CN207597892U - A kind of wallboard assists fitting machine - Google Patents
A kind of wallboard assists fitting machine Download PDFInfo
- Publication number
- CN207597892U CN207597892U CN201721691916.1U CN201721691916U CN207597892U CN 207597892 U CN207597892 U CN 207597892U CN 201721691916 U CN201721691916 U CN 201721691916U CN 207597892 U CN207597892 U CN 207597892U
- Authority
- CN
- China
- Prior art keywords
- clamping plate
- main frame
- wallboard
- fitting machine
- rotation clamping
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a kind of wallboards to assist fitting machine, include main frame, support arm is equipped on the left of main frame front end, the support arm other end is flexibly connected through rotary pin shaft with rotation clamping plate, jack is equipped in main frame, the lift side of jack is connect with clamping plate, and clamping plate is located at the front end outer side of main frame, and main back-up roller wheel is equipped in main frame and rotation clamping plate bottom.When the main frame of the utility model is concordant with rotation clamping plate, 1 space is formed between the two, facilitates being caught in for wallboard, it is protruding by the effect clamping plate of jack, surfaces of wall is resisted, so that wallboard keeps vertical plumbness, so as to facilitate the installation of wallboard.Catch bar is pushed home into so that clamping bayonet lock resists rotary pin shaft, so that rotating clamp board status remains unchanged, guarantee wallboard is in clamped condition.Fitting machine is assisted by the wallboard, the installation effectiveness of wallboard can be improved, only needs 2 people can the light installation wall batten in scene.
Description
Technical field
The utility model is related to a kind of wallboards to assist fitting machine, belongs to construction wall technical field of construction equipment.
Background technology
Over time, many old buildings are overthrown covers again.And building can use in construction process to brick, with
Preceding solid brick uses clay to fire, and with the exhausted social progress of resource, people have invented aerating coagulation again
Cob brick.But existing air entrained concrete brick still has the shortcomings that various.It is built for this purpose, my company develops a kind of utilize
Building refuse and trade waste are as concrete panel made of raw material.The concrete panel is produced due to haveing excellent performance
Can amplify its size in the process, thickness always in the case of, 1 block concrete wallboard area is the 25 of 1 piece of air entrained concrete brick
Times.Since its structure is different from the structure of existing brick, therefore piled up using traditional brick laying method unrealistic.By
It is larger in size, if using it is artificial remove remote pile up again can be cumbersome, and efficiency is than relatively low, for this reason, it may be necessary to develop it is a kind of newly
Equipment coordinate the installation of the concrete panel.
Invention content
The purpose of the utility model is to provide a kind of wallboards to assist fitting machine.When wallboard is transported to installation station, lead to
Vertical state can be remained, and be moved to need position to be mounted by wallboard fixation by crossing wallboard auxiliary fitting machine, facilitate wallboard
Splicing, so as to improve the installation speed of wallboard.
The technical solution of the utility model:A kind of wallboard assists fitting machine, includes main frame, is set on the left of main frame front end
There is support arm, the support arm other end is flexibly connected through rotary pin shaft with rotation clamping plate, and jack is equipped in main frame, jack
Lift side is connect with clamping plate, and clamping plate is located at the front end outer side of main frame, and main back-up roller is equipped in main frame and rotation clamping plate bottom
Wheel.
In aforementioned wallboard auxiliary fitting machine, a sliding slot, the axis of rotary pin shaft are equipped with the rotating clamp plate back plate
Body is passed through from the left side head end of sliding slot, and clamping bayonet lock has been caught in sliding slot, is clamped the right head end of bayonet lock with rod head end is pushed to connect, is pushed away
Another head end of lever is extend out to outside rotation clamping plate.
In aforementioned wallboard auxiliary fitting machine, 1 bayonet is equipped with the rotation clamping plate right plate, extend out to rotating clamp
Promotion club body outside plate is equipped with fixture block.
In aforementioned wallboard auxiliary fitting machine, two head end of back of the main frame and rotation clamping plate is respectively revolved through 1 stent
It ships and resell on another market and is connect with 1 supporting rack, supporting rack bottom is equipped with back-up roller wheel.
In aforementioned wallboard auxiliary fitting machine, handle is equipped at the top of the main frame and rotation clamping plate.
The beneficial effects of the utility model:Compared with prior art, the main frame of the utility model is concordant with rotation clamping plate
When, 1 space is formed between the two, facilitates being caught in for wallboard, it is protruding by the effect clamping plate of jack, resist wall
Plate surface, so that wallboard keeps vertical plumbness, so as to facilitate the installation of wallboard.Catch bar is pushed home into so that clamping
Bayonet lock resists rotary pin shaft, so that rotating clamp board status remains unchanged, ensures that wallboard is in clamped condition.Pass through the wallboard
Fitting machine is assisted, the installation effectiveness of wallboard can be improved, only needs 2 people can the light installation wall batten in scene.
Description of the drawings
Attached drawing 1 is the dimensional structure diagram of the utility model;
Attached drawing 2 is the overlooking the structure diagram of the utility model;
Attached drawing 3 is the structure diagram for rotating clamping plate;
Reference numeral:1- main frames, 2- support arms, 3- rotation clamping plates, 4- jack, 5- clamping plates, the main back-up roller wheels of 6-, 7-
Rotary pin shaft, 8- sliding slots, 9- clamping bayonet locks, 10- catch bars, 11- bayonets, 12- fixture blocks, 13- stent rotating dogs, 14- supporting racks,
15- back-up roller wheels, 16- handles.
Specific embodiment
The utility model is further described with reference to the accompanying drawings and examples, but is not intended as to the utility model
The foundation of limitation.
The embodiment of the utility model:A kind of wallboard assists fitting machine, as illustrated in the accompanying drawings from 1 to 3, includes main frame 1, main
Support arm 2 is equipped on the left of 1 front end of frame, 2 other end of support arm is flexibly connected through rotary pin shaft 7 with rotation clamping plate 3, main frame 1
Interior to be equipped with jack 4, the lift side of jack 4 is connect with clamping plate 5, and clamping plate 5 is located at the front end outer side of main frame 1, in main frame 1
Main back-up roller wheel 6 is equipped with 3 bottom of rotation clamping plate.
It waits when the utility model is used, rotation clamping plate 3 is rotated around rotary pin shaft 7 so that rotation clamping plate 3 and main frame 1
It is parallel, and keep the state.It rotates at this time and 1 card slot is formed between clamping plate 3 and main frame 1, transported by wallboard mounting machine
The wallboard come is inserted into card slot from top to bottom, then operates jack 4 by ratchet spanner so that clamping plate 5 is protruding, resists
Wallboard.So that wallboard is maintained at vertical plumbness, its inclination is avoided.Then wallboard auxiliary fitting machine movement wallboard is pushed to peace
Station is filled, is installed.After installation is complete, jack 4 is unclamped by ratchet spanner so that clamping plate 5 detaches i.e. with wallboard
It can.
A sliding slot 8 is equipped with rotation 3 back plate of clamping plate, the axle body of rotary pin shaft 7 is worn from the left side head end of sliding slot 8
It crosses, has been caught in sliding slot 8 and has clamped bayonet lock 9, clamp 9 right head end of bayonet lock and connect with 10 head end of catch bar, 10 another head end of catch bar
It extend out to outside rotation clamping plate 3.When the rotation rotation of clamping plate 3 is extremely parallel with main frame 1, catch bar 10 is inwardly pushed so that press from both sides
Tight bayonet lock 9 moves to the left along sliding slot 8, until resisting rotary pin shaft 7.At this time since rotary pin shaft 7 has been stuck, therefore revolve
Turning clamping plate 3 cannot rotate further around rotary pin shaft 7.During avoiding clamping wallboard, rotation clamping plate 3 is opened, and can not be clamped again
Firmly wallboard.
1 bayonet 11 is equipped with rotation 3 right plate of clamping plate, 10 bar of catch bar extending out to outside rotation clamping plate 3
It is equipped with fixture block 12 with it.After rotary pin shaft 7 is stuck, rotation catch bar 10 causes fixture block 12 to be thereon caught in bayonet 11,
It can ensure that rotating clamping plate 3 keeps constant with the parastate of main frame 1.
Two head end of back of the main frame 1 and rotation clamping plate 3 respectively connects through 1 stent rotating dog 13 and 1 supporting rack 14
It connects, 14 bottom of supporting rack is equipped with back-up roller wheel 15.Since the height of wallboard is very high, there is that story height is so high, in order to avoid
Wallboard, which may be found that, topples over, therefore is provided with supporting rack 14, which can rotate around stent rotating dog 13 opens, so as to fulfill
Supporting role well.When not needing to the use of time, it can be rotated around rotating dog 13 and collapse.
The main frame 1 and 3 top of rotation clamping plate are equipped with handle 16.Worker holds handle 16 and is convenient to operation the wallboard
Assist fitting machine.
Claims (5)
1. a kind of wallboard assists fitting machine, it is characterised in that:Include main frame(1), main frame(1)Support is equipped on the left of front end
Arm(2), support arm(2)The other end is through rotary pin shaft(7)With rotating clamping plate(3)Flexible connection, main frame(1)It is interior to be equipped with jack
(4), jack(4)Lift side and clamping plate(5)Connection, clamping plate(5)Positioned at main frame(1)Front end outer side, in main frame(1)
With rotation clamping plate(3)Bottom is equipped with main back-up roller wheel(6).
2. wallboard according to claim 1 assists fitting machine, it is characterised in that:The rotation clamping plate(3)With back plate
Equipped with a sliding slot(8), rotary pin shaft(7)Axle body from sliding slot(8)Left side head end pass through, sliding slot(8)In be caught in clamping card
Pin(9), clamp bayonet lock(9)Right head end and catch bar(10)Head end connects, catch bar(10)Another head end extend out to rotation clamping plate
(3)It is external.
3. wallboard according to claim 2 assists fitting machine, it is characterised in that:The rotation clamping plate(3)With right plate
Equipped with 1 bayonet(11), it extend out to rotation clamping plate(3)External catch bar(10)Shaft is equipped with fixture block(12).
4. wallboard according to claim 1 assists fitting machine, it is characterised in that:The main frame(1)With rotation clamping plate(3)
Two head end of back respectively through 1 stent rotating dog(13)With 1 supporting rack(14)Connection, supporting rack(14)Bottom is equipped with back-up roller
Wheel(15).
5. wallboard according to claim 1 assists fitting machine, it is characterised in that:The main frame(1)With rotation clamping plate(3)
Top is equipped with handle(16).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721691916.1U CN207597892U (en) | 2017-12-07 | 2017-12-07 | A kind of wallboard assists fitting machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721691916.1U CN207597892U (en) | 2017-12-07 | 2017-12-07 | A kind of wallboard assists fitting machine |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207597892U true CN207597892U (en) | 2018-07-10 |
Family
ID=62764682
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721691916.1U Active CN207597892U (en) | 2017-12-07 | 2017-12-07 | A kind of wallboard assists fitting machine |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207597892U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110318548A (en) * | 2019-06-24 | 2019-10-11 | 天元建设集团有限公司 | A kind of assembled wall mounting bracket and its construction method |
CN110499922A (en) * | 2019-08-28 | 2019-11-26 | 广东博智林机器人有限公司 | A kind of wallboard installation equipment |
-
2017
- 2017-12-07 CN CN201721691916.1U patent/CN207597892U/en active Active
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110318548A (en) * | 2019-06-24 | 2019-10-11 | 天元建设集团有限公司 | A kind of assembled wall mounting bracket and its construction method |
CN110318548B (en) * | 2019-06-24 | 2023-08-22 | 天元建设集团有限公司 | Assembled wall mounting bracket and construction method thereof |
CN110499922A (en) * | 2019-08-28 | 2019-11-26 | 广东博智林机器人有限公司 | A kind of wallboard installation equipment |
CN110499922B (en) * | 2019-08-28 | 2022-03-18 | 广东博智林机器人有限公司 | Wallboard mounting equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207597892U (en) | A kind of wallboard assists fitting machine | |
CN207844900U (en) | A kind of tower crane monitoring camera mounting device | |
CN203613792U (en) | Parapet wall formwork pouring structure | |
CN203317535U (en) | Full automatic production line for composition insulation boards of walls | |
CN107089493A (en) | A kind of sheet material transmits turning device | |
CN208792737U (en) | For hanging the detachable connecting part of external platform hanging girder steel | |
CN107939052A (en) | A kind of installation method of concrete panel | |
CN204645613U (en) | A kind of alter-pouring strips mould plate with tipping platform | |
CN208829116U (en) | The hanger structure of color steel plate | |
CN207749840U (en) | A kind of wallboard mounting machine | |
CN104495398A (en) | C-section steel receiving set | |
CN205224603U (en) | Strengthening construction device for door and window concrete arched lintel | |
CN204221945U (en) | Air entrained concrete slip is framed | |
CN204715738U (en) | A kind of corner for building template | |
CN209114651U (en) | A kind of obligatory point that can prevent wall crazing | |
CN207345885U (en) | A kind of raw material transportation equipment for being used to produce lightweight wall plate | |
CN209179482U (en) | A kind of anti-bank reinforcement tools of clean room concrete | |
CN203145202U (en) | Treatment structure for top clearance of filler wall brickwork | |
CN207314889U (en) | A kind of concrete surface film cladding system | |
CN206289802U (en) | The prefabricated built-in presstressed reinforcing steel steel reinforced concrete wall of formwork | |
CN205836874U (en) | A kind of novel architecture bricks conveyer | |
CN220667018U (en) | Construction prying tool for autoclaved sand aerated concrete light partition wall batten | |
CN205400222U (en) | Novel steel construction tower modelled after an antique | |
CN208777694U (en) | A kind of house construction engineering framed column template is reinforced and sealing device | |
CN211058255U (en) | Plastering device for cement mortar in constructional engineering |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20221215 Address after: 550399 4th Floor, Building 1, Standard Plant, Kaiyang Economic and Technological Development Zone, Xicheng Sub district Office, Kaiyang County, Guiyang City, Guizhou Province Patentee after: Guizhou Haobainian New Material Technology Co.,Ltd. Address before: 550009 Xiaomeng Industrial Park, Kaifa Avenue, wengyan village, economic and Technological Development Zone, Guiyang City, Guizhou Province Patentee before: GUIZHOU HAOBAINIAN RESIDENTIAL INDUSTRY CO.,LTD. |
|