CN207753464U - The more same period point auto-parallel systems of generating set - Google Patents

The more same period point auto-parallel systems of generating set Download PDF

Info

Publication number
CN207753464U
CN207753464U CN201721837373.XU CN201721837373U CN207753464U CN 207753464 U CN207753464 U CN 207753464U CN 201721837373 U CN201721837373 U CN 201721837373U CN 207753464 U CN207753464 U CN 207753464U
Authority
CN
China
Prior art keywords
busbar
control unit
grid
generator
same period
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721837373.XU
Other languages
Chinese (zh)
Inventor
马猛忠
杨建栋
周邦栋
李锋
张伯兴
张旭
黄凯
孙希龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SDIC QINZHOU ELECTRIC POWER Co Ltd
Original Assignee
SDIC QINZHOU ELECTRIC POWER Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SDIC QINZHOU ELECTRIC POWER Co Ltd filed Critical SDIC QINZHOU ELECTRIC POWER Co Ltd
Priority to CN201711419496.6A priority Critical patent/CN107887931A/en
Priority to CN201721837373.XU priority patent/CN207753464U/en
Application granted granted Critical
Publication of CN207753464U publication Critical patent/CN207753464U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/38Arrangements for parallely feeding a single network by two or more generators, converters or transformers
    • H02J3/40Synchronising a generator for connection to a network or to another generator
    • H02J3/42Synchronising a generator for connection to a network or to another generator with automatic parallel connection when synchronisation is achieved

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The utility model discloses a kind of more same period point auto-parallel systems of generating set, by in I busbar, II busbar and being connected on each user's line on I, II busbar and being mounted on system side voltage measurement unit, generating set is when grid-connected, by on generator wait for and side voltage measurement unit is incuded with wherein any one system side voltage measurement unit, when meeting simultaneous interconnecting condition, cutting-in control unit is controlled in synchronous device, cutting-in control unit is made to open each grid-connected disconnecting link/switch successively.Compared with prior art, as long as any one same period point in network system is normal, the paired running of generator can be achieved, substantially increase the grid connection efficiency of generating set, ensure that the stable operation of the power supply and distribution in system side;The row swithes that the utility model is used to execute grid-connected action simultaneously are 2 so that row swithes failure one of in this system nor affects on the grid-connected of generator, and grid-connected more convenient and flexible in the selection of branch.

Description

The more same period point auto-parallel systems of generating set
Technical field
The utility model is related to a kind of generating set auto-parallel devices, and in particular to the more same period points of generating set are automatically simultaneously Net system.
Background technology
In power plant, simultaneous interconnecting is a great operation before power plants generating electricity.Excitation, steam turbine, disconnecting link is needed to open Cooperation between each systems such as pass, DCS controls, it is final to realize that generator stable is connected to the grid, stable electric power is sent into power grid. Once misoperation may cause the abnormal accidents such as system fluctuation, oscillation, can be caused when serious generator asynchronous it is grid-connected, hair The serious electrical accident that motor damage, power grid spring are netted.Generator synchronous grid-connected principle is:By acquiring generator (or main transformer High-pressure side) voltage transformer (i.e. PT) in outlet voltage compared with the voltage of system side, when reaching setting condition (including When the conditions such as voltage magnitude, phase sequence, phase, the frequency of both sides) reclosing command is sent out, it will by being closed generator outlet breaker Generator and system grid connection realize electrical energy transportation.Generator synchronous grid-connected system is the key that generator and power grid paired running The reliability of equipment, function is most important.It is existing to have automatic synchronizing paralleling, same manually for generating set simultaneous interconnecting pattern Phase is grid-connected and automatic presynchronization is grid-connected, but no matter which kind of grid-connect mode used, generating set and network process be configured with phase The synchronous device answered is to achieve the purpose that automatically control.
As shown in Figure 1, the partial electric connection figure of the conventional electric generators simultaneous interconnecting originally used for our company.From figure It is not difficult to find out, exporting disconnecting link 20011 (being that row illustrate with I busbares) by transformer unit in system side is led to 220KVI busbares PT Automatic sub-synchronous device waits for that simultaneously side 1PT or 2PT carry out same period condition confirmation as on generator.When grid-connected, when waiting for And the voltage magnitude of side PT, phase sequence, phase, frequency with when all same, synchronous device can just send out closure power generation on busbar PT Machine exports the instruction of knife switch, could complete the operation of generator connecting in parallel with system in this way.Therefore, the PT in system side is also referred to as grid-connected Same period point, only there are one the same period points when traditional generator auto-parallel.Only there are one the generating set auto-parallels of same period point Although technology is connecting up and is controlling the upper relatively simple operation of operation, when the outlet PT or generating set being located in bus bar side When switch tool breaks down, generator is arranged side by side with system by termination, needs to wait for carry out after troubleshooting grid-connected.This Sample not only delays the set grid-connection time, makes the fluctuation of service of the power supply and distribution in system side, reduces Business Economic Benefit;This Outside, only there are one row swithes for the outlet of generator, and connection type is single, grid-connected to use underaction.
Utility model content
To overcome drawbacks described above, the technical problem to be solved by the utility model is to provide one kind with multiple mutual indepedent Grid-connected same period point generating set auto-parallel system, as long as the grid-connected system have one of them same period point normal work Realize the grid-connected of generating set.
In order to achieve the above objectives, the utility model is achieved through the following technical solutions:
The more same period point auto-parallel systems of generating set include for generator synchronous grid-connected network system and for controlling The synchronous device of network system auto-parallel, the network system include I busbar being in parallel, II busbar and are connected on I busbar, II N subscriber lines on busbar, the network system further include cutting-in control unit corresponding with the quantity of user's line, one with Family line corresponds to the output end of one cutting-in control unit of access, the input terminal of cutting-in control unit and the branch where generator outlet Road connects, and the cutting-in control unit is mounted on and controls generator between I busbar and II busbar and under the control of synchronous device Execute grid-connected action;It is mounted on system side voltage measurement unit on I busbar, II busbar and each user's line, wherein n is >= 1 integer.
In said program, the cutting-in control unit may include a plug-in strip control unit, master control disconnecting link, secondary plug-in strip control Unit, a row swithes and secondary row swithes processed, wherein
One end of plug-in strip control unit and the branch where generator outlet connect, and the other end is divided into two Branch:A wherein branch is connected to after a row swithes on I busbar, the input terminal of another branch and master switch connects It connects;The output end of the master switch is divided into two branches:Wherein a branch is connected to II after secondary plug-in strip control unit Busbar, another branch are connect after secondary row swithes with corresponding user's line;On the branch road where generator outlet Installation needs and side voltage measurement unit.
In said program, it is further preferred that the value of the n is 2, that is, there are 2 user's lines to be connected on I busbar, on II busbar.
The beneficial effects of the utility model are:
1) the utility model in I busbar, II busbar and being connected on each user's line on I, II busbar by being mounted on System side voltage measurement unit, generating set when grid-connected, by generator wait for and side voltage measurement unit with wherein appoint One system side voltage measurement unit of meaning is incuded, when meeting simultaneous interconnecting condition, in synchronous device to cutting-in control list Member is controlled, to make cutting-in control unit open each grid-connected disconnecting link/switch successively.With only incuded there are one same period point Existing simultaneous interconnecting device compare, as long as any one same period point (system side voltage measurement unit) in network system is just Often, the paired running of generator can be achieved;And traditional interconnection technology can only be a same period point, once the same period in system side Point break down will be unable to carry out generator and net operation.The grid-connected effect of generating set will be greatly improved using grid-connected system Rate, and can guarantee the stable operation of power supply and distribution in system side, improve Business Economic Benefit;
2) row swithes in the cutting-in control unit designed in the utility model for executing grid-connected action are 2, are made Row swithes failure one of in this system, nor affect on the grid-connected of generator, and it is grid-connected in the selection of branch more It is convenient and flexible to add.
Description of the drawings
Fig. 1 is the partial electric connection figure of traditional 1 generating set auto-parallel.
When Fig. 2 is 3 same period points, the electrical connection diagram of 1 generating set auto-parallel.
When Fig. 3 is 3 same period points, the electrical connection diagram of 2 generating set auto-parallels.
1, system side voltage measurement unit, 2, wait for and side voltage measurement unit, 3, plug-in strip control units, 4, secondary lock Knife control unit, 5, row swithes, 6, secondary row swithes, 7, master control disconnecting link, 8, cutting-in control unit.
Specific implementation mode
Embodiment 1
The more same period point auto-parallel systems of generating set include for generator synchronous grid-connected network system and for controlling The synchronous device of network system auto-parallel.Composition and the same period used in the prior art in the synchronous device main body are simultaneously Net device is the same.Except that:Each electrical detection component, control chopper switch on improved cutting-in control unit 8 The increase and connection of adaptability are done, and does adaptable logic control instruction in controller on synchronous device and improves.The electricity Net system includes I busbar being in parallel, II busbar and is connected on I busbar, the n subscriber lines on II busbar.
The network system further includes cutting-in control unit corresponding with the quantity of user's line 8.As shown in Fig. 2, being one Electrical connection diagram corresponding to subscriber lines when one group of generator connecting in parallel with system, i.e. n=1.It is grid-connected that one subscriber lines correspond to access one The output end of control unit 8, the input terminal of cutting-in control unit 8 and the branch where generator outlet connect.Described and network control Unit 8 processed, which is mounted between I busbar and II busbar and controls generator under the control of synchronous device, executes grid-connected action. It is mounted on system side voltage measurement unit 1 on I busbar, II busbar and each user's line.The system side voltage measurement unit 1 PT points as in network system, the specially same period point of generator connecting in parallel with system.It is not difficult to find out from Fig. 2, even if on two busbares It only connects there are one user's line, also has 3 same period points in this simultaneous interconnecting system, be in I busbar, II busbar and user's line successively On.
In the present embodiment, the cutting-in control unit 8 includes a plug-in strip control unit 3, master control disconnecting link 7, secondary plug-in strip 4, row swithes 5 of control unit and secondary row swithes 6.One end of plug-in strip control unit 3 goes out with generator Branch connection where mouthful, the other end are divided into two branches:A wherein branch is connected to I mother after a row swithes 5 On line, the input terminal of another branch and master switch connects.The output end of the master switch is divided into two branches:Wherein one Branch be connected to after secondary plug-in strip control unit 4 II busbar, another branch after secondary row swithes 6 with it is corresponding User's line connects.It is equipped on the branch road where generator outlet and waits for simultaneously side voltage measurement unit 2, wait for simultaneously side voltage measurement list Member 2 is on installation generator outlet and PT corresponding with the PT points in system side.
Above system side voltage measurement unit 1 and wait for and side voltage measurement unit 2 be specifically existing structure voltage it is mutual Sensor and mating electric components.
4, row swithes 5 of a plug-in strip control unit 3, master control disconnecting link 7, secondary plug-in strip control unit of above-mentioned use With secondary row swithes 6 use electrical equipment model, quantity and composition according to the voltage value on I busbar, II busbar come into Row selection.
The utility model is when in use:1) when on I busbar and II busbar system side voltage measurement unit 1 and two mothers When each way switch disconnecting link on line is normal, wait for and side voltage measurement unit 2 preferentially with the system side voltage measurement list on I busbar Member 1 is corresponded to, and when the parameter obtained after corresponding mutual inductance meets the condition of simultaneous interconnecting, synchronous device remote control is primary 3, row swithes 5 of plug-in strip control unit, master switch and secondary plug-in strip control unit 4 are opened, and generator executes grid-connected behaviour Make;
2) when the switch tool on the system side voltage measurement unit 1 or busbar on I busbar and II busbar breaks down, It waits for and side voltage measurement unit 2 carries out corresponding with the system side voltage measurement unit 1 on user's line, obtained after corresponding mutual inductance When parameter meets the condition of simultaneous interconnecting, 3, row swithes 5 of plug-in strip control unit of synchronous device remote control, master Control switch, secondary plug-in strip control unit 4 and secondary row swithes 6 are opened, and generator executes and net operation.
Embodiment 2
As shown in figure 3, the more same period point auto-parallel systems of generating set and embodiment 1 are the difference is that the n Value is 2.That is two user's lines are connected on I busbar, on II busbar, and there are two generators to carry out simultaneous interconnecting in simultaneous interconnecting There are 3 same period points in system, is on I busbar, II busbar and user's line successively.Certainly, according to the power supply and distribution demand of power grid, The user's line accessed on two busbares can be multiple, therefore the same period point quantity where it in system side of simultaneous interconnecting also corresponds to Increase, can further improve the reliability of simultaneous interconnecting.
It these are only the embodiment for illustrating the utility model, be not intended to limit the utility model, for this field For technical staff, within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on, It should be included within the scope of protection of this utility model.

Claims (3)

1. the more same period point auto-parallel systems of generating set include for generator synchronous grid-connected network system and for controlling electricity The synchronous device of net system auto-parallel, the network system include I busbar being in parallel, II busbar and are connected on I busbar, II female N subscriber lines on line, it is characterised in that:The network system further includes cutting-in control list corresponding with the quantity of user's line First (8), a subscriber lines correspond to the output end of one cutting-in control unit (8) of access, cutting-in control unit (8) input terminal with Branch connection where generator outlet, the cutting-in control unit (8) are mounted between I busbar and II busbar and in the same period Control generator executes grid-connected action under the control of device;It is mounted on system side on I busbar, II busbar and each user's line Voltage measurement unit (1), the integer that wherein n is >=1.
2. the more same period point auto-parallel systems of generating set according to claim 1, it is characterised in that:The cutting-in control Unit (8) includes a plug-in strip control unit (3), master control disconnecting link (7), secondary plug-in strip control unit (4), a row swithes (5) and secondary row swithes (6), wherein one end of the primary plug-in strip control unit (3) and the branch where generator outlet Connection, the other end are divided into two branches:A wherein branch is connected to after a row swithes (5) on I busbar, another The input terminal of branch and master switch connects;The output end of the master switch is divided into two branches:Wherein a branch is through two Be connected on II busbar after secondary plug-in strip control unit (4), another branch after secondary row swithes (6) with corresponding user Line connects;It is equipped on the branch road where generator outlet and waits for simultaneously side voltage measurement unit (2).
3. the more same period point auto-parallel systems of generating set according to claim 1, it is characterised in that:The value of the n is 2。
CN201721837373.XU 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set Active CN207753464U (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201711419496.6A CN107887931A (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set
CN201721837373.XU CN207753464U (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201711419496.6A CN107887931A (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set
CN201721837373.XU CN207753464U (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set

Publications (1)

Publication Number Publication Date
CN207753464U true CN207753464U (en) 2018-08-21

Family

ID=69419866

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201721837373.XU Active CN207753464U (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set
CN201711419496.6A Pending CN107887931A (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201711419496.6A Pending CN107887931A (en) 2017-12-25 2017-12-25 The more same period point auto-parallel systems of generating set

Country Status (1)

Country Link
CN (2) CN207753464U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107887931A (en) * 2017-12-25 2018-04-06 国投钦州发电有限公司 The more same period point auto-parallel systems of generating set
CN110011353A (en) * 2019-03-19 2019-07-12 上海唐银投资发展有限公司 A kind of parallel operation control system and method for diesel-driven generator power supply-distribution system

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110556875A (en) * 2018-05-31 2019-12-10 深圳中广核工程设计有限公司 Unit synchronization system for large power plant
CN111934353B (en) * 2020-07-03 2022-07-05 华电电力科学研究院有限公司 Method for obtaining false synchronization grid-connected signals of unit and optimizing synchronization grid-connected signals

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100315981B1 (en) * 1999-12-29 2001-12-12 김형국 Test device for Generator automatic synchronizer
CN106099973A (en) * 2016-06-29 2016-11-09 华能重庆两江燃机发电有限责任公司 A kind of Rhizoma Sparganii M701F4 type 3 simultaneous interconnecting implementation methods of unit gas turbine transformer unit
CN106684927B (en) * 2017-03-30 2019-04-02 山东中实易通集团有限公司 A kind of medium-and-large-sized generating set grid-connected system of Isolated Network System and combination method
CN207753464U (en) * 2017-12-25 2018-08-21 国投钦州发电有限公司 The more same period point auto-parallel systems of generating set

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107887931A (en) * 2017-12-25 2018-04-06 国投钦州发电有限公司 The more same period point auto-parallel systems of generating set
CN110011353A (en) * 2019-03-19 2019-07-12 上海唐银投资发展有限公司 A kind of parallel operation control system and method for diesel-driven generator power supply-distribution system
CN110011353B (en) * 2019-03-19 2022-12-27 上海唐银投资发展有限公司 Parallel operation control system and method for diesel generator power supply and distribution system

Also Published As

Publication number Publication date
CN107887931A (en) 2018-04-06

Similar Documents

Publication Publication Date Title
CN207753464U (en) The more same period point auto-parallel systems of generating set
CN104882906B (en) A kind of distributed micro-grid black starting-up control system and method based on photovoltaic and energy storage
Assis et al. Automatic reconnection from intentional islanding based on remote sensing of voltage and frequency signals
CN104009452A (en) Protection scheme for direct current distribution system short-circuit fault
CN102664459B (en) Medium-voltage electrically-propelled ship power management system and management method
CN105375519A (en) Grid-connected photovoltaic power generation system and control method therefor
CN108173267B (en) Offshore wind power plant and island microgrid combined monitoring system
CN102623994B (en) Substation area control method and system of microgrid operation mode
CN106356905A (en) Alternating-current and direct-current double-bus controllable power transmission system
CN203554074U (en) Distributed power generation grid-connected dual-power supply interface apparatus
CN202634066U (en) Power management system of medium-voltage electric propulsion ship
CN105960746A (en) Methods to form and operate multi-terminal power systems
CN107910855B (en) A kind of connection applied to intelligent substation cuts small power supply device
Ogden et al. Impacts of distributed generation on low-voltage distribution network protection
CN202524282U (en) Device for preventing frequency converter from power shaking
CN204465015U (en) Without the need to drawing the wiring system of power supply outward when a kind of power plant list returns back out line
CN204577857U (en) A kind of 110kV transformer station adopting novel wire connecting way
CN204761157U (en) A synthesize measurement and control device for distributed generator
CN103401227A (en) Fictitious load based rapid fault isolating method and system suitable for microgrid
CN110224432A (en) A kind of box-type substation and its microgrid system control method
CN203481822U (en) Closed loop power supply model of medium voltage 10 kilovolt power distribution network
CN210273512U (en) Micro-grid control system
CN208209526U (en) Marine wind electric field and island microgrid joint-monitoring system
CN106208078A (en) A kind of active power regulator control system controlled based on Multi-coil transformer and power
CN112952895A (en) Alternating current micro-grid based on forward and reverse direction impedance relay protection

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant