CN207739603U - A kind of steel building scaffold - Google Patents

A kind of steel building scaffold Download PDF

Info

Publication number
CN207739603U
CN207739603U CN201721857000.9U CN201721857000U CN207739603U CN 207739603 U CN207739603 U CN 207739603U CN 201721857000 U CN201721857000 U CN 201721857000U CN 207739603 U CN207739603 U CN 207739603U
Authority
CN
China
Prior art keywords
supporting rack
fixed block
electric telescopic
telescopic rod
scaffold
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721857000.9U
Other languages
Chinese (zh)
Inventor
何天成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lanzhou Resources and Environment Voc Tech College
Original Assignee
Lanzhou Resources and Environment Voc Tech College
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lanzhou Resources and Environment Voc Tech College filed Critical Lanzhou Resources and Environment Voc Tech College
Priority to CN201721857000.9U priority Critical patent/CN207739603U/en
Application granted granted Critical
Publication of CN207739603U publication Critical patent/CN207739603U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model provides a kind of steel building scaffold,Including placement plate,Electric telescopic rod,Through-hole,Fixed block one,First supporting rack,Second supporting rack and fixed block two,Electric telescopic rod is equipped with by setscrew on the downside of tray interior,Placement plate is connected by connecting rod with electric telescopic rod,Through-hole is opened in workbench upper surface centre position,The design solves the problems, such as that original scaffold does not have convenient conveying function,Fixed block one is mounted on scaffold body rear face by setscrew,Fixed block two is mounted on scaffold body front end face by setscrew,Fixed block one is connected by the first supporting rack with limiting slot,Fixed block two is connected by the second supporting rack with limiting slot,The design solves the problems, such as the inadequate safety and stability of original construction frame support structure,Utility model works are efficient,Material conveying is convenient,It is time saving and energy saving,Safety and stability.

Description

A kind of steel building scaffold
Technical field
The utility model is a kind of steel building scaffold, belongs to construction frame technical field.
Background technology
Scaffold is to ensure each work progress is smoothed out and is set up workbench.It is divided by the position set up outer Scaffold, inner scaffold;It can be divided into the wooden scaffold, bamboo scaffold, steel pipe scaffold by material difference;It is divided by structural form vertical Rod-type scaffold, gate-type scaffold, suspension type scaffold, hanging scaffold, chooses formula scaffold, climbs formula construction bridge-type scaffold Frame.
Existing scaffold does not have a convenient conveying function, and required material needs artificial transmission to scaffold in work progress On, when scaffold height is higher, artificial transmission's material is more troublesome arduously, and existing construction frame support structure not enough safety is steady Fixed, the inadequate safety and stability of supporting rack is easy to lead to construction accident, and it is above-mentioned to solve to be badly in need of a kind of steel building scaffold now The problem.
Utility model content
In view of the deficienciess of the prior art, the utility model aim is to provide a kind of steel building scaffold, with solution Certainly the problems mentioned above in the background art, utility model works are efficient, and material conveying is convenient, time saving and energy saving, and safety is steady It is fixed.
To achieve the goals above, the utility model is to realize by the following technical solutions:A kind of steel building Scaffold, including construction frame body, pedal, hydraulic lifting post, workbench, convenient conveying mechanism, supporting mechanism and pedestal, institute It states pedal and construction frame body front and rear sides is symmetrically mounted on by setscrew, the construction frame body upper surface is equipped with hydraulic pressure liter Column drops, and the hydraulic lifting post upper surface is equipped with workbench, and the workbench is connected by hydraulic lifting post with construction frame body It connects, in construction frame body upper surface centre position, the supporting mechanism is symmetricly set on pedestal for the convenient conveying mechanism setting Upper surface, the pedestal are arranged in scaffold lower body face, the convenient conveying mechanism include box body, connecting rod, placement plate, Electric telescopic rod, through-hole, accumulator and conveying button, the construction frame body upper surface centre position are equipped with box body, institute It states and electric telescopic rod is equipped with by setscrew on the downside of tray interior, the electric telescopic rod upper surface is equipped with connecting rod, institute It states connecting rod upper surface and is equipped with placement plate, the placement plate is connected by connecting rod with electric telescopic rod, and the through-hole opens up End face centre position on the table, the accumulator are assemblied on the right side of electric telescopic rod, and the conveying button setting is being constructed On the upside of frame body front end face, the supporting mechanism includes fixed block one, the first supporting rack, limiting slot, the second supporting rack and consolidates Determine block two, the fixed block one is mounted on scaffold body rear face by setscrew, and the fixed block two passes through expanding screw Silk is mounted on scaffold body front end face, and the limiting slot is symmetrically opened in pedestal upper surface front and rear sides, the fixed block one It is connected with limiting slot by the first supporting rack, the fixed block two is connected by the second supporting rack with limiting slot.
Further, the pedestal lower face is equipped with four groups of idler wheels, and four groups of idler wheels are equipped with foot and step on brake structure.
Further, the construction frame body is made of reinforcing bar material.
Further, the workbench upper surface is equipped with fence, and the workbench upper surface is equipped with lighting device, and illuminates Outside of deivce face is equipped with protective cover.
Further, the pedal is equipped with multigroup, and multigroup pedal specification is identical, and the pedal upper surface is equipped with anti-skidding Pad.
Further, the conveying button is connected by conducting wire with accumulator, the electric telescopic rod by conducting wire with Conveying button is connected.
Further, the fixed block one and fixed block two are equipped with two groups, first supporting rack and the second supporting rack Two groups are equipped with, and two group of first supporting rack and two group of second supporting rack are made of reinforcing bar material.
Further, first supporting rack and the second supporting rack lower face are equipped with anti-slop serrations.
The beneficial effects of the utility model:A kind of steel building scaffold of the utility model, because the utility model adds Box body, connecting rod, placement plate, electric telescopic rod, through-hole, accumulator and conveying button, the design has been added to facilitate material certainly It is dynamic to be transmitted on scaffold, reduce the amount of labour of construction personnel, improve work efficiency, solves original scaffold without just The problem of prompt conveying function, improves the working efficiency of the utility model.
Because the utility model is added to fixed block one, the first supporting rack, limiting slot, the second supporting rack and fixed block two, The design increases the security and stability that scaffold uses, and ensure that the safety of construction personnel, solves original scaffold support The problem of structure inadequate safety and stability, improve the safety in utilization of the utility model.
Because pedestal lower face is equipped with four groups of idler wheels, and four groups of idler wheels are equipped with foot and step on brake structure, which, which facilitates, applies The mobile transfer of the movements and postures of actors, because workbench upper surface is equipped with fence, which ensure that the personal safety of construction personnel, because of workbench Upper surface is equipped with lighting device, and lighting device outer surface is equipped with protective cover, which, which facilitates, carries on construction work at night, because of pedal upper end Face is equipped with non-slip mat, which increases the skid resistance of pedal, because the first supporting rack and the second supporting rack lower face be equipped with it is anti- Slip teeth, the design prevent the smooth of supporting rack, and utility model works are efficient, and material conveying is convenient, time saving and energy saving, safety Stablize.
Description of the drawings
Upon reading the detailed description of non-limiting embodiments with reference to the following drawings, other spies of the utility model Sign, objects and advantages will become more apparent upon:
Fig. 1 is a kind of structural schematic diagram of steel building scaffold of the utility model;
Fig. 2 is the structural schematic diagram of convenient conveying mechanism in a kind of steel building scaffold of the utility model;
Fig. 3 is the structural schematic diagram of supporting mechanism in a kind of steel building scaffold of the utility model;
In figure:1- constructions frame body, 2- pedals, 3- hydraulic lifting posts, 4- workbench, the convenient conveying mechanisms of 5-, 6- supports Mechanism, 7- pedestals, 51- box bodys, 52- connecting rods, 53- placement plates, 54- electric telescopic rods, 55- through-holes, 56- accumulators, 57- are defeated Send button, 61- fixed blocks one, the first supporting racks of 62-, 63- limiting slots, the second supporting racks of 64-, 65- fixed blocks two.
Specific implementation mode
To make the technical means, creative features, achievement of purpose, and effectiveness of the utility model be easy to understand, below In conjunction with specific implementation mode, the utility model is expanded on further.
- Fig. 3 is please referred to Fig.1, the utility model provides a kind of technical solution:A kind of steel building scaffold, including apply Movements and postures of actors main body 1, pedal 2, hydraulic lifting post 3, workbench 4, convenient conveying mechanism 5, supporting mechanism 6 and pedestal 7, pedal 2 are logical It crosses setscrew and is symmetrically mounted on 1 front and rear sides of construction frame body, 1 upper surface of construction frame body is equipped with hydraulic lifting post 3, hydraulic pressure 3 upper surface of lifting column is equipped with workbench 4, and workbench 4 is connected by hydraulic lifting post 3 with construction frame body 1, convenient conveyer For the setting of structure 5 in 1 upper surface centre position of construction frame body, supporting mechanism 6 is symmetricly set on 7 upper surface of pedestal, and the setting of pedestal 7 exists 1 lower face of construction frame body.
Convenient conveying mechanism 5 includes box body 51, connecting rod 52, placement plate 53, electric telescopic rod 54, through-hole 55, accumulator 56 and conveying button 57, construction frame body 1 upper surface centre position box body 51 is installed, 51 inner lower of box body passes through expansion Screw is equipped with electric telescopic rod 54, and 54 upper surface of electric telescopic rod is equipped with connecting rod 52, and 52 upper surface of connecting rod, which is equipped with, places Plate 53, placement plate 53 are connected by connecting rod 52 with electric telescopic rod 54, and through-hole 55 is opened in 4 upper surface interposition of workbench It sets, accumulator 56 is assemblied in 54 right side of electric telescopic rod, and on the upside of construction 1 front end face of frame body, this sets the setting of conveying button 57 Meter solves the problems, such as that original scaffold does not have convenient conveying function.
Supporting mechanism 6 includes fixed block 1, the first supporting rack 62, limiting slot 63, the second supporting rack 64 and fixed block 2 65, fixed block 1 is mounted on construction 1 rear end face of frame body by setscrew, and fixed block 2 65 is installed by setscrew In construction 1 front end face of frame body, limiting slot 63 is symmetrically opened in 7 upper surface front and rear sides of pedestal, and fixed block 1 passes through first Supporting rack 62 is connected with limiting slot 63, and fixed block 2 65 is connected by the second supporting rack 64 with limiting slot 63, the design solution The problem of original construction frame support structure of having determined inadequate safety and stability.
7 lower face of pedestal is equipped with four groups of idler wheels, and four groups of idler wheels are equipped with foot and step on brake structure, and construction frame body 1 is by steel Muscle material is made, and 4 upper surface of workbench is equipped with fence, and 4 upper surface of workbench is equipped with lighting device, and lighting device outer surface is set There is a protective cover, pedal 2 is equipped with multigroup, and 2 specification of multigroup pedal is identical, and 2 upper surface of pedal is equipped with non-slip mat, and conveying button 57 is logical It crosses conducting wire with accumulator 56 to be connected, electric telescopic rod 54 is connected by conducting wire with conveying button 57, fixed block 1 and solid Determine block 2 65 and be equipped with two groups, the first supporting rack 62 and the second supporting rack 64 are equipped with two groups, and two group of first 62 He of supporting rack Two group of second supporting rack 64 is made of reinforcing bar material, and the first supporting rack 62 and 64 lower face of the second supporting rack are equipped with anti-skidding Tooth.
Specific implementation mode:In progress in use, construction personnel first checks the utility model, checks whether and deposit In defect, it can not just carry out using if there is defect, need that maintenance personal is notified to repair at this time, if do not deposited It can be carried out using if problem, construction frame body 1 is moved to designated position by construction personnel by idler wheel, needs to apply When on work material transferring to construction frame body 1, material is placed in placement plate 53 by construction personnel first, is then opened conveying and is pressed Button 57, conveying button 57 are switched to on-state, and the circuit between accumulator 56 and electric telescopic rod 54 communicates, and accumulator 56 is logical It crosses conducting wire and electric energy is transferred to electric telescopic rod 54, electric telescopic rod 54 converts electrical energy into mechanical energy, because placement plate 53 passes through Connecting rod 52 is connected with electric telescopic rod 54, drives placement plate 53 to move up when electric telescopic rod 54 rises, and places Plate 53 moves upwards through through-hole 55, and the construction personnel on workbench 4 removes the material in placement plate 53, which facilitates Material is transmitted on scaffold automatically, is reduced the amount of labour of construction personnel, is improved work efficiency, and solves original scaffold There is no the problem of convenient conveying function, improves the working efficiency of the utility model.
Fixed block 1 is mounted on construction 1 rear end face of frame body by construction personnel by setscrew, and fixed block 2 65 is logical It crosses setscrew and is mounted on construction 1 front end face of frame body, 62 upper end of the first supporting rack is mounted on the downside of fixed block 1, first 62 lower end of support is placed on limiting slot 63, and fixed block 1 is connected by the first supporting rack 62 with limiting slot 63, to make One supporting rack 62 and pedestal 7 and construction frame body 1 form triangular shaped, and 64 upper end of the second supporting rack is mounted on fixed block two 65 downsides, 64 lower end of the second supporting rack are placed on limiting slot 63, and fixed block 2 65 passes through the second supporting rack 64 and 63 phase of limiting slot Connection, it is triangular shaped to make the second supporting rack 64 and pedestal 7 and construction frame body 1 be formed, increase construction frame body 1 Use stability, the first supporting rack 62 and 64 lower face of the second supporting rack setting anti-slop serrations can prevent smooth, the design The security and stability that scaffold uses is increased, ensure that the safety of construction personnel, solves original construction frame support structure not The problem of enough safety and stability, improve the safety in utilization of the utility model.
The advantages of basic principles and main features and the utility model of the utility model have been shown and described above, for For those skilled in the art, it is clear that the present invention is not limited to the details of the above exemplary embodiments, and without departing substantially from this In the case of the spirit or essential attributes of utility model, the utility model can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the utility model is by institute Attached claim rather than above description limit, it is intended that will fall within the meaning and scope of the equivalent requirements of the claims All changes are embraced therein.Any reference numeral in claim should not be considered as to the involved right of limitation It is required that.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiment being appreciated that.

Claims (8)

1. a kind of steel building scaffold, including construction frame body, pedal, hydraulic lifting post, workbench, convenient conveyer Structure, supporting mechanism and pedestal, it is characterised in that:The pedal by setscrew be symmetrically mounted on construction frame body before and after two Side, the construction frame body upper surface are equipped with hydraulic lifting post, and the hydraulic lifting post upper surface is equipped with workbench, the work Platform is connected by hydraulic lifting post with construction frame body, and the convenient conveying mechanism setting is among construction frame body upper surface Position, the supporting mechanism are symmetricly set on pedestal upper surface, and the pedestal is arranged in scaffold lower body face;
The convenient conveying mechanism include box body, connecting rod, placement plate, electric telescopic rod, through-hole, accumulator and conveying by Button, the construction frame body upper surface centre position are equipped with box body, are equipped with by setscrew on the downside of the tray interior Electric telescopic rod, the electric telescopic rod upper surface are equipped with connecting rod, and the connecting rod upper surface is equipped with placement plate, the placement Plate is connected by connecting rod with electric telescopic rod, and the through-hole is opened in workbench upper surface centre position, the accumulator It is assemblied on the right side of electric telescopic rod, the conveying button is arranged on the upside of scaffold body front end face;
The supporting mechanism includes fixed block one, the first supporting rack, limiting slot, the second supporting rack and fixed block two, described solid Determine block one and scaffold body rear face is mounted on by setscrew, the fixed block two is mounted on scaffold by setscrew Body front end face, the limiting slot are symmetrically opened in pedestal upper surface front and rear sides, and the fixed block one passes through the first supporting rack It is connected with limiting slot, the fixed block two is connected by the second supporting rack with limiting slot.
2. a kind of steel building scaffold according to claim 1, it is characterised in that:The pedestal lower face is equipped with four Group idler wheel, and four groups of idler wheels are equipped with foot and step on brake structure.
3. a kind of steel building scaffold according to claim 1, it is characterised in that:The construction frame body is by reinforcing bar Material is made.
4. a kind of steel building scaffold according to claim 1, it is characterised in that:The workbench upper surface is equipped with Fence, the workbench upper surface is equipped with lighting device, and lighting device outer surface is equipped with protective cover.
5. a kind of steel building scaffold according to claim 1, it is characterised in that:The pedal be equipped with it is multigroup, and Multigroup pedal specification is identical, and the pedal upper surface is equipped with non-slip mat.
6. a kind of steel building scaffold according to claim 1, it is characterised in that:The conveying button passes through conducting wire It is connected with accumulator, the electric telescopic rod is connected by conducting wire with conveying button.
7. a kind of steel building scaffold according to claim 1, it is characterised in that:The fixed block one and fixed block Two are equipped with two groups, and first supporting rack and the second supporting rack are equipped with two groups, and two group of first supporting rack and two group second Supporting rack is made of reinforcing bar material.
8. a kind of steel building scaffold according to claim 1, it is characterised in that:First supporting rack and second Supporting rack lower face is equipped with anti-slop serrations.
CN201721857000.9U 2017-12-27 2017-12-27 A kind of steel building scaffold Expired - Fee Related CN207739603U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721857000.9U CN207739603U (en) 2017-12-27 2017-12-27 A kind of steel building scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721857000.9U CN207739603U (en) 2017-12-27 2017-12-27 A kind of steel building scaffold

Publications (1)

Publication Number Publication Date
CN207739603U true CN207739603U (en) 2018-08-17

Family

ID=63120115

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721857000.9U Expired - Fee Related CN207739603U (en) 2017-12-27 2017-12-27 A kind of steel building scaffold

Country Status (1)

Country Link
CN (1) CN207739603U (en)

Similar Documents

Publication Publication Date Title
CN201722965U (en) Balancing and guiding device for pneumatic jacking operation of large storage tank dome
CN104533068A (en) Stone installation assisting lifting platform
CN207739603U (en) A kind of steel building scaffold
CN204386130U (en) Stone material is auxiliary installs lift platform
CN207696505U (en) A kind of construction reinforcing bar rack
CN205802864U (en) Novel architecture lowering or hoisting gear
CN206939638U (en) One kind self-control lift
CN104140061A (en) Bricking furnace lifting device
CN207251520U (en) A kind of foldable anticorrosion solar energy aluminum frame of high-performance
CN207988460U (en) One kind is multi-functional to use scaffold
CN203242940U (en) Novel carrying cart used for handcart switch
CN203158041U (en) Handcart switch transfer trolley switch-falling prevention device
CN203976309U (en) Build stove jacking system
CN209132967U (en) A kind of traffic signal control
CN206923910U (en) Put bookshelf in a kind of library
CN207392720U (en) A kind of architectural engineering scaffold bracing means
CN207418218U (en) A kind of hung moving platform for Steel Structure Installation
CN207002104U (en) A kind of universal auxiliary support apparatus
CN202201378U (en) Laminated foot stool for resin tanks
CN206328063U (en) Large scale prefabricated part hoisting running device
CN202026014U (en) Special isolation frame for overhauling GW16 type disconnecting link
CN206319611U (en) Combined formwork piling bin
CN205076241U (en) Glass all revolving racks of casing
CN208647792U (en) A kind of precast stair feeding rack
CN203306482U (en) Glass storage rack

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180817

Termination date: 20201227

CF01 Termination of patent right due to non-payment of annual fee