CN207514460U - A kind of generator bilayer for LNG surface units supplies tube-connecting part - Google Patents

A kind of generator bilayer for LNG surface units supplies tube-connecting part Download PDF

Info

Publication number
CN207514460U
CN207514460U CN201721462695.0U CN201721462695U CN207514460U CN 207514460 U CN207514460 U CN 207514460U CN 201721462695 U CN201721462695 U CN 201721462695U CN 207514460 U CN207514460 U CN 207514460U
Authority
CN
China
Prior art keywords
tube
bilayer
arc gusset
connecting part
generator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721462695.0U
Other languages
Chinese (zh)
Inventor
周建伟
袁辉
黎丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wison Clean Energy Technology Group Co ltd
Original Assignee
Wison Nantong Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wison Nantong Heavy Industry Co Ltd filed Critical Wison Nantong Heavy Industry Co Ltd
Priority to CN201721462695.0U priority Critical patent/CN207514460U/en
Application granted granted Critical
Publication of CN207514460U publication Critical patent/CN207514460U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Examining Or Testing Airtightness (AREA)

Abstract

The utility model is that a kind of generator bilayer for LNG surface units supplies tube-connecting part, and to have the sizing elbow of angle of turn identical with interior pipe bend, tube wall splits the HALF elbows for two valves along longitudinal direction;Arc gusset is each provided in two valve HALF elbows junctions, fixation is connect using bilateral foot welding manner with every valve HALF elbows, is fixed with the clamping part clamps flexibly dismantled.Such method sets a kind of component that can be easy to disassemble in inner tube commissure, simple and effective, manufactures cost economy, and the later stage checks that inner tube weld seam is convenient.

Description

A kind of generator bilayer for LNG surface units supplies tube-connecting part
Technical field
The utility model belongs to ship and marine engineering equipment manufacturing field, is related to dual fuel engine power plant pipeline Pipe fittings design, especially belong to a kind of generator bilayer gas supply tube-connecting part for LNG surface units.
Background technology
Important system of the LNG air supply systems as LNG fuels and energy ships is that the room temperature for generating LNG gasifiers is natural The pipe-line system that gas supply host uses.Since natural gas has inflammable and explosive characteristic, if leakage pair occurs for supply air line In entire LNG fuels and energies ship, on the bank, Offshore Units and personnel safety portion be likely to result in great loss.So it is Ensure air supply system safety, foundation《IGC CODE International Code for the Construction and Equipment of Ships Carrying Liquefied Gases in Bulk -2005》In To having using double-wall pipe and the requirement for keeping keeping positive pressure or negative pressure among outer tube and inner tube, air supply system for dual fuel engine Outer layer can only be taken as air hose, internal layer is higher than internal supply air line pressure for the bimetallic tube design or outer tube charge pressure of air supply pipe The mode of the bimetallic tube design of the inert gas of power, ensures the safety of air supply system with this.
Prior art discloses a kind of dual-layer pipe wall composite-type gas pipeline and the leakage monitoring methods for the pipeline (201210246597.9), it mainly solves high risk zone gas pipeline safety in operation deficiency and leakage point is difficult to determining ask Topic.It is characterized in that:Spatia between inner tube and outer tube is set, nitrogen displacement, the top of outer tube outer wall are carried out in spatia Several vertical branch pipes connected with spatia are set, and the top setting concrete slab of vertical branch pipe is sealed, side wall connection one A reclinate branch pipe, branch pipe end are equipped with pressure rupture disk, and installation combustible gas probe in concrete slab bottom surface stretches into perpendicular Inside allotment pipe, the fuel gas that is connected respectively to by analog signal line and RS485 data bus cables in remote monitoring room Alarm and industrial control computer, industrial control computer calculate the position that pipeline leaks.In the utility model is disclosed and is prepared The method of pipe bend, it is specific as follows:It is curved to prepare an outer tube with angle of turn identical with interior pipe bend and suitable length Head, tube wall are splitted along longitudinal direction as two valves, and internal diameter is equal to outer pipe outside diameter, is fastened on the corresponding outer tube in interior pipe bend both ends On, and welded seal will be carried out between its two valve and with outer tube lap-joint, finally in the periphery of outer tube, spraying 3PE is compound Corrosion-inhibiting coating so far completes the connection of channel bend;The method for preparing interior pipe bend is welding manner, and complex process is live Site operation is required to, difficulty of construction is big, and inner tube Welding Testing must be completed before outer pipe construction, complex procedures, the duration It is long.
Prior art discloses a kind of construction technologies of LNG powered ships air supply system bimetallic tube (201410336396.7), including two parts of internal field construction technology and outfield construction technology, by the portion of air supply system bimetallic tube Working procedure is divided to be advanced to internal field progress, reduces the working procedure under the severe environmental conditions of ship scene, is LNG fuels and energy ships The construction of oceangoing ship air supply system Double layer pipeline provides a kind of arrangement and method for construction in detail, clear, clear and definite, safe, which makes The connection mode all welded with inner and outer tubes particularly takes pipe bent position outer tube first is cut into two valve pipes pacify Dress, then to the mode that junction is welded, conventional weld detection is carried out after the completion of welding, although can make the outer tube of double-wall pipe with Positive pressure or negative pressure are kept among inner tube, but outer tube leakage should unload immediately as found, inspection, but repair welding time are re-started after repair welding Number must not exceed twice, and repair welding must scrap pipe or elbow more than twice, and waste of materials and working hour are relatively more, production cycle ratio It is longer, and site operation and inspection difficulty are big.
Invention content
The utility model is to provide a kind of generator bilayer for LNG surface units and supplies tube-connecting part, to have The sizing elbow of angle of turn identical with interior pipe bend, tube wall split the HALF elbows for two valves along longitudinal direction;In two valve HALF Elbow junction is each provided with arc gusset, and fixation is connect using bilateral foot welding manner with every valve HALF elbows, with flexibly tearing open The clamping part clamps unloaded are fixed.Such method sets a kind of component that can be easy to disassemble in inner tube commissure, simple and effective, system This economy is caused, the later stage checks that inner tube weld seam is convenient.
In order to achieve the above object, the utility model proposes a kind of generator bilayer air supply pipes for LNG surface units Connecting component, including inner tube 1, outer tube 2, said inner tube 1 is arranged on inside the outer tube 2, is set between said inner tube 1 and outer tube 2 Interstitial cavities 3 are equipped with, and have stent support;Characterized by further comprising the flanges 4 being welded on outer tube 2, are connect with flange 4 HALF elbows 5, the HALF elbows 5 are the sizing elbow with angle of turn identical with interior pipe bend, and tube wall is along vertical To the part splitted as two valves;Arc gusset 6, arc gusset 6 and every valve are each provided in two valve HALF elbows, 5 junction HALF elbows 5 are fixed using the connection of bilateral foot welding manner, and the identical gasket of shape is provided between arc gusset 6;Also wrap The clamping component 7 that can flexibly dismantle is included, corresponding arc gusset 6 is fixedly clamped by the clamping component 7.
Further, on the arc gusset 6 with bore connection bolt hole, clamping component 7 be fastening bolt, spiral shell Bolt spacing is evenly arranged,
Further, the bolt pore size distribution angle with brill connection on the arc gusset 6 is 10 ° -12 °.
A kind of fabrication and installation method of generator bilayer gas supply tube-connecting part for LNG surface units, feature exist In:Include the following steps:
A. supply air line is made according to design drawing, including inner and outer tubes;
B. 100% ray detection is carried out to the per pass weld seam of inner tube, conventional detection is carried out to outer tube;
C. the hydrostatic test of 1.5 times of design pressures is carried out to the supply air line after detection qualification;
D. it after pressure testing, is dried up using dry compressed air water stain in supply air line;
E. by part outer tube sleeve dress on inner pipe, several supports for being used to prevent inner and outer pipes bias are set between inner and outer pipes Device;
F. with normal bend, on elbow axis, one section of size scribing line is deviated toward both sides, is reserved gusset and the ruler of gasket It is very little to slice off;
G. it is positioned on sawing machine, cuts open and be split into two halves from the twice ground bit lines of elbow, each half is welded with arc gusset On elbow, the welding position of gusset and half elbow uses bilateral falsework slippage;
H. the bolt hole with brill connection on gusset,
I. by inner tube close up weld seam carry out welding close up, and to weld seam carry out 100% ray detection;
J. the gas pressure test of 1.5 times of design pressures is carried out to the inner tube after detection lattice;
K. two panels HALF elbows (5) close up and in centre by the use of gasket as gasket, are fastened later with bolt;
L. outer tube elbow and outer tube straight tube are fixed by flanged joint, and outer tube closes up completion;
M. the gas pressure test of 1.5 times of design pressures is carried out to the outer tube after detection lattice.
The utility model provides a kind of generator bilayer gas supply tube-connecting part for LNG surface units, for have with The sizing elbow of the identical angle of turn of interior pipe bend, tube wall split the HALF elbows for two valves along longitudinal direction;It is curved in two valve HALF Head junction is each provided with arc gusset, and fixation is connect using bilateral foot welding manner with every valve HALF elbows, with flexible dismounting Clamping part clamps fix.Such method sets a kind of component that can be easy to disassemble in inner tube commissure, simple and effective, manufacture Cost economy meets the requirement that combustion gas inner tube facilitates the welding inspection in later stage.
Description of the drawings
Fig. 1 show the utility model bilayer gas supply tube-connecting part structure diagram.
Fig. 2 show the more double-deck gas supply tube-connecting part structure A-A sectional views of the utility model.
Fig. 3 show the more double-deck gas supply tube-connecting part structure B-B sectional views of the utility model.
Fig. 4 show the utility model preferred embodiment bilayer gas supply tube-connecting part structure diagram.
Fig. 5 show the utility model preferred embodiment bilayer gas supply tube-connecting part structure A-A views.
Specific embodiment
Specific embodiment of the present utility model is provided, but the utility model is not limited to following implementation below in conjunction with attached drawing Mode.According to following explanation and claims, will be become apparent from feature the advantages of the utility model.It should be noted that attached drawing Using very simplified form and using non-accurate ratio, it is only used for convenience, lucidly aids in illustrating the utility model The purpose of embodiment.
Attached drawing 1,2,3 show a kind of generator bilayer air supply pipe for LNG surface units of utility model embodiment and connects Relay part, including inner tube 1, outer tube 2, said inner tube 1 is arranged on inside the outer tube 2, is set between said inner tube 1 and outer tube 2 There are interstitial cavities 3, and have stent support;Characterized by further comprising the flanges 4 being welded on outer tube 2, are connect with flange 4 HALF elbows 5, the HALF elbows 5 are the sizing elbow with angle of turn identical with interior pipe bend, and tube wall is along longitudinal direction Split the part for two valves;Arc gusset 6, arc gusset 6 and every valve HALF are each provided in two valve HALF elbows, 5 junction Elbow 5 is fixed using the connection of bilateral foot welding manner, and the identical gasket of shape is provided between arc gusset 6;It has further included Corresponding arc gusset 6 is fixedly clamped by the clamping component 7 that can flexibly dismantle, the clamping component 7.
A kind of component that can be easy to disassemble in inner tube commissure in above-described embodiment is set, cost economy is manufactured, meets Combustion gas inner tube facilitates the requirement of the welding inspection in later stage, and there is the easy to manufacture and install, later stage to check the convenient effect of inner tube weld seam.
It has been found that also exist during above-described embodiment work certain the defects of, in HALF types elbow before On, arc gusset is directly welded at the outer surface of half elbow, and corresponding arc gusset 6 is fixedly clamped by clamping component, in this way Cause design pressure that code requirement is not achieved, the water pressure test of pipeline workshop, leakage is seriously;And in making, difficulty is big, technique It is complicated.
In view of the above-mentioned problems, clamping component is further proposed by the way of fastening bolt, on the arc gusset 6 With the bolt hole for boring connection, clamping component 7 is fastening bolt, and pitch of bolts is evenly arranged,
Further, the bolt pore size distribution angle with brill connection on the arc gusset 6 is 10 ° -12 °.
Further, it is lengthened on the width dimensions of arc gusset, size extends to the notch both sides of half elbow, thick Increasing to equal flange thickness on degree, welding procedure uses bilateral full weld,
In above-described embodiment HALF types are completely solved for the generator bilayer of LNG surface units gas supply tube-connecting part Elbow cannot bear the technical issues of 0.7MPa, have preferable sealing and measuring body effect, the inspection of inner tube weld seam is taken Remove the mode of HALF type elbows, solve the problems, such as to check that weld seam needs to remove whole outer tube, have it is convenient, save Artificial effect.
Although the utility model has been disclosed with preferred embodiment as above, so it is not limited to the utility model.This reality It is without departing from the spirit and scope of the utility model, each when that can make with novel those of ordinary skill in the art Kind changes and retouches.Therefore, the scope of protection of the utility model is when subject to those as defined in claim.

Claims (3)

1. a kind of generator bilayer for LNG surface units supplies tube-connecting part, described including inner tube (1), outer tube (2) Inner tube (1) is arranged on the outer tube (2) inside, interstitial cavities (3) is provided between said inner tube (1) and outer tube (2), and have branch Frame supports;Characterized by further comprising the flange (4) being welded on outer tube (2), the HALF elbows (5) being connect with flange (4), institute The HALF elbows (5) stated are the sizing elbow with angle of turn identical with interior pipe bend, and tube wall is splitted along longitudinal direction as two valves Part;Arc gusset (6), arc gusset (6) and every valve HALF elbows are each provided in two valve HALF elbows (5) junctions (5) it is fixed using the connection of bilateral foot welding manner, the identical gasket of shape is provided between arc gusset (6);It has further included Corresponding arc gusset (6) is fixedly clamped by the clamping component (7) that can flexibly dismantle, the clamping component (7).
2. a kind of generator bilayer for LNG surface units according to claim 1 supplies tube-connecting part, feature It is:On the arc gusset (6) with bore connection bolt hole (71), clamping component (7) be fastening bolt (72), bolt (72) spacing is evenly arranged.
3. a kind of generator bilayer for LNG surface units according to claim 2 supplies tube-connecting part, feature It is:It is 10 ° -12 ° to be distributed angle with the bolt hole (71) for boring connection on the arc gusset (6).
CN201721462695.0U 2017-11-06 2017-11-06 A kind of generator bilayer for LNG surface units supplies tube-connecting part Active CN207514460U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721462695.0U CN207514460U (en) 2017-11-06 2017-11-06 A kind of generator bilayer for LNG surface units supplies tube-connecting part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721462695.0U CN207514460U (en) 2017-11-06 2017-11-06 A kind of generator bilayer for LNG surface units supplies tube-connecting part

Publications (1)

Publication Number Publication Date
CN207514460U true CN207514460U (en) 2018-06-19

Family

ID=62537152

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721462695.0U Active CN207514460U (en) 2017-11-06 2017-11-06 A kind of generator bilayer for LNG surface units supplies tube-connecting part

Country Status (1)

Country Link
CN (1) CN207514460U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107747655A (en) * 2017-11-06 2018-03-02 惠生(南通)重工有限公司 A kind of double-deck supply tube-connecting part of generator for LNG surface units
CN108581264A (en) * 2018-07-24 2018-09-28 张月文 A kind of double-layer bend processing method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107747655A (en) * 2017-11-06 2018-03-02 惠生(南通)重工有限公司 A kind of double-deck supply tube-connecting part of generator for LNG surface units
CN108581264A (en) * 2018-07-24 2018-09-28 张月文 A kind of double-layer bend processing method
CN108581264B (en) * 2018-07-24 2020-11-03 张月文 Double-layer elbow machining method

Similar Documents

Publication Publication Date Title
CN106322000A (en) Liquefied natural gas power driving vessel gas supply system double-wall pipe construction process
CN205938242U (en) Double -wall pipe inner tube is to removable outer tube of interface welding seam department
CN207514460U (en) A kind of generator bilayer for LNG surface units supplies tube-connecting part
JPS60184794A (en) Remotely detachable joint
CN206246840U (en) A kind of LNG Pipeline Crossing Programs tunnel headwall sealing section
CN106813036A (en) A kind of gas fuel pipe compensator with double-walled construction
CN206320464U (en) Repairing applied to PCCP pipe fittings connects section
CN111853843A (en) Carbon steel flue/chimney lining stainless steel plate structure and air tightness detection method
CN107747655A (en) A kind of double-deck supply tube-connecting part of generator for LNG surface units
CN210462090U (en) Non-welding connecting pipe type tapping/plugging tee joint
CN104121421A (en) Construction technology for double-layer pipelines of LNG powered ship gas supply system
CN216813194U (en) Three-wall pipe for dangerous medium transmission
RU176942U1 (en) PIPELINE TEE COIL FOR PIPELINES
RU2374551C2 (en) Method for repair of pipeline defects
CN212537891U (en) Carbon steel flue/chimney lining stainless steel plate structure
CN115596897A (en) Liquid oxygen supply pipeline for hypersonic high-temperature wind tunnel and precooling method thereof
CN112460380B (en) Clamping plate type on-site joint coating method for heat-insulating pipeline
CN102853184A (en) Movable joint type middle-high pressure pipeline connection part
CN203857140U (en) Direct-burial prefabricated independent thermal insulation layer sealing steam pipe with pipe bundle leakage alarm
CN204986210U (en) Big local prosthetic devices of non - excavation of pipe diameter pipeline
CN205535084U (en) Oil gas warehousing and transportation pipeline with leak detection function
CN113700946B (en) Pipeline construction method for flare emptying system
RU2325578C1 (en) Method of repairing of submerged pipeline
RU209235U1 (en) DEVICE FOR SHUT-OFF OF PIPELINE TO PRESSURE VESSEL
CN211906604U (en) Emergency leakage stoppage teaching aid

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 226000 port industrial zone 3, Nantong Economic and Technological Development Zone, Jiangsu Province

Patentee after: Wison Clean Energy Technology Group Co.,Ltd.

Country or region after: China

Address before: 226009 Jianghai Road 189, Nantong Economic and Technological Development Zone, Nantong City, Jiangsu Province

Patentee before: WISON(NANTONG) HEAVY INDUSTRY Co.,Ltd.

Country or region before: China

CP03 Change of name, title or address