CN207633344U - Slip casting component and ground restoration equipment - Google Patents

Slip casting component and ground restoration equipment Download PDF

Info

Publication number
CN207633344U
CN207633344U CN201721694523.6U CN201721694523U CN207633344U CN 207633344 U CN207633344 U CN 207633344U CN 201721694523 U CN201721694523 U CN 201721694523U CN 207633344 U CN207633344 U CN 207633344U
Authority
CN
China
Prior art keywords
grouting pipe
slip casting
pipe
casting component
connector
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721694523.6U
Other languages
Chinese (zh)
Inventor
刘选朋
苏铁志
屈浩
秦国栋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Aerospace Foundation Engineering Co Ltd
Original Assignee
Beijing Aerospace Foundation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Aerospace Foundation Engineering Co Ltd filed Critical Beijing Aerospace Foundation Engineering Co Ltd
Priority to CN201721694523.6U priority Critical patent/CN207633344U/en
Application granted granted Critical
Publication of CN207633344U publication Critical patent/CN207633344U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The utility model provides a kind of slip casting component and ground restoration equipment, is related to the technical field of architectural engineering, including connector, at least one the first Grouting Pipe of section and the second Grouting Pipe;Connector one end is connect with the first Grouting Pipe, and the other end with pick for connecting;Second Grouting Pipe is connected to the first Grouting Pipe, and the second Grouting Pipe is provided with conehead away from first Grouting Pipe one end;Wherein:Multiple slurry outlets are both provided on the tube wall of first Grouting Pipe and the second Grouting Pipe.The purpose of this utility model is to provide a kind of slip casting component and ground restoration equipment, the slip casting that backfill is carried out using small mechanical equipment can be realized, it is simple in structure, easy to operation to realize the purpose of foundation stabilization, soil remediation, and save cost.

Description

Slip casting component and ground restoration equipment
Technical field
The utility model is related to construction engineering technical fields, more particularly, to a kind of slip casting component and ground restoration equipment.
Background technology
Since building room cubsoil backfills leakiness, or because backfill moisture content is excessive, lead to building in use Bulk settling occurs for face and appearance part settles excessive ground cracking phenomena or construction finishes, and increases in later stage room Add some novel devices, equipment itself higher to ground deformation requirements, the bearing capacity of backfill cannot be satisfied when requiring, due to The interior space is limited, and large scale equipment cannot be introduced into, and directly excavates and changes that fill out cost too big.
There is the underground reparation in the business processes closing confined space of pollution there is also the above problem, big machinery is set It is standby to cannot be introduced into, directly excavate cost height.
Therefore, how to handle the problems in above-mentioned foundation stabilization or soil remediation process be those skilled in the art urgently It solves the problems, such as.
Utility model content
The purpose of this utility model is to provide a kind of slip casting component and ground restoration equipment, it can realize that man-hour manually hand-held is small Type machinery electric pick or pneumatic pick head into the Grouting Pipe merogenesis vertical flooring connected in backfill, and Grouting Pipe is headed into design It after depth, can be connected on grouting pump by high pressure rubber hose, select the grouting pressure of design, carry out the note of various slurries It penetrates, to achieve the purpose that foundation stabilization and soil remediation, and connector is set effectively prevents electric pick and be in direct contact Grouting Pipe, So that extrusion pour slurry pipe is destroyed.
To achieve the above object, the utility model provides following technical scheme:
In a first aspect, the utility model provides a kind of slip casting component, it is used for ground restoration, including:Connector, at least one section First Grouting Pipe and the second Grouting Pipe;
Described connector one end is connect with first Grouting Pipe, and the other end with pick for connecting;Second slip casting Pipe is connected to first Grouting Pipe, and second Grouting Pipe is provided with conehead away from first Grouting Pipe one end;Wherein:
It is both provided with multiple slurry outlets on the tube wall of first Grouting Pipe and second Grouting Pipe.
Further, the connector includes the head that connection is matched with pick.
Further, the head shape is hexagonal prisms.
Further, the connector uses casting and forming.
Further, the connector passes through pipe collar screwed connection with first Grouting Pipe.
Further, second Grouting Pipe passes through pipe collar screwed connection with first Grouting Pipe.
Further, first Grouting Pipe, and/or, the pulp hole number in second Grouting Pipe is not less than ten.
Further, first Grouting Pipe, and/or, the slurry outlet in second Grouting Pipe is arranged according to equilateral triangle Row.
Further, the conehead is solid steel toe.
Second aspect, the utility model also provide a kind of ground restoration equipment, including pick, further include appointing in first aspect Slip casting component described in one, the pick are connect with the slip casting component.
Slip casting component provided by the utility model and ground restoration equipment have the advantages that:
The utility model first aspect provides a kind of slip casting component, is used for ground restoration, including:Connector, at least one section First Grouting Pipe and the second Grouting Pipe;Connector one end is connect with the first Grouting Pipe, and the other end with pick for connecting;Second note Slurry pipe is connected to the first Grouting Pipe, and the second Grouting Pipe is provided with conehead away from first Grouting Pipe one end;Wherein:First Grouting Pipe It is both provided with multiple slurry outlets on the tube wall of the second Grouting Pipe.
The slip casting component provided using the utility model first aspect, man-hour manually hand-held small-sized machine electric pick or pneumatic pick pass through Connector is connect with Grouting Pipe, and the vertical flooring of Grouting Pipe merogenesis connected is headed into backfill, depth is headed into and regards back Depending on filled slope, often saves the first Grouting Pipe and connected with the second Grouting Pipe, and the second Grouting Pipe is connected to the first Grouting Pipe, second Grouting Pipe is provided with conehead away from first Grouting Pipe one end, facilitates access for backfill;Wherein:First Grouting Pipe and the second Grouting Pipe Tube wall on be both provided with multiple slurry outlets.It, can be by high pressure rubber hose by the first note after Grouting Pipe is headed into projected depth Slurry pipe is connected on grouting pump, is selected the grouting pressure of design, is carried out the injection of various slurries, slurries can be from the first Grouting Pipe It is sprayed to backfill with multiple slurry outlets on the tube wall of the second Grouting Pipe, to reach the mesh of foundation stabilization and soil remediation 's.And it connector is set effectively prevents electric pick and be in direct contact Grouting Pipe, so that extrusion pour slurry pipe is destroyed.
The slip casting that small mechanical equipment carries out backfill may be used in the slip casting component that the utility model first aspect provides, It is simple in structure, easy to operation to realize the purpose of foundation stabilization, soil remediation, and save cost.
The ground restoration equipment that the utility model second aspect provides is provided with the note of the utility model first aspect offer Component is starched, all advantageous effects possessed by the slip casting component to be provided with the utility model first aspect.
Description of the drawings
It, below will be right in order to illustrate more clearly of specific embodiment of the present invention or technical solution in the prior art Specific implementation mode or attached drawing needed to be used in the description of the prior art are briefly described, it should be apparent that, it is described below In attached drawing be that some embodiments of the utility model are not paying creativeness for those of ordinary skill in the art Under the premise of labour, other drawings may also be obtained based on these drawings.
Fig. 1 is the structural schematic diagram for the slip casting component that the utility model embodiment provides;
Fig. 2 is the structural schematic diagram of connector in the slip casting component that the utility model embodiment provides;
Fig. 3 is the vertical view of connector in the slip casting component that the utility model embodiment provides;
Fig. 4 is the structural schematic diagram of the first Grouting Pipe in the slip casting component that the utility model embodiment provides;
Fig. 5 is the structural schematic diagram of the second Grouting Pipe in the slip casting component that the utility model embodiment provides.
Icon:1- connectors;The first Grouting Pipes of 2-;The second Grouting Pipes of 3-;4- slurry outlets;5- pipe collars;11- heads;31- is bored Head.
Specific implementation mode
The technical solution of the utility model is clearly and completely described below in conjunction with attached drawing, it is clear that described Embodiment is the utility model a part of the embodiment, instead of all the embodiments.Based on the embodiments of the present invention, originally The every other embodiment that field those of ordinary skill is obtained without making creative work, belongs to this practicality Novel protected range.
It is in the description of the present invention, it should be noted that term "center", "upper", "lower", "left", "right", " perpendicular Directly ", the orientation or positional relationship of the instructions such as "horizontal", "inner", "outside" is to be based on the orientation or positional relationship shown in the drawings, and is only The utility model and simplifying describes for ease of description, do not indicate or imply the indicated device or element must have it is specific Orientation, with specific azimuth configuration and operation, therefore should not be understood as limiting the present invention.In addition, term " the One ", " second ", " third " are used for description purposes only, and are not understood to indicate or imply relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " is pacified Dress ", " connected ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integrally Connection;It can be mechanical connection, can also be electrical connection;Can be directly connected, can also indirectly connected through an intermediary, It can be the connection inside two elements.For the ordinary skill in the art, it can understand above-mentioned art with concrete condition The concrete meaning of language in the present invention.
Specific embodiment of the present utility model is described in detail below in conjunction with attached drawing.It should be understood that herein Described specific implementation mode is only used for describing and explaining the present invention, and is not intended to limit the utility model.
Fig. 1, Fig. 2, Fig. 3, Fig. 4 and Fig. 5 are please referred to, the slip casting provided the utility model embodiment below in conjunction with attached drawing Component and ground restoration equipment elaborate.
Embodiment 1
The embodiment of the utility model first aspect provides a kind of slip casting component, is used for ground restoration, including:Connector 1, at least one the first Grouting Pipe 2 of section and the second Grouting Pipe 3;
1 one end of connector is connect with the first Grouting Pipe 2, and the other end with pick for connecting;Second Grouting Pipe 3 and the first note It starches pipe 2 to be connected to, and the second Grouting Pipe 3 is provided with conehead 31 away from 2 one end of the first Grouting Pipe;Wherein:
It is both provided with multiple slurry outlets 4 on the tube wall of first Grouting Pipe 2 and the second Grouting Pipe 3.
Using the utility model first aspect embodiment provide slip casting component, man-hour manually hand-held small-sized machine electric pick or Pneumatic pick is connect by connector 1 with Grouting Pipe, and the vertical flooring of Grouting Pipe merogenesis connected is headed into backfill, is headed into Depth often saves the first Grouting Pipe 2 and the connection of the second Grouting Pipe 3, and the second Grouting Pipe 3 and the first slip casting depending on backfilling soil thickness Pipe 2 is connected to, and the second Grouting Pipe 3 is provided with conehead 31 away from 2 one end of the first Grouting Pipe, facilitates access for backfill;Wherein:First note It is both provided with multiple slurry outlets 4 on slurry pipe 2 and the tube wall of the second Grouting Pipe 3.After Grouting Pipe is headed into projected depth, it can pass through First Grouting Pipe 2 is connected on grouting pump by high pressure rubber hose, is selected the grouting pressure of design, is carried out the injection of various slurries, Slurries can be sprayed from multiple slurry outlets 4 on the tube wall of the first Grouting Pipe 2 and the second Grouting Pipe 3 to backfill, to reach The purpose of foundation stabilization and soil remediation.And it connector 1 is set effectively prevents electric pick and be in direct contact Grouting Pipe, so that squeezing Grouting Pipe is by slip casting tube damage.
The slip casting component that the embodiment of the utility model first aspect provides may be used small mechanical equipment and be backfilled The slip casting of soil, it is simple in structure, easy to operation to realize the purpose of foundation stabilization, soil remediation, and save cost.
It elaborates below to connector 1:
In the alternative of the present embodiment, further, connector 1 includes the head 11 that connection is matched with pick.
It should be noted that the shape of head 11 in the present embodiment and pick shape adaptation, size can with but not only limit In for matched with electric pick connection size.
In the alternative of the present embodiment, further, 11 shape of head is hexagonal prisms.
It should be noted that as shown in figure 3, the shape of head 11 in the present embodiment and pick shape adaptation, can with but It is not limited only to the hexagonal prism shape to be docked with electric pick.Diameter can be referred to be designed using the pick of electric pick.
In the alternative of the present embodiment, further, connector 1 uses casting and forming.
It should be noted that casting and forming may be used in connector 1, specifically, 1 cylinder of connector is not less than using intensity The steel mold casting and forming of Q235, bottom are detachably connected with the first Grouting Pipe 2.When operation construction, the bar of electric pick and connector 1 First 11 matching connection, the bottom of connector 1 are connect with the first Grouting Pipe 2, pass through connector 1 between electric pick and the first Grouting Pipe 2 Connection, effectively prevents electric pick and is in direct contact Grouting Pipe, so that extrusion pour slurry pipe is by slip casting tube damage.
In addition, if when connector 1 does not have mold working condition, for the sake of convenient, when construction, can be made, upper bar First 11 may be used electric pick pick, and lower part can be used Grouting Pipe and be welded in round steel column use of the thickness not less than 5cm.
Electric pick is connect by connector 1 with Grouting Pipe, and after Grouting Pipe is headed into back fill course, need by connector 1 from It is removed in Grouting Pipe, Grouting Pipe is then connect slip casting with grouting pump, clamping, spiral shell may be used in connector 1 and the first Grouting Pipe 2 Line connection etc. is detachably connected.
In the alternative of the present embodiment, further, connector 1 and the first Grouting Pipe 2 are connected by 5 screw thread of pipe collar It connects.
It should be noted that 1 lower part of connector is solid public screw thread, the Grouting Pipe top headed into is female screw thread, and the two can Securely to be connected, in a kind of specific implementation mode, 1 top of connector can be hollow thick walled steel tube, can hammer electric pick into shape Head is inserted, and such mode effectively prevents electric pick and is in direct contact Grouting Pipe, is destroyed so that squeezing.Grouting Pipe is headed into It after projected depth, is connected on grouting pump by high pressure rubber hose, selects the grouting pressure of design, carry out the note of various slurries It penetrates, to achieve the purpose that foundation stabilization and soil remediation.
In the alternative of the present embodiment, further, the second Grouting Pipe 3 and the first Grouting Pipe 2 pass through 5 screw thread of pipe collar Connection.
In at least one embodiment, 2 top hitch screw thread of the first Grouting Pipe is not less than 15, such as is specifically as follows 15 Road, 16,17,18,19 or 20 add mating pipe collar 5 after having covered, and connect with the public screw thread of 1 lower part of connector It connects.Also, 2 top of the first Grouting Pipe can connect the grouting pump for slip casting by high pressure rubber hose.
In at least one embodiment, 2 lower part hitch screw thread of the first Grouting Pipe is not less than 15, such as is specifically as follows 15 Road, 16,17,18,19 or 20,3 top hitch screw thread of the second Grouting Pipe are not less than 15, such as specifically can be with It is 15,16,17,18,19 or 20, adds mating pipe collar 5 after having covered, covered with 2 lower part of the first Grouting Pipe The screwed connection of button.
In at least one embodiment, diameter 30cm-35cm may be used in the first Grouting Pipe 2, wall thickness 3.5mm-4.5mm's Welded still pipe.Specifically, diameter of steel tube can be 30cm, 31cm, 32cm, 33cm, 34cm or 35cm;Wall thickness can be 3.5mm, 3.6mm, 3.7mm, 3.8mm, 3.9mm, 4mm, 4.1mm, 4.2mm, 4.3mm, 4.4mm or 4.5mm.
In the alternative of the present embodiment, further, the first Grouting Pipe 2, and/or, the pulp in the second Grouting Pipe 3 4 quantity of hole is not less than ten.
In at least one embodiment, the tube wall of the first Grouting Pipe 2 fires multiple slurry outlets 4 using electric welding, specifically goes out Starch 4 quantity of hole be not less than ten, such as be specifically as follows 10,11,12,13,14,15,16,17,18 It is a, 19 or 20.Wherein, slurry outlet 4 can be diameter 0.5cm-1.5cm circular hole, such as be specifically as follows 0.5cm, 1cm or 1.5cm.
In at least one embodiment, adhesive tape closure, and the first slip casting may be used in circular hole in the first Grouting Pipe 2 Pipe 2 can reinforce the range of soil layer as needed, selectively carry out trepanning design.
In at least one embodiment, the tube wall of the second Grouting Pipe 3 fires multiple slurry outlets 4 using electric welding, specifically goes out Starch 4 quantity of hole be not less than ten, such as be specifically as follows 10,11,12,13,14,15,16,17,18 It is a, 19 or 20.Wherein, slurry outlet 4 can be diameter 0.5cm-1.5cm circular hole, such as be specifically as follows 0.5cm, 1cm or 1.5cm.
In at least one embodiment, adhesive tape closure, and the second slip casting may be used in circular hole in the second Grouting Pipe 3 Pipe 3 can reinforce the range of soil layer as needed, selectively carry out trepanning design.
Putting in order for the slurry outlet 4 of first Grouting Pipe 2 or the second Grouting Pipe 3 can be various ways, such as plum blossom Shape.
In the alternative of the present embodiment, further, the first Grouting Pipe 2, and/or, the pulp in the second Grouting Pipe 3 Hole 4 is according to triangular arranged.
In the alternative of the present embodiment, further, conehead 31 is solid steel toe.The vertical section of conehead 31 is isosceles Triangle, and base angle is specifically as follows 60 °.The longitudinal length of conehead 31 be 14cm-16cm, be specifically as follows 14cm, 15cm or Person 16cm.Conehead 31 is for example welded with Grouting Pipe mechanical connection, and conehead 31 can be single solid steel head, and the strength of materials is not less than Q235.Or can tube head directly be pounded into flat processing in live process and be used as conehead 31.
In order to reduce sidewall resistance when Grouting Pipe squeezes into back fill course, one layer of profit can be smeared on the tube wall of Grouting Pipe Lubrication prescription, such as butter.
Grouting Pipe such as the first Grouting Pipe 2 and the second Grouting Pipe 3 can arbitrarily be intercepted according to the height of the confined space, processing set It is used after button.
Embodiment 2
The embodiment of the utility model second aspect provides a kind of ground restoration equipment, including pick, further includes first Any slip casting component, pick are connect with slip casting component in the embodiment of aspect.
The ground restoration equipment that the embodiment of the utility model second aspect provides is provided with the utility model first aspect Embodiment provide slip casting component, to the utility model first aspect embodiment provide slip casting component had All advantageous effects.
In at least one embodiment, pick is connect with the head 11 of connector 1 in slip casting component, direct to avoid electric pick Grouting Pipe is contacted, so that extrusion pour slurry pipe is by slip casting tube damage.
It to the slip casting component of the utility model and is illustrated above, still, the utility model is not limited to above-mentioned tool The embodiment of body can carry out various deformations or change without departing from the scope of the claims.The utility model The various modifications being included within the scope of the claims and change.
Finally it should be noted that:The above various embodiments is only to illustrate the technical solution of the utility model, rather than limits it System;Although utility model is described in detail with reference to foregoing embodiments, those skilled in the art should manage Solution:It still can be with technical scheme described in the above embodiments is modified, either to which part or whole skills Art feature carries out equivalent replacement;And these modifications or replacements, it does not separate the essence of the corresponding technical solution the utility model The range of each embodiment technical solution.

Claims (10)

1. a kind of slip casting component is used for ground restoration, which is characterized in that including:Connector (1), at least one the first Grouting Pipe of section (2) and the second Grouting Pipe (3);
Described connector (1) one end is connect with first Grouting Pipe (2), and the other end with pick for connecting;Second note Slurry pipe (3) is connected to first Grouting Pipe (2), and second Grouting Pipe (3) is set away from described first Grouting Pipe (2) one end It is equipped with conehead (31);Wherein:
It is both provided with multiple slurry outlets (4) on the tube wall of first Grouting Pipe (2) and second Grouting Pipe (3).
2. slip casting component according to claim 1, which is characterized in that the connector (1) includes matching connection with pick Head (11).
3. slip casting component according to claim 2, which is characterized in that head (11) shape is hexagonal prisms.
4. slip casting component according to claim 1, which is characterized in that the connector (1) uses casting and forming.
5. slip casting component according to claim 1, which is characterized in that the connector (1) and first Grouting Pipe (2) Pass through pipe collar (5) screwed connection.
6. slip casting component according to claim 1, which is characterized in that second Grouting Pipe (3) and first slip casting Pipe (2) passes through pipe collar (5) screwed connection.
7. slip casting component according to claim 1, which is characterized in that first Grouting Pipe (2), and/or, described second Slurry outlet (4) quantity in Grouting Pipe (3) is not less than ten.
8. slip casting component according to claim 1, which is characterized in that first Grouting Pipe (2), and/or, described second Slurry outlet (4) in Grouting Pipe (3) is according to triangular arranged.
9. slip casting component according to claim 1, which is characterized in that the conehead (31) is solid steel toe.
10. a kind of ground restoration equipment, including pick, which is characterized in that further include described in any one of claim 1 to 9 Slip casting component, the pick are connect with the slip casting component.
CN201721694523.6U 2017-12-07 2017-12-07 Slip casting component and ground restoration equipment Active CN207633344U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721694523.6U CN207633344U (en) 2017-12-07 2017-12-07 Slip casting component and ground restoration equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721694523.6U CN207633344U (en) 2017-12-07 2017-12-07 Slip casting component and ground restoration equipment

Publications (1)

Publication Number Publication Date
CN207633344U true CN207633344U (en) 2018-07-20

Family

ID=62855940

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721694523.6U Active CN207633344U (en) 2017-12-07 2017-12-07 Slip casting component and ground restoration equipment

Country Status (1)

Country Link
CN (1) CN207633344U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109881668A (en) * 2019-03-15 2019-06-14 中国十九冶集团有限公司 Foundation construction method for soft soil layer, filling soil and sand soil layer
CN110439258A (en) * 2019-04-15 2019-11-12 中国建筑第四工程局有限公司 A kind of disposal molding integration anchor pole and construction method
CN110886309A (en) * 2019-12-04 2020-03-17 成都轨道建设管理有限公司 Double-slurry mixing device and construction method for treating quicksand layer by using double-slurry mixing device
CN111535296A (en) * 2020-05-13 2020-08-14 安徽建筑大学 Layered grouting freezing device and layered grouting freezing method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109881668A (en) * 2019-03-15 2019-06-14 中国十九冶集团有限公司 Foundation construction method for soft soil layer, filling soil and sand soil layer
CN110439258A (en) * 2019-04-15 2019-11-12 中国建筑第四工程局有限公司 A kind of disposal molding integration anchor pole and construction method
CN110886309A (en) * 2019-12-04 2020-03-17 成都轨道建设管理有限公司 Double-slurry mixing device and construction method for treating quicksand layer by using double-slurry mixing device
CN110886309B (en) * 2019-12-04 2021-06-18 成都轨道建设管理有限公司 Double-slurry mixing device and construction method for treating quicksand layer by using double-slurry mixing device
CN111535296A (en) * 2020-05-13 2020-08-14 安徽建筑大学 Layered grouting freezing device and layered grouting freezing method

Similar Documents

Publication Publication Date Title
CN207633344U (en) Slip casting component and ground restoration equipment
CN210263647U (en) A grout sleeve for steel bar connection
CN107419734B (en) Netted retaining structure of deep side slope that bankets
CN102808413B (en) Reinforcement-replacing sectional-grouting pipe with inner piston and construction method thereof
CN205776221U (en) The portable protective baffle plate of artificial digging pile
CN205422773U (en) Novel hollow grouting anchor bolt
CN109881668A (en) Foundation construction method for soft soil layer, filling soil and sand soil layer
CN204385727U (en) Spiral grouting preformed pile
CN206448166U (en) A kind of vertical prestressing mud jacking pipeline docking facilities
CN100557145C (en) The PHC stake is interior towards interior row's auxiliary pile sinking job practices
CN212612452U (en) Groutable anchor rod
CN211949617U (en) Stagnant water split bolt
CN208899473U (en) A kind of uplift pile pile extension connecting node
CN201158818Y (en) Anti-corrosion anchor bar with centering slurry guiding tube
CN203905008U (en) Diagonal brace supporting structure for superior angle of foundation pit
CN207452894U (en) A kind of repeatable anchor pile utilized
CN212202072U (en) Ultra-long-distance secondary grouting system for shield construction
CN206655191U (en) A kind of small-sized drainage canal of hydraulic engineering
CN214660225U (en) Advanced small guide pipe parallel grouting system
CN205976565U (en) PVC pipe root protective sheath
CN216479363U (en) Steel sleeve reinforced concrete pipe
CN207062933U (en) Can consolidated subsoil prefabricated pile
CN104032746B (en) A kind of supporting fill block structure of foundation ditch angle position
CN209779678U (en) Adjustable core-pulling template for piping lane construction
CN210950211U (en) Flexible interface pipeline buttress with bottom ridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant