CN207555578U - A kind of cyclone separating rises film pure steam generator - Google Patents

A kind of cyclone separating rises film pure steam generator Download PDF

Info

Publication number
CN207555578U
CN207555578U CN201721425318.XU CN201721425318U CN207555578U CN 207555578 U CN207555578 U CN 207555578U CN 201721425318 U CN201721425318 U CN 201721425318U CN 207555578 U CN207555578 U CN 207555578U
Authority
CN
China
Prior art keywords
separation chamber
cortex
controllers
pipe
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721425318.XU
Other languages
Chinese (zh)
Inventor
韩鲁
汪涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ling'an Qi Qi Air Purification Technology Co Ltd
Original Assignee
Ling'an Qi Qi Air Purification Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ling'an Qi Qi Air Purification Technology Co Ltd filed Critical Ling'an Qi Qi Air Purification Technology Co Ltd
Priority to CN201721425318.XU priority Critical patent/CN207555578U/en
Application granted granted Critical
Publication of CN207555578U publication Critical patent/CN207555578U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Cyclones (AREA)

Abstract

The utility model discloses a kind of cyclone separatings to rise film pure steam generator,Including separation chamber,The top of the separation chamber is equipped with exhaust pipe,And air blower has been bolted it on the side outer wall of separation chamber,The other end of the air blower has been bolted air outlet pipe,The other end of the air outlet pipe is mounted on the top of vaporization chamber,The opposite side installation Cortex M3 controllers of the separation chamber,Alarm and PTS601 liquid level sensors,The alarm is between Cortex M3 controllers and PTS601 liquid level sensors,The bottom end of the separation chamber is equipped with return duct,And separation chamber is connected by return duct with vaporization chamber,The utility model is provided with cyclonic separation staving,Cortex M3 controllers,PT100 temperature sensors and heating tube,The temperature in PT100 temperature sensor senses separators inside cyclonic separation staving,When the temperature is too low,Heating tube is controlled to heat automatically by Cortex M3 controllers,To ensure the temperature in separator.

Description

A kind of cyclone separating rises film pure steam generator
Technical field
The utility model belongs to steam generation disinfection technology field, and in particular to a kind of cyclone separating rises film pure steam hair Raw device.
Background technology
Steam generator refers to the thermal energy using fuel or other energy(Such as electric energy)Water is heated as the machinery of steam Equipment.
But the existing steam generator in market is difficult to ensure that when steam is centrifuged have some vapor to be condensed into water It is discharged away, reduces the efficiency of steam generation, the in addition discharge not in time of high concentration liquid also results in machine certain journey The damage of degree.
Utility model content
The purpose of this utility model is to provide a kind of cyclone separatings to rise film pure steam generator, to solve existing rotation The problem of vapor (steam) temperature is difficult to ensure that with high concentration liquid discharge not in time when wind detaches.
To achieve the above object, the utility model provides following technical solution:A kind of cyclone separating rises film pure steam hair Raw device, including separation chamber, the top of the separation chamber is equipped with exhaust pipe, and be bolted on the side outer wall of separation chamber There is air blower, the other end of the air blower has been bolted air outlet pipe, and the other end of the air outlet pipe is mounted on evaporation The top of room, opposite side installation Cortex M3 controllers, alarm and the PTS601 liquid level sensors of the separation chamber are described For alarm between Cortex M3 controllers and PTS601 liquid level sensors, the bottom end of the separation chamber is equipped with return duct, And separation chamber is connected by return duct with vaporization chamber, condensed water drainpipe is equipped on the side outer wall of the return duct, and return The inside of flow tube is equipped with water filter plate, and filtration hole is offered on the water filter plate, and the central position of the water filter plate is equipped with YC02 concentration sensors, the separation chamber have been bolted air inlet pipe, the air inlet on the side inner wall of air blower Connection is connected with air blower across separation chamber interior walls for pipe, and the other end of the air inlet pipe is fixed on cyclonic separation staving, described Cyclonic separation staving is fixedly connected with crossing separation chamber, and the top inside the cyclonic separation staving is equipped with PT100 temperature sensing Connection is connected with exhaust pipe for device and central tube, the central tube, and the central tube is located at the side of PT100 temperature sensors, and Blade is welded on the outer wall of central tube, heating is installed at the position of conical pipe on the inner wall of the cyclonic separation staving Pipe, and the bottom end of cyclonic separation staving is welded with conical pipe, the bottom of the conical pipe are equipped with drain pipe, the alarm, PTS601 liquid level sensors, water filter plate, PT100 temperature sensors, heating tube and YC02 concentration sensors are controlled with Cortex M3 Device processed is electrically connected, and the air blower and Cortex M3 controllers are electrically connected with external power supply.
Preferably, water inlet pipe is installed at the position of return duct on the separation chamber outer wall.
Preferably, the blade is helicoidal structure.
Preferably, valve is installed on the condensed water drainpipe.
The utility model compared with prior art, has the advantages that:
(1) the utility model is provided with cyclonic separation staving, Cortex M3 controllers, PT100 temperature sensors and heating It manages, the temperature in PT100 temperature sensor senses separators inside cyclonic separation staving when the temperature is too low, passes through Cortex M3 controllers control heating tube heats automatically, to ensure the temperature in separator, ensures the efficient of steam separation.
(2) the utility model is provided with Cortex M3 controllers, alarm, return duct, condensed water drainpipe, water filter plate With YC02 concentration sensors, when the YC02 concentration sensors in return duct sense that strength of fluid is excessively high, Cortex M3 controls Device control water filter plate closes filtration hole, while alarm sends out alarm and reminding staff and carries out liquid discharge, opens condensed water Valve on drainpipe can discharge, and ensure that the liquid in steam generator can discharge in time, increase the service life of machine.
Description of the drawings
Fig. 1 is the front view of the utility model;
Fig. 2 is enlarged drawing at the A of the utility model;
Fig. 3 is enlarged drawing at the B of the utility model;
Fig. 4 is the circuit block diagram of the utility model.
In figure:1- air outlet pipes, 2- air blowers, 3- air inlet pipe, 4- exhaust pipes, 5- separation chambers, 6- blades, 7- cyclonic separation buckets Body, 8- conical pipes, 9- drain pipes, 10-Cortex M3 controllers, 11- alarms, 12-PTS601 liquid level sensors, 13- reflux Pipe, 14- condensed waters drainpipe, 15- water filter plates, 16- vaporization chambers, 17- central tubes, 18-PT100 temperature sensors, 19- heating Pipe, 20-YC02 concentration sensors, 21- filtration holes.
Specific embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out It clearly and completely describes, it is clear that the described embodiments are only a part of the embodiments of the utility model rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are without making creative work All other embodiments obtained shall fall within the protection scope of the present invention.
- 4 are please referred to Fig.1, the utility model provides following technical solution:Kind cyclone separating rises film pure steam generator, Including separation chamber 5, the top of separation chamber 5 is equipped with exhaust pipe 4, and be bolted drum on the side outer wall of separation chamber 5 Wind turbine 2, accelerates the speed that steam enters cyclone separator, and the other end of air blower 2 has been bolted air outlet pipe 1, outlet The other end of pipe 1 is mounted on the top of vaporization chamber 16, and the opposite side of separation chamber 5 is equipped with Cortex M3 controllers 10, alarm 11 and PTS601 liquid level sensors 12, alarm 11 are located between Cortex M3 controllers 10 and PTS601 liquid level sensors 12, Alarm 11 reminds the excessive liquid of staff's concentration of emission, and the bottom end of separation chamber 5 is equipped with return duct 13, and separation chamber 5 It is connected by return duct 13 with vaporization chamber 16, condensed water drainpipe 14, and return duct is installed on the side outer wall of return duct 13 13 inside is equipped with water filter plate 15, and filtration hole 21 is offered on water filter plate 15, and the central position of water filter plate 15 is equipped with YC02 concentration sensors 20, separation chamber 5 have been bolted air inlet pipe 3, air inlet pipe 3 on the side inner wall of air blower 2 Connected across 5 inner wall of separation chamber and the conducting of air blower 2, steam entered by air inlet pipe in cyclone separator, air inlet pipe 3 it is another End is fixed on cyclonic separation staving 7, and cyclonic separation staving 7 is fixedly connected with crossing separation chamber 5, inside cyclonic separation staving 7 Top is equipped with PT100 temperature sensors 18 and central tube 17, and central tube 17 is connected with the conducting of exhaust pipe 4, and central tube 17 is located at The side of PT100 temperature sensors 18, and blade 6 is welded on the outer wall of central tube 17, it is leaned on the inner wall of cyclonic separation staving 7 Heating tube 19 is installed at the position of nearly conical pipe 8, ensures the temperature in cyclone separator, prevents steam from condensing, and whirlwind point Bottom end from staving 7 is welded with conical pipe 8, and the bottom of conical pipe 8 is equipped with drain pipe 9, alarm 11, PTS601 level sensings Device 12, water filter plate 15, PT100 temperature sensors 18, heating tube 19 and YC02 concentration sensors 20 with Cortex M3 controllers 10 are electrically connected, and air blower 2 and Cortex M3 controllers 10 are electrically connected with external power supply.
In order to ensure the normal work of steam generator, in the present embodiment, it is preferred that close to reflux on 5 outer wall of separation chamber Water inlet pipe is installed at the position of pipe 13.
In order to which steam does centrifugal movement in cyclone separator, in the present embodiment, it is preferred that blade 6 is helical form knot Structure.
Liquid leakage in order to prevent, in the present embodiment, it is preferred that be equipped with valve on condensed water drainpipe 14.
The operation principle and process for using of the utility model:When steam occurs, power on, liquid passes through separation chamber 5 one The water inlet pipe of side enters separation chamber 5, enters in vaporization chamber 16 by return duct 13, will after industrial steam enters vaporization chamber 16 Liquid in vaporization chamber 16 is heated to steam condition, enters air blower 2 by air outlet pipe 1, and air blower 2 accelerates steam, Steam after acceleration enters cyclonic separation staving 7 quickly through air inlet pipe 3, and the steam of high speed carries out spiral shell by the effect of blade 6 Rotation movement, generates centrifugal force, the droplet in gas is got rid of on the inner wall of conical pipe 8, and droplet is then as the inner wall of conical pipe 8 passes through It crosses drain pipe 9 to drop back into the liquid in separation chamber 5, the steam after separation is discharged by central tube 17 and exhaust pipe 4, cyclonic separation PT100 temperature sensors 18 inside staving 7 sense the temperature in separator, when the temperature is too low, are controlled by Cortex M3 Device 10 controls heating tube 19 to heat automatically, and to ensure the temperature in separator, the liquid in separation chamber 5 is passed by PTS601 liquid levels Sensor 12 and Cortex M3 controllers 10 are controlled, when the YC02 concentration sensors 20 in return duct 13 sense that liquid is dense When spending high, Cortex M3 controllers 10 control water filter plate 15 to close filtration hole 21, while alarm 11 sends out alarm and reminding work Make personnel and carry out liquid discharge, the valve opened on condensed water drainpipe 14 can discharge.
While there has been shown and described that the embodiment of the utility model, for the ordinary skill in the art, It is appreciated that can these embodiments be carried out with a variety of variations in the case of the principle and spirit for not departing from the utility model, repaiied Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.

Claims (4)

1. a kind of cyclone separating rises film pure steam generator, including separation chamber(5), it is characterised in that:The separation chamber(5)'s Top is equipped with exhaust pipe(4), and separation chamber(5)Side outer wall on be bolted air blower(2), the air blower (2)The other end be bolted air outlet pipe(1), the air outlet pipe(1)The other end be mounted on vaporization chamber(16)Top End, the separation chamber(5)Opposite side Cortex M3 controllers are installed(10), alarm(11)With PTS601 level sensings Device(12), the alarm(11)Positioned at Cortex M3 controllers(10)With PTS601 liquid level sensors(12)Between, described point From room(5)Bottom end return duct is installed(13), and separation chamber(5)Pass through return duct(13)With vaporization chamber(16)It is connected, it is described Return duct(13)Side outer wall on condensed water drainpipe is installed(14), and return duct(13)Inside water filter plate is installed (15), the water filter plate(15)On offer filtration hole(21), the water filter plate(15)Central position to be equipped with YC02 dense Spend sensor(20), the separation chamber(5)Close to air blower(2)Side inner wall on be bolted air inlet pipe(3), institute State air inlet pipe(3)Across separation chamber(5)Inner wall and air blower(2)Conducting connection, the air inlet pipe(3)The other end be fixed on rotation Wind detaches staving(7)On, the cyclonic separation staving(7)With crossing separation chamber(5)It is fixedly connected, the cyclonic separation staving(7) Internal top is equipped with PT100 temperature sensors(18)And central tube(17), the central tube(17)With exhaust pipe(4)Conducting Connection, the central tube(17)Positioned at PT100 temperature sensors(18)Side, and central tube(17)Outer wall on be welded with rotation Piece(6), the cyclonic separation staving(7)Inner wall on close to conical pipe(8)Position at heating tube is installed(19), and whirlwind Detach staving(7)Bottom end be welded with conical pipe(8), the conical pipe(8)Bottom drain pipe is installed(9), the alarm Device(11), PTS601 liquid level sensors(12), water filter plate(15), PT100 temperature sensors(18), heating tube(19)It is dense with YC02 Spend sensor(20)With Cortex M3 controllers(10)It is electrically connected, the air blower(2)With Cortex M3 controllers (10)It is electrically connected with external power supply.
2. a kind of cyclone separating according to claim 1 rises film pure steam generator, it is characterised in that:The separation chamber (5)Close to return duct on outer wall(13)Position at water inlet pipe is installed.
3. a kind of cyclone separating according to claim 1 rises film pure steam generator, it is characterised in that:The blade (6)For helicoidal structure.
4. a kind of cyclone separating according to claim 1 rises film pure steam generator, it is characterised in that:The condensed water Drainpipe(14)On valve is installed.
CN201721425318.XU 2017-10-31 2017-10-31 A kind of cyclone separating rises film pure steam generator Expired - Fee Related CN207555578U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721425318.XU CN207555578U (en) 2017-10-31 2017-10-31 A kind of cyclone separating rises film pure steam generator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721425318.XU CN207555578U (en) 2017-10-31 2017-10-31 A kind of cyclone separating rises film pure steam generator

Publications (1)

Publication Number Publication Date
CN207555578U true CN207555578U (en) 2018-06-29

Family

ID=62674097

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721425318.XU Expired - Fee Related CN207555578U (en) 2017-10-31 2017-10-31 A kind of cyclone separating rises film pure steam generator

Country Status (1)

Country Link
CN (1) CN207555578U (en)

Similar Documents

Publication Publication Date Title
CN204100585U (en) Condensing heat exchanger and there is its forced exhaust gas water heater
CN205245139U (en) Highly -effective steam generator
CN109477664A (en) Using the condensing boiler of vaporising device
CN207555578U (en) A kind of cyclone separating rises film pure steam generator
CN101905104A (en) Moisture separator
CN201561420U (en) Feedwater heater
CN211060569U (en) Textile processing oven
CN206553376U (en) A kind of high-temperature dehumidification dryer
CN108826270A (en) A kind of energy saving and environment friendly thermal deaerator
CN206410476U (en) A kind of twin-stage high-temperature dehumidification drying plant
CN115468153A (en) Steam generation-pressurization-pressure stabilization output system utilizing high-temperature dust and waste gas
CN205002388U (en) Condensing water heater
CN210584058U (en) High-temperature flue gas condensation water separator
CN107448925A (en) One kind arranges flash vessel surely
CN207922175U (en) Efficient flue gas waste heat utilizes steam boiler
CN102626556B (en) Evaporator provided with blackout protection device
CN208395028U (en) A kind of efficient sludge drying dehumidifying heat pump
CN209732159U (en) Automatic efficient energy-saving sterilizing device for ganoderma lucidum mushroom bags
CN206918978U (en) A kind of pure steam generator
CN206488515U (en) A kind of reheater for absorption heat pump
CN206695097U (en) A kind of steam condensate (SC) cyclic utilization system
CN217795403U (en) Carbon dioxide treatment assembly and supercritical carbon dioxide circulating generator set
CN203298286U (en) Composite waste heat recovery device of steam boiler
JPS60102Y2 (en) Wet steam water droplet separator
CN207778458U (en) Small-sized movable waste incinerated smoke purification system heat exchanger

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180629