CN207549073U - New pouring structure concrete automatic maintenance device - Google Patents

New pouring structure concrete automatic maintenance device Download PDF

Info

Publication number
CN207549073U
CN207549073U CN201721676600.5U CN201721676600U CN207549073U CN 207549073 U CN207549073 U CN 207549073U CN 201721676600 U CN201721676600 U CN 201721676600U CN 207549073 U CN207549073 U CN 207549073U
Authority
CN
China
Prior art keywords
water
ppr
concrete
connect
internal thread
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721676600.5U
Other languages
Chinese (zh)
Inventor
刘亚楠
张栋梁
原增欢
徐克强
杨耀增
李甲
司江坤
郑昊阳
吴扩建
钱吉星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Yijian Group Co Ltd
Original Assignee
Zhengzhou No1 Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou No1 Construction Engineering Co Ltd filed Critical Zhengzhou No1 Construction Engineering Co Ltd
Priority to CN201721676600.5U priority Critical patent/CN207549073U/en
Application granted granted Critical
Publication of CN207549073U publication Critical patent/CN207549073U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a kind of new pouring structure concrete automatic maintenance devices, it is characterised in that:The automatic control system of simple structure is applied in combination including earth leakage protective device, timing controller, A.C. contactor, electromagnetic valve, installs and uses simple, quick;The interim water system in construction site is accessed, without individually laying water system.Water pipe is buried as in structural concrete plate, it can curing concrete plate, also it can treat that lower-layer concrete vertical member pours completion, docking silk head can be directly connect after vertical member form removable in internal thread, it is direct that internal thread is connect again, PPR branch pipes are connect again to beam bottom, then it is direct to connect internal thread, it connects 360 ° of rotary nozzles and conserves vertical concrete component, it finally treats the water-saving tap that changes the outfit after curing cycle, becomes indoor interim water system, critical loops to the lower floor of dismounting is continuing with, primary lay is used for multiple times, and comprehensive use cost is low.

Description

New pouring structure concrete automatic maintenance device
Technical field
The utility model is related to building engineering construction structural concrete component conservation field of engineering technology, specifically a kind of Structural concrete timing automatic maintenance device.
Background technology
New pouring structure concrete curing is mainly conserved using covered rearing with plastic film and watering is conserved by the way of being combined, this There are significant limitations for kind structural concrete maintenance method;After young concrete is completed for 24 hours, technical staff carries out up Operation would generally raise plastic film;Because needs are worked continuously, so watering maintenance also is difficult to grasp the opportunity of watering, and this Kind watering and covered rearing with plastic film are combined the mode of maintenance, and the heavy workload but also water requirement not only needed is big, water resource It cannot be fully used, and project management department also can not accurately monitor the watering maintenance frequency;Thus lead to structural concrete maintenance week Phase is insufficient, and maintenance quality is not high, causes concrete gain in strength early period speed slowly and surface is cracked, be easy to cause concrete Hidden danger of quality.
Invention content
In order to overcome the shortcomings of in above-mentioned existing new pouring structure concrete curing mode, the utility model provides one kind It is simple in structure, it is easy for operation, service life is long, young concrete maintenance efficiency is greatly improved, reduces what is manually put into A kind of new pouring structure concrete curing mode.
What the purpose of this utility model was realized in:A kind of new pouring structure concrete automatic maintenance device, including certainly Autocontrol system, water system and spray system;Water system includes variable frequency pump, frequency-conversion control cabinet, water tower and PPR supervisors Road, frequency-conversion control cabinet control terminal connect the control terminal of water pump, and the water outlet of water pump is by pipeline to water tower water-feeding, the water outlet of water tower Mouth is connected by PPR main pipelines with each PPR branch pipes of spray system;Automatic control system includes earth leakage protective device, timing controlled Device, A.C. contactor and electromagnetic valve, the electromagnetic valve be mounted on PPR main pipelines on, earth leakage protective device, timing controller and A.C. contactor is connect with solenoid valve, and A.C. contactor, which is powered, after timing controller reaches setting time is closed, and triggers electromagnetism Valve opening and closing;Multiple PPR branch pipes in spray system are directly connected to 360 ° of rotary nozzles and water-saving by internal thread respectively 360 ° of rotary nozzles of tap, which part PPR branch pipes and connection are embedded in concrete structure intralamellar part, by pressure to coagulation Soil structure intralamellar part sprays moisturizing.Multiple PPR branch pipes connect up PPR manifold by tee pipe fitting respectively.
Docking silk head is directly connect in internal thread, then connects PPR branch pipes to beam bottom, 360 ° of rotary nozzles is then connect and conserves vertical coagulation Native component.It is fixed on formwork-support positioned at high-order pipeline.
Positive beneficial effect:Quality and benifit:Young concrete is conserved by this system, ensure that the maintenance frequency And maintenance quality, it ensure that the intensity of concrete curing phase improves significantly;Economic benefit:This system automatically controls, without artificial Operation, reduces the input of human resources, reduces labor intensity, is used by the timing of spray system, improves water resource Service efficiency, reduce the waste of water resource;And spray head and automatic control are said after young concrete curing period System processed is removed, and changes spray head into water-saving tap, and being used as engineering, water system uses near water.
Description of the drawings
Fig. 1 is the pipeline arranging structure schematic diagram of the utility model.
Fig. 2 is another status diagram of the utility model.
It is in figure:1 is variable frequency pump, and 2 be frequency-conversion control cabinet, and 3 be water tower, and 4 be earth leakage protective device, and 5 be timing controller, 6 be A.C. contactor, and 7 be electromagnetic valve, and 8 be PPR main pipelines, and 9 be PPR branch pipes, and 10 is direct for internal thread, and 11 be 360 ° of rotation sprays Head, 12 be tee pipe fitting, and 13 be water-saving tap, and 14 be to Threaded Connector Coupling.
Specific embodiment
Below in conjunction with the accompanying drawings, the utility model is described further:
Embodiment 1:Young concrete structure automatic maintenance device as depicted in figs. 1 and 2, the automatic maintenance device packet Include automatic control system, water system and spray system;Automatic control system includes earth leakage protective device 4, timing controller 5, hands over Flow contactor 6, electromagnetic valve 7, set on timing controller 5 according to concreting time and weather condition maintenance open and Shut-in time section, reaches the energization closure of A.C. contactor 6 after setting time, and triggering electromagnetic valve 7 unlatches and closes;Water system Including variable frequency pump 1, frequency-conversion control cabinet 2, water tower 3, PPR main pipelines 8, this water system need not be separately provided, and can be directly accessed The total water system in construction site controls variable frequency pump 1 to supply water to water tower 3 from frequency-conversion control cabinet 2;Spray system includes PPR branch pipes 9th, internal thread direct 10,360 ° of rotary nozzles 11, tee pipe fittings 12, through this practical implementation in the case where hydraulic pressure is enough branch pipe Setting spacing is advisable with 10-15 meters.
This system in actual application, water system access be entire construction site water system, in water tower 3 Hydraulic pressure be less than setting limit value after, frequency-conversion control cabinet 2 automatically work, be powered open variable frequency pump 1 to water tower water-feeding, treat water tower 3 In pressure value reach the upper limit after, variable frequency pump 1 is stopped, and thereby guarantees that the holding of entire water system has water state always.
According to concreting time and weather condition setting curing time and interval time, when timing controller 5 reaches After setting time, A.C. contactor 6, which is powered, to be closed, and triggering electromagnetic valve 7 is opened to supply water and close and be supplied water(Vibration means for main pipe for supplying water road is kept Often there is water state);It is reciprocal successively, until terminating entire curing cycle.
As shown in Figure 1 and Figure 2, section of tubing is embedded in concrete structural slab, and PPR branch is connected up by tee pipe fitting Pipe 9, branch tube spacing is determined according to the maximum effectively covering radius for choosing normal water supply pressure and 360 ° of rotary nozzles 11, through this work Journey practical application branch pipe setting spacing in the case where hydraulic pressure is enough is advisable with 10-15 meters;Treat that understructure concreting is complete Into concrete vertical member pours completion, after the completion of vertical member form removal, can connect docking silk head 14, then connect in internal thread direct 10 Internal thread direct 10, then PPR branch pipes 9 are connect to beam bottom, internal thread direct 10 is then connect, 360 ° of rotary nozzles 11 is connect and conserves vertical concrete Pipeline because pipeline goes out structural slab excessive height, can be fixed on formwork-support by component;It treats 360 ° after curing cycle Rotary nozzle 11, internal thread are direct 10, docking silk head 14 is removed, and water-saving tap 13 is installed on nethermost internal thread direct 10, into For indoor interim water system;After terminating use, pick chisel 30mm down from pipe root, blocked with plug;Pipe fitting is removed to be recycled to down Layer is continuing with.
Embodiment 2:Before the initial concreting of single building only need to according to shown in Fig. 1 by automatic control system It installs, vibration means for main pipe for supplying water road is accessed into construction site water system, while bury supervisor, branch as shown in Figure 1 in structural slab Pipe, by nozzle, installation is complete.Embodiment may refer to 1 content of embodiment.Treat that concreting is completed, when reaching setting Between can automatic maintenance;It treats only bury supervisor, branch pipe before understructure concreting in concrete, installation nozzle is It can be used;It treats to say that nozzle removes the water-saving tap that changes the outfit after main body maintenance, you can say this system as indoor temporarily for water system System uses.
The program solves the problems, such as follows in actual application:
1) the problem of young concrete conserves inefficiency, water resource waste is serious;This technology passes through fixed maintenance frequency Secondary, the application of efficient nozzle reduces the input of human resources, improves maintenance efficiency, ensure maintenance quality, save water resource.
2) the problem of vertical apparatus for concrete member curing is difficult:Treat that lower-layer concrete vertical member pours completion, vertical member Docking silk head 14 can be connect, then connect internal thread direct 10, then connect PPR branch pipes 9 to beam bottom, Ran Houjie in internal thread direct 10 after form removable Internal thread direct 10 connects 360 ° of rotary nozzles 11 and conserves vertical concrete component, can be by pipeline because pipeline goes out structural slab excessive height It is fixed on formwork-support, you can meet vertical apparatus for concrete member curing demand;
3) the problem of system availability is insufficient near water:This technology is after main body apparatus for concrete member curing end cycle by 360 ° Rotary nozzle 11, internal thread are direct 10, docking silk head 14 is removed, and water-saving tap 13 is installed on nethermost internal thread direct 10, into For indoor interim water system.
The utility model conserves young concrete by this system, ensure that the maintenance frequency and maintenance quality, It ensure that the intensity of concrete curing phase improves significantly.This system automatically controls, and without human intervention, reduces human resources Input, reduces labor intensity, is used by the timing of spray system, improves the service efficiency of water resource, reduces water money The waste in source;And say that spray head and automatic control system are removed after young concrete curing period, and by spray head Change water-saving tap into, being used as engineering, water system uses near water, and entire construction period comprehensive use cost of getting off is low.

Claims (3)

1. a kind of new pouring structure concrete automatic maintenance device, including automatic control system, water system and spray system;Its It is characterized in:Water system includes variable frequency pump, frequency-conversion control cabinet, water tower and PPR main pipelines, frequency-conversion control cabinet control terminal connection water The control terminal of pump, for the water outlet of water pump by pipeline to water tower water-feeding, the water outlet of water tower passes through PPR main pipelines and spray system Each PPR branch pipes connection;Automatic control system includes earth leakage protective device, timing controller, A.C. contactor and electromagnetic valve, institute Electromagnetic valve is stated on PPR main pipelines, earth leakage protective device, timing controller and A.C. contactor are connect with solenoid valve, A.C. contactor energization is closed after timing controller reaches setting time, and triggering electromagnetic valve unlatches and closes;In spray system Multiple PPR branch pipes 360 ° of rotary nozzles and water-saving tap, which part PPR branch pipes and connection are directly connected to by internal thread respectively 360 ° of rotary nozzles be embedded in concrete structure intralamellar part, by pressure to concrete structure intralamellar part spray moisturizing.
2. new pouring structure concrete automatic maintenance device according to claim 1, it is characterized in that:It is directly connect pair in internal thread A head is connect, then connects PPR branch pipes to beam bottom, 360 ° of rotary nozzles is then connect and conserves vertical concrete component.
3. new pouring structure concrete automatic maintenance device according to claim 1, it is characterized in that:It will be positioned at high-order pipe Road is fixed on formwork-support.
CN201721676600.5U 2017-12-06 2017-12-06 New pouring structure concrete automatic maintenance device Expired - Fee Related CN207549073U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721676600.5U CN207549073U (en) 2017-12-06 2017-12-06 New pouring structure concrete automatic maintenance device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721676600.5U CN207549073U (en) 2017-12-06 2017-12-06 New pouring structure concrete automatic maintenance device

Publications (1)

Publication Number Publication Date
CN207549073U true CN207549073U (en) 2018-06-29

Family

ID=62666016

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721676600.5U Expired - Fee Related CN207549073U (en) 2017-12-06 2017-12-06 New pouring structure concrete automatic maintenance device

Country Status (1)

Country Link
CN (1) CN207549073U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565509A (en) * 2019-08-01 2019-12-13 中交二公局第二工程有限公司 High-pier built-in type health-preserving water pipe system and concrete health-preserving method thereof
CN114837443A (en) * 2022-05-28 2022-08-02 安阳建工(集团)有限责任公司 Quick-mounting type automatic concrete curing method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110565509A (en) * 2019-08-01 2019-12-13 中交二公局第二工程有限公司 High-pier built-in type health-preserving water pipe system and concrete health-preserving method thereof
CN114837443A (en) * 2022-05-28 2022-08-02 安阳建工(集团)有限责任公司 Quick-mounting type automatic concrete curing method
CN114837443B (en) * 2022-05-28 2023-11-10 安阳建工(集团)有限责任公司 Quick-mounting automatic concrete curing method

Similar Documents

Publication Publication Date Title
CN208981168U (en) A kind of bridge pier abutment body intelligent spray curing system
CN202241559U (en) Automatic concrete spraying and curing system
CN203919328U (en) The circulating automatic spray curing system in bridge prefabrication field
CN104772816B (en) Concrete curing automatic control spraying and sprinkling system and method
CN207549073U (en) New pouring structure concrete automatic maintenance device
CN207387964U (en) A kind of precast beam intelligence curing system
CN104264995A (en) Automatic spraying conservation system for high-rise building shear wall structure
CN205009378U (en) A intelligence sprays health preserving system for roof beam, board precasting yard
CN108605819A (en) Green intelligent is without electric power storage subirrigation system
CN210969332U (en) Bridge construction is with spraying maintenance system
CN204435483U (en) Plant's photovoltaic automatic spraying device
CN104255394B (en) Buried drip irrigation system
CN103147575B (en) A kind of concrete column automatic spraying device and method
CN206154492U (en) Bury shower nozzle intelligence maintenance system
CN206693132U (en) A kind of automatic sprinkler fire-extinguishing system for job site depositing dust
CN204401535U (en) A kind of tower crane Intelligent spraying system
CN203818303U (en) Large-area concrete automatic spray maintenance system
CN209273685U (en) A kind of device for the maintenance of concrete prefabricated beam
CN207480869U (en) A kind of buried automatic spray curing means of pedestal
CN204471571U (en) A kind of Precast T-Beam spray maintenance device
CN206980367U (en) A kind of depositing dust automatic sprinkler fire-extinguishing system
CN206791237U (en) A kind of Subsiding land afforests automatic sprinkling system
CN202222230U (en) Energy-saving irrigation system
CN215168249U (en) Outer wall automatic spray maintenance system
CN211113189U (en) Bridge deck pavement automatic spraying health preserving system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 450000 Shangxian Street, Longzihu Wisdom Island, Zhengdong New District, Zhengzhou City, Henan Province

Patentee after: Zhengzhou Yijian Group Co.,Ltd.

Address before: 450000, No. 91, Bauhinia Road, Zhengzhou City, Henan Province

Patentee before: ZHENGZHOU NO.1 CONSTRUCTION ENGINEERING GROUP Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180629

Termination date: 20211206