CN207714336U - A kind of deep basal pit closing fast rainfall guard system - Google Patents
A kind of deep basal pit closing fast rainfall guard system Download PDFInfo
- Publication number
- CN207714336U CN207714336U CN201721721251.4U CN201721721251U CN207714336U CN 207714336 U CN207714336 U CN 207714336U CN 201721721251 U CN201721721251 U CN 201721721251U CN 207714336 U CN207714336 U CN 207714336U
- Authority
- CN
- China
- Prior art keywords
- horizontal
- brace
- foundation pit
- foundation
- binder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
The utility model is related to a kind of deep basal pits to close fast rainfall guard system comprising foundation pit, containment system, support system and precipitation system;The containment system is set to the foundation pit surrounding medial surface, and the support system is set to the inside of the foundation pit, and the containment system is using multiple stake compositions for being erected in foundation pit surrounding medial surface;The support system includes multiple horizontal binders, multiple horizontal braces and multiple horizontal angle braces;The precipitation system is made of multiple sumps, multiple water pumpers and multiple water pipes, and the sump is set to the bottom of foundation ditch;The water pumper is set in the sump;The bottom of foundation ditch is equipped with bottom plate.
Description
Technical field
The utility model is related to technical field of building construction, and in particular to a kind of deep basal pit closing fast rainfall protection system
System.
Background technology
Foundation pit is in building trade, when building, the heatable adobe sleeping platform dug before foundation construction, and before excavation, Ying Gen
According to basic engineering drawing, accurate line setting is excavated by substrate absolute altitude and basic plane size, should also be provided according to geological hydrology
Material determines excavation plan in conjunction with live nearby buildings situation, and performs water-proof drainage work.It can be with putting side when excavating not deep
The method on slope makes Stability of Earth Slopes, gradient size provide to determine by related construction.Excavate relatively deep and neighbouring have building person, base
Crater wall must have a reliable supporting, protection outside soil layer collapse into;When due to excavating relatively depth or higher level of ground water, after excavation
Water is had in foundation pit, so draining, precipitation are necessary.
Due in current Deep foundation Pit excavation, often showing because precipitation causes surrounding building differential settlement occur
As support system is unstable;Bottom of foundation ditch is not closed, to base infiltration, soil erosion, drift sand phenomenon occur.Traditional applies
Work is cumbersome, and the period is long, and efficiency is low.Therefore, the utility model is to make up existing deficiency, provide a kind of construction period it is short,
The deep basal pit envelope of larger impact efficient, at low cost, construction quality is high, efficiently solves dewatering construction generates surrounding enviroment
Fast rainfall device is closed, therefore the invention of the utility model is particularly important.
Utility model content
In view of this, the purpose of this utility model is to provide a kind of deep basal pit closing fast rainfall guard system, solve
The deficiencies in the prior art.
The purpose of this utility model is to be achieved through the following technical solutions:
A kind of deep basal pit closing fast rainfall guard system comprising foundation pit, containment system, support system and precipitation system
System;The containment system is set to the foundation pit surrounding medial surface, and the support system is set to the inside of the foundation pit, described
Precipitation system is set to bottom in the foundation pit.
The containment system vertically downward, and is stretched using multiple stake compositions for being erected in foundation pit surrounding medial surface, the stake
Enter in the soil below the bottom of foundation ditch, and it is 1~20 meter to stretch into depth.
The support system includes multiple horizontal binders, multiple horizontal braces and multiple horizontal angle braces, and all water
Flat binder, horizontal brace and horizontal angle brace form a horizontal plane supporting construction, the supporting on the same absolute altitude
System is at least arranged one layer;The horizontal binder be arranged around the inside one week of the stake and be fixedly connected on the inside of stake;Institute
Horizontal brace is stated across the foundation pit, and the both ends of the horizontal brace horizontal system on two medial surfaces opposite with foundation pit respectively
Beam connects;The horizontal angle brace is arranged the four corners in the foundation pit, one end of the horizontal angle brace in one, the corner
The horizontal binder of side connects, and the other end of the horizontal angle brace is connect with the flat binder of another medial surface in the corner.
The precipitation system is made of multiple sumps, multiple water pumpers and multiple water pipes, and the sump is set to institute
Bottom of foundation ditch is stated, and the sump stretches into 1~20 meter of the lower section depth of bottom of foundation ditch, the upper surface of the sump and the base
Hole bottom flushes;The water pumper is set in the sump;Described water pipe one end is connect with the water pumper, and the other end prolongs
It extends to other than the foundation pit.
The bottom of foundation ditch is equipped with bottom plate.
Further, the stake is to stretch steel sheet pile, passes through head and the tail connection group between the two neighboring stretching steel sheet pile
At a plane, the degree control for stretching steel sheet pile is in 1.5% range.
Further, the support system further includes the first brace in multiple planes being set to where support system,
First brace be set to the end of horizontal brace in the corner constituted with the horizontal binder that the end is connect, and this
One end of one brace is connect with the horizontal brace, and the other end of first brace is connect with the horizontal binder.
Further, two horizontal angle braces parallel to each other are at least arranged in the corner of each foundation pit.
Further, the support system further includes multiple second braces, and second brace is set to parallel to each other
Between two horizontal angle braces, one end of second brace is connect with a horizontal angle brace, the other end of the second brace with another
Horizontal angle brace connection.
Further, the horizontal brace and horizontal binder vertical connection.
Further, multiple first level beams and multiple second horizontal beams, and first water are additionally provided in the foundation pit
Flat-topped ridge and the second horizontal beam are with the support system in same level;The first level beam is set to described horizontal horizontal
The both sides of beam, and at least two first level beams parallel to each other are equipped with per side, one end of the first level beam and the foundation pit
Sidewall horizontal binder connects, and the other end is connect with the horizontal brace;Second horizontal beam is set to parallel to each other two
Between several first level beams.
Further, the horizontal support system further includes multiple third horizontal beams, and the third horizontal beam is arranged at that
Between this two parallel horizontal brace.
Further, the third horizontal beam and the horizontal brace vertical connection;Second level and described first
Horizontal beam is vertical connection.
Further, multiple plates are additionally provided in the foundation pit, the plate is set to two first level beams disposed in parallel
Between and/or horizontal brace disposed in parallel between.
Further, the foundation pit is internally provided with multiple pillars and multiple column foundations, and the column foundation is set to the base
Bottom part down is cheated, the top mark height of the column foundation is high in the top mark of the bottom plate;One end of the pillar and the foundation pit bottom
The column foundation in portion connects, and the other end is connect with the horizontal brace.
Further, between the horizontal binder and horizontal brace, between horizontal binder and stake, the first brace and level are horizontal
Between support, between the first brace and horizontal binder, between the second brace and horizontal angle brace, first level beam and horizontal binder it
Between, between first level beam and horizontal gird, between the second horizontal beam and first level beam, the third horizontal beam and level it is horizontal
It can be bolted or weld between support and between pillar and horizontal gird etc..
Further, the water pipe is plastic tube or cast iron pipe, preferred cast iron pipe, the detachable assembling of cast iron pipe,
Assembling mode is to be bolted or weld.
Further, the bottom plate is cast in place concrete plate.
The utility model at least has the advantages that:
The utility model provides a kind of deep basal pit closing fast rainfall guard system, and the device is using stretching steel sheet piling
Pit enclosure system, continuing to draw water by the sump of bottom of foundation ditch reduces the groundwater level of bottom of foundation ditch, avoids concrete
Plate is floated inclination or crack leak by the buoyancy of underground water;In addition, bottom of foundation ditch is using concrete slab closing foundation pit bottom
Portion forms an enclosure space, can contribute to quickly pump the water in foundation pit, and avoids and substrate infiltration, water and soil occur
Phenomena such as loss, drift sand.
Support system can effectively reinforce the supporting role inside foundation pit, ensure the verticality of stake.Pass through between stake and stake
Horizontal binder forms a big integral planar harden structure, common to cooperate, the thrust of the lateral water of shared and soil;It is horizontal
The setting of the components such as crossbeam, first level beam can effectively prevent the inclination etc. of stake etc., and can be with the second horizontal beam, third
Horizontal beam etc. is coordinated, and realizes that staff can effectively be promoted by functions, the first brace, the second braces such as, material transportations
Supporting effect.
Description of the drawings
Fig. 1 is the structural schematic diagram at the top of the foundation pit described in the utility model embodiment;
Fig. 2 is the cross section structure schematic diagram inside the foundation pit described in the utility model embodiment;
Fig. 3 is the sectional elevation structural schematic diagram of the foundation pit described in the utility model embodiment;
Fig. 4 is the structural schematic diagram of the stretching steel sheet pile described in the utility model embodiment.
In figure, 1, foundation pit, 2, containment system, 3, support system, 4, precipitation system, 11, bottom plate, 12, first level beam, 13
Second horizontal beam, 14, third horizontal beam, 15, plate, 16, pillar, 17, column foundation, 21, stake, 31, horizontal binder, 32, horizontal horizontal
Beam, 33, horizontal angle brace, the 34, first brace, 35 second braces, 41, sump, 42, water pumper, 43, water pipe, 111, concrete
Plate, 211, stretch steel sheet pile.
Specific implementation mode
The technical scheme in the utility model embodiment is clearly and completely described below, it is clear that described reality
It is the utility model a part of the embodiment to apply example, instead of all the embodiments.The embodiments of the present invention presented below
Detailed description be not intended to limit claimed the scope of the utility model, but be merely representative of the selected of the utility model
Embodiment.Based on the embodiments of the present invention, this field commonsense method personnel are without creative efforts
The every other embodiment obtained, shall fall within the protection scope of the present invention.
As shown in figures 1-4, a kind of deep basal pit closes fast rainfall guard system comprising foundation pit 1, containment system 2, branch
Protecting system 3 and precipitation system 4;The containment system 2 is set to 1 surrounding medial surface of the foundation pit, prevents 1 outside of the foundation pit
Water and soil enter in foundation pit, play the role of waterproof earth-retaining, the support system 3 is set to the inside of the foundation pit 1, the base
The water and soil of 1 outside of hole generate thrust inwards to 1 madial wall of the foundation pit, make the containment system 2 be deformed inward buckling or
Person is caved in, and the support system 3 plays the internal supporting role of reinforcement, strengthens the intensity of the containment system 2, avoids described enclose
Protecting system 2 destroy, be the foundation pit 1 in operation create a safety operating environment, more effectively prevent water and soil into
Enter in the foundation pit 1, the precipitation system 4 is set to the bottom in the foundation pit 1, and the precipitation system 4 can be quickly and effectively
The water in the hole of the foundation pit 1 is pumped, is that an anhydrous operating environment is created in the operation in the foundation pit 1.
The containment system 2 using several stakes 21 form, the stake 21 vertically downward, and stretch into 1 bottom of the foundation pit with
Under soil in, it is 0.5~20 meter to be embedded to the depth below bottom of foundation ditch, such as 5 meters or 10 meters, specifically can according to actual conditions and
Fixed, which can be used as the bearing of the stake 21, will not sidesway inwards under 21 side water of the stake and native thrust
It is tilted beyond the requirement of verticality.
As shown in Fig. 1~2, the support system 3 is by several horizontal binders 31, several horizontal braces 32, several horizontal angles
Support 33, several first braces 34 and several second braces 35 composition, and on an absolute altitude, form a horizontal plane supporting knot
Structure.The support system 3 is at least arranged one layer, and according to the depth of foundation pit, which can be arranged multilayer, such as 2 layers or 3 layers
Or more etc., if 2 layers are preferably arranged one layer in the middle section of foundation pit, set in foundation pit fixed end face or close to the place of top end face
Set one layer.
The horizontal binder 31 be set to the whole length of the inside of the stake 21 and horizontal binder 31 in the stake 21
Side connects;A big integral planar harden structure is formed by the horizontal binder 31 between the stake and stake, it is common to cooperate, altogether
With the thrust for undertaking lateral water and soil;Two opposite medial surfaces at the both ends of the horizontal brace 32 and the foundation pit 1
Connection, i.e., the horizontal brace 32 is across the foundation pit 1;Specifically, one end of horizontal brace 32 connects with the horizontal binder 31 in the side
It connects, the horizontal binder 31 on the other end and opposite connects.One end of first brace 34 is connect with the horizontal brace 32, another
End is connect with the horizontal binder 31, i.e. the first brace 34 is arranged at the right angle that horizontal brace 32 and horizontal binder 31 are formed
It is interior, i.e. a bevel edge of first brace 34 as the right angle, referring specifically to Fig. 1, first brace 34 and described horizontal horizontal
Bar 32 forms horizontal supporting system, can preferably prevent planar panel structure flexural deformation into the foundation pit 1 of opposite sides;Institute
It is the horizontal angle brace 33 to state horizontal angle brace 33 medial surface in 1 four corners of the foundation pit is arranged that is, in each corner
One end is connect with the inside of the horizontal binder 31 on a side, another horizontal binder 31 that the other end intersects with the horizontal binder 31
Connection, containing 2~3 horizontal angle braces 33 parallel to each other, horizontal angle brace 33 can be rod-shaped reinforcing bar in the corner of each foundation pit
It constitutes, referring specifically to Fig. 1, second brace 35 is set between two neighboring horizontal angle brace 33, and the one of second brace 35
End is connect with a horizontal angle brace 33, and the other end is connect with another horizontal angle brace 33, and the second brace 35 can be arranged more, more
The second brace of root 35 can end to end formation polyline shaped structure, second brace 35 and the horizontal angle brace 33 one bar of composition
Part system can preferably prevent planar panel structure flexural deformation into foundation pit of two intersections, the corner of the foundation pit 1 is made to add
By force.
As shown in figure 3, the precipitation system 4 is made of several sumps 41, several water pumpers 42 and several water pipes 43, institute
It states sump 41 and is set to 1 bottom of the foundation pit, and extend to the place of 1~10 meter of foundation pit or less, i.e., the described sump 41 is deep
Degree is 1~20 meter, such as 4 meters, 10 meters, specifically can according to foundation depth, different places geology etc. depending on, the sump
Specific depth value can pass through profession calculating and be taken;The upper surface of the sump 41 is flushed with the top surface of 1 bottom of the foundation pit,
Water or rainwater in the hole of the foundation pit 1 can be flowed into the gradient in the sump 41 naturally;The water pumper 42 is set to institute
State in sump 41, such as may be disposed at sump 41 bottom or bottom above some;43 one end of the water pipe and the pumping
Water dispenser 42 connects, and the outside that the other end is positioned over 1 top of the foundation pit allows it to send out in the water in sump, the collection
Water in the hole of the foundation pit 1 can not only drop in the precipitation of well 41, moreover it is possible to 1 bottom of foundation pit water level below be made also to reduce.
1 bottom of the foundation pit is equipped with bottom plate 11.
The stake 21 can be to stretch steel sheet pile 211, two neighboring 211 group of head and the tail connection between any two of the stretching steel sheet pile
At a concave and convex plane, as shown in figure 4, the degree control for stretching steel sheet pile 211 is in 1.5% range.
It is horizontal that 1 inner top of the foundation pit can also be equipped with several first level beams 12, several second horizontal beams 13, several thirds
If beam 14 and dry plate 15, if the first level beam 12, several second horizontal beams 13, several third horizontal beams 14 and dry plate 15 with
In the support system 3 is generally aligned in the same plane, and if can be arranged in every layer of the support system 3 the first level beam 12,
If dry second horizontal beam 13, several third horizontal beams 14 and dry plate 15.
As shown in Fig. 2, in every layer of support system 3, the first level beam 12 is arranged in the both sides of horizontal brace 32,
And two first level beams 12 parallel to each other are at least set per side;The every first level beam 12 can be one end with it is described
1 sidewall horizontal binder of foundation pit, 31 vertical connection, the other end and 32 vertical connection of the horizontal brace.Second horizontal beam 13 is set
Be placed between two horizontally-supported columns in the first level beam 12, i.e., one end of the second horizontal beam 13 and one it is horizontally-supported
Column connects, and the other end is connect with another with horizontally-supported column, and preferably the second horizontal beam 13 is Bi Cichuizhied with first level beam 12.Institute
It states third horizontal beam 14 to be arranged between the two neighboring horizontal brace 32, i.e. one end of the third horizontal beam 14 and a water
Flat stull 32 connects, and the other end is connect with another horizontal brace 32;As shown in Figure 1, the plate 15 may be disposed at and be arranged in parallel
Two first level beams 12 between or horizontal brace disposed in parallel 32 between, when specific setting, which may also be arranged on
Between two neighboring second horizontal beam 13 or between two neighboring third horizontal beam 14.The plate 15, which can be both used as, stacks construction
The work surface of material, utensil can also be used as the road or maneuvering platform of construction personnel, and more construction provides an operation
Face.
The foundation pit 1 is internally provided with several pillars 16 and column foundation 17, and the column foundation 17 is set to 1 bottom of the foundation pit
In soil, the top mark height of the column foundation 17 is high in the top mark of the bottom plate 11;One end of the pillar 16 and column foundation 17
Upper surface is fixedly connected, and the other end is fixedly connected with the horizontal brace 32.The setting of the pillar 16 reduces the horizontal branch
The span of support 32 increases vertical supporting for the support system 3 in the foundation pit 1, avoids due to 1 span of the foundation pit too
Greatly, the span of the horizontal brace 32 is too big, and deflection deformation occurs, also reduces the section of 32 component of the horizontal brace, saves
About material.
The horizontal binder 31, horizontal brace 32, horizontal angle brace support 33, first level beam 12, the second horizontal beam 13, third
Horizontal beam 14, the first brace 34, the second brace 35 and 16 material of pillar can be armored concrete or section steel material, preferred type
Steel, 15 material of the plate are armored concrete or steel plate, preferably steel plate, select shaped steel or steel plate materials, this body structure is certainly
Heavy and light just, and facilitates installation, dismounting, secondary conveying, material recycling.
The horizontal binder 31, horizontal brace 32, horizontal angle brace support 33, first level beam 12, the second horizontal beam 13, third
Horizontal beam 14, the first brace 34, the second brace 35 and 16 material of pillar can be shaped steel, and its connection for being related between each other
Mainly be bolted or weld, the horizontal binder 31, horizontal brace 32, horizontal angle brace support 33, first level beam 12,
Second horizontal beam 13, third horizontal beam 14, the first brace 34, the second brace 35 and the detachable assembling of pillar 16, assembling mode
To be bolted or welding.Combination installation, for construction shorten the duration, it is to be onstructed to finish, engineering delivery use when with
Afterwards, all shaped steel and all detachable recycling of steel plate supply next engineering and reuse.
The water pipe 43 is plastic tube or cast iron pipe, preferably cast iron pipe, the detachable assembling of cast iron pipe, assembling mode
To be bolted or welding.Just it dismantles, transport, repeat and utilize, the cast iron pipe has certain intensity, can support certain
Weight eliminates and needs the trouble separately reinforced using plastic tube.
The bottom plate 11 is cast in place concrete plate 111.It is excavated to after desired absolute altitude after the foundation pit 1, uses concrete slab
A closed working space is collectively formed in 111 back covers, concrete slab and the containment system 2, to prevent the foundation pit 1
The water of side wall and soil enter in foundation pit, prevent 1 bottom of the foundation pit it is below it is waterborne instead arrive in the foundation pit 1, provided to construct
One dry work surface, but the water pumper 42 needs to work always and draw water, because once the water pumper 42 stops pumping,
Level of ground water will rise, and the buoyancy for rising to water is more than the gravity of the concrete slab 111, and the concrete 111 will go out
Existing Crack failure leak or inclination float, so the precipitation of the sump 41 is necessary, effectively, wait for Practical Completion
Afterwards, after the foundation pit 1 backfills, when the gravity of superstructure is more than buoyancy of the concrete slab 111 by water, the sump
41 precipitation could stop.
Protecting tube 44 is provided in the sump, the protecting tube 44 can be pipe of cement or pipe of concrete as support to prevent
Sump caves in, and the water pumper 42 is set in protecting tube 44.The sump includes be disposed in proximity to foundation pit surrounding
One sump and the second sump for being set to foundation pit center portion.By the foundation pit bottom surface that is connect with the stake to first collection
Well, height lower and lower (i.e. gradually diagonally downward) so that by infiltered on the outside of stake Lai water being capable of timely, fixed inflow
First sump, to be that construction impacts.
The waterproof layer for covering the seam is equipped on the inside of the seam of two neighboring stretching steel sheet pile connection, the waterproof layer can
For membrane waterproofing or splash guard etc., which can weld with the stretching steel sheet pile of seam both sides, be bolted or marine glue
Bonding etc..
Preferably, the sump includes being disposed in proximity to the first sump of foundation pit surrounding and being set to foundation pit central portion
The second sump divided;By the foundation pit bottom surface that is connect with the stake to first sump, height it is lower and lower so that by
Stake outside infilters the water come being capable of the first sump of timely, fixed inflow.
In the present invention, steel sheet pile branch is stretched using the measure combination foundation pit that intercepts water at underwater concrete foundation pit underseal bottom
Protecting system, the underground water for stopping foundation pit side-wall and foundation pit ground flow into foundation pit, while taking dewatering measure to extract or draw and oozing foundation pit
The precipitation method for excavating the existing underground water in range, by the stratum on foundation pit periphery because the additional settlement that precipitation is formed is controlled one
Degree is determined, to reduce influence of the base pit dewatering to surrounding enviroment.By stretching steel sheet pile foundation pit support system and using cast-in-place
Concrete slab closes foundation pit bottom opening, forms an enclosure space, can quickly pump the water in foundation pit, pass through bottom of foundation ditch
Sump continue to draw water and reduce the groundwater level of bottom of foundation ditch, avoid concrete slab and floated by the buoyancy of underground water
Inclination or crack leak.
The deep basal pit closing fast rainfall guard system of the utility model can effectively solve the surrounding enviroment production of dewatering construction team
Raw larger impact, shortens the construction period, improves work efficiency simultaneously, saved cost, have good social benefit with
Economic benefit has wide application space in the regional excavation of rich groundwater, has promotional value, effect is very
It is good.
The above is only the preferred embodiment of the present invention, is not intended to limit the utility model, for this field
For technical staff, the utility model can have various modifications and changes.All institutes within the spirit and principle of the utility model
Any modification, equivalent substitution, improvement and etc. of work, should be included within the scope of protection of this utility model.
Claims (10)
1. a kind of deep basal pit closes fast rainfall guard system comprising foundation pit, containment system, support system and precipitation system;
The containment system is set to the foundation pit surrounding medial surface, and the support system is set to the inside of the foundation pit, the drop
Water system is set to bottom in the foundation pit;It is characterized in that:
The containment system vertically downward, and stretches into institute using multiple stake compositions for being erected in foundation pit surrounding medial surface, the stake
It states in the soil below bottom of foundation ditch, and it is 1~20 meter to stretch into depth;
The support system includes multiple horizontal binders, multiple horizontal braces and multiple horizontal angle braces, and all levels are
Beam, horizontal brace and horizontal angle brace form a horizontal plane supporting construction, the support system on the same absolute altitude
At least it is arranged one layer;The horizontal binder be arranged around the inside one week of the stake and be fixedly connected on the inside of stake;The water
Flat stull is across the foundation pit, and horizontal binder of the both ends of the horizontal brace respectively on two medial surfaces opposite with foundation pit connects
It connects;The four corners in the foundation pit, one end of the horizontal angle brace and one, corner medial surface is arranged in the horizontal angle brace
The connection of horizontal binder, the other end of the horizontal angle brace connect with the flat binder of another medial surface in the corner;
The precipitation system is made of multiple sumps, multiple water pumpers and multiple water pipes, and the sump is set to the base
Bottom is cheated, and the sump stretches into 1~20 meter of the lower section depth of bottom of foundation ditch, the upper surface of the sump and the foundation pit bottom
Portion flushes;The water pumper is set in the sump;Described water pipe one end is connect with the water pumper, and the other end extends to
Other than the foundation pit;
The bottom of foundation ditch is equipped with bottom plate.
2. deep basal pit according to claim 1 closes fast rainfall guard system, it is characterised in that:The stake is extended steel
Sheet pile connects one plane of composition between the two neighboring stretching steel sheet pile by head and the tail, described to stretch the vertical of steel sheet pile
Degree control is in 1.5% range.
3. deep basal pit according to claim 2 closes fast rainfall guard system, it is characterised in that:The support system is also
Including the first brace in multiple planes being set to where support system, first brace is set to the end of horizontal brace
With the corner constituted with the horizontal binder that the end is connect, and one end of first brace is connect with the horizontal brace,
The other end of first brace is connect with the horizontal binder.
4. deep basal pit according to claim 3 closes fast rainfall guard system, it is characterised in that:The support system is also
Including multiple second braces, second brace is set between two horizontal angle braces parallel to each other, and the one of second brace
End is connect with a horizontal angle brace, and the other end of the second brace is connect with another horizontal angle brace.
5. deep basal pit according to claim 4 closes fast rainfall guard system, it is characterised in that:It is also set in the foundation pit
Have a multiple first level beams and multiple second horizontal beams, and the first level beam and the second horizontal beam with the support system
In same level;
The first level beam is set to the both sides of the horizontal gird, and at least two first water parallel to each other are equipped with per side
Flat-topped ridge, one end of the first level beam are connect with the horizontal binder of the foundation pit side-wall, and the other end is connect with the horizontal brace;
Second horizontal beam is set between several first level beams of parallel to each other two.
6. deep basal pit according to claim 5 closes fast rainfall guard system, it is characterised in that:The horizontal supporting system
System further includes multiple third horizontal beams, and the third horizontal beam is arranged between two horizontal braces parallel to each other.
7. deep basal pit according to claim 6 closes fast rainfall guard system, it is characterised in that:It is also set in the foundation pit
There are multiple plates, the plate to be set between two first level beams disposed in parallel and/or between horizontal brace disposed in parallel.
8. deep basal pit according to claim 7 closes fast rainfall guard system, it is characterised in that:It is set inside the foundation pit
There are multiple pillars and multiple column foundations, the column foundation to be set to below the bottom of foundation ditch, the top mark height of the column foundation
It is high in the top mark of the bottom plate;One end of the pillar is connect with the column foundation of the bottom of foundation ditch, the other end and the level
Stull connects.
9. deep basal pit according to claim 8 closes fast rainfall guard system, it is characterised in that:The horizontal binder with
Between horizontal brace, between horizontal binder and stake, between the first brace and horizontal brace, between the first brace and horizontal binder,
Between second brace and horizontal angle brace, between first level beam and horizontal binder, between first level beam and horizontal gird, second
Between horizontal beam and first level beam, equal energy between the third horizontal beam and horizontal brace and between pillar and horizontal gird
It is enough bolted or welds.
10. deep basal pit according to claim 9 closes fast rainfall guard system, it is characterised in that:The bottom plate is existing
Pouring concrete plate.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721721251.4U CN207714336U (en) | 2017-12-12 | 2017-12-12 | A kind of deep basal pit closing fast rainfall guard system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721721251.4U CN207714336U (en) | 2017-12-12 | 2017-12-12 | A kind of deep basal pit closing fast rainfall guard system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207714336U true CN207714336U (en) | 2018-08-10 |
Family
ID=63060449
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721721251.4U Expired - Fee Related CN207714336U (en) | 2017-12-12 | 2017-12-12 | A kind of deep basal pit closing fast rainfall guard system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207714336U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111749257A (en) * | 2020-05-30 | 2020-10-09 | 任康丽 | Quick dewatering device and method for deep foundation pit |
CN114482077A (en) * | 2022-04-13 | 2022-05-13 | 三亚宏岩岩土工程有限公司 | Foundation ditch intelligence braced system with antiseismic impervious effect |
-
2017
- 2017-12-12 CN CN201721721251.4U patent/CN207714336U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111749257A (en) * | 2020-05-30 | 2020-10-09 | 任康丽 | Quick dewatering device and method for deep foundation pit |
CN111749257B (en) * | 2020-05-30 | 2021-12-21 | 淮北淮海建设工程有限责任公司 | Quick dewatering device and method for deep foundation pit |
CN114482077A (en) * | 2022-04-13 | 2022-05-13 | 三亚宏岩岩土工程有限公司 | Foundation ditch intelligence braced system with antiseismic impervious effect |
CN114482077B (en) * | 2022-04-13 | 2022-06-28 | 三亚宏岩岩土工程有限公司 | Foundation ditch intelligence braced system with impervious effect of antidetonation |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10138616B2 (en) | Inverse construction method for deep, large and long pit assembling structure of suspension-type envelope enclosure | |
CN108442382B (en) | In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method | |
CN107524138B (en) | Construction method of ultra-deep foundation pit underground diaphragm wall | |
CN105736001B (en) | A kind of construction method using prefabricated parts subway station | |
CN106013052A (en) | Steel sheet pile and open caisson combined underground garage and construction method thereof | |
CN105239578B (en) | Water-rich sand layer deep foundation pit underwater construction method | |
CN103938634B (en) | A kind of deep foundation pit supporting structure and construction method | |
CN103806464B (en) | Large-scale high ferro station and subway cross top-down construction method up and down | |
CN106245653A (en) | A kind of vertical mud and water balance construction method | |
CN106013053A (en) | Steel sheet pile support construction method for building underground garage open caisson | |
CN207714348U (en) | A kind of deep basal pit fast rainfall device | |
CN106436788A (en) | Foundation reinforcement and inclination correction method for friction piles of high-rise building | |
CN205242436U (en) | Supplementary soleplate traded interim bearing structure who props during system was gone along with sb. to guard him to underground complex | |
CN105735354A (en) | Covered-excavation full-top-down construction method of municipal underground engineering | |
CN105926391B (en) | A kind of curb method for widening of existing railway roadbed | |
CN105155602A (en) | Multi-support foundation strengthening comprehensive controlling method | |
CN112878332A (en) | Basement elevator shaft sump construction structure and method thereof | |
CN207714336U (en) | A kind of deep basal pit closing fast rainfall guard system | |
CN114319435B (en) | Underground passage supporting structure with large-section shallow buried pipe gallery in underpass and construction method | |
CN106567365B (en) | Earth and rockfill dam longitudinal reinforcement construction method | |
CN111622234B (en) | Unloading type thin-wall box-type retaining wall supported by obliquely and vertically combined steel pipe pile and construction process | |
CN109487793A (en) | Inner support of pile foundation pit permanent support structure is perfused in a kind of solid matter under complex environment | |
CN106245668A (en) | A kind of truss-like pile foundation and construction method thereof | |
CN205062744U (en) | Half gravity type two -stage view anti -flood wall on half cantilever | |
CN109610508B (en) | Pipe gallery construction method for penetrating built pipe gallery and support replacing structure thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180810 Termination date: 20201212 |