CN207674427U - A kind of coal-burning boiler reducing dust pollution - Google Patents

A kind of coal-burning boiler reducing dust pollution Download PDF

Info

Publication number
CN207674427U
CN207674427U CN201721547779.4U CN201721547779U CN207674427U CN 207674427 U CN207674427 U CN 207674427U CN 201721547779 U CN201721547779 U CN 201721547779U CN 207674427 U CN207674427 U CN 207674427U
Authority
CN
China
Prior art keywords
dust
purification cylinder
dust purification
spray cleaning
discharge bucket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721547779.4U
Other languages
Chinese (zh)
Inventor
王永佳
张庆国
王学同
肖冠华
颜喜
王帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huadian Electric Power Research Institute Co Ltd
Original Assignee
Huadian Electric Power Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huadian Electric Power Research Institute Co Ltd filed Critical Huadian Electric Power Research Institute Co Ltd
Priority to CN201721547779.4U priority Critical patent/CN207674427U/en
Application granted granted Critical
Publication of CN207674427U publication Critical patent/CN207674427U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Gasification And Melting Of Waste (AREA)

Abstract

The utility model discloses a kind of coal-burning boilers reducing dust pollution,Left dust purification cylinder is welded on the left side wall of boiler furnace,Right dust purification cylinder is welded on the right side wall of boiler furnace,Left bank petticoat pipe is mounted on the right side in left dust purification cylinder,Right enclosure is mounted on the left side in right dust purification cylinder,Left spray cleaning pipe is mounted on the top in left dust purification cylinder,Right spray cleaning pipe is mounted on the top in right dust purification cylinder,Left high pressure water tank is mounted on the top on left spray cleaning pipe,Right high pressure water tank is mounted on the top on right spray cleaning pipe,Left dust discharge bucket is welded on the bottom end of left dust purification cylinder,Right dust discharge bucket is welded on the bottom end of right dust purification cylinder,Left dust discharge bucket is arranged in the underface of left spray cleaning pipe,Right dust discharge bucket is arranged in the underface of right spray cleaning pipe,Design is scientific and reasonable for it,It is simple in structure,It is easy to use.

Description

A kind of coal-burning boiler reducing dust pollution
Technical field
The utility model belongs to boiler plant field, especially a kind of coal-burning boiler reducing dust pollution.
Background technology
Coal is the main energy sources in the current available energy form in China, and 70% is accounted in China's primary energy consumption structure Above share, the whole nation are had a large capacity and a wide range at present there are about 540,000 coal-burning boilers, are not only heavy polluter, and are also that energy consumption is big Family, coal-burning boiler have more than 100 years history, and either design or operation all has accumulated the experience of comparative maturity, since the establishment of the nation Coal-burning boiler carried out fin panel casing, adds Secondary Air and the larger improvement several times such as stokehold layering cloth coal, but just design and Improve unhappy in running technology aggregate level, all in all coal-burning boiler overall thermal efficiency in China's is relatively low, and design thermal efficiency exists Between 76-85%, but it is actually general all 60-65% or so, and some is also less than 60%.Practical inadequate, the energy of contributing of boiler Source unnecessary consumption is quite serious.
Currently, there are disadvantages on coal-fired boiler combustion:Fire coal is insufficient in burner hearth internal-combustion, a large amount of suspension combustibles Grain can't burn completely, and volume of smoke exhaust emission, carbon content of cinder is caused to severely exceed.
Utility model content
The utility model proposes a kind of coal-burning boilers reducing dust pollution, utilize left spray cleaning pipe and right spray cleaning Pipe shower water purifies the dust that boiler fired coal is discharged, and by left dust discharge bucket and the discharge bucket discharge of right dust, reaches To the purpose for reducing dust pollution, design is scientific and reasonable, simple in structure, easy to use.
To solve the above-mentioned problems, the utility model proposes a kind of coal-burning boilers reducing dust pollution.
Technical solution used by the utility model is:
A kind of coal-burning boiler reducing dust pollution, including boiler furnace, left dust purification cylinder, left dust discharge bucket, Left bank petticoat pipe, left high pressure water tank, left valve, left bank chimney, fire grate, boiler combustion chamber cap, renovates dress at left spray cleaning pipe It sets, supporting rack, the fire grate is connect with the bottom in boiler combustion room, and boiler combustion chamber cap is connect with flip cover assembly, renovates dress It sets and is connect at the top of boiler furnace, boiler combustion chamber cap coordinates with boiler furnace, the side wall of supporting rack and boiler furnace Lower part is fixedly connected, and left dust purification cylinder is fixedly connected with boiler furnace side wall upper part, and left dust purification cylinder is provided with out Mouth and under shed, left bank petticoat pipe, left spray cleaning pipe, left dust discharge bucket are positioned at the inside of left dust purification cylinder, left bank petticoat pipe It connect with the inner wall of left dust purification cylinder lower opening, is connect at the top of left spray cleaning pipe and the inner wall of left dust purification cylinder, it is left High pressure water tank is located at the outside of left dust purification cylinder and is connect with the top of left spray cleaning pipe, left high pressure water tank setting There are left valve, left dust discharge bucket to be connect with the bottom end of left dust purification cylinder, left bank chimney and the company of opening on left dust purification cylinder It connects.Using left spray cleaning pipe shower water, the dust that boiler fired coal is discharged is purified, and bucket row is discharged by left dust Go out, achievees the purpose that reduce dust pollution;Left bank petticoat pipe avoids high pressure water flow into combustor from influencing for water conservancy diversion and aggregation flue gas Burning, while coordinating left dust to exclude bucket and using, facilitate high pressure water and dust to exclude.
Further, further include right dust purification cylinder, right dust discharge bucket, right enclosure, right spray cleaning pipe, right high pressure Water tank, right valve, right smoke exhaust barrel, the right dust purification cylinder are fixedly connected with boiler furnace side wall upper part, and right dust is net Change cylinder and be provided with opening and under shed, right enclosure, right spray cleaning pipe, right dust discharge bucket are positioned at right dust purification cylinder Inside, right enclosure are connect with the inner wall of right dust purification cylinder lower opening, and right spray cleaning pipe is interior with right dust purification cylinder Connection, right high pressure water tank are located at the outside of right dust purification cylinder and are connect with the top of right spray cleaning pipe at the top of wall, right High pressure water tank is provided with right valve, and right dust discharge bucket is connect with the bottom end of right dust purification cylinder, right smoke exhaust barrel and right dust Be open connection on purifying tube.It can simultaneously be used with side also both sides when normal use, when unilateral side can not come into operation or unilateral high pressure When water tank moisturizing, the other side of coming into operation.Avoid the unilateral side processing dust ability when exhaust gas volumn is larger that emission request is not achieved simultaneously.
Preferably, the left dust discharge bucket is located at right spray positioned at the underface of left spray cleaning pipe, right dust discharge bucket The underface of leaching purification pipe.Dust discharge bucket is located at immediately below spray cleaning pipe, after ensureing that flow can be sprayed by spray cleaning pipe Bucket outflow directly is discharged from dust, it will not be in dust purification cylinder inner product stream.
Preferably, the left dust discharge bucket, right dust discharge bucket are funnel-form wide at the top and narrow at the bottom, and left dust is arranged Go out bucket, the wide opening of right dust discharge bucket is connect with left and right dust purification cylinder respectively.The upper wide opening of funnel-form dust discharge bucket can protect It demonstrate,proves the flow sprayed out to fully enter in dust discharge bucket, bucket discharge is discharged by dust.
Preferably, the left bank petticoat pipe, right enclosure are funnel-form wide at the top and narrow at the bottom, and left bank petticoat pipe, right smoke evacuation The wide opening of cover is connect with left and right dust purification cylinder respectively.Funnelform enclosure flue gas by when, because of inlet and outlet Cross-sectional area is different, leads to the pressure change of air-flow, can better water conservancy diversion and aggregation flue gas.
Further, the left and right dust purification cylinder installation site is among boiler furnace and boiler combustion chamber cap Position.The flue gas generated burn since the small automatic rising of temperature high density flows to dust purification cylinder, simultaneously because dust purification Cylinder is higher than combustion chamber to avoid unburned coal from entering dust purification cylinder.
Preferably, the left and right dust purification cylinder and combustion chamber internal diameter ratio are 1:2.Ensure flue gas flow rate and combustion chamber Interior flow velocity is identical, avoids the too fast influence dust removing effects of flow velocity.
Preferably, the left and right dust purification cylinder is stainless steel cylinder.Due to persistently spraying water in dust purification cylinder, and cigarette Temperature is higher, and dust purification cylinder material is avoided that corrosion using stainless steel, extends purifying tube usage time.
Preferably, the left high pressure water tank is connected through a screw thread with left dust purification cylinder, right high pressure water tank and right powder Dirt purifying tube is connected through a screw thread.It is convenient for changing when water consume is most in high pressure water tank.
The utility model compared with the existing technology has the following advantages and effect:
1, the utility model respectively enters left and right sides dust purification cylinder using the flue gas after boiler combustion, by high pressure water It is discharged from smoke exhaust barrel after spray, bucket discharge is excluded from dust entrainment of the high pressure water of dust.Boiler coal adds right over boiler Enter, opens boiler combustion chamber cap.
2, two identical dust-extraction units of the utility model left and right settings, when normal use, can be with sides also both sides simultaneously With, when unilateral side can not come into operation or when high pressure water tank moisturizing, the other side of coming into operation.It avoids simultaneously when exhaust gas volumn is larger at unilateral side Emission request is not achieved in reason dust ability.
3, the utility model smoke exhaust barrel can process different shape and length according to live physical length and route.
4, the utility model installation operation is simple, by enclosure realize water conservancy diversion and aggregation flue gas, avoid high pressure water flow into Combustion chamber influences burning, while coordinating dust to exclude bucket and using, and high pressure water and dust is facilitated to exclude.
Description of the drawings
The attached drawing constituted part of this application is used to provide a further understanding of the present invention, the utility model Illustrative embodiments and their description are not constituted improper limits to the present invention for explaining the utility model.
Fig. 1 is the structural schematic diagram of the utility model.
Label declaration:
Boiler furnace 1;Left dust purification cylinder 2;Right dust purification cylinder 3;Left dust discharge bucket 4;
Right dust discharge bucket 5;Left bank petticoat pipe 6;Right enclosure 7;Left spray cleaning pipe 8;
Right spray cleaning pipe 9;Left high pressure water tank 10;Right high pressure water tank 11;Left valve 12;
Right valve 13;Left bank chimney 14;Right smoke exhaust barrel 15;Fire grate 16;Left pillar 17;
Boiler combustion chamber cap 18;Moveable hinge 19;Left support frame 20;Right support frame 21.
Specific implementation mode
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and implementation Example, the present invention will be further described in detail.It should be appreciated that specific embodiment described herein is only explaining this Utility model is not used to limit the utility model.
Embodiment 1:
As shown in Figure 1, a kind of coal-burning boiler reducing dust pollution, including boiler furnace 1, left dust purification cylinder 2, the right side Dust purification cylinder 3, left dust discharge bucket 4, right dust discharge bucket 5, left bank petticoat pipe 6, right enclosure 7, left spray cleaning pipe 8, the right side Spray cleaning pipe 9, left high pressure water tank 10, right high pressure water tank 11, left valve 12, right valve 13, left bank chimney 14, right smoke evacuation Cylinder 15, fire grate 16, left pillar 17, boiler combustion chamber cap 18, moveable hinge 19, left support frame 20, right support frame 21, left dust purification Cylinder 2 is welded on the left side wall of boiler furnace 1, and right dust purification cylinder 3 is welded on the right side wall of boiler furnace 1, left bank Petticoat pipe 6 is mounted on the right side in left dust purification cylinder 2, and right enclosure 7 is mounted on the left side in right dust purification cylinder 3, left spray The top that pipe 8 is mounted in left dust purification cylinder 2 is purified, right spray cleaning pipe 9 is mounted on the top in right dust purification cylinder 3, Left high pressure water tank 10 is mounted on the top on left spray cleaning pipe 8, and right high pressure water tank 11 is mounted on right spray cleaning pipe 9 Top, left dust discharge bucket 4 is welded on the bottom end of left dust purification cylinder 2, and right dust discharge bucket 5 is welded on right dust purification cylinder 3 bottom end, left dust discharge bucket 4 are arranged in the underface of left spray cleaning pipe 8, and right 5 setting of dust discharge bucket is net in right spray Change the underface of pipe 9, left bank chimney 14 is welded on the top on left dust purification cylinder 2, and it is net that right smoke exhaust barrel 15 is welded on right dust Change the top on cylinder 3, left valve 12 is mounted on the bottom end of left high pressure water tank 10, and right valve 13 is mounted on right high pressure water tank 11 Bottom end, left pillar 17 is welded on the top of 1 left side wall of boiler furnace, and boiler combustion chamber cap 18 is mounted on by moveable hinge 19 On left pillar 17, the fire grate 16 is welded on the bottom end in boiler furnace 1, and left support frame 20 is welded on boiler furnace 1 Left side wall on, right support frame 21 is welded on the right side wall of boiler furnace 1, left spray cleaning pipe 8, right spray cleaning pipe 9 Using daily spray head.
In use, the flue gas after boiler combustion respectively enters left dust purification cylinder 2, right dust purification cylinder 3, pass through left valve 12, right valve 13 controls the work of left high pressure water tank 10, right high pressure water tank 11, left high pressure water tank 10, right high pressure water storage Shower water is stored in tank 11, opens left valve 12, right valve 13, high pressure water is by left spray cleaning pipe 8, right spray cleaning pipe 9 Spray flue gas, flue gas after high pressure water sprays from left bank chimney 14, right smoke exhaust barrel 15 be discharged, entrainment of dust high pressure water from Left dust discharge bucket 4,5 discharge of right dust discharge bucket.Boiler coal is added right over boiler furnace 1, opens boiler combustion Chamber cap 18.
Embodiment 2:
The present embodiment is substantially the same manner as Example 1, and distinctive points are:In embodiment 2, left dust discharge bucket 4, right dust row It is funnel-form wide at the top and narrow at the bottom to go out bucket 5, and left bank petticoat pipe 6, right enclosure 7 are funnel-form wide at the top and narrow at the bottom.
Embodiment 3:
The present embodiment is substantially the same manner as Example 1, and distinctive points are:In embodiment 3, the left dust purification cylinder 2 and the right side 3 structure of dust purification cylinder is identical, and left and right dust purification cylinder and 1 internal diameter ratio of boiler furnace are 1:2.
Embodiment 4:
The present embodiment is substantially the same manner as Example 3, and distinctive points are:In embodiment 4, the left dust purification cylinder 2 and the right side Dust purification cylinder 3 is stainless steel cylinder.
Embodiment 5:
The present embodiment is substantially the same manner as Example 1, and distinctive points are:In embodiment 5, the left high pressure water tank 10 and a left side Dust purification cylinder 2 is connected through a screw thread, and right high pressure water tank 11 is connected through a screw thread with right dust purification cylinder 3.
The above is only the preferred embodiment of the present invention, is not intended to limit the utility model, all in this practicality Within novel spirit and principle, any modification, equivalent replacement, improvement and so on should be included in the guarantor of the utility model Within the scope of shield.

Claims (9)

1. a kind of coal-burning boiler reducing dust pollution, which is characterized in that including boiler furnace, left dust purification cylinder, Zuo Fen Bucket, left bank petticoat pipe, left spray cleaning pipe, left high pressure water tank, left valve, left bank chimney, fire grate, boiler furnace is discharged in dirt Lid, flip cover assembly, supporting rack, the fire grate are connect with the bottom in boiler combustion room, and boiler combustion chamber cap connects with flip cover assembly It connects, is connect at the top of flip cover assembly and boiler furnace, boiler combustion chamber cap coordinates with boiler furnace, supporting rack and boiler combustion The lower sidewall of room is fixedly connected, and left dust purification cylinder is fixedly connected with boiler furnace side wall upper part, and left dust purification cylinder is set It is equipped with opening and under shed, left bank petticoat pipe, left spray cleaning pipe, left dust discharge bucket are located at the inside of left dust purification cylinder, Left bank petticoat pipe is connect with the inner wall of left dust purification cylinder lower opening, the inner wall top of left spray cleaning pipe and left dust purification cylinder Connection, left high pressure water tank are located at the outside of left dust purification cylinder and are connect with the top of left spray cleaning pipe, left high pressure storage Water pot is provided with left valve, and left dust discharge bucket is connect with the bottom end of left dust purification cylinder, left bank chimney and left dust purification cylinder Upper opening connection.
2. the coal-burning boiler according to claim 1 for reducing dust pollution, which is characterized in that further include right dust purification Cylinder, right dust discharge bucket, right enclosure, right spray cleaning pipe, right high pressure water tank, right valve, right smoke exhaust barrel, the right dust Purifying tube is fixedly connected with boiler furnace side wall upper part, and right dust purification cylinder is provided with opening and under shed, right enclosure, Right spray cleaning pipe, right dust discharge bucket are positioned at the inside of right dust purification cylinder, right enclosure and right dust purification cylinder under shed The inner wall at place connects, and is connect at the top of right spray cleaning pipe and the inner wall of right dust purification cylinder, right high pressure water tank is located at right dust It the outside of purifying tube and is connect with the top of right spray cleaning pipe, right high pressure water tank is provided with right valve, right dust discharge Bucket is connect with the bottom end of right dust purification cylinder, right smoke exhaust barrel and the connection that is open on right dust purification cylinder.
3. the coal-burning boiler according to claim 2 for reducing dust pollution, which is characterized in that the left dust discharge bucket position In the underface of left spray cleaning pipe, right dust discharge bucket is positioned at the underface of right spray cleaning pipe.
4. the coal-burning boiler according to claim 3 for reducing dust pollution, which is characterized in that the left dust discharge bucket, Right dust discharge bucket is funnel-form wide at the top and narrow at the bottom, and the wide opening of left dust discharge bucket, right dust discharge bucket respectively with it is left, Right dust purification cylinder connection.
5. the coal-burning boiler according to claim 3 for reducing dust pollution, which is characterized in that the left bank petticoat pipe, right row Petticoat pipe is funnel-form wide at the top and narrow at the bottom, and the wide opening of left bank petticoat pipe, right enclosure connects with left and right dust purification cylinder respectively It connects.
6. the coal-burning boiler according to claim 2 for reducing dust pollution, which is characterized in that the left and right dust purification Cylinder installation site is in boiler furnace and boiler combustion chamber cap centre position.
7. the coal-burning boiler according to claim 6 for reducing dust pollution, which is characterized in that the left and right dust purification Cylinder and boiler furnace internal diameter ratio are 1:2.
8. the coal-burning boiler according to claim 7 for reducing dust pollution, which is characterized in that the left and right dust purification Cylinder is stainless steel cylinder.
9. it is according to claim 2 reduce dust pollution coal-burning boiler, which is characterized in that the left high pressure water tank with Left dust purification cylinder is connected through a screw thread, and right high pressure water tank is connected through a screw thread with right dust purification cylinder.
CN201721547779.4U 2017-11-17 2017-11-17 A kind of coal-burning boiler reducing dust pollution Active CN207674427U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721547779.4U CN207674427U (en) 2017-11-17 2017-11-17 A kind of coal-burning boiler reducing dust pollution

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721547779.4U CN207674427U (en) 2017-11-17 2017-11-17 A kind of coal-burning boiler reducing dust pollution

Publications (1)

Publication Number Publication Date
CN207674427U true CN207674427U (en) 2018-07-31

Family

ID=62964401

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721547779.4U Active CN207674427U (en) 2017-11-17 2017-11-17 A kind of coal-burning boiler reducing dust pollution

Country Status (1)

Country Link
CN (1) CN207674427U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859987A (en) * 2017-11-17 2018-03-30 华电电力科学研究院 Reduce the coal-burning boiler of dust pollution

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859987A (en) * 2017-11-17 2018-03-30 华电电力科学研究院 Reduce the coal-burning boiler of dust pollution

Similar Documents

Publication Publication Date Title
CN105276587B (en) A kind of garbage burning processing method
CN207674427U (en) A kind of coal-burning boiler reducing dust pollution
CN208269175U (en) A kind of Environment protection chimney with filtering function
CN107367059A (en) A kind of energy-saving, environmental protection boiler
CN201983274U (en) Smoke treatment device of garbage incinerator
CN201637284U (en) Tunnel kiln smoke gas heat exchange dust removal and exhaust reduction device
CN204648206U (en) Horizontal double-deck water pipe furnace grate many backhauls water bath dust-removing flashback coal burning boiler
CN107859987A (en) Reduce the coal-burning boiler of dust pollution
CN103063040A (en) Automatic control electric furnace flue gas combustion settling chamber
CN207621994U (en) A kind of energy-saving boiler
CN207438613U (en) Biomass semi-gasification burner
CN201342305Y (en) Powerful atomizing treatment equipment for boiler smoke desulphurization
CN106949485A (en) A kind of environmental protection and energy saving incinerator
CN203777817U (en) Hot-air dust removing device for denitration
CN208170419U (en) A kind of gas-fired Boiler System
CN106122947B (en) A kind of pulverized-coal fired boiler soot blower system
CN205664389U (en) Novel incineration boiler is recycled to rubbish
CN201718444U (en) Heat exchanger of tobacco curing furnace
CN206817496U (en) A kind of leakproof cigarette device
CN206145665U (en) Pulverized coal boiler soot blower system
CN204648659U (en) A kind of energy-saving, environmental protection boiler system
CN201225657Y (en) Stalk gasification stove with rotating fire grate
CN204693511U (en) A kind of energy-saving high-efficiency environment-friendly type air return stove
CN202884908U (en) Combustion chamber of biomass boiler
CN209386340U (en) A kind of combustion furnace with purification gas function

Legal Events

Date Code Title Description
GR01 Patent grant