CN207700680U - A kind of roof boarding hangs mould - Google Patents

A kind of roof boarding hangs mould Download PDF

Info

Publication number
CN207700680U
CN207700680U CN201721518428.0U CN201721518428U CN207700680U CN 207700680 U CN207700680 U CN 207700680U CN 201721518428 U CN201721518428 U CN 201721518428U CN 207700680 U CN207700680 U CN 207700680U
Authority
CN
China
Prior art keywords
hanging
roof boarding
formwork
hanging beam
several
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721518428.0U
Other languages
Chinese (zh)
Inventor
阮晓巍
金少惷
陆顺康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Priority to CN201721518428.0U priority Critical patent/CN207700680U/en
Application granted granted Critical
Publication of CN207700680U publication Critical patent/CN207700680U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本实用新型的一种屋面板吊模,涉及建筑施工技术领域。针对具有挑空层的屋面板的浇筑施工中,采用高支模支撑体系材料消耗较大,费工费时,而且高空支模施工危险性大的问题。它包括架设于已安装的主体结构钢梁上的若干吊梁;安装于主体结构钢梁之间的模板组件,模板组件上表面与主体结构钢梁顶端平齐;吊杆的两端分别贯穿吊梁及模板组件后锁紧固定。

The utility model relates to a roof panel hanging form, which relates to the technical field of building construction. In the pouring construction of the roof slab with a hollow layer, the use of high formwork support system consumes a lot of materials, is labor-intensive and time-consuming, and the high-altitude formwork construction is dangerous. It includes a number of hanging beams erected on the installed steel beams of the main structure; formwork components installed between the steel beams of the main structure, the upper surface of the formwork components is flush with the top of the steel beams of the main structure; The beam and formwork components are then locked and fixed.

Description

一种屋面板吊模A roof panel hanging mold

技术领域technical field

本实用新型涉及建筑施工技术领域,特别涉及一种屋面板吊模。The utility model relates to the technical field of building construction, in particular to a roof panel hanging form.

背景技术Background technique

目前,大型商业综合体建筑项目越来越多地采用钢结构体系,其中,裙房的中庭屋面板大多采用在主体结构钢梁上浇筑混凝土板的形式。由于中庭采光以及自动扶梯设置的需要,中庭屋面板下方均为挑空层,故中庭屋面板的浇筑施工一般均采用高支模支撑体系,而高支模支撑体系的排架搭设高度一般均超过20米,材料消耗较大,费工费时,而且高空支模施工的危险性较大。At present, steel structure systems are increasingly used in large-scale commercial complex construction projects. Among them, the atrium roof panels of the podium mostly adopt the form of pouring concrete slabs on the steel beams of the main structure. Due to the need for lighting in the atrium and the installation of escalators, the lower part of the atrium roof slab is a hollow floor, so the pouring construction of the atrium roof slab generally adopts a high-formwork support system, and the height of the bent frames of the high-formwork support system is generally more than 20 meters, the material consumption is large, labor and time-consuming, and the risk of high-altitude formwork construction is relatively high.

发明内容Contents of the invention

针对具有挑空层的屋面板的浇筑施工中,采用高支模支撑体系材料消耗较大,费工费时,而且高空支模施工危险性大的问题。本实用新型的目的是提供一种屋面板吊模,该屋面板吊模充分利用现有的主体结构钢梁作为受力支撑,结构更加稳定可靠,在保证施工质量的前提下更具安全性。In the pouring construction of the roof slab with a hollow layer, the use of high formwork support system consumes a lot of materials, is labor-intensive and time-consuming, and the high-altitude formwork construction is dangerous. The purpose of the utility model is to provide a roof panel hanging formwork, the roof panel hanging formwork fully utilizes the existing main structure steel beams as the force support, the structure is more stable and reliable, and it is safer under the premise of ensuring the construction quality.

本实用新型解决其技术问题所采用的技术方案是:一种屋面板吊模,它包括若干吊梁,所述吊梁架设于已安装的主体结构钢梁上;模板组件,所述模板组件安装于所述主体结构钢梁之间,且所述模板组件上表面与所述主体结构钢梁顶端平齐;以及若干吊杆,所述吊杆的两端分别贯穿所述吊梁及所述模板组件后锁紧固定。The technical solution adopted by the utility model to solve the technical problems is: a roof panel hanging form, which includes a number of hanging beams, and the hanging beams are erected on the installed steel beams of the main structure; a template assembly, the template assembly is installed Between the steel beams of the main structure, and the upper surface of the formwork assembly is flush with the top of the steel beams of the main structure; The components are locked and fixed.

优选的,所述吊梁由相对设置的两根槽钢制成,两根槽钢的腹板相靠近且保留一能够容纳所述吊杆贯穿的间隙,使得所述吊杆的顶端能够穿过所述间隙并锁紧固定。Preferably, the suspension beam is made of two oppositely arranged channel steels, the webs of the two channel steels are close to each other and a gap capable of accommodating the penetration of the suspension rod is reserved, so that the top end of the suspension rod can pass through The gap is locked and fixed.

优选的,所述吊梁的底部还设有若干立柱,所述立柱的顶端与所述吊梁固接,所述立柱的底端固接于所述主体结构钢梁,且所述立柱的高度大于待浇筑屋面板的厚度。Preferably, the bottom of the hanging beam is further provided with several uprights, the tops of the uprights are affixed to the hanging beam, the bottom ends of the uprights are affixed to the main structural steel beam, and the height of the uprights Greater than the thickness of the roof slab to be poured.

优选的,所述立柱的两侧还分别固接有限位杆,所述限位杆的底端位于待浇筑屋面板之上,所述限位杆的顶端与所述吊梁的顶端平齐。Preferably, both sides of the upright column are respectively fixed with limit rods, the bottom ends of the limit rods are located above the roof slab to be poured, and the top ends of the limit rods are flush with the top ends of the suspension beams.

优选的,所述吊梁两侧的槽口内满塞定位块,所述定位块的两侧分别与吊梁的腹板及所述限位杆相抵。Preferably, the notches on both sides of the hanging beam are filled with positioning blocks, and the two sides of the positioning block respectively abut against the web of the hanging beam and the limit rod.

优选的,所述吊杆包括一根具有外螺纹的螺杆、分别螺纹连接于所述螺杆两端的两个螺母,以及若干垫片,所述垫片呈U形,所述螺杆卡扣于所述垫片的槽口内。Preferably, the suspension rod includes a screw rod with external threads, two nuts threadedly connected to both ends of the screw rod, and several gaskets, the gaskets are U-shaped, and the screw rod is buckled on the in the notch of the gasket.

优选的,所述模板组件由并列设置于底层的若干主龙背,铺设于所述主龙骨上且与所述主龙骨交错设置的若干次龙骨,以及铺设于所述次龙骨上的模板组成。Preferably, the formwork assembly is composed of several main joists arranged side by side on the ground floor, several sub-keels laid on the main joists and interlaced with the main joists, and a formwork laid on the sub-keels.

本实用新型的效果在于:本实用新型的屋面板吊模,以已安装的建筑主体结构钢梁作为支撑,在主体结构钢梁上搭设吊梁,模板组件通过吊杆悬吊于吊梁实现固定,随后再进行屋面板钢筋绑扎及混凝土浇筑施工,该屋面板吊模充分利用现有的主体结构钢梁作为受力支撑,结构更加稳定可靠,在保证施工质量的前提下更具安全性;该屋面板吊模通过吊杆将模板组件螺栓连接于吊梁上,结构简单,拆装方便,各构件可反复利用,降低了施工成本。The utility model has the effect that: the roof panel hanging formwork of the utility model is supported by the installed main structural steel beam of the building, and a hanging beam is set up on the main structural steel beam. , and then carry out the roof slab steel bar binding and concrete pouring construction, the roof slab hanging form makes full use of the existing main structural steel beams as the force support, the structure is more stable and reliable, and it is safer under the premise of ensuring the construction quality; The roof panel hanging formwork bolts the formwork assembly to the hanging beam through the suspender rod, which has a simple structure and is easy to disassemble and assemble. Each component can be used repeatedly, which reduces the construction cost.

附图说明Description of drawings

图1为本实用新型一实施例的屋面板吊模的局部俯视图;Fig. 1 is a partial top view of a roof panel hanging formwork according to an embodiment of the present invention;

图2为图1的A-A剖视图;Fig. 2 is A-A sectional view of Fig. 1;

图3为图1的B-B剖视图;Fig. 3 is the B-B sectional view of Fig. 1;

图4为图2的C部分的局部放大图;Fig. 4 is a partially enlarged view of part C of Fig. 2;

图5为本实用新型一实施例的立柱的结构示意图;Fig. 5 is a schematic structural view of a column according to an embodiment of the present invention;

图6为本实用新型一实施例中封堵屋面板穿孔的示意图。Fig. 6 is a schematic diagram of sealing the perforation of the roof panel in an embodiment of the present invention.

图中标号如下:The numbers in the figure are as follows:

主体结构钢梁1;锚钉2;吊梁10;立柱20;限位杆20a;吊杆30;螺杆31;垫片32;螺母33;定位块40;模板组件50;主龙背51;次龙骨52;模板53;套管60;屋面板100;穿孔101;防水层102。Main structural steel beam 1; anchor 2; hanging beam 10; column 20; limit rod 20a; suspender 30; Keel 52 ; template 53 ; casing 60 ; roof panel 100 ; perforation 101 ; waterproof layer 102 .

具体实施方式Detailed ways

以下结合附图和具体实施例对本实用新型提出的一种屋面板吊模作进一步详细说明。根据下面的说明和权利要求书,本实用新型的优点和特征将更清楚。需说明的是,附图均采用非常简化的形式且均使用非精准的比例,仅用以方便、明晰地辅助说明本实用新型实施例的目的。为叙述方便,下文中所述的“上”、“下”与附图的上、下的方向一致,但这不能成为本实用新型技术方案的限制。A roof panel hanging form proposed by the utility model will be described in further detail below in conjunction with the accompanying drawings and specific embodiments. According to the following description and claims, the advantages and features of the utility model will be more clear. It should be noted that all the drawings are in very simplified form and use inaccurate scales, which are only used to facilitate and clearly illustrate the purpose of the embodiment of the present utility model. For the convenience of description, the "up" and "down" described below are consistent with the directions of up and down in the drawings, but this cannot be a limitation of the technical solution of the present utility model.

本实施例的屋面板吊模是利用已安装的主体结构钢梁1实现模板53的固定,进而实施屋面板100混凝土的浇筑施工,下面结合图1至图5说明本实用新型的一种屋面板吊模,它包括水平架设于主体结构钢梁1上的若干吊梁10;安装于主体结构钢梁1之间的模板组件50,模板组件50的上表面与主体结构钢梁1的顶端平齐;以及若干吊杆30,所述吊杆30的两端分别贯穿吊梁10及模板组件50并锁紧固定。The roof panel hanging formwork of this embodiment utilizes the installed main structure steel beam 1 to realize the fixing of the formwork 53, and then implements the concrete pouring construction of the roof panel 100. A roof panel of the present utility model is described below in conjunction with Fig. 1 to Fig. 5 Suspension formwork, it comprises several suspension beams 10 that are erected horizontally on the main structural steel beam 1; Formwork assembly 50 installed between the main structural steel beams 1, the upper surface of the formwork assembly 50 is flush with the top of the main structural steel beam 1 ; and several suspenders 30, the two ends of the suspenders 30 respectively pass through the suspension beam 10 and the template assembly 50 and are locked and fixed.

本实用新型的屋面板吊模,以已安装的建筑主体结构钢梁1作为支撑,在主体结构钢梁1上搭设吊梁10,模板组件50通过吊杆30悬吊于吊梁10实现固定,随后再进行屋面板100钢筋绑扎及混凝土浇筑施工,该屋面板吊模充分利用现有的主体结构钢梁1作为受力支撑,结构更加稳定可靠,在保证施工质量的前提下更具安全性;该屋面板吊模通过吊杆30将模板组件50螺栓连接于吊梁10上,结构简单,拆装方便,各构件可反复利用,降低了施工成本。The roof panel hanging formwork of the utility model is supported by the installed steel beam 1 of the main structure of the building, and the hanging beam 10 is set up on the steel beam 1 of the main structure. Then the roof panel 100 steel bar binding and concrete pouring construction are carried out. The roof panel hanging form makes full use of the existing main structural steel beam 1 as the force support, the structure is more stable and reliable, and it is safer under the premise of ensuring the construction quality; The roof panel hanging formwork bolts the template assembly 50 to the hanging beam 10 through the hanging rod 30, has a simple structure, is convenient to disassemble and assemble, each component can be used repeatedly, and construction cost is reduced.

如图2和图4所示,吊梁10由相对设置的两根槽钢制成,两根槽钢的腹板相靠近且保留一能够容纳吊杆30贯穿的间隙,使得吊杆30的顶端能够穿过吊梁10的间隙并锁紧固定;吊梁10由水平设置的双拼槽钢制成,其承重能力较强,而且取材方便,易于加工,可重复投入使用,节省了大量传统高支模所投入的钢管及模板等费用。本实施例的吊梁10采用14a槽钢制成,即槽钢宽度14cm,厚度6mm。As shown in Fig. 2 and Fig. 4, the suspension beam 10 is made of two oppositely arranged channel steels, the webs of the two channel steels are close together and retain a gap capable of accommodating the penetration of the suspension rod 30, so that the top of the suspension rod 30 Can pass through the gap of the hanging beam 10 and lock and fix; The cost of steel pipes and templates invested in the formwork. The hanging beam 10 of this embodiment is made of 14a channel steel, that is, the channel steel has a width of 14 cm and a thickness of 6 mm.

为保证模板组件50上方具有满足施工要求的混凝土浇筑空间,上述吊梁10的底部还设有若干立柱20,立柱20的顶端与吊梁10固接,立柱20的底端固接于主体结构钢梁1,且立柱20的高度大于待浇筑屋面板100的厚度,以满足屋面板100混凝土浇筑施工的需要,本实施例的立柱20由竖向设置的18a双拼槽钢制成,即槽钢宽度18cm,厚度7mm,当然,立柱20也可采用其他形式的材料制成,此处不作限定。更佳的,如图5所示,双拼槽钢翼板的外侧还分别固接有两根限位杆20a,该限位杆20a的底端位于待浇筑屋面板100之上,限位杆20a的顶端与吊梁10的顶端平齐,在立柱20焊接固定于主体结构钢梁1后,吊梁10仅需搭设于立柱20上,限位杆20a起到对吊梁10水平定位的作用,吊梁10的固定无需焊接施工,其拆装更加方便,而且还可以反复利用;另外,吊梁10两侧的槽口内满塞定位块40,定位块40的两侧分别与腹板及限位杆20a相抵,使得吊梁10稳定固定于立柱20上,采用限位块夹紧吊梁10,吊梁10的定位及拆卸均更加方便,减少了高空焊接作业量,提高了工作效率。本实施例中定位块40采用木方制成。In order to ensure that there is a concrete pouring space above the formwork assembly 50 that meets the construction requirements, a number of columns 20 are provided at the bottom of the suspension beam 10. Beam 1, and the height of the column 20 is greater than the thickness of the roof slab 100 to be poured, so as to meet the needs of the concrete pouring construction of the roof slab 100, the column 20 of this embodiment is made of 18a double channel steel that is vertically arranged, that is, the channel steel The width is 18cm, and the thickness is 7mm. Of course, the column 20 can also be made of other materials, which is not limited here. More preferably, as shown in Fig. 5, two stop rods 20a are fixedly connected to the outer sides of the double channel steel wing plates respectively, and the bottom ends of the stop rods 20a are positioned above the roof panel 100 to be poured, and the stop rods The top of 20a is flush with the top of the hanging beam 10. After the column 20 is welded and fixed to the steel beam 1 of the main structure, the hanging beam 10 only needs to be erected on the column 20, and the limit rod 20a plays a role in horizontally positioning the hanging beam 10. , the fixing of the hanging beam 10 does not require welding construction, its disassembly and assembly are more convenient, and it can also be used repeatedly; in addition, the slots on both sides of the hanging beam 10 are filled with positioning blocks 40, and the two sides of the positioning block 40 are respectively connected to the web and the limit plate. The positioning rods 20a offset each other, so that the hanging beam 10 is stably fixed on the column 20, and the hanging beam 10 is clamped by the limit block. The positioning and disassembly of the hanging beam 10 are more convenient, which reduces the high-altitude welding workload and improves work efficiency. In this embodiment, the positioning block 40 is made of wood.

请继续参考图4,上述吊杆30包括一根具有外螺纹的螺杆31、分别螺纹连接于螺杆31两端的两个螺母33,以及若干垫片32,利用两端与螺母33螺纹连接的吊杆30固定吊梁10及模板组件50,进而实现屋面板吊模的可拆卸式连接,操作简便,工作效率高,所述垫片32呈U形,螺杆31卡扣于垫片32的槽口内,垫片32的设置能够起到定位螺杆31及加强连接的作用,而且具有U形槽口的垫片32拆卸更加方便,有利于材料反复利用。本实施例中螺杆31采用Φ16高强螺杆31。Please continue to refer to Fig. 4, above-mentioned suspender 30 comprises a screw rod 31 with external thread, two nuts 33 that are threadedly connected to two ends of screw rod 31 respectively, and several washers 32, utilize the suspender that two ends are threadedly connected with nut 33 30 fixes the hanging beam 10 and the formwork assembly 50, and then realizes the detachable connection of the roof panel hanging form, which is easy to operate and high in work efficiency. The gasket 32 is U-shaped, and the screw rod 31 is buckled in the notch of the gasket 32. The setting of the gasket 32 can play the role of positioning the screw rod 31 and strengthening the connection, and the gasket 32 with a U-shaped notch is more convenient to disassemble, which is beneficial to the repeated utilization of materials. In this embodiment, the screw rod 31 adopts a Φ16 high-strength screw rod 31 .

如图2至图4所示,模板组件50由并列设置于底层的若干主龙背51,铺设于主龙骨51上且与主龙骨交错设置的若干次龙骨52,以及水平铺设于次龙骨52上的模板53组成,吊杆30的底端依次贯穿模板53、次龙骨52和主龙骨并由螺母33锁紧固定。纵横交错设置的主龙骨和次龙骨52形成的支撑框架增强了模板组件50的结构强度,在后续浇筑混凝土的施工中,避免模板53发生形变,保证屋面板100的施工质量。本实施例中,主龙骨采用单根8#槽钢制成,即宽度8cm,次龙骨52采用截面尺寸为100mm×100mm的木枋制成,模板53采用18mm厚九夹板制成,当然,也可采用钢模板等其他形式。As shown in Figures 2 to 4, the formwork assembly 50 consists of several main keel backs 51 arranged side by side on the bottom layer, several secondary keels 52 laid on the main keel 51 and interlaced with the main keel, and laid horizontally on the secondary keel 52. formwork 53, the bottom end of the suspender 30 runs through the formwork 53, the secondary keel 52 and the main keel in turn and is locked and fixed by the nut 33. The support frame formed by the criss-cross main keel and the secondary keel 52 enhances the structural strength of the formwork assembly 50 , and prevents the formwork 53 from being deformed during the subsequent concrete pouring construction, ensuring the construction quality of the roof panel 100 . In this embodiment, the main keel is made of a single 8# channel steel, that is, the width is 8cm, the secondary keel 52 is made of a wooden beam with a cross-sectional size of 100mm×100mm, and the formwork 53 is made of 18mm thick nine-plywood. Other forms such as steel formwork can be used.

下面结合图1至图6说明屋面板的施工过程:The construction process of the roof panel is illustrated below in conjunction with Figures 1 to 6:

S1:安装屋面板吊模,将吊梁10架设于主体结构钢梁1上方,模板组件50安装于主体结构钢梁1之间,使模板53上表面与主体结构钢梁1顶端平齐,安装吊杆30,使得吊杆30两端分别贯穿吊梁10及模板组件50并锁紧固定;S1: Install the roof panel hanging formwork, erect the hanging beam 10 above the main structural steel beam 1, install the formwork assembly 50 between the main structural steel beams 1, make the upper surface of the formwork 53 flush with the top of the main structural steel beam 1, and install Suspension rod 30, so that the two ends of the suspension rod 30 respectively pass through the suspension beam 10 and the formwork assembly 50 and are locked and fixed;

S2:浇筑屋面板100混凝土,待混凝土达到设计要求的强度后,拆除屋面板吊模。S2: Pour 100% concrete for the roof slab, and remove the roof slab hanging formwork after the concrete reaches the strength required by the design.

综上,首先,在已有主体结构钢梁1上安装吊梁10,再将模板组件50通过吊杆30悬吊固定于吊梁10,从而实现模板53的固定,最后进行混凝土浇筑施工,与传统高支模施工工艺不同的是,本实用新型的屋面板吊模固定于已有主体结构钢梁1上,避免了人工搭建高支模等高空作业,节约大量材料及人力,施工工期缩减50%以上,而且,屋面板吊模占用施工空间变小,不会阻碍施工现场地面交通,有利于安全、文明施工;因此,该施工方法针对性强、操作性强,具有明显的社会效益和经济效益。To sum up, first, the suspension beam 10 is installed on the existing steel beam 1 of the main structure, and then the formwork assembly 50 is suspended and fixed on the suspension beam 10 through the suspension rod 30, so as to realize the fixation of the formwork 53, and finally the concrete pouring construction is carried out, and the The difference between the traditional high formwork construction technology is that the roof panel hanging formwork of the utility model is fixed on the existing main structural steel beam 1, which avoids high-altitude operations such as manual construction of high formwork, saves a lot of materials and manpower, and shortens the construction period by 50% Moreover, the construction space occupied by the roof slab hanging formwork becomes smaller, which will not hinder the ground traffic on the construction site, and is conducive to safe and civilized construction; therefore, this construction method is highly targeted and operable, and has obvious social and economic benefits. benefit.

上述步骤S1还包括,位于模板53上方的螺杆31上还设有套管60,套管60的长度大于待浇筑屋面板100的厚度,套管60的设置能够避免混凝土与螺杆31外壁发生粘结,便于后续吊杆30拆卸施工。The above step S1 also includes that the screw 31 above the formwork 53 is also provided with a casing 60, the length of the casing 60 is greater than the thickness of the roof panel 100 to be poured, and the setting of the casing 60 can prevent the concrete from sticking to the outer wall of the screw 31 , to facilitate subsequent disassembly and construction of the suspender 30.

更进一步,还包括步骤S3,如图6所示,屋面板吊模拆除后,原吊杆30的位置形成的屋面板100穿孔101底部填充细石混凝土,穿孔101顶部填充发泡剂,穿孔101表面敷设防水层102。发泡剂是一种依靠湿气固化的聚氨酯弹性密封发泡材料,能够将防水层102牢固粘结于穿孔101表面,达到密封防水的目的。Furthermore, step S3 is also included. As shown in FIG. 6, after the roof slab hanging formwork is removed, the bottom of the roof slab 100 perforated 101 formed at the position of the original suspender 30 is filled with fine stone concrete, the top of the perforated 101 is filled with foaming agent, and the perforated 101 is filled with foaming agent. A waterproof layer 102 is laid on the surface. The foaming agent is a polyurethane elastic sealing foam material cured by moisture, which can firmly bond the waterproof layer 102 to the surface of the perforation 101 to achieve the purpose of sealing and waterproofing.

上述描述仅是对本实用新型较佳实施例的描述,并非对本实用新型范围的任何限定,本实用新型领域的普通技术人员根据上述揭示内容做的任何变更、修饰,均属于权利要求范围。The above description is only a description of the preferred embodiments of the present utility model, not any limitation to the scope of the present utility model. Any changes and modifications made by those skilled in the field of the present utility model according to the above disclosed content all belong to the scope of the claims.

Claims (7)

1. a kind of roof boarding hangs mould, which is characterized in that including:
Several hanging beams, the hanging beam are set up on mounted agent structure girder steel;
Template component, the template component are installed between the agent structure girder steel, and the template component upper surface and institute It is concordant to state agent structure girder steel top;
And several sunpenders, the both ends of the sunpender are locked after extending through the hanging beam and the template component.
2. roof boarding hanging mould structure according to claim 1, it is characterised in that:The hanging beam is by two slots being oppositely arranged Steel is made, and the web of two channel steels is mutually close and reservation one can accommodate the perforative gap of the sunpender so that the sunpender Top can pass through the gap and be locked.
3. roof boarding hanging mould structure according to claim 1, it is characterised in that:The bottom of the hanging beam is additionally provided with several vertical Column, the top of the column and the hanging beam are affixed, and the bottom end of the column is fixed in the agent structure girder steel, and described vertical The height of column is more than the thickness of roof boarding to be poured.
4. roof boarding hanging mould structure according to claim 3, it is characterised in that:The both sides of the column have also been respectively and fixedly connected with The bottom end of gag lever post, the gag lever post is located on roof boarding to be poured, the top on the top of the gag lever post and the hanging beam Concordantly.
5. roof boarding hanging mould structure according to claim 4, it is characterised in that:Completely plug is fixed in the notch of the hanging beam both sides Position block, the both sides of the locating piece offset with the web of hanging beam and the gag lever post respectively.
6. roof boarding hanging mould structure according to claim 1, it is characterised in that:The sunpender, which includes one, has external screw thread Screw rod, be threadedly connected to two nuts at the screw rod both ends respectively and several gaskets, the gasket take the shape of the letter U, the spiral shell Bar is snapped in the notch of the gasket.
7. roof boarding hanging mould structure according to claim 1, it is characterised in that:The template component is by being juxtaposed on bottom Several main dragon back ofs the body of layer, several secondary joists for being layed on the main joist and being staggered with the main joist, and be laid with In the template composition on the secondary joist.
CN201721518428.0U 2017-11-15 2017-11-15 A kind of roof boarding hangs mould Expired - Fee Related CN207700680U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721518428.0U CN207700680U (en) 2017-11-15 2017-11-15 A kind of roof boarding hangs mould

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721518428.0U CN207700680U (en) 2017-11-15 2017-11-15 A kind of roof boarding hangs mould

Publications (1)

Publication Number Publication Date
CN207700680U true CN207700680U (en) 2018-08-07

Family

ID=63022522

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721518428.0U Expired - Fee Related CN207700680U (en) 2017-11-15 2017-11-15 A kind of roof boarding hangs mould

Country Status (1)

Country Link
CN (1) CN207700680U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984570A (en) * 2019-12-06 2020-04-10 中冶天工集团有限公司 A kind of kitchen and bathroom anti-sill hanging formwork system support and positioning member and formwork method
CN111502252A (en) * 2019-01-30 2020-08-07 河南天丰绿色装配集团有限公司 Hanging type formwork-supporting-free system for beam system steel structure building floor and construction method
CN111980399A (en) * 2020-07-09 2020-11-24 中国十七冶集团有限公司 The anti-floating device and construction method of the prefabricated building laminated board based on the aluminum formwork system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111502252A (en) * 2019-01-30 2020-08-07 河南天丰绿色装配集团有限公司 Hanging type formwork-supporting-free system for beam system steel structure building floor and construction method
CN110984570A (en) * 2019-12-06 2020-04-10 中冶天工集团有限公司 A kind of kitchen and bathroom anti-sill hanging formwork system support and positioning member and formwork method
CN111980399A (en) * 2020-07-09 2020-11-24 中国十七冶集团有限公司 The anti-floating device and construction method of the prefabricated building laminated board based on the aluminum formwork system

Similar Documents

Publication Publication Date Title
CN205024907U (en) Vary joint construction of wide flange I -beam roof beam of prestressing force hollow floor and edge of a wing
CN102418416B (en) Long-slab-span steel beam cast-in-situ floor formwork system
CN109083275B (en) Prefabricated column and one-piece prefabricated beam-slab assembly node and its construction method
WO2015131792A1 (en) Building structure and construction method for same
CN208122301U (en) A kind of floor support plate supporting apparatus
CN203080911U (en) Inner formwork for concrete walls at deformation joint
CN206428968U (en) A kind of steel bar girder formula is without supporting template system
CN109339323A (en) A kind of assembled integral hollow floor structure system and its construction method
CN107869195A (en) A kind of shaped steel steel column and column cap sizing punching block construction method
CN207700680U (en) A kind of roof boarding hangs mould
CN108086674A (en) A kind of roof boarding hangs the construction method of mould and roof boarding
CN202755649U (en) Rebar mold-supporting frame of cantilever slab
CN207700669U (en) A kind of bracing means of builder's jack and laminated floor slab
CN204356996U (en) The U-shaped beam of prefabricated reinforced concrete with horizontal steel diaphragm
CN104674997A (en) Supporting structure of archaized wood structure building roof and construction method thereof
CN206267309U (en) A kind of assembled steel concrete frame core wall structure system
CN115075613A (en) Fabricated building supporting system and construction method thereof
CN104032855B (en) Assembled cross mixing coupled wall and construction method thereof
CN104797762B (en) Building and construction method thereof
CN107882243B (en) A hollow floor slab of a rectangular concrete-filled steel tubular rib beam structure and its construction method
CN103015713B (en) High-altitude-spanned steel reinforced concrete truss template
CN205134664U (en) A upper and lower double -deck concrete slab structure for girder steel
CN220828037U (en) Truss floor carrier plate supporting structure
CN104032859B (en) Assembled L-shaped mixing coupled wall and construction method thereof
CN202596161U (en) Combined formwork device of HR heavy type gantry and reinforced concrete temporary structural column

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180807