CN207761166U - A kind of flooring steel beam structure - Google Patents

A kind of flooring steel beam structure Download PDF

Info

Publication number
CN207761166U
CN207761166U CN201721340572.XU CN201721340572U CN207761166U CN 207761166 U CN207761166 U CN 207761166U CN 201721340572 U CN201721340572 U CN 201721340572U CN 207761166 U CN207761166 U CN 207761166U
Authority
CN
China
Prior art keywords
secondary beam
otic placode
girder
flooring
suspension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721340572.XU
Other languages
Chinese (zh)
Inventor
王生宏
王磊
陶化
朱道斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hang Xiao Steel (anhui) Co Ltd
Original Assignee
Hang Xiao Steel (anhui) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hang Xiao Steel (anhui) Co Ltd filed Critical Hang Xiao Steel (anhui) Co Ltd
Priority to CN201721340572.XU priority Critical patent/CN207761166U/en
Application granted granted Critical
Publication of CN207761166U publication Critical patent/CN207761166U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model provides a kind of flooring steel beam structure applied to technical field of building construction,Left suspension otic placode (3) is arranged in per pass secondary beam (2) left end of the flooring steel beam structure,Right suspension otic placode (4) is arranged in per pass secondary beam (2) right end,When per pass secondary beam (2) is arranged between adjacent twice girder (1),Secondary beam (2) left end is configured to the structure being resisted against by left suspension otic placode (3) on one of girder (1),Secondary beam (2) right end is configured to the structure being resisted against by right suspension otic placode (4) on another road girder (1),The flooring steel beam structure and floor steel beam construction method of the utility model,It is at low cost,When flooring is installed,Secondary beam can be installed as temporary support using girder,Make hoisting machinery (tower crane,Crane) secondary beam can be detached from and carry out other work,Secondary beam is no longer on vacant state simultaneously,Improve construction safety.

Description

A kind of flooring steel beam structure
Technical field
The utility model belongs to the realm of building construction, is to be related to a kind of flooring steel beam structure more specifically.
Background technology
In the prior art, the flooring girder steel of steel building when mounted, typically uses hoisting machinery to lift.Flooring After beam is lifted to installation site, worker carries out bolt installation to secondary beam again or welding is installed, and installs or weld in flooring bolt In installation process, hoisting machinery needs to hang secondary beam always, cannot carry out other work, until secondary beam installation terminates.It is such Mounting means causes the waste platform of hoisting machinery, inefficient, it is even more important that hoisting machinery hangs flooring and applied in high-altitude Under work environment, there are serious security risks.
Utility model content
Technical problem to be solved in the utility model is:In view of the deficiencies of the prior art, a kind of simple in structure, system is provided Make it is at low cost, can be by the way that the suspension otic placode in flooring steel beam structure secondary beam position be arranged, by flooring girder steel when flooring is installed Structure secondary beam is articulated on installed girder, installs secondary beam as temporary support using girder so that hoisting machinery (tower Hang, crane) secondary beam can be detached from and carry out other work, to have the function that improve hoisting machinery utilization rate, and meanwhile it is secondary Beam is no longer on vacant state, avoids secondary beam from being fallen in hoisting process and is damaged to ground construction personnel, raising is applied The flooring steel beam structure of work safety.
Solve the problems, such as that techniques discussed above, the technical solution that the utility model is taken are:
The utility model is a kind of flooring steel beam structure, and the flooring steel beam structure includes multiple tracks girder, multiple tracks secondary beam, Multiple tracks secondary beam is set between per adjacent twice girder, and the left suspension otic placode of plate structure, per pass secondary beam is arranged in per pass secondary beam left end The right suspension otic placode of plate structure is arranged in right end, when per pass secondary beam is arranged between adjacent twice girder, secondary beam left end setting For that can be resisted against the structure on one of girder by left suspension otic placode, which is configured to through right suspension otic placode The structure being resisted against on another road girder.
The left suspension otic placode includes left body part and left suspension part, be set as between left body part and left suspension part be in The structure of inverted L-shaped, the right suspension otic placode includes right body part and right suspension part, is arranged between right body part and right suspension part For in the structure of inverted L-shaped.
When per pass secondary beam is arranged between adjacent twice girder, the left suspension part of the left suspension otic placode of the road secondary beam is set as It can be resisted against the structure of the girder upper surface I of one of girder, the right suspension part of the right suspension otic placode of the road secondary beam is arranged to Enough it is resisted against the structure of the girder upper surface II of another road girder, after the flooring is by concreting, the coagulation of flooring Soil is configured to the structure being enclosed in left suspension part and right suspension part in concrete.
The left body part of the left suspension otic placode and left suspension part are an integral structure, the right side of the right suspension otic placode Body part and right suspension part are an integral structure, and the left body part of the left suspension otic placode on per pass secondary beam is set with secondary beam one end side Be set to the structure that can be fixedly connected by welding manner or bolt, the right body part of the right suspension otic placode on per pass secondary beam with time Beam other end side is configured to the structure being fixedly connected by welding manner or bolt.
Multiple left connecting holes are arranged in per pass secondary beam left end, and multiple right connecting holes are arranged in per pass secondary beam right end, with secondary beam left side The left connection board part of protrusion is set on the inside of one of girder of connection, is arranged on left connection board part and the quantity of left connecting hole and position One-to-one left panel hole, with the right connection board part of setting protrusion on the inside of the girder together being connect on the right side of secondary beam, right connection board Setting and the quantity of right connecting hole and position right panel hole correspondingly on part.
When per pass secondary beam is arranged between adjacent twice girder, each left connection bolt is configured to across a left company The structure in hole and a left panel hole is connect, each right connection bolt is configured to across a right connecting hole and a right panel part The structure in hole.
It is simple that the utility model further relates to a kind of step, can convenient and efficient completion flooring girder steel construction, improve construction effect Rate avoids hoisting machinery from wasting, while can effectively improve the floor steel beam construction method of construction safety.
The construction procedure of floor steel beam construction method described in the utility model is:1) it is arranged on the left of per pass secondary beam left outstanding Right suspension otic placode is arranged in earphone plate on the right side of per pass secondary beam;2) by crane loading secondary beam, the left suspension otic placode of secondary beam is supported It leans against on one of girder, the right suspension otic placode of secondary beam is resisted against on another road girder;3) crane and secondary beam are detached from;To putting The secondary beam and girder postponed is attached;4) according to above-mentioned arrangement, the lifting and connection of multiple tracks secondary beam are completed.
When carrying out the construction of flooring girder steel, the girder that multiple tracks presses gap arrangement is first set, is set between every adjacent twice girder The secondary beam that multiple tracks is arranged by gap is set, after the multiple tracks secondary beam between adjacent twice girder is placed, to the building of girder and secondary beam formation Face girder steel carries out concreting, forms flooring, the left suspension otic placode of per pass secondary beam and right suspension otic placode are imbedded in mixed by flooring In solidifying soil.
Using the technical solution of the utility model, advantageous effect below can be obtained:
Flooring steel beam structure described in the utility model is improved secondary girder construction before flooring construction, processes secondary Liang Hou, is arranged left suspension otic placode in per pass secondary beam left end, and right suspension otic placode is arranged in per pass secondary beam right end.Then in installation secondary beam When, secondary beam is lifted by crane by hoisting machinery, between secondary beam is placed into twice girder, then puts down secondary beam, secondary beam one end passes through a left side Suspension otic placode is resisted against on one of girder, and the secondary beam other end is resisted against by right first earphone plate on another road secondary beam, at this moment left outstanding Earphone plate and right suspension otic placode realize the support to secondary beam, then unclamp hoisting machinery, hoisting machinery need not rise and play always Secondary beam can carry out other work, effectively improve hoisting machinery utilization rate.And by left suspension otic placode and right suspension otic placode, it is real Now secondary beam is supported, secondary beam no longer vacantly plays, avoids falling danger from eminence, made to the construction personnel on ground when avoiding falling At injury, construction risk is effectively avoided.In construction, after flooring is poured, concrete can cover left suspension otic placode and the right side is outstanding Earphone plate does not interfere with use and the appearance of secondary beam and entire flooring.Flooring steel beam structure described in the utility model, structure letter It is single, it is at low cost, it, can be by the way that the suspension otic placode in flooring steel beam structure secondary beam position be arranged, by floor steel when flooring is installed Girder construction secondary beam is articulated on installed girder, installs secondary beam as temporary support using girder so that hoisting machinery (tower Hang, crane) secondary beam can be detached from and carry out other work, have the function that improve hoisting machinery utilization rate, while secondary beam is not It again is at vacant state, avoids secondary beam from being fallen in hoisting process and ground construction personnel is damaged, improves construction peace Entirely.
Description of the drawings
Brief description is made to the content expressed by each attached drawing of this specification and the label in figure below:
Fig. 1 is the structural schematic diagram of flooring steel beam structure described in the utility model;
Fig. 2 is the positive structure diagram when girder of flooring steel beam structure described in the utility model is connect with secondary beam;
Fig. 3 is the backsight structural representation when girder of flooring steel beam structure described in the utility model is connect with secondary beam;
Attached drawing acceptance of the bid, which is remembered, is respectively:1, girder;2, secondary beam;3, left suspension otic placode;4, right suspension otic placode;5, left body part; 6, left suspension part;7, right body part;8, right suspension part;9, girder upper surface I;10, girder upper surface II;11, left connecting hole; 12, right connecting hole;13, left connection board part;14, left panel hole;15, right connection board part;16, right panel hole;17, flooring girder steel.
Specific implementation mode
Below against attached drawing, by the description of the embodiment, for example involved to specific embodiment of the present utility model Mutual alignment and connection relation, the effect of each section and operation principle between the shape of each component, construction, each section etc. make into The detailed description of one step:
As shown in attached drawing 1- attached drawings 3, the utility model is a kind of flooring steel beam structure, and the flooring steel beam structure includes Multiple tracks girder 1, multiple tracks secondary beam 2, per setting multiple tracks secondary beam 2 between adjacent twice girder 1, plate knot is arranged in 2 left end of per pass secondary beam The right suspension otic placode 4 of plate structure is arranged in the left suspension otic placode 3 of structure, 2 right end of per pass secondary beam, and per pass secondary beam 2 is arranged adjacent two When between road girder 1, which is configured to the structure being resisted against by left suspension otic placode 3 on one of girder 1, should 2 right end of secondary beam is configured to the structure being resisted against by right suspension otic placode 4 on another road girder 1.Above structure is applied in flooring Before work, the secondary girder construction of steel beam structure is improved, after processing secondary beam, left suspension ear is set in per pass secondary beam left end Right suspension otic placode is arranged in per pass secondary beam right end in plate.Then when installing secondary beam, secondary beam is lifted by crane by hoisting machinery, by secondary beam It is placed between twice girder, then puts down secondary beam, secondary beam one end is resisted against by left suspension otic placode 3 on one of girder 1, secondary beam 2 other ends are resisted against by right first earphone plate 4 on another road secondary beam 2, and at this moment left suspension otic placode and right suspension otic placode are realized to secondary Then the support of beam 2 unclamps again hoisting machinery, hoisting machinery need not rise and play secondary beam 2 always, can carry out other work, To effectively improve hoisting machinery utilization rate.And by left suspension otic placode and right suspension otic placode, it realizes and secondary beam is supported, secondary beam is not It vacantly plays, to effectively avoid falling danger from eminence, the construction personnel on ground is damaged when avoiding falling, effectively again Avoid construction risk.And in construction, after flooring is poured, concrete can cover left suspension otic placode and right suspension otic placode, no It can influence use and the appearance of secondary beam and entire flooring.Flooring steel beam structure described in the utility model, it is simple in structure, it is manufactured into This is low, can be by the way that the suspension otic placode in flooring steel beam structure secondary beam position is arranged, by flooring steel beam structure when flooring is installed Secondary beam is articulated on installed girder, and secondary beam is installed as temporary support using girder so that (tower crane rises hoisting machinery Heavy-duty machine) secondary beam can be detached from and carry out other work, to have the function that improve hoisting machinery utilization rate, while secondary beam is no longer It in vacant state, avoids secondary beam from being fallen in hoisting process and ground construction personnel is damaged, improve construction safety.
The left suspension otic placode 3 includes left body part 5 and left suspension part 6, is set between left body part 5 and left suspension part 6 It is set to the structure in inverted L-shaped, the right suspension otic placode 4 includes right body part 7 and right suspension part 8, and right body part 7 and the right side are outstanding The structure in inverted L-shaped is set as between extension portion 8.The left body part of above structure, left suspension otic placode realizes secondary beam and left suspension part Connection, left suspension part then realizes the support on girder, and the right body part of right suspension otic placode realizes secondary beam and right suspension part Connection, right suspension part then realizes the support on girder, as long as in this way, lift by crane secondary beam, and secondary beam is placed on twice girder Between, it will be able to realize the secure support of secondary beam so that the placement and support of secondary beam are extremely convenient and quick, effectively improve construction effect Rate.
When per pass secondary beam 2 is arranged between adjacent twice girder 1, the left suspension part 6 of the left suspension otic placode 3 of the road secondary beam 2 It is configured to be resisted against the structure of the girder upper surface I 9 of one of girder 1, the right suspension of the right suspension otic placode 4 of the road secondary beam 2 Portion 8 is configured to be resisted against the structure of the girder upper surface II 10 of another road girder 1, and the flooring passes through concreting Afterwards, the concrete of flooring is configured to the structure being enclosed in left suspension part and right suspension part in concrete.Above structure, After secondary beam is placed between twice girder, left suspension otic placode and right suspension otic placode realize support of the secondary beam on twice girder, and When flooring casting concrete, casting concrete above girder and above secondary beam, after concreting, concrete can be by master Beam, secondary beam and left suspension otic placode, right suspension otic placode are completely enclosed in concrete, in this way, left suspension otic placode and right suspension otic placode It will not have any impact to steel beam structure in structure, flooring appearance will not be influenced, to effectively improve flooring construction While efficiency, additionally it is possible to ensure that flooring construction quality will not be affected.
The left body part 5 of the left suspension otic placode 3 and left suspension part 6 are an integral structure, the right suspension otic placode 4 Right body part 7 and right suspension part 8 be an integral structure, the left body part 5 of the left suspension otic placode 3 on per pass secondary beam 2 and secondary beam 2 One end side is configured to the structure being fixedly connected by welding manner or bolt, the right suspension otic placode 4 on per pass secondary beam 2 Right body part 6 is configured to the structure being fixedly connected by welding manner or bolt with 2 other end side of secondary beam.Above-mentioned knot Structure, it is left suspension otic placode 3 left body part 5 and left suspension part 6 be an integral structure, in this way, it is only necessary to by left suspension otic placode according to Shape design above, is then fixedly connected with secondary beam one end by welding manner or bolt, by right suspension otic placode according to above Shape design, be then fixedly connected by welding manner or bolt with the secondary beam other end, connection is reliable.
Multiple left connecting holes 11 are arranged in 2 left end of per pass secondary beam, and multiple right connecting holes 12 are arranged in 2 right end of per pass secondary beam, and secondary The left connection board part 13 of protrusion is arranged in one of girder, 1 inside connected on the left of beam 2, is arranged and left connecting hole on left connection board part 13 The right side of protrusion is arranged in left panel hole 14,1 inside of girder together being connect with 2 right side of secondary beam correspondingly for 11 quantity and position Attaching plate elements 15, setting and the quantity of right connecting hole 12 and position right panel hole 16 correspondingly on right connection board part 15.Often When road secondary beam 2 is arranged between adjacent twice girder 1, each left connection bolt is configured to across 11 He of left connecting hole The structure of one left panel hole 14, each right connection bolt are configured to across a right connecting hole 12 and a right panel part The structure in hole 16.Above structure, by the setting of left connection board part and right connection board part, secondary beam by left suspension otic placode and After right suspension otic placode is hooked between twice girder, the connection of left connection board part and secondary beam is realized by left connection bolt, is passed through Right connection bolt realizes the connection of secondary beam and another road girder, it is ensured that in the construction process, further realizes girder and secondary beam Connection effectively avoids because left suspension otic placode and right suspension otic placode are fallen off with secondary beam, and secondary beam remains able to and twice master Beam is reliably connected, and high-altitude is avoided to fall danger.
It is simple that the utility model further relates to a kind of step, can convenient and efficient completion flooring girder steel construction, improve construction effect Rate avoids hoisting machinery from wasting, while can effectively improve the floor steel beam construction method of construction safety.
The construction procedure of floor steel beam construction method described in the utility model is:1) left in the 2 left side setting of per pass secondary beam Otic placode 3 is hung, right suspension otic placode 4 is set on 2 right side of per pass secondary beam;2) by crane loading secondary beam 2, a left side for secondary beam 2 is hanged Earphone plate 3 is resisted against on one of girder 1, and the right suspension otic placode 4 of secondary beam 2 is resisted against on another road girder 1;3) by crane It is detached from secondary beam 2;To after placement secondary beam 2 and girder 1 be attached;4) according to above-mentioned arrangement, the lifting of multiple tracks secondary beam 2 is completed And connection.
When carrying out the construction of flooring girder steel, the girder 1 that multiple tracks presses gap arrangement is first set, between every adjacent twice girder 1 The secondary beam 2 that multiple tracks presses gap arrangement is set, after the multiple tracks secondary beam 2 between adjacent twice girder 1 is placed, to 2 shape of girder 1 and secondary beam At flooring girder steel 17 carry out concreting, form flooring, flooring is by the left suspension otic placode 3 of per pass secondary beam 2 and right suspension ear Plate 4 is imbedded in concrete.
Floor steel beam construction method described in the utility model, step is simple, at low cost, when flooring is installed, by setting The suspension otic placode in flooring steel beam structure secondary beam position is set, flooring steel beam structure secondary beam is articulated on installed girder, Secondary beam is installed as temporary support using girder so that hoisting machinery (tower crane, crane) can be detached from secondary beam and carry out other Work, to have the function that improve hoisting machinery utilization rate, while secondary beam is no longer on vacant state, and secondary beam is avoided to lift It falls in the process and ground construction personnel is damaged, improve construction safety.Flooring is formed after concreting, is not needed Left suspension otic placode and right suspension otic placode are cut, left suspension otic placode and right suspension otic placode can further function as supporting role, improve Flooring intensity.
The flooring steel beam structure and floor steel beam construction method of the utility model carry out secondary girder construction before flooring construction It improves, after processing secondary beam, left suspension otic placode is set in per pass secondary beam left end, right suspension otic placode is set in per pass secondary beam right end. Then when installing secondary beam, secondary beam is lifted by crane by hoisting machinery and then puts down secondary beam between secondary beam is placed into twice girder, Secondary beam one end is resisted against by left suspension otic placode on one of girder, and the secondary beam other end is resisted against another passage by right first earphone plate Liang Shang, at this moment the support of left suspension otic placode and right suspension otic placode realization to secondary beam, then unclamps hoisting machinery, hoisting machinery is not required to Always it to rise and play secondary beam, other work can be carried out, effectively improve hoisting machinery utilization rate.And pass through left suspension otic placode and the right side Otic placode is hung, realizes and secondary beam is supported, secondary beam no longer vacantly plays, avoids falling danger from eminence, to ground when avoiding falling Construction personnel damage, effectively avoid construction risk.In construction, after flooring is poured, concrete can cover left outstanding Earphone plate and right suspension otic placode do not interfere with use and the appearance of secondary beam and entire flooring, and need not be cut after the completion of constructing yet Cut left suspension otic placode and right suspension otic placode.The flooring steel beam structure and floor steel beam construction method of the utility model, it is at low cost, When flooring is installed, flooring steel beam structure secondary beam can be hung by the way that the suspension otic placode in flooring steel beam structure secondary beam position is arranged It is connected on installed girder, secondary beam is installed as temporary support using girder so that hoisting machinery (tower crane, crane) can Other work are carried out to be detached from secondary beam, have the function that improve hoisting machinery utilization rate, while secondary beam is no longer on hanging shape State avoids secondary beam from being fallen in hoisting process and is damaged to ground construction personnel, improves construction safety.
Illustrative description is carried out to the utility model above in conjunction with attached drawing, it is clear that the utility model concrete implementation is simultaneously It is not limited by aforesaid way, if the various improvement of the methodology and technical solution progress of the utility model are used, or It is not improved that the design of the utility model and technical solution are directly applied into other occasions, in the protection of the utility model In range.

Claims (6)

1. a kind of flooring steel beam structure, the flooring steel beam structure includes multiple tracks girder (1), multiple tracks secondary beam (2), per adjacent two Multiple tracks secondary beam (2) is set between road girder (1), it is characterised in that:The left suspension ear of plate structure is arranged in per pass secondary beam (2) left end The right suspension otic placode (4) of plate structure is arranged in plate (3), per pass secondary beam (2) right end, and per pass secondary beam (2) is arranged in adjacent twice master When between beam (1), which is configured to the knot being resisted against by left suspension otic placode (3) on one of girder (1) Structure, secondary beam (2) right end are configured to the structure being resisted against by right suspension otic placode (4) on another road girder (1).
2. flooring steel beam structure according to claim 1, it is characterised in that:The left suspension otic placode (3) includes left Body portion (5) and left suspension part (6) are set as the structure in inverted L-shaped, the right side between left body part (5) and left suspension part (6) Hang otic placode (4) include right body part (7) and right suspension part (8), be set as between right body part (7) and right suspension part (8) be in The structure of inverted L-shaped.
3. flooring steel beam structure according to claim 1, it is characterised in that:Per pass secondary beam (2) is arranged in adjacent twice master When between beam (1), the left suspension part (6) of the left suspension otic placode (3) of the road secondary beam (2) is configured to be resisted against one of girder (1) structure of girder upper surface I (9), the right suspension part (8) of the right suspension otic placode (4) of the road secondary beam (2) be configured to The structure for leaning against the girder upper surface II (10) of another road girder (1), after the flooring is by concreting, flooring mixes Solidifying soil is configured to the structure being enclosed in left suspension part (6) and right suspension part (8) in concrete.
4. flooring steel beam structure according to claim 1, it is characterised in that:The left ontology of the left suspension otic placode (3) Portion (5) and left suspension part (6) are an integral structure, the right body part (7) of the right suspension otic placode (4) and right suspension part (8) It is an integral structure, left body part (5) and secondary beam (2) one end side of the left suspension otic placode (3) on per pass secondary beam (2) are set as The structure that can be fixedly connected by welding manner or bolt, the right body part of the right suspension otic placode (4) on per pass secondary beam (2) (6) it is configured to the structure being fixedly connected by welding manner or bolt with secondary beam (2) other end side.
5. flooring steel beam structure according to claim 1, it is characterised in that:Multiple left companies are arranged in per pass secondary beam (2) left end Hole (11) is connect, multiple right connecting holes (12) are arranged in per pass secondary beam (2) right end, in one of the girder (1) being connect on the left of secondary beam (2) The left connection board part (13) of side setting protrusion, setting and the quantity of left connecting hole (11) and position be one by one on left connection board part (13) Corresponding left panel hole (14), with the right connection board part of setting protrusion on the inside of one of the girder (1) being connect on the right side of secondary beam (2) (15), setting and the quantity of right connecting hole (12) and position right panel hole (16) correspondingly on right connection board part (15).
6. flooring steel beam structure according to claim 1, it is characterised in that:Per pass secondary beam (2) is arranged in adjacent twice master When between beam (1), each left connection bolt is configured to across a left connecting hole (11) and left panel hole (14) Structure, each right connection bolt are configured to the structure across a right connecting hole (12) and a right panel hole (16).
CN201721340572.XU 2017-10-16 2017-10-16 A kind of flooring steel beam structure Expired - Fee Related CN207761166U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721340572.XU CN207761166U (en) 2017-10-16 2017-10-16 A kind of flooring steel beam structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721340572.XU CN207761166U (en) 2017-10-16 2017-10-16 A kind of flooring steel beam structure

Publications (1)

Publication Number Publication Date
CN207761166U true CN207761166U (en) 2018-08-24

Family

ID=63178633

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721340572.XU Expired - Fee Related CN207761166U (en) 2017-10-16 2017-10-16 A kind of flooring steel beam structure

Country Status (1)

Country Link
CN (1) CN207761166U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107762065A (en) * 2017-10-16 2018-03-06 杭萧钢构(安徽)有限公司 A kind of flooring steel beam structure and floor steel beam construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107762065A (en) * 2017-10-16 2018-03-06 杭萧钢构(安徽)有限公司 A kind of flooring steel beam structure and floor steel beam construction method

Similar Documents

Publication Publication Date Title
CN107762065A (en) A kind of flooring steel beam structure and floor steel beam construction method
CN104652298B (en) A kind of whole dismounting system and construction method thereof transferred across box beam supported based on bridge floor
CN103669902A (en) Cast-in-place beam support truss integral dropping and dismounting tool and construction method thereof
CN109440985A (en) Super high-rise building super large curtain wall unit hydraulic synchronizing lifting system and its construction method
CN207761166U (en) A kind of flooring steel beam structure
CN104895335A (en) Method for mounting hanging pillar
CN103552911B (en) A kind of movable boom hoisting and the construction installation method of use thereof
CN105932601A (en) Method for repairing break strand of overhead ground wire
CN202822531U (en) Safety rope fixing support
CN204212065U (en) Bridge crossing anticollision barrier punching block erection equipment
CN209177842U (en) Fixed system
CN205875168U (en) A prevent structure of falling for foundation ditch steel shotcrete
CN206289544U (en) A kind of simple electric nacelle device
CN109488008A (en) A kind of coupling type hanger job platform
CN109138272A (en) A kind of Super High rod iron group is connected and fixed device and method
CN211923034U (en) Building steel structure connecting piece
CN201703960U (en) Hoisting clamp of electric dust removal and collecting pole plate
CN205088580U (en) Iron road bridge mound hanging flower basket installation frock
CN202990386U (en) Externally-suspended scaffold
CN204038917U (en) Dismountable external hanging service platform
CN202831591U (en) Special-shaped truss operation platform capable of hoisting to super high space
CN205772813U (en) For 40 tons of door machines built-in decelerator remove and install one suspender
CN203022327U (en) Elevator shaft high-altitude construction platform device
CN110950254A (en) Quick mounting and dismounting type tower crane attachment operation platform and manufacturing method thereof
CN205892526U (en) Hoist and mount platform of spinning corridor equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180824

Termination date: 20211016

CF01 Termination of patent right due to non-payment of annual fee