A kind of high-rise building pump line grafting fastening-type structure Download PDFInfo
- Publication number
- CN207777834U CN207777834U CN201820124790.8U CN201820124790U CN207777834U CN 207777834 U CN207777834 U CN 207777834U CN 201820124790 U CN201820124790 U CN 201820124790U CN 207777834 U CN207777834 U CN 207777834U
- Authority
- CN
- China
- Prior art keywords
- pump line
- pump
- locating piece
- rise building
- type structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000013011 mating Effects 0.000 claims abstract description 8
- 238000005452 bending Methods 0.000 claims description 24
- 238000009434 installation Methods 0.000 claims description 11
- 238000003032 molecular docking Methods 0.000 claims description 11
- 210000002421 cell wall Anatomy 0.000 claims 1
- 238000010586 diagram Methods 0.000 description 5
- 230000005540 biological transmission Effects 0.000 description 2
- 230000006378 damage Effects 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 230000007812 deficiency Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
Landscapes
- Structures Of Non-Positive Displacement Pumps (AREA)
Abstract
The utility model discloses a kind of high-rise building pump line grafting fastening-type structures, it is intended to provide a kind of structure of pump line easy to disassemble, its key points of the technical solution are that including two pump lines for delivering concrete, two pump lines are respectively the first pump line and the second pump line, one end of the pump line is equipped with annular lug, the other end of the pump line is equipped with annular groove, and the annular lug and annular groove are mating;First pump line is rotatably connected at least two locking levers close to the lateral surface of the second pump line, and second pump line is fixedly installed card column close to the lateral surface of the first pump line, and the locking lever is equipped with and the matched bayonet of card column;The card column sliding is connected with locating piece, and the locking lever is equipped with the locating slot mating with locating piece, and the locking lever is additionally provided with for locating piece to be fixed on to the secure component with the position of locating slot grafting.The structure makes pump line design more reasonable, pump line easy to disassemble.
Description
Technical field
The utility model is related to technical field of buildings, more specifically, it relates to which a kind of high-rise building pump line grafting is tight
Stationary structure.
Background technology
High-rise building refers to 40 layers or more, highly 100 meters or more of building, and the terrestrial reference for often becoming a city is built
It builds, irreplaceable role is played to city image.In high-rise building builds design, pump line can be used, to pump line
Design comparison is important;Pump line is the abbreviation of concrete delivery pump pipe, the place for needing to pour into a mould concrete conveyance to eminence.
Pump line is spliced successively by one, and the connecting method of the two adjacent sections pump line designed by the prior art is to pass through flange
It connects to install fixation;When installing or removing pump line, need that the multipair bolt and nut that ring flange one encloses is fixed and divided respectively
From.
However, the pump line design be not quite reasonable, the stitching portion of pump line is more, thus in the prior art the dismounting of pump line compared with
For inconvenience.
Utility model content
In view of the deficiencies of the prior art, the purpose of this utility model is to provide a kind of high-rise building pump line grafting fastening-type
Structure, the structure keep pump line design more reasonable, have the effect of pump line easy to disassemble.
The above-mentioned technical purpose of the utility model technical scheme is that:A kind of high-rise building pump
Pipe grafting fastening-type structure, includes two pump lines for delivering concrete, and two pump lines are respectively the first pump line and
Two pump lines, one end and one end of the second pump line of first pump line are connected to each other, and one end of the pump line is equipped with annular lug, institute
The other end for stating pump line is equipped with annular groove, and the annular lug and annular groove are mating;First pump line is close to
The lateral surface of two pump lines is rotatably connected at least two locking levers, and second pump line is set close to the lateral surface fixation of the first pump line
It is equipped with card column, the locking lever is equipped with and the matched bayonet of card column;The card column sliding is connected with locating piece, the locking lever
Equipped with the locating slot mating with locating piece, the locking lever is additionally provided with for locating piece to be fixed on and locating slot grafting
The secure component of position.
By using above-mentioned technical proposal, by the annular groove of the annular lug of first pump line one end and second pump line one end
Grafting, rotates locking lever, and bayonet turns to card column, card column is made to engage with bayonet;Then locating piece is slided, locating piece is inserted into and is positioned
Slot is fixed locating piece by secure component, so that two pump lines are connected and fixed;Secure component is unclamped, locating piece is skidded off,
Locking lever is gone back to, bayonet is made to be detached from card column;Pump line design is more reasonable, dismounts pump line more convenient and quicker.
Preferably, the secure component includes being set to locating piece towards the end of locating slot and positioning the mutual of groove groove wall
The magnet of actuation.
By using above-mentioned technical proposal, when locating piece and locating slot grafting, magnet automatic pick can be fixed quickly
Locating piece, and locating slot is skidded off convenient for locating piece, determine so that locating piece is fixed in slot and skids off locating piece
Position slot is convenient and efficient.
Preferably, the secure component includes being threadedly connected to locking lever and stretching into the screw rod in locating slot and be set to determine
The groove of position block, the screw rod is embedded in groove and and fit depressions.
By using above-mentioned technical proposal, after locating piece is inserted into locating slot, screw rod is rotated, screw rod is made to stretch into locating slot and embedding
Enter in groove, so firmly limit locating piece be detached from locating slot, and can easily stationary positioned block and unclamp locating piece.
Preferably, the pump line is socketed with the elastic ring at the first pump line and the second pump line docking.
By using above-mentioned technical proposal, elastic ring is sleeved on outside pump line, and is sleeved on the docking of the first pump line and the second pump line
Place reduces the case where concrete leaks out in transmission process at the docking of two pump lines.
Preferably, the elastic ring is socketed with clip.
By using above-mentioned technical proposal, it is more stable that clip makes elastic ring be sleeved at the docking of two pump lines, and clip
Further make two pump line connections more secured.
Preferably, further include installation pouring weight, the upper end of the installation pouring weight is fixedly installed support plate, the support plate
Upper surface is equipped with to be equipped with and the matched clamping bar of pump line, the pump with the matched recessed portion of pump line, the upper end of the support plate
Pipe clamp is held between clamping bar and recessed portion;The both ends of the clamping bar are equipped with elastic fastening hook, and the support plate, which is equipped with, is located at recessed portion
The protrusive board on both sides, the protrusive board are equipped with card hole, and the elastic fastening hook is engaged by clamping through card hole and with card hole.
By using above-mentioned technical proposal, the cooperation of elastic fastening hook and card hole makes pump line steadily be held on clamping bar and recess
Between portion, pump line is less susceptible to shake in delivering concrete;Support plate is fixed on installation pouring weight, pre- compared to support plate
System reduces the destruction to building, and have the advantages that mobility is strong in building, and installation pouring weight is transported convenient for concentrating,
Convenient for use next time.
Preferably, further include bending pump line for delivering concrete, the described one end of first pump line far from the second pump line
It is connected to each other with one end of bending pump line;The bending pump line is equipped with holder, and the holder includes chassis and positioned at chassis top
Support ring, the bending pump line are matched through support ring and with support ring;The outer wall of the bending pump line, which is equipped with, is connected to branch
The abutting block of pushing out ring upper surface.
By using above-mentioned technical proposal, bending pump line is convenient for the route turning of concrete conveyance;Pump line is bent through branch
Pushing out ring, and abut block and be connected in support ring, make bending pump line by the support force stablized, it is fixed steady to improve bending pump line
It is qualitative.
Preferably, the support ring be threaded with through abut block bolt, the head of the bolt with abut block phase
It abuts.
By using above-mentioned technical proposal, in delivering concrete, bending pump line is less susceptible to shake bending pump line, makes conveying
The process of concrete is more stable.
In conclusion the utility model has the advantages that:
1, after two pump line docking, locking lever is rotated, card column is made to engage with bayonet, locating piece is slided, locating piece is inserted into
Locating slot is fixed locating piece by secure component;Secure component is unclamped, locating piece is skidded off, goes back to locking lever, keeps bayonet de-
From;Pump line more convenient and quicker is dismounted, pump line design is more reasonable;
2, the bending pump line being connect with the first pump line is convenient for the route turning of concrete conveyance;Pump line is bent through support
Ring, and abut block and be connected in support ring, make bending pump line by the support force stablized, improves the bending fixed stabilization of pump line
Property.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model embodiment one;
Fig. 2 is the assembly relation schematic diagram of the first pump line and the second pump line in the utility model embodiment one;
Fig. 3 is the attachment structure schematic diagram of the first pump line and the second pump line in the utility model embodiment one;
Fig. 4 is the assembly relation schematic diagram of support plate and clamping bar in the utility model embodiment one;
Fig. 5 is the assembly relation schematic diagram of locking lever and card column in the utility model embodiment two.
In figure:1, the first pump line;2, the second pump line;3, annular lug;4, annular groove;5, locking lever;6, card column;7, block
Mouthful;8, locating piece;9, locating slot;101, magnet;102, screw rod;103, groove;11, elastic ring;12, clip;13, installation weight
Block;14, support plate;15, recessed portion;16, clamping bar;17, elastic fastening hook;18, protrusive board;19, card hole;20, pump line is bent;21, it props up
Frame;211, chassis;212, support ring;22, block is abutted;23, bolt.
Specific implementation mode
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment one:A kind of high-rise building pump line grafting fastening-type structure, as depicted in figs. 1 and 2, including is used to convey
Two pump lines of concrete, two pump lines are horizontally disposed.Two pump lines are respectively the first pump line 1 and the second pump line 2,
One end of first pump line 1 and one end of the second pump line 2 are connected to each other.One end of two pump lines is respectively and fixedly provided with annular lug 3, two pumps
The other end of pipe offers annular groove 4, and annular lug 3 and annular groove 4 are mating, and then makes the first pump line 1 and
Two pump lines 2 are docked by way of grafting.
As shown in figures 1 and 3, the first pump line 1 is rotatably connected to locking lever 5, locking lever close to the lateral surface of the second pump line 2
5 there are two and be located at the opposite sides of the first pump line 1;Second pump line 2 close to the first pump line 1 lateral surface fix there are two
Card column 6, each locking lever 5 offer respectively with a 6 matched bayonet 7 of card column.The sliding of card column 6 is connected with locating piece
8, locating piece 8 can slide along the length direction of card column 6;Locking lever 5 is provided with the locating slot 9 mating with locating piece 8.Locking lever
5 are additionally provided with secure component, and secure component includes being fixedly installed in locating piece 8 towards 9 slot of the end of locating slot 9 and locating slot
The magnet 101 of wall being mutually attracted.
When installing pump line, after two pump line docking, locking lever 5 is rotated, bayonet 7 turns to card column 6, makes card column 6 and bayonet 7
Engaging;Then locating piece 8 is slided, locating piece 8 is inserted into locating slot 9,101 automatic pick of magnet, locating piece 8 is and locating slot 9
Stablize grafting, makes two pump line stable connections.When dismantling pump line, locating piece 8 is skidded off into locating slot 9, goes back to locking lever 5, is blocked
Mouth 7 is detached from card column 6, and then is detached convenient for two pump lines, dismounting pump line more convenient and quicker.
Pump line is socketed with the elastic ring 11 at 2 docking of the first pump line 1 and the second pump line, and elastic ring 11 is nested and fixed
Clip 12.Elastic ring 11 reduces the case where concrete leaks out in transmission process at the docking of two pump lines;Clip 12 makes
Elastic ring 11 is sleeved on to be less susceptible to deviate or fall off at the docking of two pump lines.
As shown in Figure 1 and Figure 4, installation pouring weight 13 is both provided with below two pump lines, the upper end of installation pouring weight 13 is fixed
There is the support plate 14 being vertically arranged;The upper surface of support plate 14 offers and the matched recessed portion 15 of pump line, support
The upper end of plate 14, which is provided with, to be held on the matched clamping bar 16 of pump line, pump line between clamping bar 16 and recessed portion 15.Clamping bar 16
Both ends are fixed with elastic fastening hook 17, and support plate 14 is fixed with the protrusive board 18 positioned at 15 both sides of recessed portion, and protrusive board 18 is provided with card hole 19,
Elastic fastening hook 17 is engaged by clamping through card hole 19 and with card hole 19.
The cooperation of elastic fastening hook 17 and card hole 19 makes pump line steadily be held between clamping bar 16 and recessed portion 15, and pump line exists
It is less susceptible to shake when delivering concrete.Support plate 14 is fixed on installation pouring weight 13, prefabricated compared to support plate 14 to build
It builds, reduces the destruction to building, and have the advantages that mobility is strong, transport installation pouring weight 13 convenient for concentrating, also allow for
Use next time.
End of first pump line 1 far from the second pump line 2 bends pump line 20 and first to being connected to arc-shaped bending pump line 20
The connection type of pump line 1 is identical as the connection type of two pump lines, is turned convenient for the path of concrete conveyance by bending pump line 20
To.
It bends pump line 20 and connects one end of the first pump line 1 towards horizontal direction, the other end is towards direction straight up.Bending
Pump line 20 is provided with holder 21, and holder 21 includes chassis 211 and the support ring 212 for being fixed on 211 top of chassis, bends pump line 20
It is matched through support ring 212 and with support ring 212.The outer wall of bending pump line 20, which is fixed with, is connected to 212 upper surface of support ring
Abutting block 22, support ring 212 be threaded with through abut block 22 bolt 23, the head of bolt 23 offsets with block 22 is abutted
It connects so that abut block 22 and bending pump line 20 and 212 fix stably of support ring.Pump line 20 is bent by the support force stablized, from
And bend pump line 20 and be less susceptible to shake in delivering concrete, and improve bending 20 fixed stability of pump line.
Embodiment two:A kind of high-rise building pump line grafting fastening-type structure, as shown in figure 5, the present embodiment and embodiment
One difference lies in:Secure component includes being threadedly connected to locking lever 5 and the screw rod 102 that stretches into locating slot 9 and being opened in
The groove 103 of locating piece 8, screw rod 102 are embedded in groove 103 and are matched with groove 103.After locating piece 8 is inserted into locating slot 9,
Screw rod 102 is rotated, so that screw rod 102 is stretched into locating slot 9 and embedded groove 103, and then firmly limit locating piece 8 and be detached from positioning
Slot 9, and can easily stationary positioned block 8 and unclamp locating piece 8.
Above-described embodiment is only the explanation to the utility model, is not limitations of the present invention, this field
Technical staff can as needed make the present embodiment the modification of not creative contribution after reading this specification, but only
It all to be protected by Patent Law in the right of the utility model.
Claims (8)
1. a kind of high-rise building pump line grafting fastening-type structure includes two pump lines for delivering concrete, described in two
Pump line is respectively the first pump line (1) and the second pump line (2), one end phase of one end and the second pump line (2) of first pump line (1)
Docking, it is characterized in that:One end of the pump line is equipped with annular lug (3), and the other end of the pump line is equipped with annular groove (4),
The annular lug (3) and annular groove (4) are mating;First pump line (1) turns close to the lateral surface of the second pump line (2)
Dynamic to be connected at least two locking levers (5), second pump line (2) is fixedly installed card close to the lateral surface of the first pump line (1)
Column (6), the locking lever (5) are equipped with and card column (6) matched bayonet (7);Card column (6) sliding is connected with locating piece
(8), the locking lever (5) is equipped with the locating slot (9) mating with locating piece (8), and the locking lever (5) is additionally provided with for inciting somebody to action
Locating piece (8) is fixed on and the secure component of the position of locating slot (9) grafting.
2. a kind of high-rise building pump line grafting fastening-type structure according to claim 1, it is characterized in that:The fastening part
Part includes being set to locating piece (8) towards the end of locating slot (9) and the magnet (101) being mutually attracted of locating slot (9) cell wall.
3. a kind of high-rise building pump line grafting fastening-type structure according to claim 1, it is characterized in that:The fastening part
Part includes being threadedly connected to locking lever (5) and stretching into the screw rod (102) in locating slot (9) and the groove set on locating piece (8)
(103), it is matched in the embedded groove (103) of the screw rod (102) and with groove (103).
4. a kind of high-rise building pump line grafting fastening-type structure according to claim 1, it is characterized in that:The pump line set
The elastic ring (11) being connected at the first pump line (1) and the second pump line (2) docking.
5. a kind of high-rise building pump line grafting fastening-type structure according to claim 4, it is characterized in that:The elastic ring
(11) it is socketed with clip (12).
6. a kind of high-rise building pump line grafting fastening-type structure according to claim 1, it is characterized in that:It further include installation
The upper end of pouring weight (13), the installation pouring weight (13) is fixedly installed support plate (14), and the upper surface of the support plate (14) is set
Have and is equipped with and the matched clamping bar of pump line (16), institute with the matched recessed portion of pump line (15), the upper end of the support plate (14)
Pump line is stated to be held between clamping bar (16) and recessed portion (15);The both ends of the clamping bar (16) are equipped with elastic fastening hook (17), described
Support plate (14) is equipped with the protrusive board (18) positioned at recessed portion (15) both sides, and the protrusive board (18) is equipped with card hole (19), the elasticity
Grab (17) is engaged by clamping through card hole (19) and with card hole (19).
7. a kind of high-rise building pump line grafting fastening-type structure according to claim 1, it is characterized in that:Further include being used for
The bending pump line (20) of delivering concrete, the one end of first pump line (1) far from the second pump line (2) and bending pump line (20)
One end is connected to each other;The bending pump line (20) be equipped with holder (21), the holder (21) include chassis (211) and be located at chassis
(211) support ring (212) on top, the bending pump line (20) match through support ring (212) and with support ring (212);
The outer wall of the bending pump line (20) is equipped with the abutting block (22) for being connected to support ring (212) upper surface.
8. a kind of high-rise building pump line grafting fastening-type structure according to claim 7, it is characterized in that:The support ring
(212) it is threaded with through the bolt (23) for abutting block (22), the head of the bolt (23) is abutted against with block (22) is abutted.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820124790.8U CN207777834U (en) | 2018-01-24 | 2018-01-24 | A kind of high-rise building pump line grafting fastening-type structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820124790.8U CN207777834U (en) | 2018-01-24 | 2018-01-24 | A kind of high-rise building pump line grafting fastening-type structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207777834U true CN207777834U (en) | 2018-08-28 |
Family
ID=63211445
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820124790.8U Expired - Fee Related CN207777834U (en) | 2018-01-24 | 2018-01-24 | A kind of high-rise building pump line grafting fastening-type structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207777834U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110425342A (en) * | 2019-07-31 | 2019-11-08 | 厦门三航混凝土有限公司 | A kind of Super High concrete pumping pipe mounting structure and its installation method |
CN110745688A (en) * | 2019-09-27 | 2020-02-04 | 中国五冶集团有限公司 | Hoisting tool for installing bent pipe |
-
2018
- 2018-01-24 CN CN201820124790.8U patent/CN207777834U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110425342A (en) * | 2019-07-31 | 2019-11-08 | 厦门三航混凝土有限公司 | A kind of Super High concrete pumping pipe mounting structure and its installation method |
CN110745688A (en) * | 2019-09-27 | 2020-02-04 | 中国五冶集团有限公司 | Hoisting tool for installing bent pipe |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207777834U (en) | A kind of high-rise building pump line grafting fastening-type structure | |
US8186723B2 (en) | Pipe fixing system and pipe fastening device | |
US9022357B2 (en) | Aerial roller spacer apparatus and associated methods thereof | |
CN203671031U (en) | Pipeline fixing hoop | |
CN109163146A (en) | Pipe installing structure and its installation method | |
CN207794628U (en) | A kind of high-rise building pump line connection structure | |
CN210887506U (en) | Municipal drainage pipeline structure | |
CN101147024A (en) | Temporary support structure for use when installing or removing components | |
CN205614591U (en) | A interfacing apparatus for petroleum pipeline flange installation | |
CN213081244U (en) | Clamp for mounting HDPE double-wall corrugated pipe | |
CN215445333U (en) | Flexible multilayer pipeline support | |
CN205919200U (en) | Ceiling lamp support convenient to install | |
CN209703555U (en) | A kind of novel piping lane support system | |
CN215146370U (en) | Welding device for water outlet pipe component of engine | |
CN207034401U (en) | A kind of double fixing point suspension and supports | |
CN205716025U (en) | A kind of snap ring fixing for pipeline | |
CN217815387U (en) | Concrete conveying pipeline reinforcing apparatus | |
CN217302012U (en) | Fire control suction pipe connection structure | |
CN220727373U (en) | Supporting and reinforcing structure of metallurgical safety conveying pipeline | |
CN212470445U (en) | Embrace of supplementary pipeline interim displacement and push away seat | |
CN220226256U (en) | Side wall template supporting device suitable for disc buckle type support | |
CN220713507U (en) | Quick lapped showcase | |
CN212079387U (en) | Pre-buried support of subway tunnel | |
CN220385988U (en) | UPVC pipe for sewage treatment | |
CN108916477A (en) | A kind of petroleum pipeline mounting bracket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180828 |
|
CF01 | Termination of patent right due to non-payment of annual fee |