CN207671255U - Double end jacking travelling device - Google Patents

Double end jacking travelling device Download PDF

Info

Publication number
CN207671255U
CN207671255U CN201721730450.1U CN201721730450U CN207671255U CN 207671255 U CN207671255 U CN 207671255U CN 201721730450 U CN201721730450 U CN 201721730450U CN 207671255 U CN207671255 U CN 207671255U
Authority
CN
China
Prior art keywords
crane
rack
production line
transition axis
jacking
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721730450.1U
Other languages
Chinese (zh)
Inventor
胡云高
林伟通
童敏
贾开奇
吕金
曹品
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Wei Gen Five Yang Intelligent Equipment Co Ltd
Shenzhen Weichuang Automation Equipment Co Ltd
Guangdong Weichuang Wuyang Intelligent Equipment Co Ltd
Original Assignee
Guangdong Wei Gen Five Yang Intelligent Equipment Co Ltd
Shenzhen Weichuang Automation Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Wei Gen Five Yang Intelligent Equipment Co Ltd, Shenzhen Weichuang Automation Equipment Co Ltd filed Critical Guangdong Wei Gen Five Yang Intelligent Equipment Co Ltd
Priority to CN201721730450.1U priority Critical patent/CN207671255U/en
Application granted granted Critical
Publication of CN207671255U publication Critical patent/CN207671255U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Carriers, Traveling Bodies, And Overhead Traveling Cranes (AREA)

Abstract

It the utility model discloses a kind of double end jacking travelling device, is set between two production lines side by side, including rack, transition axis, the first crane, the second crane, lifting body, migrates pipeline and driving motor.Transition axis is arranged loaded on rack and along the length direction of production line;Loaded on transition axis, the second end of the first crane is horizontally placed in a production line first end of first crane;Loaded on transition axis, the second end of the second crane is horizontally placed in another production line the first end of second crane;Lifting body is loaded between the first crane and rack and between the second crane and rack respectively, and lifting body drives the first crane and the second crane to protrude production line along rack upper and lower directions or be recessed in production line;It migrates pipeline to be respectively arranged on the first crane and the second crane, it is staggered with production line to migrate pipeline;Driving motor, which is installed on rack and drives, migrates pipeline conveying workpieces.The utility model can save the time and improve production efficiency.

Description

Double end jacking travelling device
Technical field
The utility model is related to a kind of double end jacking travelling device more particularly to a kind of being adapted to the production line to be sought quickness of beat On double end jacking travelling device.
Background technology
With the development of society, the household appliances such as the raising that people require quality of life, air-conditioning and water heater are gradually It spreads in our daily life, becomes aily life necessitys.
Demand with people to quality of life makes the raising of production efficiency become the direction that entire society makes great efforts.Wherein, It is the common way of household appliances using two production lines being arranged side by side.By the use side by side of two production lines, can greatly carry High efficiency reduces the production cost of enterprise, and therefore, two production lines side by side is very favored by enterprise.
Wherein, needs are flowed in order to meet workpiece between different production lines, need to be often equipped between two production lines side by side Carryover apparatus is jacked, by jacking carryover apparatus, the workpiece on a production line first to be jacked up, then makes workpiece toward another production It conveys at line, will finally be dropped at another production line toward the workpiece of conveying at another production line again.
But in existing jacking carryover apparatus, when the workpiece between realizing two side-by-side production lines conveys, at this time Two production lines side by side will break-off so that the beat of production line is slower, production efficiency is relatively low, so that existing Jacking carryover apparatus can not adapt to the production line occasion for being produced in beat.
Therefore, be badly in need of want a kind of double end jacking travelling device, be adapted to the production line occasion of productive temp, with save the time and Improve production efficiency.
Utility model content
The purpose of this utility model is to provide a kind of double end jacking travelling devices, are adapted to the production field of line of productive temp It closes, to save the time and improve production efficiency.
To achieve the goals above, the double end jacking travelling device of the utility model is set between two production lines side by side, packet Including rack, transition axis, the first crane, the second crane, lifting body and migrate pipeline.The transition axis is installed on described Rack is simultaneously arranged along the length direction of the production line;The first end of first crane is installed on the transition axis, institute The second end for stating the first crane is horizontally placed in a production line;The first end of second crane is installed on the transition axis On, the second end of second crane is horizontally placed in another production line;The lifting body is respectively arranged in described first liter It drops between frame and rack and between second crane and rack, the lifting body drives first crane and second Crane protrudes production line along the rack upper and lower directions or is recessed in production line;It is described migrate pipeline be respectively arranged in it is described On first crane and the second crane, described to migrate pipeline staggered with production line;The driving motor is installed on described Rack simultaneously drives and described migrates pipeline conveying workpieces.
Preferably, the pipeline that migrates includes the installation axle parallel with the transition axis, is respectively correspondingly installed on institute State the transportation sprocket in installation axle and transition axis and the carrier chain on the transportation sprocket and transition axis that are set around in the installation axle Conveyor chain on wheel.
Preferably, the transportation sprocket is duplex chain wheel, the conveyor chain is double strand chain.
Preferably, the lifting body include jacking cylinder, the support base that is connect with the output end of the jacking cylinder and The jacking head being installed on the support base.
Preferably, the jacking head is installed on the support base in sustained height respectively along the axial direction of the transition axis On both ends.
Preferably, the output end of the jacking cylinder is upwardly disposed, liter is installed between the support base and the rack Guide rail group drops.
Preferably, the riser guide group includes the guide rod being installed on the support base and is installed in the rack Guide bearing, the guide rod are placed through in the guide bearing.
Preferably, the jacking head and guide bearing are respectively flanged (FLGD) linear bearing.
Preferably, being equipped with chain-drive mechanism between the driving motor and the transition axis.
Preferably, the chain-drive mechanism drives sprocket wheel, driven sprocket wheel and the winding being installed on the transition axis comprising main In the main drive chain driven on sprocket wheel and driven sprocket wheel.
Compared with prior art, since the double end jacking travelling device of the utility model is set between two production lines side by side simultaneously Including rack, transition axis, the first crane, the second crane, lifting body and pipeline is migrated, transition axis is installed on rack simultaneously Length direction along production line arranges that the first end of the first crane is installed on transition axis, and the second end of the first crane is horizontal It is placed in a production line, the first end of the second crane is installed on transition axis, and the second end of the second crane is horizontally placed on another In production line, lifting body is respectively arranged between the first crane and rack and between the second crane and rack so that the One crane and the second crane are lifted around transition axis with respect to production line each independently, so that two production lines side by side is not Need at the same break-off, i.e. one pause and another one works on so that the utility model double end jacking migrate Machine is adapted to the fast production line occasion of beat, to save the time and improve production efficiency;Simultaneously as the first crane and second The power for migrating pipeline on crane is simultaneously from driving motor, is driven by same driving motor, therefore reduces power source Quantity, accordingly decrease cost.
Description of the drawings
Fig. 1 is that the double end jacking travelling device of the utility model is set to the front view between two production lines side by side.
Fig. 2 is the vertical view that double end jacking travelling device shown in FIG. 1 is set between two production lines side by side.
Fig. 3 is the sectional view after line A-A cutting along Fig. 1.
Fig. 4 is the sectional view after line B-B cutting along Fig. 1.
Fig. 5 is front view of the double end jacking travelling device shown in FIG. 1 after hiding two side-by-side production lines.
Fig. 6 is the vertical view of double end jacking travelling device shown in fig. 5.
Fig. 7 is the sectional view of the lifting body after line C-C cutting along Fig. 5.
Fig. 8 is the side view of lifting body shown in Fig. 7.
Specific implementation mode
In order to which the technology contents, construction feature of the utility model is described in detail, below in conjunction with embodiment and coordinate attached drawing It is described further.
It please refers to Fig.1 to Fig.4, the double end jacking travelling device 100 of the utility model is set to two production lines 200,300 side by side Between, referred to as the first production line 200 and the second production line 300, give birth to for carrying the first production line 200 and second for convenience of description Workpiece flows between producing line 300.
Wherein, the double end jacking travelling device 100 of the utility model includes rack 10, transition axis 20, the first crane 30, the Two cranes 40, lifting body 50 and migrate pipeline 60.Transition axis 20 is installed on rack 10 and along the length of production line 200,300 Spend direction (i.e. left and right directions in Fig. 1) arrangement.The first end of first crane 30 is installed on transition axis 20, the first crane 30 second end is horizontally placed in the first production line 200, with will be at the first production line 200 when the first crane 30 is raised above Workpiece jacks up, or workpiece is positioned on the first production line 200 when falling downwards, but not limited to this;The of second crane 40 One end is installed on transition axis 20, and the second end of the second crane 40 is horizontally placed in the second production line 300, in the second crane 40 jack up the workpiece at the second production line 300 when being raised above, or workpiece is positioned over the second production line 300 when falling downwards On, but not limited to this.Lifting body 50 be respectively arranged between the first crane 30 and rack 10 and the second crane 40 with Between rack 10 so that the first crane 30 and the independent pivot lifted that done around transition axis 20 of the second crane 40 are put;Lifting body 50 drive the first crane 30 and the second crane 40 to protrude production line 200,300 along 10 upper and lower directions of rack or be recessed in production Line 200,300, that is, the lifting body 50 being installed between the first crane 30 and rack 10 drives the first crane 30 around transition Axis 20 does the pivot pendulum lifted with respect to rack 10, to make the first crane 30 protrude the first production line 200, or is recessed in the first life Workpiece on first production line 200 is jacked up with meeting or workpiece is positioned at the first production line 200 by producing line 200;Equally, The lifting body 50 being installed between the second crane 40 and rack 10 drives the second crane 40 around transition axis 20 with respect to rack 10 do the pivot pendulum lifted, to make the second crane 40 protrude the second production line 300, or the second production line 300 are recessed in, with full Workpiece on second production line 300 is jacked up or workpiece is positioned at the second production line 300 by foot, but not limited to this.It migrates defeated Line sending 60 is respectively arranged on the first crane 30 and the second crane 40, is migrated pipeline 60 and is intersected with production line 200,300 It is wrong;Specifically, as shown in Fig. 2, migrating pipeline 60 and production line 200,300 is perpendicular, to simplify space hold amount, but not with This is limited;Preferably it is, as shown in Figure 1, the pipeline 60 that migrates on the first crane 30 is not being jacked by lifting body 50 When with the first production line 200 be located at same level height, migrate pipeline 60 not by lifting body 50 on the second crane 40 It is located at same level height with the second production line 300 when jacked.Driving motor 70, which is installed on rack 10 and drives, migrates conveying 60 conveying workpieces of line, in order to workpiece on the first crane 30 to migrate pipeline 60 defeated with migrating on the second crane 40 It is conveyed between line sending 60.More specifically, as follows:
As shown in Figure 1, Figure 2, shown in Fig. 5 and Fig. 6, it includes the installation axle 61 parallel with transition axis 20, difference to migrate pipeline 60 The transportation sprocket 62 being accordingly installed in installation axle 61 and transition axis 20 and 62 He of transportation sprocket being set around in installation axle 61 The conveyor chain 63 on transportation sprocket 62 on transition axis 20, while more reliable conveying workpieces, also to reach simple in structure The advantages of.For example, in this present embodiment, transportation sprocket 62 is duplex chain wheel, and conveyor chain 63 is double strand chain, to ensure The reliability of workpiece conveying, but not limited to this.
As shown in Fig. 1, Fig. 4, Fig. 7 and Fig. 8, lifting body 50 includes jacking cylinder 51, the output end with jacking cylinder 51 The support base 52 of connection and the jacking head 53 being installed on support base 51;Specifically, in this present embodiment, jacking head 53 is along transition The axial direction of axis 20 is installed on the both ends of support base 52 respectively in sustained height, increases lifting body 50 to the first crane 30 And second crane 40 jacking impetus, to more reliably jack the first crane 30 and the second crane 40 movement;Compared with Excellent, the output end of jacking cylinder 51 is upwardly disposed, prevents jacking cylinder 51 from causing rack 10 because output end is arranged downward Bulky defect;Riser guide group 54 is installed, to go to make by riser guide group 54 between support base 52 and rack 10 The oscilaltion for obtaining support base 52 is more stable reliable;For example, riser guide group 54 includes to be installed on leading on support base 52 Bar 54a and the guide bearing 54b being installed in rack 10, guide rod 54a are placed through in guide bearing 54b, to improve riser guide The accuracy that group 54 is oriented to, but do not illustrated and be limited with this.Preferably it is that jacking head 53 and guide bearing 54b are respectively flanged (FLGD) Linear bearing, to improve the reliability respectively to work.
As shown in Fig. 1, Fig. 3 and Fig. 5, chain-drive mechanism 80 is installed between driving motor 70 and transition axis 20, so that Driving motor can more reliably drive transition axis 20 to rotate by chain-drive mechanism 80, be moved to be driven by the transition axis 20 rotated The transportation sprocket 62 of row pipeline 60 rotates, to drive conveyor chain 63 to do rotary motion by the transportation sprocket 62 rotated, because And the workpiece carried by the conveyor chain of rotary motion 63 is conveyed.Specifically, in this present embodiment, chain-drive mechanism 80 comprising main drive sprocket wheel 81, the driven sprocket wheel 82 that is installed on transition axis 20 and are set around on main drive sprocket wheel 81 and driven sprocket wheel 82 Drive chain 83 so that transition axis 20 obtains desired power, and makes the compact-sized of chain-drive mechanism 80, but be not limited to This.
In conjunction with attached drawing, the operation principle of the double end lifting body 100 of the utility model is illustrated:When the first production line 200 make workpiece be delivered to jacking position when, at the same time 200 break-off of the first production line at this time is installed on the first lifting Lifting body 50 between frame 30 and rack 10 works, and jacks the first crane 30 upwards and puts around 20 pivot of transition axis and given birth to first Producing line 200 conveys the workpiece come and jacks up, and makes the Workpiece carrier of jack-up in migrating at pipeline 60 on first crane 30;By Workpiece is delivered to the migrating at pipeline 60 of the second crane 40 by the pipeline 60 that migrates on the first crane 30, to flow into At second production line 300, continue to convey by the second production line 300;When the first crane 30 to migrate pipeline 60 defeated by workpiece It send to the migrating at pipeline 60 of the second crane 40, the jack being installed at this time between the first crane 30 and rack 10 Structure 50 makes the first crane 30 reset, to make the pipeline 60 that migrates on the first crane 30 be in the first production line 200 Same level height is prepared for jacking next time.For the lifting principle of the second crane 40, with the first crane 30 Lifting principle is identical, therefore this will not be detailed here.
Compared with prior art, since the double end jacking travelling device 100 of the utility model is set to two production lines side by side 200, between 300 and include rack 10, transition axis 20, the first crane 30, the second crane 40, lifting body 50 and migrate defeated Line sending 60, transition axis 20 are installed on rack 10 and are arranged along the length direction of production line 200,300, the first of the first crane 30 End is installed on transition axis 20, and the second end of the first crane 30 is horizontally placed in the first production line 200, and the of the second crane 40 One end is installed on transition axis 20, and the second end of the second crane 40 is horizontally placed in the second production line 300, and lifting body 50 is distinguished It is installed between the first crane 30 and rack 10 and between the second crane 40 and rack 10 so that the first crane 30 and Two cranes 40 are lifted around transition axis 20 with respect to production line 200,300 each independently, so that two production lines side by side 200,300 break-off simultaneously is not needed, i.e., one is suspended and another one works on, so that the double end of the utility model Jacking travelling device 100 is adapted to the fast production line 200 of beat, 300 occasions, to save the time and improve production efficiency;Meanwhile by It is simultaneously from driving motor 70 in the power for migrating pipeline 60 on the first crane 30 and the second crane 40, by same drive Dynamic motor 70 is driven, therefore reduces the quantity of power source, accordingly decreases cost.
Above disclosed is only the preferred embodiments of the utility model, and the power of the utility model cannot be limited with this Sharp range, therefore equivalent variations made according to the claim of the utility model belong to the range that the utility model is covered.

Claims (10)

1. a kind of double end jacking travelling device is set between two production lines side by side, which is characterized in that the double end jacking travelling device Including:
Rack;
Transition axis, the transition axis are installed on the rack and are arranged along the length direction of the production line;
The first end of first crane, first crane is installed on the transition axis, and the second of first crane End is horizontally placed in a production line;
The first end of second crane, second crane is installed on the transition axis, and the second of second crane End is horizontally placed in another production line;
Lifting body, the lifting body be respectively arranged between first crane and rack and second crane with Between rack, the lifting body drives first crane and the second crane to be protruded along the rack upper and lower directions and produces Line is recessed in production line;
Pipeline is migrated, the pipeline that migrates is respectively arranged on first crane and the second crane, described to migrate Pipeline is staggered with production line;And
Driving motor, the driving motor, which is installed on the rack and drives, described migrates pipeline conveying workpieces.
2. double end jacking travelling device according to claim 1, which is characterized in that it is described migrate pipeline include and the mistake It crosses the parallel installation axle of axis, the transportation sprocket being respectively correspondingly installed on the installation axle and transition axis and is set around the peace Fill the conveyor chain on the transportation sprocket on the transportation sprocket and transition axis on axis.
3. double end jacking travelling device according to claim 2, which is characterized in that the transportation sprocket is duplex chain wheel, institute It is double strand chain to state conveyor chain.
4. double end jacking travelling device according to claim 1, which is characterized in that the lifting body include jacking cylinder, The support base being connect with the output end of the jacking cylinder and the jacking head being installed on the support base.
5. double end jacking travelling device according to claim 4, which is characterized in that axis of the jacking head along the transition axis To being installed on the both ends of the support base in sustained height respectively.
6. double end jacking travelling device according to claim 4, which is characterized in that the output end of jacking cylinder cloth upward It sets, riser guide group is installed between the support base and the rack.
7. double end jacking travelling device according to claim 6, which is characterized in that the riser guide group includes to be installed on institute The guide bearing stated the guide rod on support base and be installed in the rack, the guide rod are placed through in the guide bearing.
8. double end jacking travelling device according to claim 7, which is characterized in that the jacking head and guide bearing are respectively band The linear bearing of flange.
9. double end jacking travelling device according to claim 1, which is characterized in that the driving motor and the transition axis it Between chain-drive mechanism is installed.
10. double end jacking travelling device according to claim 9, which is characterized in that the chain-drive mechanism includes main drive chain The driven sprocket wheel take turns, being installed on the transition axis and the drive chain being set around on the main drive sprocket wheel and driven sprocket wheel.
CN201721730450.1U 2017-12-11 2017-12-11 Double end jacking travelling device Active CN207671255U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721730450.1U CN207671255U (en) 2017-12-11 2017-12-11 Double end jacking travelling device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721730450.1U CN207671255U (en) 2017-12-11 2017-12-11 Double end jacking travelling device

Publications (1)

Publication Number Publication Date
CN207671255U true CN207671255U (en) 2018-07-31

Family

ID=62969118

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721730450.1U Active CN207671255U (en) 2017-12-11 2017-12-11 Double end jacking travelling device

Country Status (1)

Country Link
CN (1) CN207671255U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107934498A (en) * 2017-12-11 2018-04-20 广东伟创五洋智能设备有限公司 Double end jacking travelling device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107934498A (en) * 2017-12-11 2018-04-20 广东伟创五洋智能设备有限公司 Double end jacking travelling device

Similar Documents

Publication Publication Date Title
CN207580748U (en) Garment production suspension conveying line based on RFID
CN201990253U (en) Falling positioning device for floating type products
CN203497544U (en) Novel putaway conveyor lifting supporting roller frame
CN207671255U (en) Double end jacking travelling device
CN210944676U (en) Small-size jacking equipment is used in civil engineering
CN216038232U (en) Hanger rail replacing system for spiral track conveying production line
CN107934498A (en) Double end jacking travelling device
CN206032463U (en) Two casees automatic butt joint dress discharge apparatus of method
CN205060887U (en) Hoist mechanism of assembly line is hung to ready -made clothe
CN202273598U (en) Removable servo frame
CN102400648A (en) Detachable follow-up frame and installation process thereof
CN206486015U (en) A kind of material stirring-up mechanism of type board collecting bottom machine
CN206580242U (en) A kind of tubing delivery clamping device
CN203143515U (en) Vertical lifting conveyor
CN203512717U (en) High-speed tank erecting machine
CN209492791U (en) A kind of labelling machine and its turnover mechanism
CN204530977U (en) Omnidistance slidingtype connects bucket device
CN209253828U (en) Syringe feeder
CN208647919U (en) A kind of motor rotor lath circulation mechanism
CN206666052U (en) Gear fast lifting mechanism
CN206375635U (en) A kind of two-direction moving feeder
CN202675858U (en) Roller kiln
CN207903849U (en) A kind of worm and gear elevator of inscribed lead screw
CN207156302U (en) A kind of linear foam box equipment
CN207314932U (en) A kind of Novel hoisting swing mechanism

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant