The precast segment and prefabricated assembled storage pond of a kind of assembled storage pond
Technical field
The utility model is related to water storage device fields, and in particular to the precast segment and prefabricated dress of a kind of assembled storage pond
With formula storage pond.
Background technology
Storage pond has to the flow-rate adjustment of initial rainwater, confluence of rainwater and sewage rainwater and later stage rainwater, storage of shutting off, pretreatment
Etc. functions, in engineering as water conservancy project structure may be arranged at cell, road, greening region, be mainly embedded in underground, be steel
Tendon concrete structure, intensity and load must satisfy related specifications requirement, and antiseep and anti-odour.Pond body volume and embedded
Depth is different regarding actual demands of engineering.
In practical implementation at this stage, storage pond construction is commonly carried out using cast-in-place mode, have with
Lower defect:
(1) long construction period, security risk are higher.
(2) construction site is big by such environmental effects such as place, weather.
(3) different construction teams management level mixed causes quality control on construction difficulty larger.
In addition, also there is scheme of the part using prefabricated component assembling, but there are still Assembling complexity, prefabricated component type are numerous
The defects of mostly and being difficult to meet personalized designs.
Invention content
For defect in the prior art, the purpose of this utility model is to provide a kind of the pre- of assembled storage pond
Component processed, each unit of the precast segment can be assembled into storage pond, can shorten the construction period, the pre- manufacturing of factory programsization, matter
Amount is controllable.
To achieve the above objectives, the technical scheme adopted by the utility model is that:
A kind of precast segment of assembled storage pond, including:Angle unit, positive side unit, side unit and temporary location;Its
In,
The angle unit includes at least:First longitudinal direction channel and the first interconnection, in the first longitudinal direction channel
Portion is communicated with one end of first interconnection, one end closing of the first longitudinal direction channel;
The positive side unit includes at least:Second longitudinal direction channel and the second interconnection, second interconnection
It is communicated in the middle part of one end and the second longitudinal direction channel;
The side unit includes at least:Third vertical passage and third interconnection, the third interconnection with
The third vertical passage intersection communicates, one end closing of the third vertical passage;
The temporary location includes at least the 4th vertical passage and the 4th interconnection, the 4th vertical passage, institute
The 4th interconnection intersection is stated to communicate.
Based on the above technical solution, the angle unit further includes the first side plate of a pair being oppositely arranged and connection two
First transverse slat of a described first side plate one end and the first top plate being arranged at the top of two first side plates, a pair described in
The first longitudinal direction channel is set along the first side plate length direction between first side plate, on first transverse slat described in setting
First interconnection;
The positive side unit further includes the second side plate of a pair being oppositely arranged and is arranged on two the second side plate tops
Second top plate in portion sets the second longitudinal direction channel between a pair of second side plate along the second side plate length direction,
Second interconnection is set on one of them described second side plate;
The side unit further includes a pair of of the third side plate being oppositely arranged and is arranged on two third side plate tops
The third top plate in portion sets the third vertical passage between a pair of third side plate along the third side plate length direction,
The third interconnection is set on one of them described third side plate;
The temporary location further includes the 4th side plate of a pair being oppositely arranged and is arranged on two the 4th side plate tops
4th top plate in portion is provided with the 4th vertical passage between a pair of 4th side plate, institute along the 4th side plate length direction
The both ends open for stating the 4th interconnection is located on two the 4th side plates respectively.
Based on the above technical solution, the precast segment of the assembled storage pond further includes transition element;It is described
Transition element includes the 5th side plate of a pair that is oppositely arranged and the 5th top plate being arranged at the top of two the 5th side plates, and one
The 5th side plate length direction is provided with the 5th transition passage between the 5th side plate.
Based on the above technical solution, the precast segment of the assembled storage pond, which further includes, is used to form bottom wall simultaneously
The foundation structure of the precast segment of multiple assembled storage ponds is installed;
Multiple grooves for installation, the angle unit, the positive side unit, the side are set in the foundation structure
The assembling protrusion of setting and groove cooperation on unit, the temporary location and the transition element;Alternatively,
Multiple protrusions for installation, the angle unit, the positive side unit, the side are set in the foundation structure
The assembling groove of setting and protrusion cooperation on unit, the temporary location and the transition element.
Based on the above technical solution, the angle unit, the positive side unit, the side unit, the centre
Reinforcing rib for enhancing intensity and anti-pressure ability is set on the outer wall and/or inner wall of unit and the transition element.
Based on the above technical solution, the angle unit, the positive side unit, the side unit, the centre
Joining place setting waterproof structure between unit and the installation place and/or adjacent cells of the transition element and the foundation structure
It makes.
Based on the above technical solution, the bottom of the foundation structure is equipped with the pump hole for placing suction pump.
Based on the above technical solution, the angle unit, the positive side unit, the side unit, the centre
Unit and the transition element pass through tongue and groove assembly.
A kind of prefabricated assembled storage pond, which is characterized in that by the prefabricated of assembled storage pond as described in claim 1
Parts assembling forms, and concrete condition is as follows:
When the assembled storage pond is a row multirow, by two angle units and at least one positive side unit
Assembled, all positive side units are assembled into successively to be arranged on one side, and two angle units are assembled in the both ends of side row respectively;
All first longitudinal direction channels and the second longitudinal direction channel piece together the assembled storage pond jointly
Circulation passage;
When the assembled storage pond is a line multiple row, by two angle units and at least one side unit
Assembled, all side units are assembled into successively to be arranged on one side, and two angle units difference assembly are in side row
Both ends;
All first interconnections and the third interconnection piece together the assembled storage pond jointly
Circulation passage;
When the assembled storage pond is multiple lines and multiple rows, by at least two angle units, at least one positive side
Unit, at least one side unit and at least one temporary location are assembled, and all first longitudinal directions are led to
Road connects jointly with the second longitudinal direction channel, and all first interconnections and the third interconnection connect jointly
Logical, all second interconnections connect jointly with the 4th interconnection, all third vertical passages and
4th vertical passage connects jointly.
A kind of prefabricated assembled storage pond, concrete condition are as follows:
When the transition element is connect with the positive side unit, second interconnection and the 5th transition passage
Connection;
When the transition element is connect with the side unit, the third vertical passage and the 5th transition passage
Connection;
When the transition element is connect with the temporary location, the 5th transition passage and the 4th vertical passage
Or the 4th interconnection connection.
Compared with prior art, the utility model has the advantage of:
It is single that the assembled storage pond precast segment of the utility model includes angle unit, positive side unit, side unit and centre
Member, each unit composite assembly form storage pond, and each unit simple structure, assembling is flexibly;Each assembled rigid unit separate operaton, quality
Controllably.It is more specialized compared with cast-in-place mode, each unit is factory produced, can shorten the construction period, it is cost-effective;By place item
Part, such environmental effects are small, and progress is controllable;The pre- manufacturing of factory programsization, it is quality controllable;Storage pond construction is mostly that deep basal pit is made
Industry can largely reduce the activity duration at scene by prefabrication and assembly construction mode, reduce security risk.
Description of the drawings
Fig. 1 is the schematic layout pattern of the precast segment for the assembled storage pond that the utility model embodiment provides;
Fig. 2 is the overlooking the structure diagram for the angle unit that the utility model embodiment provides;
Fig. 3 is the horizontal section schematic diagram for the angle unit that the utility model embodiment provides;
Fig. 4 is the longitudinal profile schematic diagram for the angle unit that the utility model embodiment provides;
Fig. 5 is the overlooking the structure diagram for the positive side unit that the utility model embodiment provides;
Fig. 6 is the horizontal section schematic diagram for the positive side unit that the utility model embodiment provides;
Fig. 7 is the longitudinal profile schematic diagram for the positive side unit that the utility model embodiment provides;
Fig. 8 is the overlooking the structure diagram for the side unit that the utility model embodiment provides;
Fig. 9 is the overlooking the structure diagram for the temporary location that the utility model embodiment provides;
Figure 10 is the dimensional structure diagram for the temporary location that the utility model embodiment provides;
Figure 11 is the overlooking the structure diagram for the transition element that the utility model embodiment provides;
Figure 12 is the dimensional structure diagram for the transition element that the utility model embodiment provides;
Figure 13 is the horizontal section schematic diagram for the assembled storage pond that the utility model embodiment provides;
Figure 14 is the longitudinal profile schematic diagram for the assembled storage pond that the utility model embodiment provides.
In figure:1st, angle unit;10th, first longitudinal direction channel;11st, the first interconnection;12nd, the first side plate;13rd, first is horizontal
Plate;14th, the first top plate;2nd, positive side unit;20th, second longitudinal direction channel;21st, the second interconnection;22nd, the second side plate;23rd, second
Top plate;3rd, side unit;30th, third vertical passage;31st, third interconnection;32nd, third side plate;33rd, third top plate;4th, in
Between unit;40th, the 4th vertical passage;41st, the 4th interconnection;42nd, the 4th side plate;43rd, the 4th top plate;5th, transition element;50、
5th transition passage;51st, the 5th side plate;52nd, the 5th top plate;6th, foundation structure;60th, pump hole.
Specific embodiment
The utility model is described in further detail with reference to the accompanying drawings and embodiments.
Referring to shown in Fig. 1 to 10, the utility model embodiment provides a kind of precast segment of assembled storage pond, packet
It includes:Angle unit 1, positive side unit 2, side unit 3 and temporary location 4;Wherein, angle unit 1 includes at least:First longitudinal direction channel 10
And first interconnection 11, the middle part of first longitudinal direction channel 10 are communicated with one end of the first interconnection 11, first longitudinal direction is led to
One end closing in road 10;Positive side unit 2 includes at least:20 and second interconnection 21 of second longitudinal direction channel, second is laterally logical
The one end in road 21 is communicated with the middle part of second longitudinal direction channel 20;Side unit 3 includes at least:Third vertical passage 30 and third
Interconnection 31, third interconnection 31 intersects with third vertical passage 30 to be communicated, one end closing of third vertical passage 30;In
Between unit 4 include at least the 4th vertical passage 40 and the 4th interconnection 41, the 4th vertical passage 40, the 4th interconnection 41
Intersection communicates.
For the utility model using prefabricated above-mentioned a variety of unit splicings into storage pond, each unit of the precast segment can be with
Storage pond is assembled into, can be shortened the construction period, the pre- manufacturing of factory programsization is quality controllable
In the present embodiment, angle unit 1 further includes two the first side plates 12 of the first side plate of a pair 12 being oppositely arranged and connection
First transverse slat 13 of one end and the first top plate 14 for being arranged on two the first side plates, 12 top, edge between a pair of first side plate 12
First side plate, 12 length direction sets first longitudinal direction channel 10, and the first interconnection 11 is set on the first transverse slat 13;
Positive side unit 2 further includes the second side plate of a pair 22 being oppositely arranged and is arranged at the top of two the second side plates 22
Second top plate 23, along 22 length direction of the second side plate setting second longitudinal direction channel 20 between a pair of second side plate 22, one of them
Second interconnection 21 is set on second side plate 22;
Side unit 3 further includes a pair of of the third side plate 32 being oppositely arranged and is arranged at the top of two third side plates 32
Third top plate 33, along 32 length direction of third side plate setting third vertical passage 30 between a pair of of third side plate 32, one of them
Third interconnection 31 is set on third side plate 32;
Temporary location 4 further includes the 4th side plate 42 of a pair being oppositely arranged and is arranged at the top of two the 4th side plates 42
4th top plate 43 is provided with the 4th vertical passage 40 between a pair of 4th side plate 42 along 42 length direction of the 4th side plate, and the 4th is horizontal
It is located on two the 4th side plates 42 respectively to the both ends open of channel 41.
The utility model, into storage pond, is made using prefabricated above-mentioned a variety of unit splicings by the roof and outer wall being spliced into
For the periphery of storage pond, and the channel inside storage pond can realize that flow flows between each unit, structure it is simpler, it can be achieved that
Batch production generation prefabricated components are more than, and can shorten the construction period, cost-effective.
It should be noted that as shown in Fig. 3,6, angle unit 1, positive side unit 2, side unit 3, temporary location 4 and mistake
The assembly of a precast segment can be formed with itself by crossing unit 5, for component storage pond;
If two angle units 1 are combined according to modularity shown in Fig. 3, as shown in two positive side units 2 according to Fig. 6
Modularity be combined.
Specifically, the 4th interconnection 41 on temporary location 4 can be curved channel, the 4th vertical passage 40 is rectangular
Channel.Preferably, for the ease of processing and improving the entire compression ability of unit and intensity, temporary location 4 includes transversely setting
The body structure put hollows out inside body structure to form the 4th vertical passage 40, the both ends extension of the body structure along longitudinal direction
There is arc arch structure, to form the entrance of the 4th interconnection.Preferably, the upper surface of arc arched door is equipped with and babinet knot
The tablet reinforcing rib that structure is connected, so not only so that the upper surface of temporary location 4 is concordant, but also enhances its whole rigid.
The utility model, into storage pond, is used as by the roof and outer wall being spliced into and adjusted using prefabricated a variety of unit splicings
The periphery of reservoir, and the channel inside storage pond can realize that flow flows between each unit, structure is simpler, it can be achieved that factory
Metaplasia is more than into prefabricated components, can shorten the construction period, cost-effective.
Referring to shown in Figure 11 and Figure 12, based on the above technical solution, the precast segment of assembled storage pond also wraps
Include transition element 5;
Transition element 5 include 5th side plate 51 of a pair that is oppositely arranged and be arranged at the top of two the 5th side plates 51 the
Five top plates 52 are provided with the 5th transition passage 50 between a pair of 5th side plate 51 along 51 length direction of the 5th side plate.
Wherein, transition element 5 is optional dispensing unit, for adjustment unit row and/or the quantity of cell columns;Transition element
5 open up two the 5th transition passages 50 along longitudinal direction, the setting of side wall face closure transversely so that its in a lateral direction not with
Adjacent unit connection, convenient for follow-up maintenance.
Preferably, it sets to enhance intensity and resistance to compression on the outer wall and/or inner wall of above-mentioned multiple prefabricated profiled units
The reinforcing rib of ability.For example, shown in Figure 12,5 longitudinally disposed waling of transition element, transversely setting laterally adds
Strengthening tendons.
Referring to shown in Figure 13 and Figure 14, based on the above technical solution, the precast segment of assembled storage pond also wraps
Include the foundation structure 6 for being used to form bottom wall;
Multiple grooves for installation, angle unit 1, positive side unit 2, side unit 3, intermediate list are set in foundation structure 6
The assembling protrusion of setting and groove cooperation in member 4 and transition element 5;Or set in foundation structure 6 it is multiple for installation
Protrusion, the assembling of setting and protrusion cooperation on angle unit 1, positive side unit 2, side unit 3, temporary location 4 and transition element 5
Groove;
In the present embodiment, each unit is integral prefabricated, is assembled without recombinant, only need to successively be assembled in foundation structure 6 each
Unit greatly improves construction efficiency.
In the present embodiment, the inlet tube and outlet tube reserved opening of storage pond can be set to pond peripheral wall according to engineering actual demand
On.Preferably, outlet pipe reserved opening is not less than water inlet pipe reserved opening.
Based on the above technical solution, angle unit 1, positive side unit 2, side unit 3, temporary location 4 and transition
Reinforcing rib for enhancing intensity and anti-pressure ability is set on the outer wall and/or inner wall of unit 5.
Based on the above technical solution, angle unit 1, positive side unit 2, side unit 3, temporary location 4 and transition
Joining place setting water proof structure between the installation place and/or adjacent cells of unit 5 and foundation structure 6.
Based on the above technical solution, the bottom of foundation structure 6 is equipped with the pump hole 60 for placing suction pump;
Pump hole 60, which can concentrate that the water quality in storage pond is handled or aspirated, to be transferred at watering equipment.
Based on the above technical solution, angle unit 1, positive side unit 2, side unit 3, temporary location 4 and transition
Unit 5 is integral prefabricated molding.
Based on the above technical solution, each unit is assembled by two prefabricated profiled subdivisions;
Angle unit 1, positive side unit 2, side unit 3, temporary location 4 and transition element 5 pass through tongue and groove assembly;
Two subdivisions are symmetrical arranged and are assembled through tongue and groove, it is achieved thereby that assembling simply, convenient for the purpose of transhipment.
In the present embodiment, foundation structure 6 is cast-in-situ steel reinforced concrete.Before on-site consolidation construction, foundation structure should be by inspection
It is qualified.Storage pond prefabricated components unit location and installation, hand fit's machinery should successively carry out line by line or by column since the unit of angle,
Each unit should place smooth, firm, and piece is straight, uniform.After the completion of member unit mounting and adjusting, then carry out the waterproof structure of piece
Make construction.
A kind of assembled storage pond, the precast segment by assembled storage pond is assembled, and concrete condition is as follows:
It is assembled by two angle units 1 and at least one positive side unit 2 when assembled storage pond is a row multirow,
All positive side units 2 are assembled into successively to be arranged on one side, and two angle units 1 are assembled in the both ends of side row respectively;
All first longitudinal direction channels 10 and second longitudinal direction channel 20 piece together the circulation passage of assembled storage pond jointly;
It is assembled by two angle units 1 and at least one side unit 3 when assembled storage pond is a line multiple row,
All sides unit 3 is assembled into successively to be arranged on one side, and two angle units 1 are assembled in the both ends of side row respectively;
The first all interconnections 11 and third interconnection 31 piece together the circulation passage of assembled storage pond jointly;
When assembled storage pond is multiple lines and multiple rows, by least two jiaos of units 1, at least one positive side unit 2, at least one
A side unit 3 and at least one temporary location 4 are assembled, and all first longitudinal direction channels 10 and second longitudinal direction channel 20 are common
With connection, the first all interconnections 11 connects jointly with third interconnection 31, the second all interconnection 21 and the
Connection, all third vertical passages 30 connect four interconnections 41 jointly with the 4th vertical passage 40 jointly.
A kind of assembled storage pond, concrete condition are as follows:
When transition element 5 is connect with positive side unit 2, the second interconnection 21 is connected with the 5th transition passage 50;
When transition element 5 is connect with side unit 3, third vertical passage 30 is connected with the 5th transition passage 50;
When transition element 5 is connect with temporary location 4, the 5th transition passage 50 and the 4th vertical passage 40 or the 4th are lateral
Channel 41 connects.
The utility model is not limited to the above embodiment, for those skilled in the art, not
Under the premise of being detached from the utility model principle, several improvements and modifications can also be made, these improvements and modifications are also considered as this reality
Within novel protection domain.The content not being described in detail in this specification belongs to well known to professional and technical personnel in the field
The prior art.