CN207672673U - A kind of interim fire water box of entirety container-type building - Google Patents

A kind of interim fire water box of entirety container-type building Download PDF

Info

Publication number
CN207672673U
CN207672673U CN201721701024.5U CN201721701024U CN207672673U CN 207672673 U CN207672673 U CN 207672673U CN 201721701024 U CN201721701024 U CN 201721701024U CN 207672673 U CN207672673 U CN 207672673U
Authority
CN
China
Prior art keywords
water
box
fire
container
container body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721701024.5U
Other languages
Chinese (zh)
Inventor
盛景
马亮
马方
马一方
白珂
王聪聪
陈斌
俞能文
蒋德标
金磊
程瑶
樊星
陆伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd, Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN201721701024.5U priority Critical patent/CN207672673U/en
Application granted granted Critical
Publication of CN207672673U publication Critical patent/CN207672673U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Fire-Extinguishing By Fire Departments, And Fire-Extinguishing Equipment And Control Thereof (AREA)

Abstract

The utility model discloses a kind of interim fire water box of whole container-type building, includes the container body of rectangular shape;The automatic water compensating valve being connected with babinet water inlet is equipped in the container body;The automatic water compensating valve is ball-cock assembly;The ball-cock assembly includes the connecting rod and the valve for being connected to the connecting rod other end that the hollow floating ball swum on the water surface, one end are interspersed in floating ball;The container body upper end is equipped with gap, and middle part is exported equipped with construction water, and lower end is equipped with fire demand water outlet and discharge opening.The utility model makes fire water box really realize that water level automatically controls, and avoids fire water box water shortage, spilling water, reduces the generation of accident beyond control, and the scene of not needing is assembled, and greatly facilitates construction site installation personnel, reduces process time.

Description

A kind of interim fire water box of entirety container-type building
Technical field
The utility model belongs to construction site fire-fighting domain, specifically a kind of to be transformed to be formed using container Can integral installation, can have enough to meet the need, automate interim use fire water box.
Background technology
In the construction of work China Democratic National Construction Association and other building trades, scene is both needed to be equipped with interim fire fighting water system, ensures fire water It covers in entire construction site, especially high-building construction, needs to be equipped with fire water box, to ensure that fire water can cover institute Have in floor.
The interim fire water box in construction site is typically to use steel plate integral solder molding at the scene by welder at present.It is this Fire water box long processing time.Process takes up a large area.The fire water box of steel plate welding is internal in use can not Disconnected corrosion, seriously affects and is used in turn the service life.Setting concrete foundation is also needed under fire water box after the completion of welding.Steel plate welds The steel plate of the fire water box connect needs high capacity waggon to be transported, and site welding processing and transhipment are also required for crane to coordinate, non- It is often inconvenient.
Utility model content
The purpose of this utility model is to provide a kind of whole container-types to build interim fire water box, to solve existing disappear The technical issues of water level control that caisson is not available for, and solve dismounting construction it is cumbersome, easy-to-rust destroy and service life it is short The problem of.
The purpose of this utility model can be achieved through the following technical solutions:
A kind of interim fire water box of entirety container-type building, includes the container body of rectangular shape;The container The automatic water compensating valve being connected with babinet water inlet is equipped in babinet;The automatic water compensating valve is ball-cock assembly;The ball-cock assembly includes Connecting rod that the hollow floating ball that swims on the water surface, one end are interspersed in floating ball and the valve for being connected to the connecting rod other end;Institute It states container body upper end and is equipped with gap, middle part is exported equipped with construction water, and lower end is equipped with fire demand water outlet and discharge opening.
The installation position of the inlet and outlet pipes of the container body is according to water source spare interface position and water pump installation site It determines, requirement for height is specifically set:Fire demand water outlet is close to bottom of box position, and construction water outlet is close to top of the box three The position of/mono- position, gap and discharge opening is according to pump house gutter location determination, and automatic water compensating valve setting is convenient for sight Examine position.
The container body upper end is uniformly welded with four U-shaped suspension hooks;Container body outer surface is equipped with anti-decaying paint Layer.
The beneficial effects of the utility model:
1, the utility model makes fire water box really realize that water level automatically controls, and avoids fire water box water shortage, spilling water, reduces The generation of accident beyond control.
2, the fire water box of the utility model is made of container, and the scene of not needing is assembled, and greatly facilitates construction In-site installation personnel, reduce process time.In addition, the utility model fire water box need not build on the basis of, so not Interim casting concrete basis is needed, as long as being placed on by the smooth construction site in the place of production.Due to the utility model fire-fighting Water tank does not need scene for monoblock type container and is assembled, and more traditional fire water box is compared to that need not weld, so existing Field does not have to get angry, and reduces fire hazard.
3, the utility model entirety container-type fire water box is only needed by Freight Transport, crane lifting when transporting installation Crane once can installation is complete, greatly save human and material resources, financial resources, to reach human and material resources, financial resource saving The purpose not wasted.
4, anti-decaying paint is used outside the container body that the utility model uses, improves rust resistance, and in fire water box Portion's reinforcing member ties up zinc-plated ironware with connector office, there is extraordinary anticorrosion effect.
5, the utility model is assembled without dismantling, and artificial, machinery expenses consumption is saved, further, it is also possible to be had enough to meet the need It uses, it is cheaper compared with conventional steel plates welding fire water box expense after expense amortization.
The utility model can be widely applied in fire-fighting system.
Description of the drawings
In order to facilitate the understanding of those skilled in the art, the utility model will be further described below with reference to the accompanying drawings.
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the positive schematic view of facade structure of whole container-type;
Fig. 3 is the side elevation structural schematic diagram of whole container-type;
Reference numeral:1- container bodies, 2- automatic water compensating valves, 3- gaps, the outlet of 4- construction waters, 5- fire demand waters Outlet, 6- discharge openings.
Specific implementation mode
Referring to shown in Fig. 1-3, a kind of interim fire water box of entirety container-type building includes the container case of rectangular shape Body 1;The automatic water compensating valve 2 being connected with babinet water inlet is equipped in the container body 1;The automatic water compensating valve 2 is floating ball Valve, specification DN80 are that DN100 × DN80 reducer pipes are connect with DN100 main feed water pipes road by specification;The ball-cock assembly includes Connecting rod that the hollow floating ball that swims on the water surface, one end are interspersed in floating ball and the valve for being connected to the connecting rod other end;Institute It states 1 upper end of container body and is equipped with gap 3, middle part is equipped with construction water and exports 4, and lower end is equipped with fire demand water outlet 5 and lets out The mouth of a river 6.
The installation position of the inlet and outlet pipes of the container body 1 is according to water source spare interface position and water pump installation site It determines, requirement for height is specifically set:Fire demand water outlet 5 is close to bottom of box position, and construction water outlet 4 is close to top of the box The position of one third position, gap 3 and discharge opening 6 is arranged just according to pump house gutter location determination, automatic water compensating valve In look-out station.
When water level is low in babinet, floating ball is reduced with water level, in valve body of the connecting rod with movable valve by fixed floating ball Piston pulls outward, and makes to generate air between valve body and piston, tap water can be made to enter babinet;When water level reaches setting in babinet Height and position when, floating ball with water level rise caused by power the piston in valve body is pushed away in valve body by connecting rod, due to work The top of plug is equipped with caulking gum washer, and the water outlet in valve body is processed more smooth, smooth again, when the buoyancy of floating ball is super When crossing tap water pressure, water outlet in the piston and valve body of caulking gum washer is installed by top tight sealing, tap water is also It is closed by ball-cock assembly.
1 upper end of the container body is uniformly welded with four U-shaped suspension hooks, and whole container-type fire water box is by lorry Transport, crane lifting, transport install when only need crane once can installation is complete, greatly save human and material resources, financial resources, To achieve the purpose that human and material resources, financial resource saving do not waste.
1 outer surface of container body of use is equipped with anti-corrosion enamelled coating, improves rust resistance, and fire water box internal reinforcement Part ties up zinc-plated ironware with connector office, there is extraordinary anticorrosion effect.
According to the mating installation water inlet pipe of the use function of fire water box, outlet pipe, permeability cell, overflow pipe, tapping pipe, interior people The accessories such as terraced, outer helper, water-level gauge and electric signal pipe.
Above content is only to the utility model structure example and explanation, the technology people of affiliated the art Member makes various modifications or additions to the described embodiments or substitutes by a similar method, without departing from reality With novel structure or beyond the scope defined by this claim, all should belong to the protection range of the utility model.

Claims (3)

1. a kind of entirety container-type builds interim fire water box, which is characterized in that the container body including rectangular shape (1);The automatic water compensating valve (2) being connected with babinet water inlet is equipped in the container body (1);The automatic water compensating valve (2) For ball-cock assembly;The ball-cock assembly includes connecting rod and the company that the hollow floating ball swum on the water surface, one end are interspersed in floating ball It is connected on the valve of the connecting rod other end;Container body (1) upper end is equipped with gap (3), and middle part is exported equipped with construction water (4), lower end is equipped with fire demand water outlet (5) and discharge opening (6).
2. a kind of whole container-type according to claim 1 builds interim fire water box, which is characterized in that the packaging The installation position of the inlet and outlet pipes of box body (1) is determined according to water source spare interface position and water pump installation site, is specifically set Set requirement for height:Fire demand water exports (5) close to bottom of box position, and construction water exports (4) close to top of the box one third The position of position, gap (3) and discharge opening (6) is according to pump house gutter location determination, and automatic water compensating valve setting is convenient for sight Examine position.
3. a kind of whole container-type according to claim 1 builds interim fire water box, which is characterized in that the packaging Box body (1) upper end is uniformly welded with four U-shaped suspension hooks;Container body (1) outer surface is equipped with anti-corrosion enamelled coating.
CN201721701024.5U 2017-12-08 2017-12-08 A kind of interim fire water box of entirety container-type building Expired - Fee Related CN207672673U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721701024.5U CN207672673U (en) 2017-12-08 2017-12-08 A kind of interim fire water box of entirety container-type building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721701024.5U CN207672673U (en) 2017-12-08 2017-12-08 A kind of interim fire water box of entirety container-type building

Publications (1)

Publication Number Publication Date
CN207672673U true CN207672673U (en) 2018-07-31

Family

ID=62968034

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721701024.5U Expired - Fee Related CN207672673U (en) 2017-12-08 2017-12-08 A kind of interim fire water box of entirety container-type building

Country Status (1)

Country Link
CN (1) CN207672673U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110639147A (en) * 2019-11-12 2020-01-03 国网湖南省电力有限公司 Power transmission line forest fire aviation fire extinguishing device
CN111330201A (en) * 2018-12-18 2020-06-26 林城宇 Temporary fire-fighting water system for construction site

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111330201A (en) * 2018-12-18 2020-06-26 林城宇 Temporary fire-fighting water system for construction site
CN110639147A (en) * 2019-11-12 2020-01-03 国网湖南省电力有限公司 Power transmission line forest fire aviation fire extinguishing device

Similar Documents

Publication Publication Date Title
CN103523411B (en) Horizontal buried oil storage tank and installation and construction method of matched device pipeline thereof
CN207672673U (en) A kind of interim fire water box of entirety container-type building
CN202213886U (en) A large metal container
CN200974984Y (en) Self-floating type PE pipeline for dredge
CN216405651U (en) Prefabricated assembled concrete drainage inspection shaft structure
CN207498991U (en) A kind of exhaust valve pit
CN2937361Y (en) Oil storage depot
CN206973112U (en) A kind of steel pipe pole spacer flanger junction waterproof treatment structure
CN206220178U (en) Can have enough to meet need interim fire water tank of pin-connected panel building
CN204004929U (en) A kind of flanged pipe cuff structure connecting for corrugated steel culvert
CN208686105U (en) A kind of device controlling framework lower end filling concrete height
CN215565830U (en) Dewatering well shut-in structure
CN207609165U (en) A kind of piping lane hanging ring template
CN221142982U (en) Soy sauce flavor type white spirit bottom pot water inspection well
CN204690934U (en) Pump house discharge pressure well
CN219140040U (en) Vertical jacking steel pipe joint
CN221142981U (en) Maotai-flavor liquor pit bottom water inspection pit
CN213542092U (en) Liquid level adjustable balance pipeline and slurry circulation tank with same
CN213417864U (en) Foundation pit dewatering system without secondary well sealing
CN211949251U (en) Connecting structure of roof floor slab and air pipe
CN211344344U (en) Building water supply and drainage pipe connecting device
CN217439066U (en) Integrated fire pump room
CN209494131U (en) Restressed beam slab anchor ring pressure maintaining closure assembly
CN202081499U (en) Plastic inspection well with steel skeleton
CN220078732U (en) Fast-assembling formula magnetism coagulating sedimentation tank body

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180731

Termination date: 20191208