CN207597395U - The foundation pit enclosure structure system of steel pipe and the compound diagonal brace combination campshed of PHC pile piles - Google Patents

The foundation pit enclosure structure system of steel pipe and the compound diagonal brace combination campshed of PHC pile piles Download PDF

Info

Publication number
CN207597395U
CN207597395U CN201721357802.3U CN201721357802U CN207597395U CN 207597395 U CN207597395 U CN 207597395U CN 201721357802 U CN201721357802 U CN 201721357802U CN 207597395 U CN207597395 U CN 207597395U
Authority
CN
China
Prior art keywords
steel pipe
pile
campshed
piles
foundation pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721357802.3U
Other languages
Chinese (zh)
Inventor
何健
张云达
朱火根
费纬
王亦玄
廖志坚
蔡剑韬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Geo Geological Research Institute Co Ltd
SHANGHAI MINE ENGINEERING INSPECTION Co Ltd
SHANGHAI GEOLOGICAL CONSTRUCTION CO Ltd
Original Assignee
Shanghai Geo Geological Research Institute Co Ltd
SHANGHAI MINE ENGINEERING INSPECTION Co Ltd
SHANGHAI GEOLOGICAL CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Geo Geological Research Institute Co Ltd, SHANGHAI MINE ENGINEERING INSPECTION Co Ltd, SHANGHAI GEOLOGICAL CONSTRUCTION CO Ltd filed Critical Shanghai Geo Geological Research Institute Co Ltd
Priority to CN201721357802.3U priority Critical patent/CN207597395U/en
Application granted granted Critical
Publication of CN207597395U publication Critical patent/CN207597395U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model is related to a kind of steel pipes and the foundation pit enclosure structure system of the compound diagonal brace combination campshed of PHC pile piles, the foundation pit enclosure structure system includes campshed building enclosure (5), rotary churning pile (3), jet grouting enlarged footing (4), PHC pile piles (2) and steel pipe (1), the top of campshed building enclosure (5) is equipped with Guan Liang (6), rotary churning pile (3) is angularly disposed on the inside of campshed building enclosure (5), the bottom end of steel pipe (1) is connect with the top of PHC pile piles (2), and inside connection, the top of steel pipe (1) is connect with Guan Liang (6), steel pipe (1) and PHC pile piles (2) are inserted into rotary churning pile (3), and slip casting obturator is equipped in steel pipe (1) and PHC pile piles (2).Compared with prior art, the utility model can save the foundation pit in the range of certain depth horizontally-supported, reduce construction cost, shorten the construction period.

Description

The foundation pit enclosure structure system of steel pipe and the compound diagonal brace combination campshed of PHC pile piles
Technical field
The utility model belongs to foundation pit enclosure technical field, more particularly, to a kind of steel pipe and the compound diagonal brace of PHC pile piles With reference to the foundation pit enclosure structure system of campshed.
Background technology
At present, the domestic especially research of Soft Deep Foundation Pit engineering has the experience of many decades, engineering with practical work Usually there are many dig that deep and local environmental conditions to go along with sb. to guard him form available for different in practice.
For digging deeply in the foundation pit within 6m, cement-soil wall, soil nail wall, row generally can be used at present The diversified forms such as stake (with reference to inner support or soil bolt), gantry type double cantilever piles.Wherein, for the foundation pit within 6m, weight It goes along with sb. to guard him form and is most widely used in power dam.
In addition, surrounding enviroment especially basement red line moves back the important factor in order that boundary is base pit engineering.Basement red line It moves back boundary and refers to build outer wall of underground structure to the distance of land red-line, according to the rules, the foundation pit enclosure structure as temporary structure Land red-line must not be exceeded, i.e. building enclosure can utilize range of the space between basement and red line.Yangtze River Delta Area in recent years Especially for the real estate project of District of Shanghai generally using basement is completely spread, boundary is moved back very in the partially or fully region of many engineerings Small, the prior art is extremely difficult to require or to reach cost needed for requirement very high.
Invention content
The purpose of this utility model be exactly in order to overcome the problems of the above-mentioned prior art and provide a kind of steel pipe with The foundation pit enclosure structure system of the compound diagonal brace combination campshed of PHC pile piles.
The purpose of this utility model can be achieved through the following technical solutions:
A kind of steel pipe and the foundation pit enclosure structure system of the compound diagonal brace combination campshed of PHC pile piles, knot is gone along with sb. to guard him including campshed Structure, the top of the campshed building enclosure are equipped with Guan Liang, further include rotary churning pile, PHC pile piles and steel pipe, the rotary churning pile is oblique To being arranged on the inside of campshed building enclosure, the bottom end of steel pipe is connect with the top of PHC pile piles, and internal connection, the top of steel pipe End is connect with Guan Liang, and steel pipe and PHC pile piles are inserted into rotary churning pile, and slip casting obturator is equipped in steel pipe and PHC pile piles.
Preferably, the bottom end point of the rotary churning pile is equipped with enlarged footing.
Preferably, cement mortar or pea gravel concreten in the slip casting obturator.
Preferably, the campshed building enclosure is made of campshed, and the campshed is made of water-stop curtain and soil blocking pile, The water-stop curtain includes two axis mixing piles, three axes agitating pile, five axis mixing piles, six axis mixing piles or rotary churning pile;Described Soil blocking pile includes double pile soil-baffling structure of Single row pillars composition of cast-in-situ bored pile, shaped steel or precast concrete pile composition etc..
Preferably, the top of the steel pipe and Guan Liang anchor connection.
Preferably, the bottom end of the steel pipe and the top of PHC pile piles pass through electric welding connection.
The steel pipe and the application of the foundation pit enclosure structure system of the compound diagonal brace combination campshed of PHC pile piles, are answered For the construction of underground structure, include the following steps:
S1:For underground structure foundation pit, boundary's requirement is moved back according to basement, carry out campshed building enclosure and angularly disposed is being arranged The construction of rotary churning pile on the inside of stake building enclosure, should carry out preexisting hole before jet grouting pile construction;
S2:By the bottom end of steel pipe and the top electric welding connection of PHC pile piles;
S3:Steel pipe and PHC pile piles are inserted into rotary churning pile;
S4:Cement mortar or pea gravel concreten are injected into steel pipe and PHC pile piles by grouting equipment;
S5:By steel pipe top and the bar connecting of Guan Liang that is arranged at the top of campshed building enclosure, and casting concrete, into Foundation pit enclosure structure system of the steel pipe with the compound diagonal brace combination campshed of PHC pile piles is formed after type;
S6:Rotary churning pile outside steel pipe more than excavation face and steel pipe are removed;
S7:The excavation of foundation pit is carried out, the reinforced bed of steel pipe, steel pipe and arrangement of reinforcement are arranged through on the inside of campshed building enclosure Bed course bar connecting;
S8:The construction of basement structure is carried out, in work progress, the exterior wall of basement structure is made to pass through steel pipe.
Preferably, in step S3, before rotary churning pile consolidation molding, steel pipe and PHC pile piles are inserted into rotary churning pile;Step S4 In, before Guan Liang construction, the cement mortar of microdilatancy or microlith coagulation are injected into steel pipe and PHC pile piles by grouting equipment Soil.
Preferably, the bottom end of the steel pipe is located at 0.5~2m below reinforced bed.
The utility model moves back the small situation in boundary for engine request, proposes a kind of novel retaining design --- a kind of steel pipe With the foundation pit enclosure structure system of the compound diagonal brace combination campshed of PHC pile piles.The retaining design of the utility model can be used for underground The smaller base pit engineerings of Shi Tui circle due to not using large area inner support, can excavate specified regional earthwork in batches.
Compared with prior art, the utility model has the advantages that:Technical side involved by the utility model Case provides a kind of method for substituting one of horizontally-supported structural protective system.By adding in pile pile diagonal brace in hole, save Foundation pit horizontal support structure, facilitates excavation construction.In addition, by high-pressure rotary jet grouting pile and enlarged footing, branch is formed in limited range The stronger structure of support ability effectively limits the deformation of pile pile support, improves the stability of building enclosure.The utility model Supporting top, bending strength is high, more safe and reliable to retaining design using steel pipe;Simultaneously be conducive to underground structure bottom plate and The waterproof construction of exterior wall.
Description of the drawings
Fig. 1 is the schematic diagram before excavation of foundation pit in embodiment 1;
Fig. 2 is the schematic diagram after excavation of foundation pit in embodiment 1;
Fig. 3 is the cross-sectional view of PHC pile piles.
In figure, 1 is steel pipe, and 2 be PHC pile piles, and 3 be rotary churning pile, and 4 be enlarged footing, and 5 be campshed building enclosure, and 6 be Guan Liang, 7 It is reinforced bed for the soil body, 8.
Specific embodiment
The utility model is described in detail in the following with reference to the drawings and specific embodiments.
Embodiment 1
A kind of foundation pit enclosure structure system of steel pipe and the compound diagonal brace combination campshed of PHC pile piles, as shown in Figure 1, including Campshed building enclosure 5, rotary churning pile 3, PHC pile piles 2 and steel pipe 1, the top of campshed building enclosure 5 are equipped with Guan Liang 6, and rotary churning pile 3 is oblique 5 inside of campshed building enclosure is arranged on to (being tilted from 5 top of campshed building enclosure to its inside), bottom end and the PHC of steel pipe 1 are managed The top connection of stake 2, and internal connection, the top of steel pipe 1 are connect with Guan Liang 6, and steel pipe 1 and PHC pile piles 2 are inserted into rotary churning pile 3 In, and slip casting obturator is equipped in steel pipe 1 and PHC pile piles 2.
In the present embodiment, campshed building enclosure 5 is made of water-stop curtain and soil blocking pile, and the water-stop curtain includes two axis Mixing pile, three axes agitating pile, five axis mixing piles, six axis mixing piles or rotary churning pile;The soil blocking pile includes cast-in-situ bored pile, type The single or double pile soil-baffling structure of steel or precast concrete pile composition.In order to increase the frictional resistance of rotary churning pile 3 and the soil body 7, revolve The bottom end point for spraying stake 3 is equipped with enlarged footing 4, and rotary churning pile and enlarged footing need higher intensity.Slip casting obturator (such as water Cement mortar) it can effectively enhance the intensity of steel pipe 1 and PHC pile piles 2, in order to further enhance intensity, slip casting obturator can be micro- The pea gravel concreten of expansion.In the present embodiment, top and 6 anchor connection of Guan Liang of steel pipe 1.The bottom end of steel pipe 1 and PHC pile piles 2 Top by electric welding connection, the cross section of rotary churning pile is as shown in Figure 3.
The steel pipe of the present embodiment can be applied to the foundation pit enclosure structure system of the compound diagonal brace combination campshed of PHC pile piles Basement moves back the smaller base pit engineering in boundary, is applied to the construction of basement structure, includes the following steps:
S1:For underground structure foundation pit, boundary's requirement is moved back according to basement, carry out campshed building enclosure 5 and it is angularly disposed The construction of the rotary churning pile 3 of 5 inside of campshed building enclosure, rotary churning pile 3 should carry out preexisting hole before constructing;
S2:By the bottom end of steel pipe 1 and the top electric welding connection of PHC pile piles 2;
S3:Steel pipe 1 and PHC pile piles 2 are inserted into rotary churning pile 3;
S4:Cement mortar or pea gravel concreten are injected into steel pipe 1 and PHC pile piles 2 by grouting equipment;
S5:By 1 top of steel pipe and the bar connecting for the Guan Liang 6 for being arranged on 5 top of campshed building enclosure, and pour coagulation Soil forms foundation pit enclosure structure system of the steel pipe with the compound diagonal brace combination campshed of PHC pile piles, as shown in Figure 1 after molding;
S6:Rotary churning pile 3 more than 1 outer excavation face of steel pipe is removed with steel pipe 1;
S7:Carry out the excavation of foundation pit, be arranged through the reinforced bed 8 of steel pipe 1 in the inside of campshed building enclosure 5, steel pipe 1 with 8 bar connecting of reinforced bed;As shown in Figure 2
S8:The construction of basement structure is carried out, in work progress, the exterior wall of basement structure is made to pass through steel pipe 1.
Wherein, in step S3, before 3 cement slurry initial set of rotary churning pile, steel pipe 1 and PHC pipes 2 are inserted into rotary churning pile 3; In step S4, before Guan Liang construction, pass through grouting equipment slip casting into steel pipe 1 and PHC pile piles 2.The bottom end of steel pipe 1 is located at and matches 8 0.5~2m of lower section of muscle bed course.
The above description of the embodiments is intended to facilitate ordinary skill in the art to understand and use the invention. Person skilled in the art obviously can easily make these embodiments various modifications, and described herein general Principle is applied in other embodiment without having to go through creative labor.Therefore, the utility model is not limited to the above embodiments, Those skilled in the art's announcement according to the present utility model, does not depart from improvement that the utility model scope made and modification all should This is within the protection scope of the utility model.

Claims (6)

1. a kind of foundation pit enclosure structure system of steel pipe and the compound diagonal brace combination campshed of PHC pile piles, including campshed building enclosure (5), the top of the campshed building enclosure (5) is equipped with Guan Liang (6), which is characterized in that further includes rotary churning pile (3), PHC pile piles (2) and steel pipe (1), the rotary churning pile (3) are angularly disposed in campshed building enclosure (5) inside, the bottom end of steel pipe (1) and PHC The top connection of pile pile (2), and internal connection, the top of steel pipe (1) are connect with Guan Liang (6), steel pipe (1) and PHC pile piles (2) It is inserted into rotary churning pile (3), and slip casting obturator is equipped in steel pipe (1) and PHC pile piles (2).
2. the foundation pit enclosure structure system of steel pipe according to claim 1 and the compound diagonal brace combination campshed of PHC pile piles, It is characterized in that, the bottom end point of the rotary churning pile (3) is equipped with enlarged footing (4).
3. the foundation pit enclosure structure system of steel pipe according to claim 1 and the compound diagonal brace combination campshed of PHC pile piles, It is characterized in that, the slip casting obturator is cement mortar or pea gravel concreten.
4. the foundation pit enclosure structure system of steel pipe according to claim 1 and the compound diagonal brace combination campshed of PHC pile piles, It is characterized in that, the campshed building enclosure (5) is made of water-stop curtain and soil blocking pile, and the water-stop curtain is stirred including two axis Mix stake, three axes agitating pile, five axis mixing piles, six axis mixing piles or rotary churning pile;The soil blocking pile includes cast-in-situ bored pile, shaped steel Or the single or double pile soil-baffling structure of precast concrete pile composition.
5. the foundation pit enclosure structure system of steel pipe according to claim 1 and the compound diagonal brace combination campshed of PHC pile piles, It is characterized in that, top and Guan Liang (6) anchor connection of the steel pipe (1).
6. the foundation pit enclosure structure system of steel pipe according to claim 1 and the compound diagonal brace combination campshed of PHC pile piles, It is characterized in that, the bottom end of the steel pipe (1) passes through electric welding connection with the top of PHC pile piles (2).
CN201721357802.3U 2017-10-20 2017-10-20 The foundation pit enclosure structure system of steel pipe and the compound diagonal brace combination campshed of PHC pile piles Active CN207597395U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721357802.3U CN207597395U (en) 2017-10-20 2017-10-20 The foundation pit enclosure structure system of steel pipe and the compound diagonal brace combination campshed of PHC pile piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721357802.3U CN207597395U (en) 2017-10-20 2017-10-20 The foundation pit enclosure structure system of steel pipe and the compound diagonal brace combination campshed of PHC pile piles

Publications (1)

Publication Number Publication Date
CN207597395U true CN207597395U (en) 2018-07-10

Family

ID=62756199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721357802.3U Active CN207597395U (en) 2017-10-20 2017-10-20 The foundation pit enclosure structure system of steel pipe and the compound diagonal brace combination campshed of PHC pile piles

Country Status (1)

Country Link
CN (1) CN207597395U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501772A (en) * 2020-04-10 2020-08-07 深圳市地质环境研究院有限公司 Construction method for supporting and protecting piles by combining grouting with steel pipes in SMW (soil mixing wall) construction method
CN112227384A (en) * 2020-10-29 2021-01-15 北京中岩大地科技股份有限公司 Construction method of resistance-increasing large-deformation enclosure structure
CN112267472A (en) * 2020-10-17 2021-01-26 江苏建院营造股份有限公司 Construction process for foundation pit support of inclined pile of advanced mixing pile
CN113322971A (en) * 2021-05-10 2021-08-31 广东省建筑设计研究院有限公司 Combined prefabricated dado square pile foundation pit supporting structure and construction method thereof
CN114197485A (en) * 2021-12-23 2022-03-18 上海勇创环境岩土工程有限公司 Construction process of inclined support pile for soft soil base enclosure

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111501772A (en) * 2020-04-10 2020-08-07 深圳市地质环境研究院有限公司 Construction method for supporting and protecting piles by combining grouting with steel pipes in SMW (soil mixing wall) construction method
CN112267472A (en) * 2020-10-17 2021-01-26 江苏建院营造股份有限公司 Construction process for foundation pit support of inclined pile of advanced mixing pile
CN112227384A (en) * 2020-10-29 2021-01-15 北京中岩大地科技股份有限公司 Construction method of resistance-increasing large-deformation enclosure structure
CN112227384B (en) * 2020-10-29 2022-06-21 北京中岩大地科技股份有限公司 Construction method of resistance-increasing large-deformation enclosure structure
CN113322971A (en) * 2021-05-10 2021-08-31 广东省建筑设计研究院有限公司 Combined prefabricated dado square pile foundation pit supporting structure and construction method thereof
CN114197485A (en) * 2021-12-23 2022-03-18 上海勇创环境岩土工程有限公司 Construction process of inclined support pile for soft soil base enclosure

Similar Documents

Publication Publication Date Title
CN207597395U (en) The foundation pit enclosure structure system of steel pipe and the compound diagonal brace combination campshed of PHC pile piles
CN206971232U (en) A kind of oblique inner support foundation pit enclosure structure of shaped steel cement earth pile
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN105951843A (en) Construction method of deep foundation pit
CN104775440A (en) Mineshaft-type underground garage deep foundation pit supporting structure
CN204590038U (en) A kind of permanent foundation pit supporting construction
CN202440823U (en) Supporting structure of pipe jacking pit
CN207646746U (en) A kind of arch interlocking pile formula foundation pit supporting construction
CN204825928U (en) Excavation supporting
CN109024609A (en) A kind of foundation pit supporting construction and its construction method based on old campshed
CN104846832A (en) Construction method of circular deep foundation pit enclosure of discrete pile support
CN102220764B (en) Construction method of deep foundation pit bracing system
CN207211158U (en) Assembled pile board wall foundation pit supporting construction
CN203768914U (en) Foundation pit bracing diagonal support pile structure
CN206220101U (en) A kind of support reinforcement structure of deep basal pit
CN108035360A (en) A kind of method for pattern foundation pit supporting structure
CN209443472U (en) A kind of supporting construction of double-row pile combination wide-angle anchor cable
CN106836230A (en) A kind of foundation ditch point hole construction method
CN106013168A (en) Slag trough structure and construction method for same
CN203625911U (en) Soil discharging construction structure with pit-in-pit door opening arranged in deep foundation pit
CN216515701U (en) Miniature stake raft board combination foundation structure
CN207062958U (en) A kind of deep basal pit complexity some support combining structure
CN106567382B (en) A kind of pit curtain construction method in metalling
CN213625605U (en) Dig deep basal pit structure of stake anchor and hanging net injection concrete soon
CN212896447U (en) Structure of manual hole digging cast-in-place pile foundation underpinning raft foundation