CN207596364U - A kind of sash weight winch structure on pile driving barge - Google Patents

A kind of sash weight winch structure on pile driving barge Download PDF

Info

Publication number
CN207596364U
CN207596364U CN201721614771.5U CN201721614771U CN207596364U CN 207596364 U CN207596364 U CN 207596364U CN 201721614771 U CN201721614771 U CN 201721614771U CN 207596364 U CN207596364 U CN 207596364U
Authority
CN
China
Prior art keywords
brake
roller
sash weight
ribbon
oil cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721614771.5U
Other languages
Chinese (zh)
Inventor
章庆生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Xiong Cheng Marine Engineering Ltd By Share Ltd
Original Assignee
Shanghai Xiong Cheng Marine Engineering Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Xiong Cheng Marine Engineering Ltd By Share Ltd filed Critical Shanghai Xiong Cheng Marine Engineering Ltd By Share Ltd
Priority to CN201721614771.5U priority Critical patent/CN207596364U/en
Application granted granted Critical
Publication of CN207596364U publication Critical patent/CN207596364U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)

Abstract

The utility model provides the sash weight winch structure on a kind of pile driving barge, sash weight winch includes stent and roller, roller is equipped with twisted rope, roller is driven by motor, the end of the roller is equipped with brake hub, the winch is equipped with main brake structure, further include auxiliary brake structure, auxiliary brake structure includes encoder, oil cylinder and brake ribbon, the encoder is connect with oil cylinder circuit, encoder is equipped with the detection structure for detecting drum rotation speed, brake ribbon is located at the excircle of brake hub, the cylinder body of the oil cylinder is fixed on stent, brake ribbon is hinged on stent, the piston rod of the oil cylinder is hinged with brake ribbon.The utility model is always maintained at certain resistance when pile monkey falls by auxiliary brake structure, when pile monkey whereabouts is too fast, a brake brake is carried out to brake hub, and then reduce the falling speed of pile monkey, played a protective role to pile monkey and pile frame.

Description

A kind of sash weight winch structure on pile driving barge
Technical field
The utility model is related to the sash weight winch structures in pile driving barge structure more particularly to a kind of pile driving barge.
Background technology
Pile driving barge is a kind of marine guidance piling equipment, what marine guidance piling was mainly completed by the pile frame on pile driving barge.
In piling, when seabed surface is normal geological condition, routinely piling work program does not have technical problem;But it meets To special geology, such as seabed surface, one layer is normal soil property, and is below soft soil property, when stake pass through normal soil property into When entering soft soil property, due to the hitting power of pile monkey and the effect of acceleration of gravity, stake can hurtle down, while drive pile monkey also fast Speed falls, this can lead to the generation for slipping hammer problem, i.e. pile monkey is fallen into water, is damaged when sash weight winch is hammered into shape because slipping, such as in this process In as by force start sash weight winch brake, then may lead to the damage of pile frame, therefore, how prevent the hammer that slips of sash weight winch from asking Topic is those skilled in the art's technical issues that need to address.
Utility model content
The technical problem to be solved by the present invention is to provide a kind of pile driving barges for effectivelying prevent slipping hammer problem during piling On sash weight winch structure, the defects of to overcome in the prior art.
In order to solve the above-mentioned technical problem, the utility model adopts the following technical solution:A kind of sash weight on pile driving barge twists Bassinet structure, sash weight winch include stent and roller, and roller is equipped with twisted rope, and roller is driven by motor, the end of the roller Equipped with brake hub, the winch is equipped with main brake structure, further includes auxiliary brake structure, and auxiliary brake structure includes coding Device, oil cylinder and brake ribbon, the encoder are connect with oil cylinder circuit, and encoder is equipped with the detection knot for detecting drum rotation speed Structure, brake ribbon are located at the excircle of brake hub, and the cylinder body of the oil cylinder is fixed on stent, and brake ribbon is hinged on stent, The piston rod of the oil cylinder is hinged with brake ribbon, and brake ribbon is contacted with brake hub when piston rod stretches out.
Preferably, the contact area of the brake ribbon and brake hub excircle is less than the one of brake hub excircle perimeter Half.
Preferably, the roller includes two sections of horizontal direction, passes through intermediate axis connection, the centre between two sections of rollers The diameter of axis is less than the diameter of roller.
Further, it is respectively equipped with a main brake structure on two sections of rollers.
As described above, the sash weight winch structure on a kind of pile driving barge of the utility model, has the advantages that:
The utility model is always maintained at certain resistance when pile monkey falls by auxiliary brake structure, special when encountering When geology causes the pile monkey to fall too fast, sensing device detects electric signal, feeds back and passes through brake ribbon brake hub is carried out a little Brake, and then the falling speed of pile monkey is reduced, it plays a protective role to pile monkey and pile frame.
Description of the drawings
Fig. 1 is the front view of the utility model.
Fig. 2 is the vertical view of the utility model.
Fig. 3 is the side view of the utility model.
Fig. 4 is the structure chart of auxiliary brake structure in the utility model.
Fig. 5 is the use state diagram of the utility model.
In figure:
1 sash weight winch, 2 main brake device
3 auxiliary brake, 11 stent
12 roller, 13 brake hub
31 encoder, 32 oil cylinder
33 brake ribbon, 311 sensing device
100 hull, 101 crab
102 pile frame, 103 pile monkey
104 pile covers 200
5 motors
Specific embodiment
Structure, ratio, size depicted in Figure of description etc., only to coordinate the revealed content of specification, with Understand for those skilled in the art and read, be not limited to the enforceable qualifications of the utility model, therefore do not have skill Essential meaning in art, the modification of any structure, the change of proportionate relationship or the adjustment of size are not influencing the utility model institute Under the effect of generating and the purpose that can reach, the model that can cover in the revealed technology contents of the utility model should all be fallen In enclosing.Meanwhile cited such as " on ", " under ", "front", "rear", " centre " term in this specification, it is merely convenient to describe Understand rather than to limit the enforceable range of the utility model, relativeness is altered or modified, without substantive change Under technology contents, when being also considered as the enforceable scope of the utility model.
As Figure 1-Figure 4, the utility model discloses the sash weight winch structure on a kind of pile driving barge, and sash weight winch 1 includes Stent 11 and roller 12, roller 12 are located at by support bracket on stent 11, and roller 12 is equipped with twisted rope (generally steel wire rope), The roller 12 is driven by motor 5, and the end of the roller 12 is equipped with brake hub 13.The winch 1 is equipped with main brake Structure 2, main brake structure 2 are 1 original conventional structures of sash weight winch, and disk type brake may be used, and belt can also be used to stop Vehicle does not do excessive statement.The utility model further includes auxiliary brake structure 3, and auxiliary brake structure 3 includes encoder 31, oil cylinder 32 and brake ribbon 33, the encoder 31 is connect with 32 circuit of oil cylinder and then control cylinder piston rod is flexible, on encoder 31 Equipped with for detecting the detection structure 311 of drum rotation speed, brake ribbon 33 is located at the excircle of brake hub 13, the oil cylinder 32 Cylinder body is fixed on stent 11, and brake ribbon 33 is hinged on stent 11, and the piston rod and brake ribbon 33 of the oil cylinder 32 are hinged, oil Brake ribbon 33 is pushed to rotate when the piston rod of cylinder 32 stretches out and then brake ribbon 33 is allowed to be contacted with brake hub 13 and realize braking action.
With reference to Fig. 1-Fig. 5, operation and use principle of the utility model on pile driving barge are as follows:
(1) pile driving barge 100 is travelled to pile driving position, and pile frame 102 is erected, crab 101 by stake 200 sling and with stake Frame 102 coordinates, and pile monkey 103 and pile cover 104 slowly fall under the lifting of sash weight winch 1, and pile cover 104 is sleeved on the upper end of stake 200.
(2) crab 101 and sash weight winch 1 put rope simultaneously, make stake 200, pile cover 104 and pile monkey 103 by gravity edge Longkou track on pile frame 102 falls, and pile top buries after stopping, the hoisting line in stake 200 is unlocked, sash weight winch 1 open from Clutch off the row opens main brake structure 2, start pile monkey 103 and start to drive piles.Before this, auxiliary brake structure 3 is non-always Working condition.
(3) auxiliary brake structure 3 is started to work, and the piston rod of 31 control cylinder 32 of encoder stretches out, and brake ribbon 33 is allowed to omit It is micro- have with brake hub 13 centainly contact, and then generate certain skid resistance, allow pile monkey 103 piling process will not quickly under It falls.Hereafter, detection structure 311 persistently detects the rotating speed of brake hub 13, if illustrating that pile monkey 103 does not have in the range of rated speed Hammer is slipped, auxiliary brake structure 3 does not act further;When rotating speed is too fast is more than preset value, electric signal feedback, encoder 31 32 piston rod reciprocal telescopic of control cylinder, realization brake ribbon 33 stop to the point of brake hub 13 and brake, that is, repeat to be contacting and separating, Effectively reduce pile monkey 103 falling speed, even and if then ensure to encounter special geology, also can be to pile monkey 103 and pile frame 102 It plays a protective role.
Detection structure 311 is encoder 31 from band structure, different and distinct according to the encoder 31 used, is belonged to The prior art does not do excessive statement.
In a preferred embodiment, as shown in figure 4, the brake ribbon 33 and the contact area of 13 excircle of brake hub are less than The half of brake hub excircle perimeter in order to control, effectively realizes that point is stopped and brakes.
In a preferred embodiment, the roller 12 includes two sections of horizontal direction, is connected between two sections of rollers by jackshaft 4 It connects, the diameter of the jackshaft 4 is less than the diameter of roller 12, transmits power by jackshaft 4, avoids 12 stress larger impact of roller Influence service life.As depicted in figs. 1 and 2, a main brake structure 2, each main brake structure 2 are respectively equipped on two sections of rollers On one end brake hub of one section of roller.
In conclusion the sash weight winch structure on a kind of pile driving barge of the utility model, can solve when pile driving barge is driven piles Slip hammer problem.So the utility model effectively overcomes some practical problems of the prior art so as to there is very high exploitation value It is worth and uses meaning.
The above embodiment is only illustrative of the principle and efficacy of the utility model, new not for this practicality is limited Type.The utility model can be improved there are many more aspect under the premise of without prejudice to overall thought, for being familiar with this technology Personage all can under the spirit and scope without prejudice to the utility model, can to above-described embodiment carry out modifications and changes.Therefore, Such as those of ordinary skill in the art is in spirit revealed without departing from the utility model and institute under technological thought All equivalent modifications completed or change, should be covered by the claim of the utility model.

Claims (4)

1. the sash weight winch structure on a kind of pile driving barge, sash weight winch (1) includes stent (11) and roller (12), on roller (12) Equipped with twisted rope, roller (12) is driven by motor (5), and the end of the roller (12) is equipped with brake hub (13), the winch (1) it is equipped with main brake structure (2), it is characterised in that:Auxiliary brake structure (3) is further included, auxiliary brake structure (3) is including compiling Code device (31), oil cylinder (32) and brake ribbon (33), the encoder (31) connect with oil cylinder (32) circuit, and encoder is set on (31) The detection structure (311) of detection drum rotation speed is useful for, brake ribbon (33) is positioned at the excircle of brake hub (13), the oil cylinder (32) cylinder body is fixed on stent (11), and brake ribbon (33) is hinged on stent (11), the piston rod of the oil cylinder (32) with Brake ribbon (33) is hinged, and brake ribbon (33) is contacted with brake hub (13) when piston rod stretches out.
2. the sash weight winch structure on a kind of pile driving barge according to claim 1, it is characterised in that:The brake ribbon (33) It is less than the half of brake hub excircle perimeter with the contact area of brake hub (13) excircle.
3. the sash weight winch structure on a kind of pile driving barge according to claim 1, it is characterised in that:Roller (12) packet Two sections of horizontal direction are included, are connected between two sections of rollers by jackshaft (4), the diameter of the jackshaft (4) is less than roller (12) diameter.
4. the sash weight winch structure on a kind of pile driving barge according to claim 3, it is characterised in that:On two sections of rollers respectively If there are one main brake structures (2).
CN201721614771.5U 2017-11-28 2017-11-28 A kind of sash weight winch structure on pile driving barge Active CN207596364U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721614771.5U CN207596364U (en) 2017-11-28 2017-11-28 A kind of sash weight winch structure on pile driving barge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721614771.5U CN207596364U (en) 2017-11-28 2017-11-28 A kind of sash weight winch structure on pile driving barge

Publications (1)

Publication Number Publication Date
CN207596364U true CN207596364U (en) 2018-07-10

Family

ID=62759990

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721614771.5U Active CN207596364U (en) 2017-11-28 2017-11-28 A kind of sash weight winch structure on pile driving barge

Country Status (1)

Country Link
CN (1) CN207596364U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853559A (en) * 2019-03-13 2019-06-07 江苏科技大学 Pile driving barge slips a brake apparatus and its braking method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109853559A (en) * 2019-03-13 2019-06-07 江苏科技大学 Pile driving barge slips a brake apparatus and its braking method

Similar Documents

Publication Publication Date Title
CN205591266U (en) Bridge pile foundation's detection device under water
CN104563917A (en) Multifunctional robot for drilling site
CN207596364U (en) A kind of sash weight winch structure on pile driving barge
CN107671676A (en) A kind of bridge construction scaffold derusting device
CN106869205A (en) Ropes guide
CN110589704A (en) Building tower crane hoist wheel is with preventing overload device
CN107190667A (en) A kind of road and bridge construction special efficient alarm set
CN205294649U (en) Multi -functional caterpillar crane is with device of surely fighting of grabbing bucket
CN202596569U (en) Impact air lift reverse circulation drilling machine
CN204416762U (en) Hawser balance device of boarding
CN207445564U (en) A kind of sea rover
CN106185629A (en) A kind of caterpillar crane hook height detecting system and its implementation
CN201459791U (en) Grab bucket underground pore-forming device
CN203768967U (en) Grab bucket underground-hole-forming device
CN203428378U (en) Anti-reversal bucket elevator
CN205604776U (en) Underground bicycle garage
CN105174083A (en) Marine single-arm rescue boat hanging bracket
CN207565606U (en) Play formula buffer stop to a kind of electropneumatic
CN104355234A (en) Stroke detection device for crane steel rope
CN203866882U (en) Underground diaphragm wall grab bucket balancing device and underground diaphragm wall construction machine
CN108252304A (en) Electric impacting pile hammer
CN210368958U (en) Piling equipment for bridge construction
CN206751213U (en) It is a kind of can arbitrary height deslagging crane structure
CN205187669U (en) Novel timber hoist and mount grab bucket
CN105425313B (en) Deep-well alluvial detection alarm device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A hammer winch structure on a pile driving barge

Effective date of registration: 20220107

Granted publication date: 20180710

Pledgee: Industrial Bank Co.,Ltd. Shanghai pilot Free Trade Zone Lingang New District sub branch

Pledgor: SHANGHAI XIONGCHENG MARINE ENGINEERING CO.,LTD.

Registration number: Y2022980000225

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20230128

Granted publication date: 20180710

Pledgee: Industrial Bank Co.,Ltd. Shanghai pilot Free Trade Zone Lingang New District sub branch

Pledgor: SHANGHAI XIONGCHENG MARINE ENGINEERING CO.,LTD.|SHANGHAI XIONGCHENG SHIP ENGINEERING Co.,Ltd.

Registration number: Y2022980000225

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of utility model: A hammer hoist structure on a pile driver

Effective date of registration: 20230201

Granted publication date: 20180710

Pledgee: Industrial Bank Co.,Ltd. Shanghai pilot Free Trade Zone Lingang New District sub branch

Pledgor: SHANGHAI XIONGCHENG MARINE ENGINEERING CO.,LTD.|SHANGHAI XIONGCHENG SHIP ENGINEERING Co.,Ltd.

Registration number: Y2023310000019