is in water inlet pipe 13 and water inlet At the positions that mouth 11 connects, for controlling flow of inlet water.
As shown in figure 5, similar with water inlet water distribution module, reflux water distribution module is diagonally arranged using with the first column 2 Third column 4 flows back into the upper end of water down-comer through water inlet pipe 16 and the reflux water inlet 15 of flowing back as water down-comer is flowed back into Connect, the lower end for flowing back into water down-comer connects with the reflux water distributor 17 positioned at 1 bottom of sewage disposal device, is come from realizing The water distribution uniformity of the recirculation water of reflux water inlet 15.For example, the hydrodynamic force of contact oxidation technology section is flowed back into hydrolysis acidification section, To realize denitrification function.
As shown in fig. 6, aeration module is to utilize other two diagonal hollow columns i.e. the second column 3 and the 4th column 5 As air induction conduit.The top of two air induction conduits is connected with the first air inlet gas-distribution pipe 23 and the second air inlet gas-distribution pipe 24 respectively It connects, the first air inlet gas-distribution pipe 23 and the second air inlet gas-distribution pipe 24 connect through three-way piece with one end of air inlet pipe 22, air inlet pipe 22 The other end connects with air inlet 21.Air resistance in first air inlet gas-distribution pipe 23 and the second air inlet gas-distribution pipe 24 is equal, with profit In uniform blasting.The lower end of air induction conduit connects with one end of aeration distribution tracheae 25, can according to the needs of sewage treatment process It directly uses aeration distribution tracheae 25 to be aerated, or several aeration heads 26 is connected on aeration distribution tracheae 25, thus will Aeration air from air inlet 21 carries out uniform aeration through aeration head 26.The quantity and arrangement spacing of aeration head 26 must satisfy 《Biological contact oxidation process sewage disposal technology specification》(HJ2009-2011)、《Blast aeration module design regulation》[CECS 97: 97] related request, to realize efficient reasonable oxygen supply function to contact oxidation technology section.Aeration head 26 in the present embodiment Arrangement on the basis of meeting aforementioned claim as shown in fig. 7, can also carry out using other arrangements.
As shown in Fig. 1 ~ 2,8, portion, i.e. filler 32 are located on filler under hanging beam 6 and filler the setting of filler module in the bracket Between hanging beam 7.According to the processing capacity of sewage disposal device and required amount of filler, filler auxiliary hanging beam 31 can be also set.This When, it is connected with four hollow columns by hanging beam on filler 6, filler lower hanging beam 7 and forms interior cube stable frame, filler auxiliary Hanging beam 31 be arranged outside interior cube frame, be located in same level with filler lower hanging beam 7, and with 7 phase of filler lower hanging beam It connects, is used for Auxiliary support filler.It is shown in Fig. 8 and is provided with two filler auxiliary hanging beams on the horizontal plane of filler lower hanging beam 7 31, can also be arranged as required to more filler auxiliary hanging beams 31 makes filler 32 fill as possible with more securely supported and suspended filler 32 Full sewage disposal device, improves volume loading rate.The layout density of filler 32 and height determine by filler volumetric loading, according to 《Biological contact oxidation process sewage disposal technology specification》(HJ2009-2011)、《Biological contact oxidation process design discipline》[CECS 128:2001] it determines, to realize that filler volumetric loading is distributed rationally, the anaerobism section in sewage disposal process and catalytic oxidation Process section plays a role.
As shown in Fig. 2,9, receive water module be arranged on the top of water inlet pipe 13 and filler module, and positioned at air inlet pipe 13 and into The lower part of gas gas-distribution pipe.It includes water receiving tank 41 and water receiving tank support 42 to receive water module.Water receiving tank outlet 43 is arranged in water receiving tank 41 Lower surface, for exporting the water outlet of this sewage disposal device 1 to next process section.For the ease of supporting the weir of water receiving tank 41 Plate, and avoid air inlet pipe 22, it is I-shaped that water receiving tank 41 may be configured as symmetrical inequilateral, as shown in Figure 9.Using such machine Water receiving tank support 42 is arranged in the first column 2 structure(It intakes down-comer)On the third column 4 diagonal with it, top is formed Dual-gripper is held in the palm, not only ensures to receive water uniformly without dead zone, but also can get stable support, is also convenient for adjusting the level essence of water receiving tank 41 Degree, to reach the receipts water effect of high quality.
In the present embodiment, after placing water distribution module, aeration module, filler module and receipts water module, integrated liftable For whole load weights of modular support within 3500 ~ 5000Kg, the structural strength of hollow column can ensure will be integrated Liftable modular support is disposably integrally hung out from sewage disposal device 1.It waits for integrated liftable modular support is whole After body is hung out, it can overhaul in the case where not interrupting sewage treatment process operation, replace its inner components, or to wherein institute The function module of setting carries out integral replacing and modular support is put back to sewage disposal in time and is set after maintenance or replacement parts In standby 1.If temporarily without using the holder, the connection structures such as disassembled connecting bracket 9 and diagonal brace 10, by integrated liftable mould Block formula holder is decomposed into single chip architecture, in order to transport and store.
Sewage disposal device in the utility model can be that the sewage disposals such as treatment tank and/or treatment tank tank are led The common equipment in domain.Meanwhile at least one integrated liftable modular support can be set in sewage disposal device, it carries out more It organizes and is used in combination, when needed, overhauled successively, realize repair and maintenance normalization, it is ensured that the effluent quality of sewage disposal device is steady It is fixed.

Claims (10)

1. a kind of integrated liftable modular support of sewage disposal, which is characterized in that hung oneself by four hollow columns, fillers Beam and filler lower hanging beam assemble to form cube frame, and water distribution module is provided on the cube frame, aeration module, is filled out Expect module and receive at least one of water module, the hollow column is divided into the first column, second vertical in the direction of the clock Column, third column and the 4th column, four hollow columns set up the corner location in quadrangle separately, are provided on each hollow column To the lifting lug for hanging out this sewage disposal from sewage disposal device with integrated liftable modular support.
2. the integrated liftable modular support of sewage disposal according to claim 1, which is characterized in that in the cloth It is provided in water module into water water distribution module, the water inlet water distribution module includes water inlet pipe and cloth water distribution pipe, and described first is vertical As water inlet down-comer, the upper end connects through the water inlet pipe with the water inlet on sewage disposal device column, lower end with it is described Cloth water distribution pipe connects.
3. the integrated liftable modular support of sewage disposal according to claim 2, which is characterized in that in the cloth Reflux water distribution module is additionally provided in water module comprising reflux water inlet pipe and reflux cloth water distribution pipe, the third column are made To flow back into water down-comer, the upper end connects through the reflux water inlet pipe with the reflux water inlet on sewage disposal device, under End connects with the reflux cloth water distribution pipe.
4. the integrated liftable modular support of sewage disposal according to claim 1, which is characterized in that the aeration Module includes air inlet pipe, the first air inlet distribution pipe, the second air inlet distribution pipe and aeration distribution pipe, and second column and the 4th is stood Column connects as air induction conduit, one end of the air inlet pipe with the air inlet on sewage disposal device, other end difference Connecting with first air inlet pipe and second air inlet pipe, the upper end of the second column connects with the first air inlet distribution pipe, The upper end of 4th column connects with second air inlet pipe, the lower end of the second column, the 4th column lower end with the aeration Distribution pipe connects.
5. the integrated liftable modular support of sewage disposal according to claim 4, which is characterized in that the aeration Module further includes aeration head, and the aeration head is arranged in the aeration distribution pipe, is used for uniform aeration.
6. the integrated liftable modular support of sewage disposal according to claim 1, which is characterized in that the filler Module is arranged on the filler between hanging beam and the filler lower hanging beam.
7. the integrated liftable modular support of sewage disposal according to claim 1, which is characterized in that the receipts water Module includes water receiving tank and water receiving tank support, and the water receiving tank support is arranged on first column and the third column, It is used to support the water receiving tank;Be provided in the water receiving tank water receiving tank outlet, for by the water outlet in water receiving tank export to Next technique unit.
8. the integrated liftable modular support of sewage disposal according to claim 7, which is characterized in that the receipts water Slot is that symmetrical inequilateral is I-shaped, to form jacking dual-gripper using first column and the third column.
9. the integrated liftable modular support of sewage disposal according to claim 1, which is characterized in that by four Hanging beam and filler lower hanging beam assemble and are provided with diagonal brace on the outer surface of the cube frame to be formed on hollow column, filler.
10. the integrated liftable modular support of sewage disposal according to claim 1, which is characterized in that four skies Heart column connects with hanging beam on the filler and the filler lower hanging beam through connecting bracket or flange.
CN201721897787.1U 2017-12-29 2017-12-29 The integrated liftable modular support of sewage disposal Active CN207792805U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721897787.1U CN207792805U (en) 2017-12-29 2017-12-29 The integrated liftable modular support of sewage disposal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721897787.1U CN207792805U (en) 2017-12-29 2017-12-29 The integrated liftable modular support of sewage disposal

Publications (1)

Publication Number Publication Date
CN207792805U true CN207792805U (en) 2018-08-31

Family

ID=63279616

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721897787.1U Active CN207792805U (en) 2017-12-29 2017-12-29 The integrated liftable modular support of sewage disposal

Country Status (1)

Country Link
CN (1) CN207792805U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107857361A (en) * 2017-12-29 2018-03-30 石家庄顺时科技有限公司 The integrated liftable modular support of sewage disposal

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107857361A (en) * 2017-12-29 2018-03-30 石家庄顺时科技有限公司 The integrated liftable modular support of sewage disposal
CN107857361B (en) * 2017-12-29 2024-02-13 广东顺时环保科技有限公司 Integrated lifting module type bracket for sewage treatment

Similar Documents

Publication Publication Date Title
CN204022537U (en) A kind of air water co-flow magnetic force enhanced biological filtration reactor
CN101481172B (en) Modularized bioreactor
CN207792805U (en) The integrated liftable modular support of sewage disposal
CN203938519U (en) A kind of novel modularized bio-packing apparatus
CN102001744A (en) Integral Orbal oxidation ditch combination type aeration system
CN107857361A (en) The integrated liftable modular support of sewage disposal
CN110386661B (en) Liftable combined aeration system suitable for MBBR (moving bed biofilm reactor) process and mounting method
CN201914966U (en) Integrated orbal oxidation ditch assembled type aeration device
CN108298680A (en) One kind, which is not cut off the water, is transformed MBBR systems
CN105541029B (en) A kind of unpowered return integrated Treated sewage reusing device
CN102976503A (en) Lifting aerating device arranged in high density
CN203877964U (en) Up-flow anaerobic sludge blanket reactor
CN114251518A (en) Pipeline installation structure of non-laminate closed pipe well and construction method thereof
CN210944991U (en) Splicing type adjustable biochemical filler module device
CN203360231U (en) Biological cascade nest
CN215855320U (en) Liftable aerator installation assembly
CN213231660U (en) MBR integration equipment for emergency treatment of landfill leachate
CN111675311B (en) Method for changing surface aeration into bottom aeration without stopping production and mounting structure thereof
CN218709600U (en) Suspension type MABR sewage treatment plant
CN210237201U (en) Membrane bioreactor capable of accelerating sewage treatment
CN213773610U (en) Automatic water replenishing and exhausting constant pressure unit with pressure buffering structure
CN220223276U (en) Portable film frame lifting device
CN109879408A (en) Modularization biological aerated filter
CN219652814U (en) Unit type liftable aeration pipeline
CN216106186U (en) Filler support in biological contact oxidation pond

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 511675 temporary exhibition hall 012, Guangfo (Fogang) Industrial Park, Guangqing Special Economic Cooperation Zone, Tangtang Town, Fogang County, Qingyuan City, Guangdong Province

Patentee after: Guangdong shunshi Environmental Protection Technology Co.,Ltd.

Address before: 050000 Hebei province high tech Zone in Shijiazhuang City, Mount Everest Street No. 218, building 58, unit 6, Huadu Shuixie room 402

Patentee before: SHIJIAZHUANG SHUNSHI TECHNOLOGY Co.,Ltd.

CP03 Change of name, title or address