CN207625245U - A kind of pipe busbar gold utensil bracket - Google Patents

A kind of pipe busbar gold utensil bracket Download PDF

Info

Publication number
CN207625245U
CN207625245U CN201721317316.9U CN201721317316U CN207625245U CN 207625245 U CN207625245 U CN 207625245U CN 201721317316 U CN201721317316 U CN 201721317316U CN 207625245 U CN207625245 U CN 207625245U
Authority
CN
China
Prior art keywords
gold utensil
alar part
pipe busbar
busbar gold
support plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721317316.9U
Other languages
Chinese (zh)
Inventor
肖冰
路平
苏光
杨旭方
秦海波
何明霞
董博
孙运涛
姚欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Construction Group Nanjing Line Equipment Co Ltd
State Nuclear Electric Power Planning Design and Research Institute Co Ltd
Original Assignee
China Energy Construction Group Nanjing Line Equipment Co Ltd
State Nuclear Electric Power Planning Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Construction Group Nanjing Line Equipment Co Ltd, State Nuclear Electric Power Planning Design and Research Institute Co Ltd filed Critical China Energy Construction Group Nanjing Line Equipment Co Ltd
Priority to CN201721317316.9U priority Critical patent/CN207625245U/en
Application granted granted Critical
Publication of CN207625245U publication Critical patent/CN207625245U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model discloses a kind of pipe busbar gold utensil brackets, belong to transmission line of electricity technical field, and the pipe busbar gold utensil bracket includes support plate, and the support plate includes the first alar part being sequentially connected in the direction of extension, middle part and the second alar part;The first mounting hole for installing fixing pipe busbar gold utensil is provided on first alar part;The second mounting hole for being connect with support insulator is provided on the middle part;Two plate portions for being provided perpendicular to second alar part on second alar part and being oppositely arranged in parallel along the extending direction;The elongate holes extended along the extending direction are respectively arranged in two plate portions.Pipe busbar gold utensil bracket provided by the utility model can be fixedly connected with fixing pipe busbar gold utensil, opposite can be slidably connected with sliding tube busbar gold utensil.

Description

A kind of pipe busbar gold utensil bracket
Technical field
The utility model is related to transmission line of electricity technical field, more particularly to a kind of pipe busbar gold utensil bracket.
Background technology
Pipe busbar is one of equipment crucial in electric power power transmission and transformation system, to the safety of power transmission and transformation system and power equipment, Reliability service plays a crucial role.Pipe busbar is generally fixed in pipe busbar gold utensil, and pipe busbar gold utensil passes through gold utensil support Frame is connected on support insulator.Support insulator plays support tube busbar and keeps pipe busbar and other metal components mutual The effect of insulation.Connection is there are two pipe busbar gold utensil on same support insulator, pipe caused by order to meet under earthquake conditions The structure of the sliding problem of busbar, bracket will make fixing pipe busbar gold utensil be fixed on support insulator, and sliding tube busbar gold utensil can It is slided relative to support insulator.
There is presently no the pipe busbar gold utensil brackets that can meet above-mentioned requirements.
Utility model content
In view of this, the utility model provides a kind of pipe busbar gold utensil bracket, it is fixedly connected with fixing pipe busbar gold utensil, with Sliding tube busbar gold utensil opposite can be slidably connected.
Specifically, the utility model provides a kind of pipe busbar gold utensil bracket, including support plate, the support plate include The first alar part, middle part and the second alar part being sequentially connected in the direction of extension;
The first mounting hole for installing fixing pipe busbar gold utensil is provided on first alar part;
The second mounting hole for being connect with support insulator is provided on the middle part;
It is provided perpendicular to second alar part on second alar part and is oppositely arranged in parallel along the extending direction Two plate portions;
The elongate holes extended along the extending direction are respectively arranged in two plate portions.
Selectively, the quantity of first mounting hole is multiple, and multiple first mounting holes are evenly spaced on On same circumference.
Selectively, the quantity of second mounting hole is multiple, and multiple second mounting holes are evenly spaced on On same circumference.
Selectively, the middle part of the support plate forms recess, and straight gusset is provided in the recess;
The straight gusset is connect perpendicular to the bottom surface of the recess, the lower wall of the straight gusset with the bottom surface of the recess, Opposite two sides of the opposite two side walls of the straight gusset respectively with the recess are connect.
Selectively, further include four diagonal bar plates;
Two sides parallel with the extending direction of first alar part and second alar part respectively with it is adjacent The side of the recess is at a right angle;
The diagonal bar plate is right-angled trapezium, and the straight waist of each diagonal bar plate is connect with a side, longer The side of the bottom edge recess adjacent with the side connects.
Selectively, perforative first through hole up and down is offered on first alar part.
Selectively, perforative second through-hole up and down is offered on second alar part.
Selectively, the area of the first through hole is less than the area of second through-hole.
The advantageous effect of technical solution that the utility model embodiment provides is:
Pipe busbar gold utensil bracket provided by the utility model, by the way that the first installation is arranged on the first alar part of support plate Hole, convenient for fixing pipe busbar gold utensil to be fixed in support plate;By the way that the second mounting hole is arranged on the middle part of support plate, it is convenient for Support plate is installed on support insulator;By being arranged perpendicular to the second alar part and along extension on the second alar part of support plate Two plate portions that direction is oppositely arranged in parallel, and elongate holes are set in plate portion, it is convenient for sliding tube busbar gold utensil and plate Portion opposite can be slidably connected.Therefore, pipe busbar gold utensil bracket provided by the utility model can be fixed on support insulator, and It can be fixedly connected with fixing pipe busbar gold utensil, and opposite can be slidably connected with sliding tube busbar gold utensil, to keep fixing pipe female Line gold utensil is fixed relative to support insulator, and sliding tube busbar gold utensil can be slided relative to support insulator.
Description of the drawings
It is required in being described below to embodiment in order to illustrate more clearly of the technical scheme in the embodiment of the utility model Attached drawing to be used is briefly described, it should be apparent that, the accompanying drawings in the following description is only some realities of the utility model Example is applied, it for those of ordinary skill in the art, without creative efforts, can also be according to these attached drawings Obtain other attached drawings.
Fig. 1 is the vertical view of one embodiment middle pipe busbar gold utensil bracket of the utility model;
Fig. 2 is the side view of one embodiment middle pipe busbar gold utensil bracket of the utility model;
Fig. 3 is the vertical view of support plate in one embodiment of the utility model;
Fig. 4 is the side view of support plate in one embodiment of the utility model;
Fig. 5 is the schematic diagram of plate portion in one embodiment of the utility model;
Fig. 6 is the schematic diagram of straight gusset in one embodiment of the utility model;
Fig. 7 is the schematic diagram of diagonal bar plate in one embodiment of the utility model;
Fig. 8 is the pipe busbar gold utensil bracket that is provided using one embodiment of the utility model by pipe busbar installation to pillar Schematic diagram on insulator.
Reference numeral in figure indicates respectively:
1, support plate;
101, the first alar part;
1011, the first mounting hole;
1012, first through hole;
102, middle part;
1021, the second mounting hole;
103, the second alar part;
1031, the second through-hole;
2, plate portion;
201, elongate holes;
3, straight gusset;
4, diagonal bar plate.
Specific implementation mode
To keep the technical solution of the utility model and advantage clearer, the utility model is implemented below in conjunction with attached drawing Mode is described in further detail.
One embodiment of the utility model provides a kind of pipe busbar gold utensil bracket, as shown in Figure 1, including support plate 1, support Plate 1 includes the first alar part 101, middle part 102 and the second alar part 103 being sequentially connected in the direction of extension;
The first mounting hole 1011 for installing fixing pipe busbar gold utensil is provided on first alar part 101 of support plate 1;
The middle part 102 of support plate 1 is provided with the second mounting hole 1021 for being connect with support insulator;
It is provided perpendicular to the second alar part 103 on second alar part 103 of support plate 1 and is put down along the extending direction of support plate 1 Two plate portions 2 that row is oppositely arranged;
As shown in figure 5, being respectively arranged with the elongate holes 201 of the extending direction extension along support plate 1 in two plate portions 2.
As shown in Figure 1, the extending direction for being oriented to support plate 1 of arrow.
The use principle of pipe busbar gold utensil bracket provided by the utility model is given below and is described:
First alar part 101 of the screw bolt and nut by mounting hole and support plate 1 on fixing pipe busbar gold utensil is used first On the first mounting hole 1011, will fixing pipe busbar gold utensil be fixed to support plate 1 the first alar part 101 on;Then by sliding tube Busbar gold utensil is placed between two plate portions 2, and elongate holes 201, sliding tube busbar in a plate portion 2 are sequentially passed through using axis pin The elongate holes 201 on through-hole and another plate portion 2 on the otic placode of the both sides of gold utensil, and be respectively inserted in using two pins The both ends of axis pin.Wherein axis pin can slide in elongate holes 201, to which sliding tube busbar gold utensil is passed through two otic placodes and two A plate portion 2 opposite can be slidably connected.
Finally, the second mounting hole 1021 on middle part 102 for passing through support plate 1 using screw bolt and nut is by pipe busbar gold utensil Bracket is installed on support insulator.
As shown in figure 8, being fixed to pillar by pipe busbar gold utensil bracket for fixing pipe busbar gold utensil, sliding tube busbar gold utensil Schematic diagram on insulator.
Pipe busbar gold utensil bracket provided by the utility model, by the way that the first peace is arranged on the first alar part 101 of support plate 1 Hole 1011 is filled, convenient for fixing pipe busbar gold utensil to be fixed in support plate 1;By being arranged second on the middle part of support plate 1 102 Mounting hole 1021, convenient for support plate 1 to be installed on support insulator;By the way that edge is arranged on the second alar part 103 of support plate 1 The extending direction of support plate 1 and two plate portions 2 being oppositely arranged in parallel, and be arranged along the extension side of support plate 1 in plate portion 2 To the elongate holes 201 of extension, convenient for sliding tube busbar gold utensil and plate portion 2 opposite can be slidably connected.Therefore, the utility model The pipe busbar gold utensil bracket of offer can be fixed on support insulator, and can be fixedly connected with fixing pipe busbar gold utensil, and It opposite can be slidably connected with sliding tube busbar gold utensil, to make fixing pipe busbar gold utensil be fixed relative to support insulator, sliding Pipe busbar gold utensil can be slided relative to support insulator.
Wherein, the length of the extending direction along support plate 1 of the elongate holes 201 in plate portion 2 may be designed as 500mm, protect The sliding scale for demonstrate,proving sliding tube busbar gold utensil is ± 250mm, horizontal to make pipe busbar gold utensil bracket satisfaction provide fortification against earthquakes It needs.But the utility model is without being limited thereto, and the length of the extending direction along support plate 1 of the elongate holes 201 in plate portion 2 also may be used Different from 500mm.
In order to make pipe busbar gold utensil bracket be connected firmly with fixing pipe busbar gold utensil, as shown in Figure 1, the first mounting hole 1011 Quantity be four, four the first mounting holes 1011 are evenly spaced on the same circumference.In this way, being cooperated using four Duis Bolt and nut, pass through the mounting hole and first mounting hole on a fixing pipe busbar gold utensil per a pair of bolts and nut 1011 connect pipe bus bar fixing hardware with pipe busbar gold utensil bracket, it is ensured that the two is connected firmly.Wherein, the first mounting hole 1011 diameter can be 18mm, and four the first mounting holes 1011 can be evenly spaced on the circumference of the circle of a diameter of 225mm. But the utility model is without being limited thereto, and in other embodiments, the diameter of the first mounting hole 1011 may also differ from 18mm, four One mounting hole 1011 can also be distributed in diameter different from the circumference of the circle of 225mm.In addition, with the first mounting hole in the present embodiment 1011 quantity is four and is illustrated that in other embodiments, the quantity of the first mounting hole 1011 can be other.
In order to make pipe busbar gold utensil bracket be connected firmly with support insulator, as shown in Figure 1, the number of the second mounting hole 1021 Amount is four, and four the second mounting holes 1021 are evenly spaced on the same circumference.In this way, using four pairs of mutually matched spiral shells Bolt and nut, per a pair of bolts and nut is by the mounting hole on second mounting hole 1021 and support insulator, by pipe mother Line gold utensil bracket is connect with support insulator, it is ensured that the two is connected firmly.Wherein, the diameter of the second mounting hole 1021 can be 18mm, four the second mounting holes 1021 can be evenly spaced on the circumference of the circle of a diameter of 225mm.But the utility model is not It is limited to this, in other embodiments, the diameter of the second mounting hole 1021 may also differ from 18mm, four the second mounting holes 1021 Diameter can be distributed in different from the circumference of the circle of 225mm.In addition, with the quantity of the second mounting hole 1021 for four in the present embodiment A to be illustrated, in other embodiments, the quantity of the second mounting hole 1021 can be other.
As a kind of structure of support plate 1, as shown in Figs 1-4, the middle part 102 of support plate 1 forms recess.In order to reinforce branch Fagging 1, as shown in Fig. 2, being provided with straight gusset 3 in recess;Straight gusset 3 perpendicular to the bottom surface of recess, the lower wall of straight gusset 3 with it is recessed Sunken bottom surface connection, the two opposite sides of the opposite two side walls of straight gusset 3 respectively with recess connects, thus straight gusset 3 can play the role of reinforcing support plate 1.As shown in fig. 6, straight gusset 3 is rectangle, but the utility model is without being limited thereto, straight gusset 3 It is alternatively other shapes.
In order to further reinforce support plate 1, as shown in Fig. 2, pipe busbar gold utensil bracket further includes four diagonal bar plates 4, support First alar part 101 of plate 1 and two sides parallel with the extending direction of support plate 1 of the second alar part 103 respectively with it is adjacent The side of recess is at a right angle;As shown in fig. 7, diagonal bar plate 4 is right-angled trapezium, the straight waist and the first alar part 101 of diagonal bar plate 4 or One side of the second alar part 103 connects, the side connection of the longer bottom edge recess adjacent with the side of diagonal bar plate 4.Branch First alar part 101 of fagging 1 and each side parallel with the extending direction of support plate 1 of the second alar part 103 are separately connected one A diagonal bar plate 4 can play the role of reinforcing support plate 1.It should be noted that diagonal bar plate 4 or other shapes, such as right angle three It is angular, rectangle etc..
In order to mitigate the weight of pipe busbar gold utensil bracket, as shown in Figure 1, being offered on the first alar part 101 perforative up and down First through hole 1012.Specifically, as shown in Figure 1, the first alar part 101 opens up respectively in the part of the both sides of the first mounting hole 1011 There are one first through hole 1012.In order to maintain the first alar part 101 in the balance of center line both sides, first through hole 1012 is uniformly distributed In the center line both sides of support plate 1.
In order to further mitigate the weight of pipe busbar gold utensil bracket and ensure the balance at 1 both ends of support plate, as shown in Figure 1, Perforative second through-hole 1031 up and down is offered on second alar part 103 of support plate 1.Specifically, the second through-hole 1031 can be located at Between two plate portions 2, it is symmetrically distributed in the center line both sides of support plate 1.
Further, in order to make two alar parts of support plate 1 balance, the difference in quality of two alar parts of guarantee is little, two first The sum of area of through-hole 1012 is less than the area of the second through-hole 1031.In this way, the quality of the first alar part 101 is approximately equal to the second alar part 103 quality adds the quality sum of two plate portions 2, to can guarantee the both ends balance of support plate 1.
In embodiment provided herein, it should be understood that term " first ", " second " etc. are only used for description mesh , it is not understood to indicate or imply relative importance or implicitly indicates the quantity of indicated technical characteristic.
The above is merely for convenience of it will be understood by those skilled in the art that the technical solution of the utility model, not to Limit the utility model.Within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on, It should be included within the scope of protection of this utility model.

Claims (8)

1. a kind of pipe busbar gold utensil bracket, which is characterized in that including support plate (1), the support plate (1) is included in extending direction On the first alar part (101), middle part (102) and the second alar part (103) that are sequentially connected;
The first mounting hole (1011) for installing fixing pipe busbar gold utensil is provided on first alar part (101);
The second mounting hole (1021) for being connect with support insulator is provided on the middle part (102);
Second alar part (103) and parallel opposite along the extending direction is provided perpendicular on second alar part (103) Two plate portions (2) being arranged;
It is respectively arranged with the elongate holes (201) extended along the extending direction on two plate portions (2).
2. pipe busbar gold utensil bracket according to claim 1, which is characterized in that the quantity of first mounting hole (1011) To be multiple, multiple first mounting holes (1011) are evenly spaced on the same circumference.
3. pipe busbar gold utensil bracket according to claim 1, which is characterized in that the quantity of second mounting hole (1021) To be multiple, multiple second mounting holes (1021) are evenly spaced on the same circumference.
4. pipe busbar gold utensil bracket according to claim 1, which is characterized in that middle part (102) shape of the support plate (1) At recess, straight gusset (3) is provided in the recess;
The straight gusset (3) connects perpendicular to the bottom surface of the recess, the lower wall of the straight gusset (3) with the bottom surface of the recess It connects, the two opposite sides of the opposite two side walls of the straight gusset (3) respectively with the recess are connect.
5. pipe busbar gold utensil bracket according to claim 4, which is characterized in that further include four diagonal bar plates (4);
Two sides parallel with the extending direction of first alar part (101) and second alar part (103) respectively with The side of the adjacent recess is at a right angle;
The diagonal bar plate (4) is right-angled trapezium, and the straight waist of each diagonal bar plate (4) is connect with a side, longer The bottom edge recess adjacent with the side side connection.
6. pipe busbar gold utensil bracket according to claim 1, which is characterized in that offered on first alar part (101) Upper and lower perforative first through hole (1012).
7. pipe busbar gold utensil bracket according to claim 6, which is characterized in that offered on second alar part (103) Upper and lower perforative second through-hole (1031).
8. pipe busbar gold utensil bracket according to claim 7, which is characterized in that the area of the first through hole (1012) is small In the area of second through-hole (1031).
CN201721317316.9U 2017-10-13 2017-10-13 A kind of pipe busbar gold utensil bracket Active CN207625245U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721317316.9U CN207625245U (en) 2017-10-13 2017-10-13 A kind of pipe busbar gold utensil bracket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721317316.9U CN207625245U (en) 2017-10-13 2017-10-13 A kind of pipe busbar gold utensil bracket

Publications (1)

Publication Number Publication Date
CN207625245U true CN207625245U (en) 2018-07-17

Family

ID=62825863

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721317316.9U Active CN207625245U (en) 2017-10-13 2017-10-13 A kind of pipe busbar gold utensil bracket

Country Status (1)

Country Link
CN (1) CN207625245U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110042389A (en) * 2019-05-30 2019-07-23 中国长江电力股份有限公司 Heavy current aluminum bus fitting terminal surfaces laser melting coating silver layer technique

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110042389A (en) * 2019-05-30 2019-07-23 中国长江电力股份有限公司 Heavy current aluminum bus fitting terminal surfaces laser melting coating silver layer technique
CN110042389B (en) * 2019-05-30 2021-04-13 中国长江电力股份有限公司 Silver layer laser cladding process for large-current aluminum bus hardware terminal surface

Similar Documents

Publication Publication Date Title
ITMI940630A1 (en) INSTRUMENT CABINET
CN207625245U (en) A kind of pipe busbar gold utensil bracket
CN205566926U (en) Cloud calculated data center rack
CN207588402U (en) A kind of double sliding tube busbar gold utensil brackets
CN207459659U (en) Support device
CN209150670U (en) A kind of cable testing bridge
CN208638850U (en) Modified bus frame installs crossbeam and electric control cabinet
CN206041258U (en) Equipment distribution box
CN205646613U (en) Gas -insulated metal enclosed switchgear and GIS power station of using this equipment
CN208656175U (en) A kind of high-voltage board metering lifting cabinet
CN210273038U (en) Main transformer tube bus structure convenient to install
CN105909878A (en) Cable rack
CN211369613U (en) Edge protection device is faced to assembly type structure
CN207010178U (en) Female two T of pipe connect two split conductor gold utensils
RU139985U1 (en) TRAILER FOR FASTENING TWO CONSOLEES IN THE CIRCLE OF THE SUPPORT (OPTIONS)
CN201556854U (en) Cable distribution box of low-pressure cabinet
RU121206U1 (en) REINFORCED WIRING AREA ASSEMBLY ASSEMBLY ON TWO-CHAIN METAL SUPPORT
CN105449605B (en) High intensity bus bridge framework
CN208723497U (en) A kind of Multifunctional cable stand
US3311365A (en) Cable floor structure
CN215733336U (en) Adjustable bus duct mounting bracket
CN207203361U (en) A kind of right angle splicing apparatus
CN204852852U (en) Hanging mechanism and electronic display unit thereof
CN209730740U (en) A kind of safety and stability cell enclosed type bus duct
CN217975745U (en) Construction enclosure partition plate stable in supporting

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant