CN207620124U - A kind of connecting node of new increasing steel beam and former beams of concrete - Google Patents

A kind of connecting node of new increasing steel beam and former beams of concrete Download PDF

Info

Publication number
CN207620124U
CN207620124U CN201720639923.0U CN201720639923U CN207620124U CN 207620124 U CN207620124 U CN 207620124U CN 201720639923 U CN201720639923 U CN 201720639923U CN 207620124 U CN207620124 U CN 207620124U
Authority
CN
China
Prior art keywords
steel beam
concrete
beams
connector
profile steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720639923.0U
Other languages
Chinese (zh)
Inventor
金学菊
罗军
舒蓉
陈生林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Construction Research And Construction Engineering Co Ltd
GANSU PROVINCIAL ACADEMY OF BUILDING RESEARCH
Original Assignee
Gansu Construction Research And Construction Engineering Co Ltd
GANSU PROVINCIAL ACADEMY OF BUILDING RESEARCH
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Construction Research And Construction Engineering Co Ltd, GANSU PROVINCIAL ACADEMY OF BUILDING RESEARCH filed Critical Gansu Construction Research And Construction Engineering Co Ltd
Priority to CN201720639923.0U priority Critical patent/CN207620124U/en
Application granted granted Critical
Publication of CN207620124U publication Critical patent/CN207620124U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model is related to building field, the connecting node of specially a kind of new increasing steel beam and former beams of concrete;Solve the problems, such as that with former beams of concrete sliding easily occurs for new increasing steel beam existing in the prior art and connecting node stress is unsatisfactory for engine request;It includes:Beams of concrete, H profile steel beam, on beams of concrete fastening cage plate is fixed with by chemical anchor bolts, it is equipped with equally distributed card slot in fastening cage plate, card slot cooperates with the latch that connector is equipped with, sidesway occurs for the H profile steel beam for preventing connector and installing thereon, and floor is welded on the H profile steel beam of H profile steel beam Yu connector connecting pin, and reinforcing bar is tightened after passing through floor using double nut;Advantage is:The flexible connection for realizing new increasing steel beam and former beams of concrete, handles without following process, is capable of providing enough extensions and energy dissipation capacity, good seismic performance, while reducing influence of the temperature effect to girder steel stress.

Description

A kind of connecting node of new increasing steel beam and former beams of concrete
Technical field
The utility model is related to building engineering field, the connecting node of specially a kind of new increasing steel beam and former beams of concrete.
Background technology
In reinforcing engineering is transformed, the problem of owner requires to add elevator outside existing building is frequently encountered.To ensure The safety of elevator operation and necessary comfort level, surrounding newly-increased component (beam, column etc.) are made in elevator eccentric vibrating load Under, it is necessary to have enough stability and be reliably connected with original structure.Traditional connection method is new increasing steel beam and original structure It is attached using bar planting and welding hybrid mode.Using the connection method of bar planting and welding hybrid mode, need to be cut in original beam The upper limb or lower edge in face are implanted into more bolt (or reinforcing bar), so that bar planting reinforcing bar is located at the tensile region of beam, easily make Bar planting band glue slides with concrete, and bar planting reinforcing bar generates bond-anchorage and destroys.In addition, newly-increased steel structure lift shaft with both After thering is building to be connected common stress so that original concrete component stress increases, and is frequently encountered former member stress not Meet the requirements the case where need to being reinforced.
It is mixed mounted in reinforcing bar application No. is the reinforced column of 201320407967.2 designs and newly-increased steel beam connecting joint Cuff steel plate is attached by junction steel plate and new increasing steel beam on solidifying earth pillar, is also set between cuff steel plate and reinforced column There is structured packing gap filling between the two is closely knit and that the two is fixed together.It is found in constructing at the scene, reinforcing bar is mixed The main problem that solidifying earth pillar is connect with new increasing steel beam is that forced position is concentrated, and stability is poor, easily occurs between the two relatively sliding It moves or connection disconnects.And company is fixed only with junction steel plate in the above-mentioned connecting node in reinforced column and new increasing steel beam It connects, the stress of junction steel plate is unsatisfactory for engineering demand.
Therefore a kind of connecting node of new increasing steel beam and former beams of concrete is devised, new increasing steel beam and former concrete are realized The flexible connection of beam handles without following process, is capable of providing enough extensions and energy dissipation capacity, good seismic performance, simultaneously Reduce influence of the temperature effect to girder steel stress.
Utility model content
The utility model provides the connecting node of a kind of new increasing steel beam and former beams of concrete, the existing skill of effective solution The problem of new increasing steel beam present in art easily occurs to slide with former beams of concrete and connecting node stress is unsatisfactory for engineering demand, leads to The flexible connection mode using connector is crossed, can meet engineering force request without subsequent reinforcement, it is stable newly-increased to reach raising The purpose of the stability of girder steel.
To achieve the above object, the technical solution adopted in the utility model is specific as follows:
A kind of connecting node of new increasing steel beam and former beams of concrete, including:Beams of concrete 1 can be fixed on beams of concrete 1 H profile steel beam 4, it is characterised in that:It is fixed there are two cage plate 2 is fastened, in adapter sleeve by chemical anchor bolts 3 on beams of concrete 1 The face that plate 2 is used to install H profile steel beam 4 is equipped with equally distributed card slot 201, the latch that card slot 201 is equipped with connector 5 501 cooperate, and sidesway occurs for the H profile steel beam 4 for preventing connector 5 and installing thereon;In H profile steel beam 4 and 5 connecting pin of connector H profile steel beam 4 on be welded with floor 6, reinforcing bar 7 passed through floor 6 to be tightened using double nut 8.
Two sides is mounted on connector 5 before and after beams of concrete 1 installs H profile steel beam 4 so that 7 other end of reinforcing bar stretches out It is tightened using double nut after preformed hole on connector 5.
The preformed hole 504 being equipped on floor 6 and on connector 5 is slotted eye, is allowed in vertical uniform load q It is lower to generate certain deformation.
100~150mm deformation joints are reserved between the connector 5 and beams of concrete 1.
The beneficial effects of the utility model are:The design uses the flexible connection mode of connector, has the following advantages:One It is to reduce to increase influence of the steel construction to original concrete component stress newly, original concrete component is not required to carry out consolidation process;Two It is using bar planting and welding Hybrid connections node, under geological process, failure mechanism and reliability are indefinite, are providing fortification against earthquakes It should be used with caution in the case of grade is higher, and use this flexible connection, under geological process, be capable of providing enough ductility and energy consumption energy Power, good seismic performance;Third, using bar planting and welding Hybrid connections node, temperature action makes girder steel generate larger internal force, It is unfavorable to girder steel stress.And this flexible connection is used, allow junction to have certain horizontal and vertical deformation, temperature work can be reduced With the influence to girder steel stress;Fourth, bilateral connector mixes stress, installation is simple, easy for construction, safe and reliable, effect is aobvious It writes, there is larger popularizing value.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is enlarged drawing at Figure 1A;
Fig. 3 is the right view of the utility model;
Fig. 4 is enlarged drawing at Fig. 3 B;
Fig. 5 is the utility model adapter sleeve plate structure schematic diagram;
Fig. 6 is the utility model connecting-piece structure schematic diagram;
As shown in the figure:Beams of concrete 1, fastening cage plate 2, card slot 201, chemical anchor bolts 3, H profile steel beam 4, connector 5, latch 501, fastening cage plate installing zone 502, steel girder erection area 503, preformed hole 504, floor 6, reinforcing bar 7, double nut 8.
Specific implementation mode
Below in conjunction with the accompanying drawings and pass through specific embodiment further instruction the technical solution of the utility model:
Embodiment 1
The connecting node of a kind of new increasing steel beam as shown in figures 1 and 3 and former beams of concrete, by fastening cage plate 2, chemical anchors Bolt 3, connector 5, floor 6, reinforcing bar 7 and bolt nut 8 form, by the mutual cooperation and the use that fasten cage plate 2 and connector 5 The mounting means of flexible connection so that new increasing steel beam and the sufficiently stable reliable connection of beams of concrete.
One H profile steel beam 4 of installation needs two fastening cage plates 2, fastening cage plate 2 to be fixed on concrete by chemical anchor bolts 3 On beam 1, chemical anchor bolts are by special chemical bonding agent, by spiral shell by the high intensity anchor bolt of raw material based on vinylite Bar is cementing to be fixed in the drilling of concrete base material, to realize the composite members anchored to fixing piece, its advantage is that clipping room with back gauge away from wanting Ask smaller, it is quick for installation, it can cure rapidly.Chemical anchor bolts 3 there are two being respectively mounted on each face of fastening cage plate 2, such as Fig. 5 institutes Show.
It is equipped with 201 structure of card slot on fastening 2 mounting surface of cage plate, as shown in Figure 5.Simultaneously cage plate peace is fastened in connector 5 Dress area 502 is equipped with can effectively prevent H-type after installation with 201 mutually matched latch of card slot, 501 structure, the two intermeshing Relative to beams of concrete 1 transverse shakiness occurs for girder steel 4.
5 both ends of connector are passed through in the fixation of chemical anchor bolts 3 and beams of concrete 1 so that the cage plate installing zone on connector 5 502 are connected on fastening cage plate 2, and since fastening cage plate 2 is fixed on beams of concrete 1, which can effectively prevent from pacifying H profile steel beam 4 occurs to slide vertically relative to beams of concrete 1 after dress.
After 5 both ends of connector are by the fixation of chemical anchor bolts 3 and beams of concrete 1, between connector 5 and beams of concrete 1 Reserved 100~150mm deformation joints, the purpose of the deformation joint are that junction is allowed to have certain horizontal and vertical deformation, can be reduced Influence of the temperature action to girder steel stress.
H profile steel beam 4 is by being fixed on 503 position of steel girder erection area of connector 5 through the reinforcing bar 7 of beams of concrete 1.In H The installation end face of section steel beam 4 is welded with floor 6, and reinforcing bar 7 passes through floor 6, and the both ends of reinforcing bar 7 are fixed by double nut 8.It is reserved Hole 504 is slotted eye, and permission generates certain deformation under vertical uniform load q.
Specific practice is:It will fasten on cage plate fixation and beams of concrete first, while bar construction is installed by drilling, by Connector is fixed with after specific position, installs H profile steel beam, double nut is used in combination to tighten.
It is obvious to a person skilled in the art that the present invention is not limited to the details of the above exemplary embodiments, and And without departing substantially from the spirit or essential attributes of the utility model, it can realize that this practicality is new in other specific forms Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this practicality is new The range of type is indicated by the appended claims rather than the foregoing description, it is intended that containing in the equivalent requirements of the claims will be fallen All changes in justice and range are embraced therein.Any reference numeral in claim should not be considered as limitation Involved claim.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiment being appreciated that.

Claims (4)

1. the connecting node of a kind of new increasing steel beam and former beams of concrete, including:Beams of concrete (1) can be fixed on beams of concrete (1) On H profile steel beam (4), it is characterised in that:By chemical anchor bolts (3) fixation, there are two fasten cage plate on beams of concrete (1) (2), equally distributed card slot (201), card slot are equipped on the mounting surface that fastening cage plate (2) is used to install H profile steel beam (4) (201) latch (501) being equipped with connector (5) cooperates, the H profile steel beam (4) for preventing connector (5) and installing thereon Sidesway occurs;Floor (6) is welded on the H profile steel beam (4) of H profile steel beam (4) Yu connector (5) connecting pin, reinforcing bar (7) passes through Rear use double nut (8) on floor (6) and connector (5) is tightened.
2. the connecting node of a kind of new increasing steel beam according to claim 1 and former beams of concrete, it is characterised in that:In coagulation The front and back two sides of Tu Liang (1) installation H profile steel beams (4) is mounted on connector (5) so that reinforcing bar (7) other end stretches out another It is tightened using double nut (8) after preformed hole on connector (5).
3. the connecting node of a kind of new increasing steel beam according to claim 1 and former beams of concrete, it is characterised in that:It is described The preformed hole (504) that connector (5) is equipped with is slotted eye, and permission generates certain deformation under vertical uniform load q.
4. the connecting node of a kind of new increasing steel beam according to claim 1 and former beams of concrete, it is characterised in that:The company 100~150mm deformation joints are reserved between fitting (5) and beams of concrete (1).
CN201720639923.0U 2017-06-05 2017-06-05 A kind of connecting node of new increasing steel beam and former beams of concrete Expired - Fee Related CN207620124U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720639923.0U CN207620124U (en) 2017-06-05 2017-06-05 A kind of connecting node of new increasing steel beam and former beams of concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720639923.0U CN207620124U (en) 2017-06-05 2017-06-05 A kind of connecting node of new increasing steel beam and former beams of concrete

Publications (1)

Publication Number Publication Date
CN207620124U true CN207620124U (en) 2018-07-17

Family

ID=62817437

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720639923.0U Expired - Fee Related CN207620124U (en) 2017-06-05 2017-06-05 A kind of connecting node of new increasing steel beam and former beams of concrete

Country Status (1)

Country Link
CN (1) CN207620124U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113323135A (en) * 2021-06-01 2021-08-31 台州学院 Assembly type steel pipe column and concrete beam connecting component
CN113550622A (en) * 2021-08-13 2021-10-26 中冶天工集团有限公司 Rear connecting device and method for solid-web steel beam and concrete beam
CN113756450A (en) * 2021-09-13 2021-12-07 湖北建科结构加固有限责任公司 Beam column node steel staple bolt reinforced structure
CN114458043A (en) * 2022-02-24 2022-05-10 山东建筑大学 Connecting structure of newly-added steel beam and existing concrete column and construction method thereof
CN114658166A (en) * 2022-04-02 2022-06-24 东南大学建筑设计研究院有限公司 Clamping plate type lockable sliding node suitable for laminated open-web truss
CN115324221A (en) * 2022-08-08 2022-11-11 中国建筑第八工程局有限公司 Rear damper connecting piece based on reinforced concrete column and mounting method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113323135A (en) * 2021-06-01 2021-08-31 台州学院 Assembly type steel pipe column and concrete beam connecting component
CN113550622A (en) * 2021-08-13 2021-10-26 中冶天工集团有限公司 Rear connecting device and method for solid-web steel beam and concrete beam
CN113756450A (en) * 2021-09-13 2021-12-07 湖北建科结构加固有限责任公司 Beam column node steel staple bolt reinforced structure
CN114458043A (en) * 2022-02-24 2022-05-10 山东建筑大学 Connecting structure of newly-added steel beam and existing concrete column and construction method thereof
CN114658166A (en) * 2022-04-02 2022-06-24 东南大学建筑设计研究院有限公司 Clamping plate type lockable sliding node suitable for laminated open-web truss
CN114658166B (en) * 2022-04-02 2023-11-17 东南大学建筑设计研究院有限公司 Clamping plate type lockable sliding node suitable for laminated hollow truss
CN115324221A (en) * 2022-08-08 2022-11-11 中国建筑第八工程局有限公司 Rear damper connecting piece based on reinforced concrete column and mounting method thereof

Similar Documents

Publication Publication Date Title
CN207620124U (en) A kind of connecting node of new increasing steel beam and former beams of concrete
CN206815666U (en) A kind of connecting node of multilayer wallboard and wallboard and floor
KR101995496B1 (en) the rigid connection structure between the upper precast concrete column and the lower precast concrete column and the rigid connection structure of the precast concrete girder using the same
CN107338864A (en) A kind of prefabricated reinforced concrete frame structure node
CN106088348A (en) A kind of precast concrete method of attachment
JP6788981B2 (en) Joining structure of steel members
CN108265855A (en) Reinforced concrete shear wall and its frame with anchor steel Shear Strengthening
CN205617578U (en) Fossil fragments embedding slot for building
CN104746893B (en) Connecting method for newly added steel beam and existing steel reinforced concrete beam
CN207003672U (en) A kind of connecting node of precast beam and prefabricated panel
CN207003673U (en) A kind of connecting node of beam and wallboard
CN103334580B (en) Section steel tripod in a kind of overhanging scaffold and connection system for guide rail
CN108691358A (en) A kind of combination anchor slab, anti-buckling support connecting node and its installation method
CN106836632A (en) A kind of attachment structure of multilayer wallboard and beam, floor and prefabricated panel
CN109869011A (en) A kind of assembled wall body construction reinforcement by connection device
JP4081602B2 (en) Joint structure of steel-concrete composite structure and reinforced concrete structure
CN206815580U (en) A kind of wallboard installs node
CN110185219A (en) A kind of decoration integrated system of architectural exterior insulation
CN109322388A (en) A kind of assembled beam-column node structure positioned at plastic zone energy dissipation
CN115233833A (en) Sleeve connection structure is exempted from to assembled shear force wall
CN108086481A (en) A kind of metro depot upper cover Estate Development Self-resetting integral structure and method
CN204826679U (en) A anchor that is used for prefabricated superimposed sheet of anchor and prefabricated component
CN208329267U (en) A kind of wall body structure
CN107419852A (en) House prefabricated plate beam column built from concrete sleeve grouting string muscle anchoring assembling constructing method
CN202248529U (en) Steel plate concrete shear wall connecting beam bestrewed with toggle pins

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180717

Termination date: 20200605

CF01 Termination of patent right due to non-payment of annual fee