CN207728112U - A kind of concrete construction guardrail - Google Patents
A kind of concrete construction guardrail Download PDFInfo
- Publication number
- CN207728112U CN207728112U CN201721647919.5U CN201721647919U CN207728112U CN 207728112 U CN207728112 U CN 207728112U CN 201721647919 U CN201721647919 U CN 201721647919U CN 207728112 U CN207728112 U CN 207728112U
- Authority
- CN
- China
- Prior art keywords
- wind
- curtain wall
- resistant column
- wall penel
- block
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model discloses a kind of concrete construction guardrails, including wind-resistant column and curtain wall penel, the wind-resistant column bottom end is provided with for passing through bolt and the mutually fixed setscrew mouth in ground, the sliding groove being slidably connected for curtain wall penel and wind-resistant column is provided on the wind-resistant column, be slidably installed the abutting block for being useful for offseting with curtain wall penel on the wind-resistant column, the abutting block is arranged on the side of sliding groove, it is provided in the wind-resistant column for driving the linkage portion for pushing against block and offseting with curtain wall penel, its key points of the technical solution are that having the advantages that dismountable.
Description
Technical field
The utility model is related to the realm of building construction, more particularly to a kind of concrete construction guardrail.
Background technology
In existing, concrete construction guardrail is generally comprised to be made of wind-resistant column and curtain wall penel, and wind-resistant column and curtain wall penel
It is linked together by way of pouring.
Although such construction guardrail can play the role of protection, together with wind-resistant column is poured with curtain wall penel, applying
It must be poured on road surface when work, cause road surface to be unable to normal pass for a long time, and need to set in one section
It when setting outlet, needs to destroy integrated curtain wall penel, then carries out the port at mend fences plate both ends again, it is time-consuming to take
Power, and integrated construction guardrail cannot be dismantled, and can not be applied to otherwise, cause the increase of use cost.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of concrete construction guardrail, tool
There is dismountable advantage.
The above-mentioned technical purpose of the utility model technical scheme is that:
A kind of concrete construction guardrail, including wind-resistant column and curtain wall penel, the wind-resistant column bottom end are provided with for passing through spiral shell
Bolt and the mutually fixed setscrew mouth in ground are provided with the sliding being slidably connected for curtain wall penel and wind-resistant column on the wind-resistant column
Slot, be slidably installed on the wind-resistant column abutting block for being useful for offseting with curtain wall penel, and the abutting block is arranged in sliding groove
On side, it is provided in the wind-resistant column for driving the linkage portion for pushing against block and offseting with curtain wall penel.
So set, being connect with ground across setscrew mouth by bolt, being detachably connected for wind-resistant column is realized, and
Curtain wall penel is placed in the sliding groove between two wind-resistant columns, the abutting block and curtain wall penel had nothing to do by the driving effect of linkage portion
It offsets on one side so that curtain wall penel is limited in sliding groove, realizes the fixed effect of curtain wall penel, and curtain wall penel and wind-resistant column
It can dismantle, have the advantages that dismountable;
On the basis of dismountable, it can be deduced that, can dismantle can put many places use, recycle, in certain journey
Cost can be reduced on degree.
Further preferably:The linkage portion includes the screw thread being rotatably arranged on wind-resistant column to be threadedly coupled with abutting block
Bar and for drive threaded rod rotate and limit the counter-rotational actuator of threaded rod simultaneously.
So set, by the driving effect of actuator, threaded rod rotation is driven, block is pushed against and is limited in wind-resistant column,
It can only cannot be moved up and down, as a result, the rotation of threaded rod close to curtain wall penel and far from curtain wall penel so that push against block and curtain wall penel
It pushes against or detaches so that curtain wall penel is detachable between wind-resistant column.
Further preferably:The actuator includes the worm gear being arranged on threaded rod and is rotatably arranged on curtain wall penel
On worm screw to be engaged with worm gear, worm screw one end is pierced by curtain wall penel.
So set, rotary worm, drives worm gear rotation, and then drive threaded rod rotation so that push against block and curtain wall penel
Push against, and the connection of worm gear and worm screw, can prevent worm screw from rotating backward in the case where hand decontrols worm screw, ensure that
The abutting state of tight block and curtain wall penel.
Further preferably:The curtain wall penel is provided with the casing being rotatablely connected with worm screw outside in worm screw.
So set, since worm screw rotates on curtain wall penel, worm screw can be worn, by the connection of casing, snail can be reduced
The abrasion of bar can ensure the service life of worm screw to a certain extent.
Further preferably:It is provided with grafting block on the abutting block, is provided on the curtain wall penel and is mutually inserted for grafting block
The inserting groove connect.
So set, being pushed against with curtain wall penel due to pushing against block, curtain wall penel still has the possibility slided up and down, fixed effect
It is not fine, by the connection of grafting block and inserting groove on abutting block, curtain wall penel can be limited and up moved, it is further right
Curtain wall penel is fixed.
Further preferably:The wind-resistant column is set as steel fiber reinforced concrete material.
So set, steel fiber reinforced concrete material is compared to concrete, more securely.
Further preferably:The wind-resistant column or enclosure wall plate surface are provided with fluorescent powder.
So set, due at night when, have that there are passerbys or vehicle to knock wind-resistant column and curtain wall penel, pass through fluorescent powder
Setting, can serve as a warning, prevent to some extent the generation of accident, and the energy such as electricity need not be consumed
Source, energy conservation and environmental protection.
Further preferably:Wind-resistant column bottom end is provided with the tripod to offset with ground.
So set, the supporting role for passing through tripod so that wind-resistant column connection is more secured on the ground.
In conclusion the utility model having the beneficial effect that in contrast to the prior art:Two pieces are placed on by curtain wall penel to resist
In sliding groove between wind column, and with the linkage effect for closing driving portion and threaded rod, drives and pushes against block and curtain wall penel abutting,
Whole device realizes that curtain wall penel is fixed it is also possible to dismantle.
Description of the drawings
Fig. 1 is the structural schematic diagram of embodiment;
Fig. 2 is the internal structure schematic diagram that embodiment Fig. 1 removes tripod portion;
Fig. 3 is the structural schematic diagram of A in embodiment Fig. 2.
Reference numeral:1, wind-resistant column;2, curtain wall penel;3, sliding groove;4, block is abutted;5, threaded rod;6, actuator;61, snail
Wheel;62, worm screw;7, casing;8, inserting groove;9, it is seated block;10, tripod;11, runner.
Specific implementation mode
The utility model is described in further detail below in conjunction with attached drawing.
A kind of concrete construction guardrail, it is shown referring to Fig.1, including wind-resistant column 1 and curtain wall penel 2.
Wherein, wind-resistant column 1 is set as steel fiber reinforced concrete material, the bottom end of wind-resistant column 1 be provided with for by bolt with
The mutually fixed setscrew mouth in ground, 1 bottom end of wind-resistant column are provided with the tripod 10 to offset with ground, and tripod 10 is set respectively
It sets at the both ends of wind-resistant column 1.
The sliding groove 3 being slidably connected for curtain wall penel 2 and wind-resistant column 1 is provided on wind-resistant column 1, between two wind-resistant columns 1
Sliding groove 3 is oppositely arranged, and curtain wall penel 2 is placed in two sliding grooves 3, realizes limit.
With reference to shown in Fig. 2 and Fig. 3, be slidably installed the abutting block 4 for being useful for offseting with curtain wall penel 2 on wind-resistant column 1, pushes against
Block 4 is arranged on the one side of sliding groove 3, pushes against and is provided with grafting block 9 on block 4, the position opposite with grafting block 9 on curtain wall penel 2
Set the inserting groove 8 for being provided with and being plugged for grafting block 9.
It is worth noting that being provided in wind-resistant column 1 for driving the linkage portion for pushing against block 4 and offseting with curtain wall penel 2, support
Threaded hole is offered on tight block 4(It is not shown in figure), linkage portion includes being rotatably arranged on wind-resistant column 1 to connect with threaded hole screw thread
The threaded rod 5 that connects and for driving threaded rod 5 to rotate and limiting 5 counter-rotational actuator 6 of threaded rod simultaneously.
Actuator 6 includes the worm gear 61 being arranged on threaded rod 5, and worm screw 62 is engaged on worm screw 62, and the rotation of worm screw 62 is set
It sets on curtain wall penel 2, and one end of worm screw 62 is pierced by curtain wall penel 2, worm screw 62 is externally connected with runner 11 in curtain wall penel 2.
It is noted that curtain wall penel 2 is provided with the casing 7 being rotatablely connected with worm screw 62, and enclosure wall outside in worm screw 62
2 surface of plate is provided with fluorescent powder.
The course of work:
Wind-resistant column 1 is fixed on the ground across setscrew mouth by bolt, both ends by bolt tripod 10
Tripod 10 on wind-resistant column 1 is fixed on to offset with ground.
Curtain wall penel 2 is placed in the sliding groove 3 between two wind-resistant columns 1, rotating wheel 11 drives worm screw 62 to rotate, band
Dynamic worm gear 61 rotates so that threaded rod 5 rotates, and in the case where abutting block 4 is limited, pushes against block 4 and is slided towards 2 direction of curtain wall penel
It is dynamic, and end offsets with curtain wall penel 2, during abutting, pushes against the grafting block 9 on block 4 and enters inserting in curtain wall penel 2
In access slot 8, the fixation of curtain wall penel 2 is realized.
When needing dismounting, runner 11 is rotated backward, worm screw 62 is driven to rotate backward, by the gearing of worm gear 61,
Threaded rod 5 is driven to rotate backward so as to push against block 4 and carry out the sliding detached with curtain wall penel 2.
When grafting block 9 enters in wind-resistant column 1, you can to take out curtain wall penel 2.
The above is only the exemplary embodiment of the utility model, the protection model rather than limited the present invention
It encloses, the scope of protection of the utility model is determined by the attached claims.
Claims (8)
1. a kind of concrete construction guardrail, including wind-resistant column (1) and curtain wall penel (2), it is characterized in that:Wind-resistant column (1) bottom end
Be provided with for by bolt and the mutually fixed setscrew mouth in ground, being provided on the wind-resistant column (1) for curtain wall penel (2) and
The sliding groove (3) that wind-resistant column (1) is slidably connected, being slidably installed on the wind-resistant column (1) is useful for offseting with curtain wall penel (2)
Block (4) is pushed against, the abutting block (4) is arranged on the side of sliding groove (3), is provided in the wind-resistant column (1) for driving
Push against the linkage portion that block (4) offsets with curtain wall penel (2).
2. a kind of concrete construction guardrail according to claim 1, it is characterized in that:The linkage portion includes being rotatably arranged on
On wind-resistant column (1) with push against block (4) threaded rod (5) that is threadedly coupled and for driving threaded rod (5) rotation and same time limit
The counter-rotational actuator of threaded rod (5) processed (6).
3. a kind of concrete construction guardrail according to claim 2, it is characterized in that:The actuator (6) includes that setting exists
Worm gear (61) on threaded rod (5) and worm screw (62) to be engaged with worm gear (61) is rotatably arranged on curtain wall penel (2), snail
Bar (62) one end is pierced by curtain wall penel (2).
4. a kind of concrete construction guardrail according to claim 3, it is characterized in that:The curtain wall penel (2) is in worm screw (62)
The outer casing (7) being provided with worm screw (62) rotation connection.
5. a kind of concrete construction guardrail according to claim 2, it is characterized in that:It is provided on the abutting block (4) slotting
Block (9) is connect, the inserting groove (8) plugged for grafting block (9) is provided on the curtain wall penel (2).
6. a kind of concrete construction guardrail according to claim 1, it is characterized in that:The wind-resistant column (1) or curtain wall penel (2)
Surface is provided with fluorescent powder.
7. a kind of concrete construction guardrail according to claim 1, it is characterized in that:Wind-resistant column (1) bottom end is provided with
The tripod (10) to offset with ground.
8. a kind of concrete construction guardrail according to claim 1, it is characterized in that:The wind-resistant column (1) is set as steel fibre
Tie up concrete material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721647919.5U CN207728112U (en) | 2017-11-30 | 2017-11-30 | A kind of concrete construction guardrail |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721647919.5U CN207728112U (en) | 2017-11-30 | 2017-11-30 | A kind of concrete construction guardrail |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207728112U true CN207728112U (en) | 2018-08-14 |
Family
ID=63088772
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721647919.5U Active CN207728112U (en) | 2017-11-30 | 2017-11-30 | A kind of concrete construction guardrail |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207728112U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109083495A (en) * | 2018-08-17 | 2018-12-25 | 贵州大学 | A kind of civil engineering enclosing mounting device |
-
2017
- 2017-11-30 CN CN201721647919.5U patent/CN207728112U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109083495A (en) * | 2018-08-17 | 2018-12-25 | 贵州大学 | A kind of civil engineering enclosing mounting device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107905068A (en) | A kind of municipal construction road repair dead-weight compaction apparatus | |
CN207728112U (en) | A kind of concrete construction guardrail | |
CN104120660A (en) | Adjustable vehicle width-limiting device | |
CN207794292U (en) | A kind of container house with solar panels | |
CN209394021U (en) | A kind of new-energy automobile rear-box hinge borehole drill construction | |
CN204023448U (en) | Adjustable car limit for width device | |
CN215906595U (en) | Highway bridge and culvert supporting structure for bridge engineering | |
CN214575720U (en) | Building templates connection structure for civil engineering | |
CN206747687U (en) | A kind of annular cutting type CFG pile crown cutting equipments | |
CN207728114U (en) | A kind of concrete construction guardrail | |
CN207244673U (en) | The interim protective device in post-cast strip | |
CN211689784U (en) | Highway construction paving device | |
CN203514166U (en) | Built-in hydraulic concrete vibrating lever | |
CN204160735U (en) | Single screw extrusion machine | |
CN208074122U (en) | The power drive mechanism of toy car differential mechanism | |
CN206897207U (en) | A kind of pony mixer for building | |
CN207848616U (en) | A kind of water pipe mounting structure | |
CN207998770U (en) | A kind of town road asphalt paving device | |
CN207566349U (en) | A kind of interior decoration sandy soil are paved with unloading husky device | |
CN220319280U (en) | Protection device for building civil engineering | |
CN204455784U (en) | A kind of for the thermosol discharging device on pouring machine | |
CN219491017U (en) | Foundation pit supporting structure | |
CN208073034U (en) | A kind of municipal construction fence | |
CN106703049B (en) | A kind of strong improved device of building municipal works side slope | |
CN216043047U (en) | Assembled building construction encloses fender |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |