CN207523479U - Double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel - Google Patents

Double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel Download PDF

Info

Publication number
CN207523479U
CN207523479U CN201721314375.0U CN201721314375U CN207523479U CN 207523479 U CN207523479 U CN 207523479U CN 201721314375 U CN201721314375 U CN 201721314375U CN 207523479 U CN207523479 U CN 207523479U
Authority
CN
China
Prior art keywords
crossbeam
mounting base
screw rod
buried channel
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721314375.0U
Other languages
Chinese (zh)
Inventor
郭春霞
许悦
范远涛
樊毓惠
刘娟
强力
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Iron and high - speed electrical equipment Limited by Share Ltd
Original Assignee
China Railway Electric Industry Co Ltd
Baoji Equipment Co Ltd of China Railway Electrification Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Electric Industry Co Ltd, Baoji Equipment Co Ltd of China Railway Electrification Engineering Group Co Ltd filed Critical China Railway Electric Industry Co Ltd
Priority to CN201721314375.0U priority Critical patent/CN207523479U/en
Application granted granted Critical
Publication of CN207523479U publication Critical patent/CN207523479U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses pre-buried channel flow overheat rigid suspension apparatus double in a kind of tunnel, the mounting base (1) being connect including a pair with built-in groove, the mounting base (1) is U-shaped, suspension screw rod (2) is respectively connected in each mounting base (1), it is connected in the one end of the suspension screw rod (2) far from mounting base (1) across the crossbeam (3) hung at two between screw rod (2), the bar hole (4) set along crossbeam (3) length is equipped on the crossbeam (3), connection again can be along the insulation clamping device (5) of bar hole (4) activity adjustment on the crossbeam (3).

Description

Double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel
Technical field
The utility model is related to urban rail transit technology fields, and in particular to one kind rigid contact net system in tunnel The double pre-buried channel flow overheat rigid suspension apparatus used.
Background technology
Pre-buried channel flow application originates in 1931, has the history of more than 80 years so far.China's rail traffic also has been introduced by Technique starts the contact network in tunnel installation for being applied to Chinese high ferro, such as military wide high ferro, Harbin-to-Dalian high ferro, capital for 2008 Shanghai high ferro, Hangzhou-Zhejiang high ferro, Shanghai elder brother's high ferro etc..In recent years, city rail traffic also begins to use.At present Shenzhen test section, on It is used in rigid contact net in the urban subway tunnels such as sea, Tianjin.Single pre-buried channel flow is usually that double bolts connect with conversion cradle It connects, contact surface is small, and there are the risks of conduit connecting portion deformation;Aerial rigid suspension device is installed using double pre-buried channel flows Solves the above problem very well.But it is existing lifting the complicated occupied space of suspension apparatus it is big, cost is higher.
Utility model content
In order to solve deficiency of the prior art, provide that a kind of stable connection is firm, and simple and compact for structure, at low cost is outstanding Device for hoisting, technical solution is used by the utility model:
Double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel, including the mounting base that a pair is connect with built-in groove, institute The mounting base stated is U-shaped, and suspension screw rod is respectively connected in each mounting base, in the suspension screw rod far from mounting base One end be connected with across the crossbeam hung at two between screw rod, the item that is set along crossbeam length is equipped on the crossbeam Shape hole, connection again can be along the insulation clamping device of bar hole activity adjustment on the crossbeam.
The mounting base includes connecting fixed fixed part and the connecting portion for installing suspension screw rod with built-in groove, The fixed part is plate-like and is obliquely installed that the high side in side is low to be matched with tunnel inner wall radian, and the connecting portion is U-shaped Reserve the installation space of suspension screw rod top nut.
Being equipped on the connecting portion prevents the limit ribs of nut rotation.
The insulation clamping device includes the insulator being mounted on crossbeam, and it is fixed to be equipped with below the insulator Bit line presss from both sides, and bus-bar is clamped on the registration clamp.
Using the suspension apparatus of above structure due to directly being connected between mounting base and crossbeam by Hanging bolt, reduce Transition portion occupies little space and is applicable in the smaller tunnel of headroom, and reduce cost, while can pass through Hanging bolt It realizes that horizontal depth of beam is adjusted, while the lateral adjustments for the bar hole realization insulation clamping device for passing through crossbeam, adjusts more Add conveniently.
Description of the drawings
Fig. 1 is the utility model front view;
Fig. 2 is the utility model vertical view;
Fig. 3 is mounting base structure diagram.
Specific embodiment
Suspension apparatus as shown in Figure 1 includes a pair of of mounting base 1, and mounting base 1 is U-shaped for connecting fixation with built-in groove, Mounting base 1 as shown in Figure 3 includes fixed part 1-1 and connecting portion 1-2, and connecting portion 1-2 is U-shaped, and fixed part 1-1 is arranged on connecting portion The U-shaped opening both ends of 1-2 are plate-like, and connection of the mounting hole for bolt and built-in groove is equipped on fixed part 1-1 and is fixed, is set Fixed part 1-1 in connecting portion 1-2 both sides is inclined to set and the high side in side is low, surface arc transition, and setting in this way causes Fixed part 1-1 can be bonded with tunnel top domes so that mounting base 1 is installed more firm, be connected in mounting base 1 Screw rod 2 is hung, suspension screw rod 2 is arranged on connecting portion 1-2, and it is in order to which slot milling is come the company of placement that connecting portion 1-2, which is arranged to U-shaped, The nut of suspension screw rod 2 is connect, being equipped on the connecting portion 1-2 prevents the limit ribs 6 of nut rotation so that it is convenient to lower section The nut rotation of suspension screw rod 2 is fixed in connecting portion 1-2 positions during installation, while connects Hanging bolt 2 on connecting portion 1-2 and save About insufficient space spanner cannot enter the problem of connecting portion 1-2, directly prevent nut rotation by limit ribs 6, will connect Portion 1-2 make it is U-shaped can also make mounting base 1 have certain elasticity facilitate installation fix, suspension screw rod 2 far from mounting base 1 One end is connected with crossbeam 3, since mounting base 1 and suspension screw rod 2 are respectively provided with a pair, therefore crossbeam 3 across hung at two screw rods 2 it Between connect, adjusting that is fixed and can carrying out height in vertical direction to crossbeam 3 by nut is connected by nut.Such as figure Bar hole 4 is provided with shown in 2 on crossbeam 3, bar hole 4 is set along 3 length direction of crossbeam, and insulating blanked clamper is provided on crossbeam 3 Device 5 is held, insulation clamping device 5 is connected to 4 position of bar hole, can realize insulation clamping dress in the horizontal direction along bar hole 4 Put 5 activity adjustment.
The clamping device 5 that insulate includes insulator 5-1, registration clamp 5-2 is equipped with below insulator 5-1, in position line Bus-bar 5-3 is clamped on folder 5-2.

Claims (4)

1. double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel, including the mounting base (1) that a pair is connect with built-in groove, It is characterized in that:The mounting base (1) is U-shaped, suspension screw rod (2) is respectively connected in each mounting base (1), described The one end of suspension screw rod (2) far from mounting base (1) be connected with across the crossbeam (3) hung at two between screw rod (2), in institute The crossbeam (3) stated is equipped with the bar hole (4) set along crossbeam (3) length, and connection again can be along bar shaped on the crossbeam (3) The insulation clamping device (5) of hole (4) activity adjustment.
2. double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel according to claim 1, it is characterised in that:It is described Mounting base (1) including connect with built-in groove fixed fixed part (1-1) and for install suspension screw rod (2) connecting portion (1-2), the fixed part (1-1) is plate-like and is obliquely installed that the high side in side is low to be matched with tunnel inner wall radian, described The U-shaped installation space for reserving suspension screw rod (2) top nut of connecting portion (1-2).
3. double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel according to claim 2, it is characterised in that:Institute The connecting portion (1-2) stated is equipped with the limit ribs (6) for preventing nut rotation.
4. double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel according to claim 1 or 2, it is characterised in that: The insulation clamping device (5) includes the insulator (5-1) that is mounted on crossbeam (3), below the insulator (5-1) Registration clamp (5-2) is installed, bus-bar (5-3) is clamped on the registration clamp (5-2).
CN201721314375.0U 2017-10-12 2017-10-12 Double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel Active CN207523479U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721314375.0U CN207523479U (en) 2017-10-12 2017-10-12 Double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721314375.0U CN207523479U (en) 2017-10-12 2017-10-12 Double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel

Publications (1)

Publication Number Publication Date
CN207523479U true CN207523479U (en) 2018-06-22

Family

ID=62569908

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721314375.0U Active CN207523479U (en) 2017-10-12 2017-10-12 Double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel

Country Status (1)

Country Link
CN (1) CN207523479U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114383556A (en) * 2022-01-06 2022-04-22 杭州申昊科技股份有限公司 Detection device and method for rigid contact net

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114383556A (en) * 2022-01-06 2022-04-22 杭州申昊科技股份有限公司 Detection device and method for rigid contact net
CN114383556B (en) * 2022-01-06 2023-08-04 杭州申昊科技股份有限公司 Detection device and method for rigid contact net

Similar Documents

Publication Publication Date Title
CN207523479U (en) Double pre-buried channel flow overheat rigid suspension apparatus in a kind of tunnel
CN208565819U (en) A kind of adjustable suspension and support
CN103151752A (en) General lightning arrester bracket
CN106025963A (en) Anti-leakage overhead incoming line combination fixing apparatus for 10kV distribution room
CN208069463U (en) Reversely hung Yong Horizontal messenger wire clamp support construction
CN206976559U (en) A kind of high inclination-angle support
CN110061457A (en) A kind of high-voltage cable retaining clip
CN206938510U (en) A kind of Traction networks suspended structure
CN105350691A (en) Curtain wall side hanging device
CN213070755U (en) Bus post insulator convenient to installation
CN205791352U (en) The 10kV switchgear house service drop combination fastener of antiseep
CN106555499A (en) Existing single loop strain insulator steel tower cable draws lower beam
CN211971544U (en) Tower crane cable fixing device
CN209169914U (en) It broadens the cable suspension and support of section for pipe gallery
CN209881269U (en) Leaky cable lifting appliance with dual-purpose structure
CN208797510U (en) A kind of combination gantry
CN207166092U (en) A kind of adjustable suspension bracket of enclosed busbar
CN210483216U (en) Steel pipe pole cross arm
CN211018172U (en) Cable fixing and routing device for communication
CN213584125U (en) Antenna mounting device on communication tower
CN110970843A (en) Novel electronic communication wire support
CN213087619U (en) Iron tower power transmission line connecting device
CN211252280U (en) Suspension support device of rigid overhead contact network
CN209581204U (en) A kind of composite material contact network cantilever positioning device
CN205077947U (en) Communication single -pipe tower's newly -increased support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 721013 No. 196 High-tech Avenue, Baoji High-tech Development Zone, Shaanxi Province

Co-patentee after: In ferroelectric gas Industrial Co., Ltd

Patentee after: China Iron and high - speed electrical equipment Limited by Share Ltd

Address before: 721000 No. 196 Gaoxin Avenue, Weibin District, Baoji City, Shaanxi Province

Co-patentee before: In ferroelectric gas Industrial Co., Ltd

Patentee before: China Railway Electrification Bureau Group Baoji Equipment Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191219

Address after: 721013 No. 196 High-tech Avenue, Baoji High-tech Development Zone, Shaanxi Province

Patentee after: China Iron and high - speed electrical equipment Limited by Share Ltd

Address before: 721013 No. 196 High-tech Avenue, Baoji High-tech Development Zone, Shaanxi Province

Co-patentee before: In ferroelectric gas Industrial Co., Ltd

Patentee before: China Iron and high - speed electrical equipment Limited by Share Ltd