- CN207582497U CN207582497U CN201721242221.5U CN201721242221U CN207582497U CN 207582497 U CN207582497 U CN 207582497U CN 201721242221 U CN201721242221 U CN 201721242221U CN 207582497 U CN207582497 U CN 207582497U
- Authority
- CN
- China
- Prior art keywords
- hypogee
- splitlevel
- vertical pipe
- foundation pit
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Supports For Pipes And Cables (AREA)
Abstract
Structure is protected in a kind of support the utility model discloses vertical pipe for splitlevel hypogee, and support protection structure is suitable for the laying of splitlevel hypogee outside vertical pipeline.It is pattern foundation pit supporting structure formula structure that structure is protected in the support for splitlevel hypogee vertical pipe, and the pattern foundation pit supporting structure includes PE pipelines(1), fixing bracket(2)With foundation pit backfilling material(3), the PE pipelines(1)It is set in the structure of splitlevel hypogee, the fixing bracket(2)For fixing the PE pipelines, the foundation pit backfilling material(3)For being backfilling and compacted for the pattern foundation pit supporting structure.The support protection structure of the vertical pipe for splitlevel hypogee of the utility model, can effectively reduce pipeline construction security risk, ensure that entire geothermal heat pump air-conditioning system is run steadily in the long term.
Description
Technical field
The utility model is related to a kind of piping support structures, and in particular to a kind of vertical tube for splitlevel hypogee
The support protection structure in road.
Background technology
Today's society, environmental protection and utilization of new energy resources have become the Important Problems of building trade concern, and earth source heat pump is empty
Adjusting system extensive use therewith.Geothermal heat pump air-conditioning system is mainly by outdoor heat exchange system, heat pump computer room and indoor end system
Composition, wherein, the design and construction of outdoor heat exchange system are the guarantees of entire air-conditioning system safe and stable operation.
The real native greenery patches that can be used for the design of outdoor heat exchange hole due to building plans, plot ratio etc., in numerous items is empty
Between it is limited, therefore select by outdoor heat exchange hole design below ground house bottom plate.Heat exchanging holes are carried out by horizontal pipe under ground house bottom plate
Connection, horizontal pipe are returned along the exterior wall vertical run of ground library, are connected to underground pipe water collecting and diversifying device.
Conventional construction technique, when horizontal connection pipeline is returned along ground library exterior wall vertical run, closely library exterior wall as possible, ground
Library exterior wall gives its support, while is protected on the outside of pipeline using brick wall, and pipeline is made to be placed in brick wall and is formed with ground library exterior wall
Go along with sb. to guard him in space, protective conduit will not be bent in later stage foundation pit backfilling process, deform.
Building ground library in part uses the design form of staggered floor, when horizontal connection pipeline is returned along ground library exterior wall, in order to close to
Ground library exterior wall and be bent, tube bends are supported without position.The backfill of staggered floor region is backfilled using foundation pit backfill material,
Regular situation is graded sand and stone, and graded sand and stone backfill has certain destructiveness to PE pipelines, need to use fine sand will for protection PE pipelines
Pipeline is isolated with graded sand and stone.Increase quarantine measures, can make construction delay to a certain extent, and foundation pit degree of being backfilling and compacted generally by
Building requirements are implemented, it is difficult to reach the code requirement of buried polyethylene pipeline laying, the later stage is it is possible that local pipe sinks
The phenomenon that.Meanwhile during vertical pipe backfilling of pipe canal, compaction in layers is needed, and for the building of ground library staggered floor design, staggered floor area
Domain can not necessarily ensure operation side and the duration of backfilling of pipe canal compacting.
Due to the design limitations of outdoor heat exchange system, exchange heat hole drilling and horizontal pipe construction etc. often for it is permanent,
Unrepairable, it is contemplated that the operation steady in a long-term of whole system when carrying out horizontal pipe design and construction, should avoid breaking as possible
Mouth connection and up and down bending.When being returned on pipeline, at pipe bending it is possible that the problems such as gas collection, interface fracture can occur, so as to shadow
Ring the stable operation of whole system.Pipe bending is laid compared to pipeline vertical run, and every pipeline can increase 2n elbow(n
To be not less than 1 natural number, staggered floor number is represented), then the possibility of gas collection occurs at pipe bending to be multiplied.
Therefore, in order to simplify working procedure, ensure construction speed, gas collection, interface break caused by reduction pipe bending is possible
Split equivalent risk, it is ensured that air-conditioning system can be run steadily in the long term, and one kind can be supported vertical pipe protection, avoid pipeline
Bending, but the form of construction work that can reduce crossed construction becomes particularly important.
Utility model content
In order to solve the above-mentioned technical problem, the utility model provides a kind of vertical pipe for splitlevel hypogee
Support protection structure, pipeline construction security risk can be effectively reduced, ensure the long-term steady of entire geothermal heat pump air-conditioning system
Fixed operation.
To achieve these goals, the utility model adopts the following technical solution.
A kind of vertical pipe for splitlevel hypogee support protection structure, suitable for splitlevel hypogee outside
The laying of side vertical pipe is particularly suitable for the laying of splitlevel hypogee outdoor heat exchange systematic vertical pipeline.This is used for mistake
The support protection structure of laminar hypogee vertical pipe is pattern foundation pit supporting structure formula structure, and the pattern foundation pit supporting structure includes PE pipelines, consolidates
Fixed rack and foundation pit backfilling material, the PE pipelines are set in the structure of splitlevel hypogee, and the fixing bracket is for solid
The fixed PE pipelines, the foundation pit backfilling material are backfilling and compacted for the pattern foundation pit supporting structure.
Preferably, the PE pipelines are embedded in below the ground house bottom plate of splitlevel hypogee, built-in length extension
To ground library outermost exterior wall(That is library exterior wall)Place, to avoid staggered floor region.
It is preferably in any of the above-described technical solution, below with the being embedded in splitlevel hypogee house bottom plate, prolongs
Extend to ground library outermost exterior wall(That is library exterior wall)The PE pipelines at place, use fixing bracket to fix, then splitlevel hypogee
It is returned on outside vertical pipeline is vertical under support bracket fastened support protection.
In any of the above-described technical solution preferably, it is described it is vertical on the splitlevel hypogee outside vertical pipeline that returns
After the completion of being returned in laying, it is connected to underground pipe water collecting and diversifying device.
In any of the above-described technical solution preferably, the support bracket fastened side is inserted into real soil, the fixed branch
The opposite side of frame be fixed on close to ground library exterior wall on, consolidate support bracket fastened fixed structure firm.
In any of the above-described technical solution preferably, the foundation pit backfilling material is formed with PE pipelines, fixing bracket and is used
Structure is protected in the support of splitlevel hypogee vertical pipe, the foundation pit backfilling material provides support for vertical pipe and makees
With.
In any of the above-described technical solution preferably, the pattern foundation pit supporting structure and ground library outermost exterior wall(That is library exterior wall)
Between have 1m operation side, for completing support bracket fastened installation.
In any of the above-described technical solution preferably, the foundation pit backfilling material, which uses, meets splitlevel hypogee room
The foundation pit backfilling material of outer heat-exchange system design or vertical pipe laying code requirement.
The support protection structure of the vertical pipe for splitlevel hypogee of the utility model, is that one kind is avoided that vertical
Straight pipeline because hypogee structure staggered floor, supported without position due to the support protected mode that occurs bending and deformation, be particularly suitable for mistake
The laying of laminar hypogee outdoor heat exchange systematic vertical pipeline is a kind of to can guarantee outdoor heat exchange system safe and stable operation
Construction new construction.
Compared with prior art, the above-mentioned technical proposal of the utility model has the advantages that:
1st, the structure using fixing bracket support protection vertical pipe, not only can be to avoid being returned on vertical pipe during
What is be likely to occur returns curved phenomenon, reduces the construction hidden danger such as gas collection, interface fracture;Meanwhile staggered floor region is avoided in pipeline laying, without
Operation side and duration are fought for construction.
2nd, the structure is applicable to the laying of splitlevel hypogee outside vertical pipeline, is particularly suitable for splitlevel underground
Build the laying of outdoor heat exchange systematic vertical pipeline.The structure can effectively reduce pipeline construction security risk, ensure entire air-conditioning
System is run steadily in the long term.
Description of the drawings
It in order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment
Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only
It is some embodiments of the utility model, for those of ordinary skill in the art, before not making the creative labor property
It puts, can also be obtained according to these attached drawings other attached drawings.
Fig. 1 is to protect the one excellent of structure according to the support of the vertical pipe for splitlevel hypogee of the utility model
Select the diagrammatic cross-section of embodiment;
Fig. 2 is to protect the one excellent of structure according to the support of the vertical pipe for splitlevel hypogee of the utility model
Select the floor map of embodiment.
Reference numeral:
1st, PE is managed, 2, fixing bracket, 3, foundation pit backfilling material, 4, heat exchanging holes below house bottom plate, 5, real soil, 6, foundation pit branch
Shield, 7, water collecting and diversifying device, 8, library exterior wall.
Specific embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out
It clearly and completely describes, it is clear that the described embodiments are only a part of the embodiments of the utility model rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are without making creative work
All other embodiments obtained shall fall within the protection scope of the present invention.
In order to which the support for overcoming the vertical pipe of splitlevel hypogee protects technology existing in the prior art to ask
Topic, the utility model embodiment propose a kind of support protection structure of vertical pipe for splitlevel hypogee, and realization has
Effect reduces pipeline construction security risk, ensures the operation steady in a long-term of entire geothermal heat pump air-conditioning system.
The support protection structure of the vertical pipe for splitlevel hypogee described in the present embodiment is pattern foundation pit supporting structure formula
Structure, as shown in Figure 1,6 structure of pattern foundation pit supporting structure includes PE pipelines 1, fixing bracket 2 and foundation pit backfilling material 3, PE pipelines
1 is set in the structure of splitlevel hypogee, and for fixing bracket 2 for fixing PE pipelines 1, foundation pit backfilling material 3 is used for foundation pit branch
Shield is backfilling and compacted.
The support protection structure of the vertical pipe for splitlevel hypogee described in the present embodiment, is that one kind is avoided that
Vertical pipe because hypogee structure staggered floor, supported without position due to the support protected mode that occurs bending and deformation, be particularly suitable for
The laying of splitlevel hypogee outdoor heat exchange systematic vertical pipeline is that one kind can guarantee outdoor heat exchange system safe and stable operation
Construction new construction.It with cross-sectional view shown in Fig. 1 and ties Fig. 2 floor map below and is specifically described.
In Fig. 1, n is the natural number not less than 1, represents staggered floor number.Hypogee staggered floor quantity for 0,1,2
A ... n.
The support protection structure of the vertical pipe for splitlevel hypogee described in the present embodiment, PE pipelines 1 are embedding
Below the ground house bottom plate of splitlevel hypogee, built-in length extends to ground library outermost exterior wall(I.e.:Ground library exterior wall 8)
Place.
The support protection structure of the vertical pipe for splitlevel hypogee described in the present embodiment, splitlevel underground is built
It builds with heat exchanging holes 4 below ground house bottom plate.
The support protection structure of the vertical pipe for splitlevel hypogee described in the present embodiment, is embedded in splitlevel
Hypogee below house bottom plate, extend to ground library outermost exterior wall(I.e.:Ground library exterior wall 8)The PE pipelines 1 at place, use fixation
Stent 2 is fixed, then splitlevel hypogee outside vertical pipeline it is vertical under support bracket fastened support protection on return.
The support protection structure of the vertical pipe for splitlevel hypogee described in the present embodiment, it is vertical on the mistake returned
After the completion of laminar hypogee outside vertical pipeline returns in laying, it is connected to underground pipe water collecting and diversifying device 7.
The support protection structure of the vertical pipe for splitlevel hypogee described in the present embodiment, fixing bracket 2
Side is inserted into real soil 5, the opposite side of fixing bracket 2 be fixed on close to ground library outermost exterior wall(I.e.:Ground library exterior wall 8)On,
Make fixing bracket 2 fixed structure consolidate it is firm.
The support protection structure of the vertical pipe for splitlevel hypogee described in the present embodiment, foundation pit backfilling material
3 form the support protection structure for splitlevel hypogee vertical pipe, foundation pit backfilling material with PE pipelines 1, fixing bracket 2
3 provide a supporting role for vertical pipe.
The vertical pipe for splitlevel hypogee described in the present embodiment support protection structure, pattern foundation pit supporting structure 6 with
Ground library outermost exterior wall(I.e.:Ground library exterior wall 8)Between have 1m operation side.
The support protection structure of the vertical pipe for splitlevel hypogee described in the present embodiment, foundation pit backfilling material
3 using the foundation pit backfilling material for meeting the outdoor heat exchange system design of splitlevel hypogee or vertical pipe laying code requirement.
The support protection structure of the vertical pipe for splitlevel hypogee described in the present embodiment, is mainly managed by PE
Road, fixing bracket, the design of splitlevel hypogee outdoor heat exchange system or vertical pipe lay the foundation pit backfill material of code requirement
Material is formed, and protection vertical pipe is supported using fixing bracket, not only can be to avoid being likely to occur during being returned on vertical pipe
Return curved phenomenon, reduce the construction hidden danger such as gas collection, interface fracture;Meanwhile staggered floor region is avoided in pipeline laying, without being applied with building
Work fights for operation side and duration.The support protection knot of the vertical pipe for splitlevel hypogee described in the present embodiment
Structure is applicable to the laying of splitlevel hypogee outside vertical pipeline, is particularly suitable for splitlevel hypogee outdoor heat exchange
The laying of systematic vertical pipeline.The structure can effectively reduce pipeline construction security risk, ensure that entire air-conditioning system is steady in a long-term
Operation.
In specific implementation, building ground library is designed using staggered floor, is used for splitlevel hypogee described in the present embodiment
The support protection structure of vertical pipe will be embedded in the PE pipelines below building ground house bottom plate, extend to ground library outermost exterior wall
Place, avoids staggered floor region, using fixing bracket, PE pipelines is fixed, pipeline can it is vertical under support bracket fastened support protection on
It returns.Support bracket fastened side is inserted into real soil, opposite side be fixed on close to ground library exterior wall on, consolidate supporting structure firm.
Using the construction technology, pipeline vertical run can be constructed simultaneously with the backfill of staggered floor region foundation pit, and it can be vertical to be backfilling and compacted part
Straight pipeline provides certain supporting role.
In specific implementation, it is protected using the support of the vertical pipe for splitlevel hypogee described in the present embodiment
Structure supports protection vertical pipe using fixing bracket, i.e., pipeline it is vertical on when returning, without closely library exterior wall, but utilize
Vertical pipe is fixed between ground library outermost exterior wall and foundation pit supporting construction, returns, connect on pipeline vertical run by fixing bracket
To underground pipe water collecting and diversifying device.The structure effectively solves the outdoor heat exchange systematic vertical pipeline laying of splitlevel hypogee and can meet
To without position support, return the problems such as curved, crossed construction up and down, avoid the gas collection generated due to pipe bending, interface fracture, office
Phenomena such as portion's pipeline commissioning, makes outdoor heat exchange system construction more perfect, ensures the operation steady in a long-term of entire air-conditioning system.
In specific implementation, it should be noted that when being constructed using the construction technology, it should be ensured that support bracket fastened peace
Stability is filled, vertical pipe is unable to flexural deformation;It, should be by construction personnel's stand-by supervision, it is ensured that pipeline is not when later stage foundation pit backfills
It is damaged.
The above is only that the preferred embodiment of the utility model is described, and is not the model to the utility model
It encloses and is defined;The foregoing is merely specific embodiment of the present utility model, are not used to limit the utility model
Protection domain;Under the premise of the spirit of the design of the utility model is not departed from, this field ordinary skill technical staff is new to this practicality
Any modification, equivalent substitution, improvement and etc. that the technical solution of type is made, the claims that should all fall into the utility model determine
Protection domain in.
Claims (8)
1. a kind of support protection structure of vertical pipe for splitlevel hypogee, suitable on the outside of splitlevel hypogee
The laying of vertical pipe, it is characterised in that:It is foundation pit that structure is protected in the support for splitlevel hypogee vertical pipe
Supporting type structure, the pattern foundation pit supporting structure include PE pipelines, fixing bracket and foundation pit backfilling material, and the PE pipelines are set to staggered floor
In the structure of formula hypogee, for the fixing bracket for fixing the PE pipelines, the foundation pit backfilling material is used for the foundation pit
Supporting is backfilling and compacted.
2. as described in claim 1 for the support protection structure of the vertical pipe of splitlevel hypogee, it is characterised in that:
The PE pipelines are embedded in below the ground house bottom plate of splitlevel hypogee, and built-in length extends to ground library outermost exterior wall
Place.
3. as claimed in claim 2 for the support protection structure of the vertical pipe of splitlevel hypogee, it is characterised in that:
Below with the being embedded in splitlevel hypogee house bottom plate, PE pipelines at the outermost exterior wall of ground library are extended to, are used solid
Fixed rack is fixed, then splitlevel hypogee outside vertical pipeline it is vertical under support bracket fastened support protection on return.
4. as claimed in claim 3 for the support protection structure of the vertical pipe of splitlevel hypogee, it is characterised in that:
It is described it is vertical on after the completion of the splitlevel hypogee outside vertical pipeline that returns returns in laying, be connected to underground pipe water collecting and diversifying device.
5. as described in claim 1 for the support protection structure of the vertical pipe of splitlevel hypogee, it is characterised in that:
The support bracket fastened side is inserted into real soil, the support bracket fastened opposite side be fixed on close to ground library exterior wall on, make solid
It is firm that the fixed structure of fixed rack consolidates.
6. as described in claim 1 for the support protection structure of the vertical pipe of splitlevel hypogee, it is characterised in that:
The foundation pit backfilling material is formed with PE pipelines, fixing bracket and is tied for the support protection of splitlevel hypogee vertical pipe
Structure, the foundation pit backfilling material are provided a supporting role for vertical pipe.
7. as described in claim 1 for the support protection structure of the vertical pipe of splitlevel hypogee, it is characterised in that:
There is the operation side of 1m between the pattern foundation pit supporting structure and ground library outermost exterior wall.
8. as described in claim 1 for the support protection structure of the vertical pipe of splitlevel hypogee, it is characterised in that:
Using meeting, splitlevel hypogee outdoor heat exchange system designs the foundation pit backfilling material or vertical pipe lays code requirement
Foundation pit backfilling material.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721242221.5U CN207582497U (en) | 2017-09-26 | 2017-09-26 | A kind of support protection structure of vertical pipe for splitlevel hypogee |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721242221.5U CN207582497U (en) | 2017-09-26 | 2017-09-26 | A kind of support protection structure of vertical pipe for splitlevel hypogee |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207582497U true CN207582497U (en) | 2018-07-06 |
Family
ID=62727902
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721242221.5U Active CN207582497U (en) | 2017-09-26 | 2017-09-26 | A kind of support protection structure of vertical pipe for splitlevel hypogee |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207582497U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108616104A (en) * | 2018-07-13 | 2018-10-02 | 安徽华电工程咨询设计有限公司 | A kind of open caisson of staggered floor cable laying |
-
2017
- 2017-09-26 CN CN201721242221.5U patent/CN207582497U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108616104A (en) * | 2018-07-13 | 2018-10-02 | 安徽华电工程咨询设计有限公司 | A kind of open caisson of staggered floor cable laying |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203603174U (en) | Waterproof structure in basement top slab descending area | |
CN104197587B (en) | Buried tube type underground heat exchange structure and construction method thereof is disturbed in a kind of ring foundation ditch | |
CN104514218A (en) | Energy pile and system thereof | |
CN205617426U (en) | Cast -in -place bottom plate of utility tunnel and prefabricated outer panel connection structure | |
CN207582497U (en) | A kind of support protection structure of vertical pipe for splitlevel hypogee | |
CN105207148B (en) | A kind of construction method for the architectural electricity pipeline system for crossing aseismatic joint | |
CN205092540U (en) | Cross seismic joint's building electrical pipeline system | |
CN201383556Y (en) | Deep well grounding resistance-reducing device | |
CN209892228U (en) | Underground comprehensive pipe gallery structure constructed by adopting underground excavation method | |
CN204590040U (en) | Support of Foundation Pit Excavation device | |
CN208486459U (en) | Planted roof | |
CN207376648U (en) | One kind is used for novel energy underground pipe gallery structure | |
CN211599856U (en) | Gas pipeline anti-settling device | |
CN108194764A (en) | The means of defence of underground piping during a kind of excavation pipe trench | |
CN109357423A (en) | A kind of double-U-shaped half immersed tube closed-loop ground source heat pump air-conditioning system construction method | |
CN203160236U (en) | Anti-floating anchor rod capable of collecting ground source heat energy | |
CN204229010U (en) | For the miniature porous bundle pipe of field of communication transmission | |
CN103982707B (en) | The most now spread concrete and surround soft pipe flow guide system | |
CN204202246U (en) | Ground source heat pump imbedded pipe mounting structure | |
CN209001496U (en) | A kind of electric power tunnel push pipe with electro-magnetic screen function | |
CN207714341U (en) | A kind of double-row pile formula pile plate wall slope retaining structure | |
CN206529796U (en) | A kind of outer wall formwork of basement installs strengthening construction platform | |
CN206554932U (en) | A kind of interflow of oval shield machine construction regulate and store moldeed depth layer tunnel | |
CN206308583U (en) | A kind of mountain area side drainage structure | |
CN214307667U (en) | Ground source heat exchanger mounting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |