CN207749426U - A kind of bridge side guardrail template construction device - Google Patents

A kind of bridge side guardrail template construction device Download PDF

Info

Publication number
CN207749426U
CN207749426U CN201820056224.8U CN201820056224U CN207749426U CN 207749426 U CN207749426 U CN 207749426U CN 201820056224 U CN201820056224 U CN 201820056224U CN 207749426 U CN207749426 U CN 207749426U
Authority
CN
China
Prior art keywords
bar
workbench
rod
fixedly connected
suspension
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820056224.8U
Other languages
Chinese (zh)
Inventor
刘来君
郭洪超
杨懿杰
陈冰洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changan University
Original Assignee
Changan University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changan University filed Critical Changan University
Priority to CN201820056224.8U priority Critical patent/CN207749426U/en
Application granted granted Critical
Publication of CN207749426U publication Critical patent/CN207749426U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型公开了一种桥梁边护栏模板施工装置,包括工作台、车架、设置在桥梁上的车架滑轨、以及设置在车架上的模板吊装单元和工作台悬挂单元,车架包括底板,底板的下端设置有车架滑轮,模板吊装单元包括链轮和链轮手柄,链轮上缠绕有吊链,吊链的一端固定在链轮上,吊链的另一端连接有吊钩,底板上设置有吊链支撑杆,吊链支撑杆的一端固定设置在底板上,吊链支撑杆的另一端设置有吊链滑轮。本实用新型中,车架滑轮与车架滑轨滑动连接,提高了桥梁边护栏模板施工的便捷性,通过模板吊装单元和吊链支撑杆起吊桥梁边护栏模板,通过工作台悬挂单元将工作台设置在桥梁外侧,方便工作台上的施工人员进行桥梁边护栏模板施工。

The utility model discloses a bridge side guardrail formwork construction device, which comprises a workbench, a vehicle frame, a vehicle frame slide rail arranged on the bridge, a formwork hoisting unit and a workbench suspension unit arranged on the vehicle frame, and the vehicle frame includes Bottom plate, the lower end of the bottom plate is provided with a frame pulley, the formwork hoisting unit includes a sprocket and a sprocket handle, a hanging chain is wound on the sprocket, one end of the hanging chain is fixed on the sprocket, and the other end of the hanging chain is connected with a hook. A suspension chain support rod is arranged on the base plate, one end of the suspension chain support rod is fixedly arranged on the base plate, and the other end of the suspension chain support rod is provided with a suspension chain pulley. In the utility model, the frame pulley is slidably connected with the frame slide rail, which improves the convenience of bridge side guardrail formwork construction. The bridge side guardrail formwork is hoisted by the formwork hoisting unit and the hanging chain support rod, and the workbench is lifted by the workbench suspension unit. It is installed on the outside of the bridge, which is convenient for the construction personnel on the workbench to carry out the construction of the bridge side guardrail formwork.

Description

一种桥梁边护栏模板施工装置A bridge side guardrail formwork construction device

技术领域technical field

本实用新型属于桥梁建筑技术领域,具体涉及一种桥梁边护栏模板施工装置。The utility model belongs to the technical field of bridge construction, in particular to a bridge side guardrail formwork construction device.

背景技术Background technique

近几年来,我国桥梁建设快速发展,桥梁的建成和运营极大方便了群众的出行和沿途各地的经济发展。但随着我国经济的快速增长和桥梁运输事业的蓬勃发展,交通量迅速增长,特别是大型重载车辆的增多,直接导致桥梁交通设施使用频率以及负荷的增加,因此桥梁上车辆意外撞击造成的设备、设施的损坏日益增多,因此在土木工程建设领域,尤其是桥梁领域中,防撞边护栏设施是必不可少的。In recent years, my country's bridge construction has developed rapidly. The completion and operation of bridges have greatly facilitated the travel of the masses and the economic development of various places along the way. However, with the rapid growth of my country's economy and the vigorous development of bridge transportation, the traffic volume has increased rapidly, especially the increase in large and heavy-duty vehicles, which directly leads to the increase in the frequency of use of bridge transportation facilities and the increase in load, so accidental collisions caused by vehicles on bridges The damage of equipment and facilities is increasing day by day, so in the field of civil engineering construction, especially in the field of bridges, anti-collision side barrier facilities are indispensable.

防撞边护栏施工,特别是桥梁两端的边护栏施工往往受到很多限制长期以来,桥梁的边护栏施工一直都是高危工作,原因是桥梁一般都跨越水面或路面以上,桥面两侧边护栏的位置处于悬空状态,由于尚未施工防撞边护栏,使得桥梁上部结构充满了安全隐患,同时也提高了防撞边护栏施工的难度。The construction of anti-collision side guardrails, especially the construction of side guardrails at both ends of bridges, is often subject to many restrictions. The position is in a suspended state. Since the anti-collision side guardrail has not yet been constructed, the upper structure of the bridge is full of safety hazards, and it also increases the difficulty of the construction of the anti-collision side guardrail.

目前,桥梁边护栏施工工艺分为现浇和预制,现浇边护栏采用混凝土浇筑而成,混凝土基础连接牢固,可达到较高防护等级,但施工方法较为复杂,不便于现场施工,且安装后拆除通常为破坏性拆除,不可重复利用。预制边护栏采用混凝土预制模板,可重复利用,低碳环保,但是边护栏的外侧模板安装、拆卸过程中,施工人员高空作业比较费力,而且护栏施工周期长,在护栏施工周期内一直使用大型机械吊车进行模板吊装,不仅费用昂贵,而且大型机械吊车占地较多,不利于桥梁其他部位施工的同时进行。因此需要一种可用于桥梁边护栏模板施工并可以代替大型机械吊车的小型装置。At present, the construction technology of bridge side guardrails is divided into cast-in-place and prefabricated. The cast-in-place side guardrails are made of concrete, and the concrete foundation is firmly connected, which can achieve a higher protection level. Demolition is usually destructive and cannot be reused. The prefabricated side guardrail uses concrete prefabricated formwork, which is reusable and low-carbon and environmentally friendly. However, during the installation and disassembly of the outer formwork of the side guardrail, it is laborious for the construction personnel to work at heights, and the construction period of the guardrail is long. During the construction period of the guardrail, large machinery has been used The formwork hoisting by crane is not only expensive, but also large-scale mechanical cranes occupy a large area, which is not conducive to the simultaneous construction of other parts of the bridge. Therefore need a kind of small-sized device that can be used in bridge edge guardrail formwork construction and can replace large mechanical crane.

实用新型内容Utility model content

本实用新型所要解决的技术问题在于针对上述现有技术中的不足,提供一种桥梁边护栏模板施工装置,其结构简单、设计合理,车架滑轮与车架滑轨滑动连接,提高了桥梁边护栏模板施工的便捷性,通过模板吊装单元和吊链支撑杆起吊桥梁边护栏模板,通过工作台悬挂单元将工作台设置在桥梁外侧,方便工作台上的施工人员进行桥梁边护栏模板施工,使用操作方便,实用性强,使用效果好,便于推广使用。The technical problem to be solved by the utility model is to provide a bridge side guardrail formwork construction device for the deficiencies in the above-mentioned prior art, which has a simple structure and a reasonable design. Convenience of guardrail formwork construction, the bridge side guardrail formwork is lifted by the formwork lifting unit and the lifting chain support rod, and the workbench is set on the outside of the bridge through the workbench suspension unit, which is convenient for the construction personnel on the workbench to carry out bridge side guardrail formwork construction. The operation is convenient, the practicability is strong, the use effect is good, and it is convenient to popularize and use.

为解决上述技术问题,本实用新型采用的技术方案是:一种桥梁边护栏模板施工装置,其特征在于:包括工作台、车架、设置在桥梁上的车架滑轨、以及设置在车架上的模板吊装单元和工作台悬挂单元,所述车架包括底板、设置在底板上方的横杆和用于固定连接所述底板与横杆的车架斜杆,所述底板的下端设置有与所述车架滑轨滑动连接的车架滑轮,所述模板吊装单元包括链轮和用于转动所述链轮的链轮手柄,所述链轮上缠绕有吊链,所述吊链的一端固定连接在链轮上,所述吊链的另一端固定连接有吊钩,所述底板上设置有吊链支撑杆,所述吊链支撑杆的一端固定设置在底板上,所述吊链支撑杆的另一端设置有吊链滑轮,所述工作台悬挂单元包括分别设置在横杆两端的第一工作台吊装杆和第二工作台吊装杆,所述第一工作台吊装杆上设置有用于连接工作台一端的第一吊索,所述第二工作台吊装杆上设置有用于连接工作台另一端的第二吊索。In order to solve the above-mentioned technical problems, the technical solution adopted by the utility model is: a bridge side guardrail formwork construction device, which is characterized in that it includes a workbench, a vehicle frame, a vehicle frame slide rail arranged on the bridge, and a vehicle frame formwork hoisting unit and workbench suspension unit, the vehicle frame includes a bottom plate, a cross bar arranged above the bottom plate, and a vehicle frame slant bar for fixedly connecting the bottom plate and the cross bar, and the lower end of the bottom plate is provided with a The frame pulley slidably connected to the frame slide rail, the template hoisting unit includes a sprocket and a sprocket handle for rotating the sprocket, a suspension chain is wound around the sprocket, and one end of the suspension chain Fixedly connected to the sprocket, the other end of the suspension chain is fixedly connected with a suspension hook, the bottom plate is provided with a suspension chain support rod, one end of the suspension chain support rod is fixedly arranged on the bottom plate, and the suspension chain supports The other end of the bar is provided with a chain pulley, and the workbench suspension unit includes a first workbench lifting rod and a second workbench lifting rod respectively arranged at both ends of the cross bar, and the first workbench lifting rod is provided with a A first sling connected to one end of the workbench, and a second sling used to connect to the other end of the workbench is arranged on the second workbench lifting rod.

上述的一种桥梁边护栏模板施工装置,其特征在于:所述第一工作台吊装杆包括与横杆固定连接的第一斜杆和与所述第一斜杆固定连接的第一水平杆,所述第一吊索与第一水平杆固定连接;所述第二工作台吊装杆包括与横杆固定连接的第二斜杆和与所述第二斜杆固定连接的第二水平杆,所述第二吊索与第二水平杆固定连接。The above-mentioned bridge side guardrail formwork construction device is characterized in that: the first workbench hoisting rod includes a first oblique rod fixedly connected with the cross bar and a first horizontal rod fixedly connected with the first oblique rod, The first sling is fixedly connected to the first horizontal bar; the second workbench hoisting bar includes a second slanting bar fixedly connected to the cross bar and a second horizontal bar fixedly connected to the second slanting bar, so The second sling is fixedly connected to the second horizontal bar.

上述的一种桥梁边护栏模板施工装置,其特征在于:所述车架斜杆包括第三斜杆、第四斜杆、第五斜杆和第六斜杆,第三斜杆的一端和第四斜杆的一端分别与底板的一端固定连接,第三斜杆的另一端和第四斜杆的另一端均与横杆的一端固定连接,第五斜杆的一端和第六斜杆的一端分别与底板的另一端固定连接,第五斜杆的一端和第六斜杆的一端均与横杆的另一端固定连接。The above-mentioned bridge side guardrail formwork construction device is characterized in that: the frame slanting bar includes the third slanting bar, the fourth slanting bar, the fifth slanting bar and the sixth slanting bar, one end of the third slanting bar and the sixth slanting bar One end of the four oblique rods is fixedly connected with one end of the bottom plate respectively, the other end of the third oblique rod and the other end of the fourth oblique rod are fixedly connected with one end of the cross bar, one end of the fifth oblique rod and one end of the sixth oblique rod They are respectively fixedly connected with the other end of the bottom plate, and one end of the fifth oblique rod and one end of the sixth oblique rod are both fixedly connected with the other end of the cross bar.

上述的一种桥梁边护栏模板施工装置,其特征在于:所述吊链支撑杆为伸缩杆。The above-mentioned bridge side guardrail formwork construction device is characterized in that: the suspension chain support rod is a telescopic rod.

上述的一种桥梁边护栏模板施工装置,其特征在于:所述底板上设置有配重台。The above-mentioned bridge side guardrail formwork construction device is characterized in that: the bottom plate is provided with a counterweight platform.

本实用新型与现有技术相比具有以下优点:Compared with the prior art, the utility model has the following advantages:

1、本实用新型的结构简单、设计合理,体积小,不会占用较大的施工空间,有利于桥梁其他部位施工的同时进行,实现及使用操作方便。1. The utility model is simple in structure, reasonable in design, small in size, does not occupy a large construction space, is beneficial to the simultaneous construction of other parts of the bridge, and is easy to realize, use and operate.

2、本实用新型在底板的下端设置车架滑轮,在桥梁上设置车架滑轨,车架滑轮与车架滑轨滑动连接,因此底板可在桥梁上滑动,从而带动车架在桥梁上滑动,提高了桥梁边护栏模板施工的便捷性。2. In the utility model, frame pulleys are arranged at the lower end of the bottom plate, and frame slide rails are set on the bridge. The frame pulleys are slidingly connected with the frame slide rails, so the bottom plate can slide on the bridge, thereby driving the frame to slide on the bridge. , which improves the convenience of bridge side guardrail formwork construction.

3、本实用新型通过模板吊装单元和吊链支撑杆起吊桥梁边护栏模板,施工人员通过链轮手柄转动链轮,达到收放吊链的目的,从而改变吊钩的高度;吊链支撑杆上的吊链滑轮为对吊链提供支撑点,使得吊链在自然状态下以吊链滑轮的位置点垂直于地面,从而改变吊链的垂直位置,以此改变吊链上连接的吊钩与桥梁边护栏之间的距离,适应于不同的工作环境,使用效果好。3. The utility model lifts the bridge side guardrail template through the template hoisting unit and the hanging chain support rod, and the construction personnel rotate the sprocket through the chain wheel handle to achieve the purpose of retracting the lifting chain, thereby changing the height of the hook; The hanging chain pulley provides a support point for the hanging chain, so that the hanging chain is perpendicular to the ground at the position of the hanging chain pulley in the natural state, thereby changing the vertical position of the hanging chain, thereby changing the connection between the hook and the bridge on the hanging chain The distance between the side guardrails is suitable for different working environments, and the use effect is good.

4、本实用新型通过工作台悬挂单元将工作台设置在桥梁外侧,第一工作台吊装杆和第二工作台吊装杆均伸出桥梁边护栏,设置在第一工作台吊装杆上的第一吊索也伸出桥梁边护栏,第一吊索与工作台的一端固定连接,设置在第二工作台吊装杆上的第二吊索也伸出桥梁边护栏,第二吊索与工作台的另一端固定连接,以此将工作台设置在桥梁外侧,工作台为施工人员提供桥梁边护栏模板施工场地。4. The utility model sets the workbench outside the bridge through the workbench suspension unit, the first workbench hoisting rod and the second workbench hoisting rod both protrude from the bridge side guardrail, and the first workbench hoisting rod set on the first workbench The sling also extends out of the bridge side guardrail, the first sling is fixedly connected to one end of the workbench, the second sling installed on the lifting rod of the second workbench also extends out of the bridge side guardrail, and the second sling is connected to the end of the workbench. The other end is fixedly connected, so that the workbench is set on the outside of the bridge, and the workbench provides a construction site for the bridge side guardrail formwork for the construction personnel.

综上所述,本实用新型结构简单、设计合理,车架滑轮与车架滑轨滑动连接,提高了桥梁边护栏模板施工的便捷性,通过模板吊装单元和吊链支撑杆起吊桥梁边护栏模板,通过工作台悬挂单元将工作台设置在桥梁外侧,方便工作台上的施工人员进行桥梁边护栏模板施工,使用操作方便,实用性强,使用效果好,便于推广使用。In summary, the utility model has a simple structure and a reasonable design. The frame pulley and the frame slide rail are slidingly connected, which improves the convenience of bridge side guardrail formwork construction. The bridge side guardrail formwork is lifted by the formwork lifting unit and the lifting chain support rod. , the workbench is set on the outside of the bridge through the workbench suspension unit, which is convenient for the construction personnel on the workbench to carry out the construction of the bridge side guardrail formwork.

下面通过附图和实施例,对本实用新型的技术方案做进一步的详细描述。The technical solutions of the present utility model will be further described in detail through the drawings and embodiments below.

附图说明Description of drawings

图1为本实用新型的结构示意图。Fig. 1 is the structural representation of the utility model.

附图标记说明:Explanation of reference signs:

1—底板; 2-1—第三斜杆; 2-2—第四斜杆;1—bottom plate; 2-1—third slanting bar; 2-2—fourth slanting bar;

2-3—第五斜杆; 2-4—第六斜杆; 3—横杆;2-3—fifth diagonal bar; 2-4—sixth diagonal bar; 3—cross bar;

4—工作台; 5—车架滑轨; 6—车架滑轮;4—workbench; 5—frame slide rail; 6—frame pulley;

7—配重台; 8-1—手柄; 8-2—链轮;7—counterweight platform; 8-1—handle; 8-2—sprocket;

8-3—吊链; 8-4—吊钩; 9—吊链支撑杆;8-3—hanging chain; 8-4—hook; 9—hanging chain support rod;

9-1—吊链滑轮; 10-1—第一水平杆; 10-2—第一吊索;9-1—chain pulley; 10-1—the first horizontal bar; 10-2—the first sling;

10-3—第一斜杆; 11-1—第二水平杆; 11-2—第二吊索;10-3—the first inclined bar; 11-1—the second horizontal bar; 11-2—the second sling;

11-3—第二斜杆。11-3—Second diagonal bar.

具体实施方式Detailed ways

如图1所示,本实用新型包括工作台4、车架、设置在桥梁上的车架滑轨5、以及设置在车架上的模板吊装单元和工作台悬挂单元,所述车架包括底板1、设置在底板1上方的横杆3和用于固定连接所述底板1与横杆3的车架斜杆,所述底板1的下端设置有与所述车架滑轨5滑动连接的车架滑轮6,所述模板吊装单元包括链轮8-2和用于转动所述链轮8-2的链轮手柄8-1,所述链轮8-2上缠绕有吊链8-3,所述吊链8-3的一端固定连接在链轮8-2上,所述吊链8-3的另一端固定连接有吊钩8-4,所述底板1上设置有吊链支撑杆9,所述吊链支撑杆9的一端固定设置在底板1上,所述吊链支撑杆9的另一端设置有吊链滑轮9-1,所述工作台悬挂单元包括分别设置在横杆3两端的第一工作台吊装杆和第二工作台吊装杆,所述第一工作台吊装杆上设置有用于连接工作台4一端的第一吊索10-2,所述第二工作台吊装杆上设置有用于连接工作台4另一端的第二吊索11-2。As shown in Figure 1, the utility model comprises a workbench 4, a vehicle frame, a vehicle frame slide rail 5 arranged on the bridge, and a template hoisting unit and a workbench suspension unit arranged on the vehicle frame, and the vehicle frame includes a bottom plate 1. The cross bar 3 arranged above the base plate 1 and the frame diagonal bar for fixedly connecting the base plate 1 and the cross bar 3, the lower end of the base plate 1 is provided with a car frame slidingly connected with the frame slide rail 5 Frame pulley 6, the template hoisting unit includes a sprocket 8-2 and a sprocket handle 8-1 for rotating the sprocket 8-2, the sprocket 8-2 is wound with a lifting chain 8-3, One end of the suspension chain 8-3 is fixedly connected to the sprocket 8-2, the other end of the suspension chain 8-3 is fixedly connected with a suspension hook 8-4, and the bottom plate 1 is provided with a suspension chain support rod 9 One end of the chain support rod 9 is fixed on the base plate 1, the other end of the chain support rod 9 is provided with a chain pulley 9-1, and the workbench suspension unit includes two The first workbench lifting rod at the end and the second workbench lifting rod, the first workbench lifting rod is provided with a first sling 10-2 for connecting one end of the workbench 4, and the second workbench lifting rod is A second sling 11-2 for connecting the other end of the workbench 4 is provided.

需要说明的是,桥梁上的车架滑轨5的个数为两个,底板1的下端共设置有4个车架滑轮6。4个车架滑轮6分别布设在底板1的四个角的下端,车架滑轮6与车架滑轨5滑动连接,因此底板1可在桥梁上滑动,从而带动车架在桥梁上滑动,提高了桥梁施工的便捷性。It should be noted that there are two frame slide rails 5 on the bridge, and four frame pulleys 6 are arranged at the lower end of the bottom plate 1. The four frame pulleys 6 are arranged on the four corners of the bottom plate 1 respectively. At the lower end, the frame pulley 6 is slidingly connected with the frame slide rail 5, so the base plate 1 can slide on the bridge, thereby driving the frame to slide on the bridge, improving the convenience of bridge construction.

需要说明的是,吊链支撑杆9、第一工作台吊装杆和第二工作台吊装杆均位于桥梁的同一侧。It should be noted that the suspension chain support rod 9, the first workbench lifting rod and the second workbench lifting rod are all located on the same side of the bridge.

实际使用时,吊链8-3为链条或钢丝绳,可任意弯曲,在没有吊链支撑杆9的情况下,伸出桥梁边护栏的吊链8-3在自然状态下以吊链8-3与桥梁边护栏的接触点垂直于地面,起吊的桥梁边护栏模板容易与桥梁边护栏发生磕碰,影响施工效果。因此在底板1上设置伸出桥梁边护栏的吊链支撑杆9,吊链支撑杆9上的吊链滑轮9-1为对吊链8-3提供支撑点,使得吊链8-3在自然状态下以吊链滑轮9-1的位置点垂直于地面,从而改变吊链8-3的垂直位置,以此改变吊链8-3上连接的吊钩8-4与桥梁边护栏之间的距离,使用效果好。吊链支撑杆9的一端与底板1固定连接,吊链支撑杆9的中间段与横杆3抵靠连接,横杆3为吊链支撑杆9提供支撑点,提高吊链支撑杆9的稳定性。During actual use, the suspension chain 8-3 is a chain or a steel wire rope, which can be bent arbitrarily. In the absence of the suspension chain support bar 9, the suspension chain 8-3 extending out of the bridge side guardrail is in the natural state with the suspension chain 8-3 The contact point with the bridge side guardrail is perpendicular to the ground, and the hoisted bridge side guardrail template is easy to collide with the bridge side guardrail, which affects the construction effect. Therefore on the base plate 1, the hanging chain support bar 9 extending out from the bridge side guardrail is set, and the hanging chain pulley 9-1 on the hanging chain supporting bar 9 provides a support point for the hanging chain 8-3, so that the hanging chain 8-3 is in a natural position. In this state, the position point of the suspension chain pulley 9-1 is perpendicular to the ground, thereby changing the vertical position of the suspension chain 8-3, thereby changing the distance between the suspension hook 8-4 connected on the suspension chain 8-3 and the bridge side guardrail. distance, the effect is good. One end of the chain support rod 9 is fixedly connected to the bottom plate 1, and the middle section of the chain support rod 9 is connected to the cross bar 3. The cross bar 3 provides a support point for the chain support rod 9 to improve the stability of the chain support rod 9. sex.

实际使用时,吊链8-3的一端固定连接在链轮8-2上,吊链8-3的另一端绕过吊链滑轮9-1后与吊钩8-4固定连接,吊钩8-4用于钩吊地面上的桥梁边护栏模板。施工人员通过链轮手柄8-1转动链轮8-2,达到收放吊链8-3的目的,从而改变吊钩8-4的高度,将地面上的桥梁边护栏模板吊装到施工位置。During actual use, one end of the suspension chain 8-3 is fixedly connected on the sprocket wheel 8-2, and the other end of the suspension chain 8-3 is fixedly connected with the suspension hook 8-4 after bypassing the suspension chain pulley 9-1, and the suspension hook 8 -4 are used for hooking the bridge side railing template on the ground. The construction workers rotate the sprocket 8-2 through the sprocket handle 8-1 to achieve the purpose of retracting the hanging chain 8-3, thereby changing the height of the hook 8-4, and hoisting the bridge side guardrail formwork on the ground to the construction position.

需要说明的是,第一工作台吊装杆和第二工作台吊装杆对称设置在工作台4的两侧,提高了工作台4的稳定性。第一工作台吊装杆和第二工作台吊装杆均伸出桥梁边护栏,设置在第一工作台吊装杆上的第一吊索10-2也伸出桥梁边护栏,第一吊索10-2与工作台4的一端固定连接,设置在第二工作台吊装杆上的第二吊索11-2也伸出桥梁边护栏,第二吊索11-2与工作台4的另一端固定连接,以此将工作台4设置在桥梁外侧。It should be noted that the first workbench lifting rod and the second workbench lifting rod are arranged symmetrically on both sides of the workbench 4 , which improves the stability of the workbench 4 . The first workbench hoisting rod and the second workbench hoisting rod all stretch out the bridge side guardrail, the first sling 10-2 that is arranged on the first workbench hoisting rod also stretches out the bridge side guardrail, the first sling 10- 2 is fixedly connected with one end of the workbench 4, and the second sling 11-2 arranged on the second workbench lifting rod also extends out of the bridge side guardrail, and the second sling 11-2 is fixedly connected with the other end of the workbench 4 , so that the workbench 4 is arranged on the outside of the bridge.

施工人员仅通过机械吊车进出工作台4,机械吊车不会参与整个桥梁边护栏模板施工周期,降低了施工成本,工作台4为施工人员提供桥梁边护栏模板施工场地,与传统采用机械吊车进行桥梁边护栏模板施工相比,本申请的装置不会占用较大的施工空间,有利于桥梁其他部位施工的同时进行。The construction personnel only enter and exit the work platform 4 through the mechanical crane, and the mechanical crane will not participate in the entire bridge side guardrail formwork construction cycle, which reduces the construction cost. Compared with the construction of the side guardrail formwork, the device of the present application does not occupy a larger construction space, which is beneficial to the simultaneous construction of other parts of the bridge.

如图1所示,本实施例中,所述第一工作台吊装杆包括与横杆3固定连接的第一斜杆10-3和与所述第一斜杆10-3固定连接的第一水平杆10-1,所述第一吊索10-2与第一水平杆10-1固定连接;所述第二工作台吊装杆包括与横杆3固定连接的第二斜杆11-3和与所述第二斜杆11-3固定连接的第二水平杆11-1,所述第二吊索11-2与第二水平杆11-1固定连接。As shown in Fig. 1, in this embodiment, the first workbench lifting rod includes a first slanting bar 10-3 fixedly connected to the cross bar 3 and a first slanting bar 10-3 fixedly connected to the first slanting bar 10-3. The horizontal bar 10-1, the first sling 10-2 is fixedly connected with the first horizontal bar 10-1; the second workbench hoisting bar includes a second oblique bar 11-3 fixedly connected with the cross bar 3 and The second horizontal bar 11-1 is fixedly connected with the second inclined bar 11-3, and the second sling 11-2 is fixedly connected with the second horizontal bar 11-1.

实际使用时,不同桥梁的边护栏模板的高度和厚度不同,在不同的工作环境下,通过改变第一斜杆10-3和第二斜杆11-3的长度或倾斜角度,可调节工作台4的高度,从而适应不同高度的桥梁边护栏;通过改变第一水平杆10-1和第二水平杆11-1的长度,可调节工作台4与桥梁之间的距离,从而适应不同厚度的边护栏模板,使用效果好。In actual use, the height and thickness of the side guardrail templates of different bridges are different. In different working environments, the workbench can be adjusted by changing the length or inclination angle of the first inclined bar 10-3 and the second inclined bar 11-3. 4, so as to adapt to bridge side guardrails of different heights; by changing the length of the first horizontal bar 10-1 and the second horizontal bar 11-1, the distance between the workbench 4 and the bridge can be adjusted, so as to adapt to different thicknesses Side guardrail template, the use effect is good.

如图1所示,本实施例中,所述车架斜杆包括第三斜杆2-1、第四斜杆2-2、第五斜杆2-3和第六斜杆2-4,第三斜杆2-1的一端和第四斜杆2-2的一端分别与底板1的一端固定连接,第三斜杆2-1的另一端和第四斜杆2-2的另一端均与横杆3的一端固定连接,第五斜杆2-3的一端和第六斜杆2-4的一端分别与底板1的另一端固定连接,第五斜杆2-3的一端和第六斜杆2-4的一端均与横杆3的另一端固定连接。As shown in Figure 1, in this embodiment, the frame slanting rods include a third slanting rod 2-1, a fourth slanting rod 2-2, a fifth slanting rod 2-3 and a sixth slanting rod 2-4, One end of the third slanting bar 2-1 and one end of the fourth slanting bar 2-2 are fixedly connected to one end of the base plate 1 respectively, and the other end of the third slanting bar 2-1 and the other end of the fourth slanting bar 2-2 are both One end of the cross bar 3 is fixedly connected, one end of the fifth slanting bar 2-3 and one end of the sixth slanting bar 2-4 are respectively fixedly connected with the other end of the bottom plate 1, one end of the fifth slanting bar 2-3 and the sixth slanting bar One end of the diagonal bar 2-4 is all fixedly connected with the other end of the cross bar 3.

实际使用时,第三斜杆2-1、第四斜杆2-2和底板1的一端围成三角形,第五斜杆2-3、第六斜杆2-4和底板1的另一端围成三角形,利用三角形的稳定性原理,使车架的整体结构更加牢固,且构造简单,避免了复杂的设置,提高了加工效率。In actual use, one end of the third slanting bar 2-1, the fourth slanting bar 2-2 and the base plate 1 forms a triangle, and the other end of the fifth slanting bar 2-3, the sixth slanting bar 2-4 and the base plate 1 encircles a triangle. Formed into a triangle, using the stability principle of the triangle, the overall structure of the frame is more solid, and the structure is simple, which avoids complicated settings and improves processing efficiency.

如图1所示,本实施例中,所述吊链支撑杆9为伸缩杆。As shown in FIG. 1 , in this embodiment, the suspension chain support rod 9 is a telescopic rod.

实际使用时,通过调节吊链支撑杆9的长度可改变吊钩8-4的位置,从而改变悬挂在吊钩8-4上的桥梁边护栏模板的位置,适用于不同的施工环境,方便工作台4上的施工人员对桥梁边护栏模板进行操作。In actual use, the position of the suspension hook 8-4 can be changed by adjusting the length of the suspension chain support rod 9, thereby changing the position of the bridge side guardrail template suspended on the suspension hook 8-4, which is suitable for different construction environments and is convenient for work The construction workers on platform 4 operate the bridge side guardrail formwork.

如图1所示,本实施例中,所述底板1上设置有配重台7,配重台7由混凝土块或金属块制成。As shown in FIG. 1 , in this embodiment, a counterweight platform 7 is arranged on the bottom plate 1 , and the counterweight platform 7 is made of concrete blocks or metal blocks.

实际使用时,在底板1上设置配重台7,增加车架的重量,避免桥梁边护栏模板、工作台4和工作台4上施工人员的总重量大于车架的重量,造成车架倾翻。In actual use, a counterweight platform 7 is set on the bottom plate 1 to increase the weight of the vehicle frame, so as to avoid the total weight of the construction personnel on the bridge side guardrail formwork, workbench 4 and workbench 4 being greater than the weight of the vehicle frame, causing the vehicle frame to overturn .

以上所述,仅是本实用新型的实施例,并非对本实用新型作任何限制,凡是根据本实用新型技术实质对以上实施例所作的任何简单修改、变更以及等效结构变化,均仍属于本实用新型技术方案的保护范围内。The above is only an embodiment of the utility model, and does not limit the utility model in any way. All simple modifications, changes and equivalent structural changes made to the above embodiments according to the technical essence of the utility model still belong to the utility model. Within the scope of protection of new technical solutions.

Claims (5)

1.一种桥梁边护栏模板施工装置,其特征在于:包括工作台(4)、车架、设置在桥梁上的车架滑轨(5)、以及设置在车架上的模板吊装单元和工作台悬挂单元;1. A bridge side guardrail formwork construction device is characterized in that: comprise workbench (4), vehicle frame, the vehicle frame slide rail (5) that is arranged on the bridge, and the formwork hoisting unit that is arranged on the vehicle frame and work table suspension unit; 所述车架包括底板(1)、设置在底板(1)上方的横杆(3)和用于固定连接所述底板(1)与横杆(3)的车架斜杆,所述底板(1)的下端设置有与所述车架滑轨(5)滑动连接的车架滑轮(6);The vehicle frame comprises a base plate (1), a cross bar (3) arranged above the base plate (1) and a vehicle frame slanting bar for fixedly connecting the base plate (1) and the cross bar (3), the base plate ( 1) The lower end is provided with a frame pulley (6) slidingly connected to the frame slide rail (5); 所述模板吊装单元包括链轮(8-2)和用于转动所述链轮(8-2)的链轮手柄(8-1),所述链轮(8-2)上缠绕有吊链(8-3),所述吊链(8-3)的一端固定连接在链轮(8-2)上,所述吊链(8-3)的另一端固定连接有吊钩(8-4),所述底板(1)上设置有吊链支撑杆(9),所述吊链支撑杆(9)的一端固定设置在底板(1)上,所述吊链支撑杆(9)的另一端设置有吊链滑轮(9-1);The formwork hoisting unit includes a sprocket (8-2) and a sprocket handle (8-1) for rotating the sprocket (8-2), and a lifting chain is wound on the sprocket (8-2) (8-3), one end of the suspension chain (8-3) is fixedly connected to the sprocket (8-2), and the other end of the suspension chain (8-3) is fixedly connected to the suspension hook (8-4 ), the base plate (1) is provided with a suspension chain support rod (9), one end of the suspension chain support rod (9) is fixedly arranged on the base plate (1), and the other end of the suspension chain support rod (9) One end is provided with a hanging chain pulley (9-1); 所述工作台悬挂单元包括分别设置在横杆(3)两端的第一工作台吊装杆和第二工作台吊装杆,所述第一工作台吊装杆上设置有用于连接工作台(4)一端的第一吊索(10-2),所述第二工作台吊装杆上设置有用于连接工作台(4)另一端的第二吊索(11-2)。The workbench suspension unit includes a first workbench lifting rod and a second workbench lifting rod respectively arranged at both ends of the crossbar (3), and the first workbench lifting rod is provided with a The first sling (10-2) for the second workbench is provided with a second sling (11-2) for connecting the other end of the workbench (4) on the lifting rod of the second workbench. 2.按照权利要求1所述的一种桥梁边护栏模板施工装置,其特征在于:所述第一工作台吊装杆包括与横杆(3)固定连接的第一斜杆(10-3)和与所述第一斜杆(10-3)固定连接的第一水平杆(10-1),所述第一吊索(10-2)与第一水平杆(10-1)固定连接;所述第二工作台吊装杆包括与横杆(3)固定连接的第二斜杆(11-3)和与所述第二斜杆(11-3)固定连接的第二水平杆(11-1),所述第二吊索(11-2)与第二水平杆(11-1)固定连接。2. according to a kind of bridge side guardrail formwork construction device according to claim 1, it is characterized in that: the first workbench hoisting bar comprises the first inclined bar (10-3) that is fixedly connected with cross bar (3) and A first horizontal bar (10-1) fixedly connected to the first inclined bar (10-3), the first sling (10-2) fixedly connected to the first horizontal bar (10-1); The second workbench lifting rod includes a second oblique rod (11-3) fixedly connected to the cross bar (3) and a second horizontal rod (11-1) fixedly connected to the second oblique rod (11-3). ), the second sling (11-2) is fixedly connected to the second horizontal bar (11-1). 3.按照权利要求1所述的一种桥梁边护栏模板施工装置,其特征在于:所述车架斜杆包括第三斜杆(2-1)、第四斜杆(2-2)、第五斜杆(2-3)和第六斜杆(2-4),第三斜杆(2-1)的一端和第四斜杆(2-2)的一端分别与底板(1)的一端固定连接,第三斜杆(2-1)的另一端和第四斜杆(2-2)的另一端均与横杆(3)的一端固定连接,第五斜杆(2-3)的一端和第六斜杆(2-4)的一端分别与底板(1)的另一端固定连接,第五斜杆(2-3)的一端和第六斜杆(2-4)的一端均与横杆(3)的另一端固定连接。3. according to the described construction device of a kind of bridge side guardrail formwork according to claim 1, it is characterized in that: described vehicle frame slanting bar comprises the 3rd slanting bar (2-1), the 4th slanting bar (2-2), the 4th slanting bar Five oblique rods (2-3) and the sixth oblique rod (2-4), one end of the third oblique rod (2-1) and one end of the fourth oblique rod (2-2) are respectively connected with one end of the base plate (1) Fixedly connected, the other end of the third oblique bar (2-1) and the other end of the fourth oblique bar (2-2) are all fixedly connected with one end of the cross bar (3), and the fifth oblique bar (2-3) One end and one end of the sixth oblique rod (2-4) are respectively fixedly connected with the other end of the base plate (1), and one end of the fifth oblique rod (2-3) and one end of the sixth oblique rod (2-4) are connected with The other end of cross bar (3) is fixedly connected. 4.按照权利要求1所述的一种桥梁边护栏模板施工装置,其特征在于:所述吊链支撑杆(9)为伸缩杆。4. A bridge side guardrail formwork construction device according to claim 1, characterized in that: said suspension chain support rod (9) is a telescopic rod. 5.按照权利要求1所述的一种桥梁边护栏模板施工装置,其特征在于:所述底板(1)上设置有配重台(7)。5. A bridge side guardrail formwork construction device according to claim 1, characterized in that: a counterweight platform (7) is arranged on the bottom plate (1).
CN201820056224.8U 2018-01-13 2018-01-13 A kind of bridge side guardrail template construction device Expired - Fee Related CN207749426U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820056224.8U CN207749426U (en) 2018-01-13 2018-01-13 A kind of bridge side guardrail template construction device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820056224.8U CN207749426U (en) 2018-01-13 2018-01-13 A kind of bridge side guardrail template construction device

Publications (1)

Publication Number Publication Date
CN207749426U true CN207749426U (en) 2018-08-21

Family

ID=63151748

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820056224.8U Expired - Fee Related CN207749426U (en) 2018-01-13 2018-01-13 A kind of bridge side guardrail template construction device

Country Status (1)

Country Link
CN (1) CN207749426U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110205939A (en) * 2019-06-04 2019-09-06 中铁十局集团城市轨道交通工程有限公司 Trolley and method for mobile dismounting formwork of bridge rail
CN116145543A (en) * 2022-12-28 2023-05-23 中铁大桥局武汉桥梁特种技术有限公司 A monorail sliding operation platform for the maintenance of the outer side of the subway viaduct

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110205939A (en) * 2019-06-04 2019-09-06 中铁十局集团城市轨道交通工程有限公司 Trolley and method for mobile dismounting formwork of bridge rail
CN116145543A (en) * 2022-12-28 2023-05-23 中铁大桥局武汉桥梁特种技术有限公司 A monorail sliding operation platform for the maintenance of the outer side of the subway viaduct

Similar Documents

Publication Publication Date Title
CN106939707B (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
CN202785364U (en) Movable dual-door-type mast hoisting device
CN209011528U (en) An all-steel attached lifting scaffold
CN217839714U (en) Adjustable railway pier top hanging fence installation device
CN206799021U (en) A kind of full circle swinging traveling derrick crane
CN207749426U (en) A kind of bridge side guardrail template construction device
CN203255892U (en) Heightened gantry type crane
CN211775618U (en) Assembled folding walkways system
CN204625045U (en) A kind of steel structure hoisting door shaped stent formula hanging apparatus
CN205857026U (en) A kind of movable type bridge anticollision barrier construction operation chassis
CN112942110B (en) Convenient and fast movable type bridge centralized drainage pipeline installation operation platform
CN205934730U (en) Installation device of wave form steel web
CN210341680U (en) Door type corrugated steel web plate installation and overhanging type hanging bracket structure
CN211647239U (en) A steel platform hanging device
CN210049105U (en) Self-propelled bridge formwork operation trolley
CN201722937U (en) Sliding platform for installation of net rack
CN206769343U (en) It is a kind of to be used for the travelling bridge that guardrail is constructed that builds a bridge
CN106639303A (en) Hydraulic climbing formwork frame special for lift
CN110748140A (en) Track beam hanging basket special for stepped curtain wall
CN201144134Y (en) Double herringbone hoisting derrick mast
CN205688778U (en) A kind of elevating scaffold special over sling structure
CN211078166U (en) Pipeline vertical hoisting device
CN211169608U (en) Hanging basket prismatic sheet hoisting device
CN212477430U (en) Wave form steel web SCC worker method hangs basket with hoisting accessory
CN214243479U (en) Small-size lifting device of creeping formwork processing usefulness

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180821

Termination date: 20190113

CF01 Termination of patent right due to non-payment of annual fee