CN211906604U - Emergency leakage stoppage teaching aid - Google Patents

Emergency leakage stoppage teaching aid Download PDF

Info

Publication number
CN211906604U
CN211906604U CN202020818128.XU CN202020818128U CN211906604U CN 211906604 U CN211906604 U CN 211906604U CN 202020818128 U CN202020818128 U CN 202020818128U CN 211906604 U CN211906604 U CN 211906604U
Authority
CN
China
Prior art keywords
pipe
horizontal pipe
blind plate
clamp
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020818128.XU
Other languages
Chinese (zh)
Inventor
胡忆沩
赵志刚
牛雅士
王希智
潘万年
翟福栋
郭永兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Branch Of Gunnerys Co ltd
Original Assignee
Tianjin Branch Of Gunnerys Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Branch Of Gunnerys Co ltd filed Critical Tianjin Branch Of Gunnerys Co ltd
Priority to CN202020818128.XU priority Critical patent/CN211906604U/en
Application granted granted Critical
Publication of CN211906604U publication Critical patent/CN211906604U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses an emergency leakage stoppage teaching aid, which comprises a bottom plate and two vertical pipes on the bottom plate, wherein an upper blind plate and a lower blind plate are respectively arranged in each vertical pipe at intervals; a first quick joint and a first leakage point are respectively arranged on the vertical pipe section between the upper blind plate and the lower blind plate; the upper end of one vertical pipe is connected with a first horizontal pipe and a second horizontal pipe through a tee joint, the upper end of the other vertical pipe is welded with a third horizontal pipe, a left blind plate is arranged in the first horizontal pipe, and a right blind plate is arranged in the third horizontal pipe; the first horizontal pipe and the third horizontal pipe are connected with a valve through a connecting flange; a second quick joint is arranged on a horizontal pipe section between the left blind plate and the right blind plate; a pressure container is welded on the outer side of the third horizontal pipe, a second leakage point is arranged on the pressure container, and one end of the pressure container is connected with a third quick joint; the second horizontal pipe is connected with the reducing straight pipe through an elbow, and a fourth quick joint is arranged on the reducing straight pipe; the second horizontal pipe is provided with a third leakage point. The utility model discloses realize the all-round emergent leaking stoppage teaching training that carries on pressure water or pressure gas.

Description

Emergency leakage stoppage teaching aid
Technical Field
The utility model relates to an emergent leaking stoppage teaching aid technical field, concretely relates to emergent leaking stoppage teaching aid.
Background
The emergency leaking stoppage technology of the fluid conveying pipeline is continuously explored and improved, but the special leakage defects of various pipelines under different working conditions are difficult to predict, and a plurality of problems are brought to emergency leaking stoppage work. Therefore, people develop an emergency leaking stoppage teaching aid and perform teaching training by simulating various different conditions. However, the existing emergency leaking stoppage teaching aid is large in size and unreasonable in structural design, teaching demonstration and operation cannot be performed in a classroom, and simulation, leaking stoppage training and teaching meeting actual multiple leakage working conditions cannot be realized.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing an emergent leaking stoppage teaching aid to the technical defect who exists among the prior art.
For realizing the utility model discloses a technical scheme that the purpose adopted is:
an emergency leakage stoppage teaching aid comprises a bottom plate and two vertical pipes arranged on the bottom plate, wherein an upper blind plate and a lower blind plate are arranged in each vertical pipe at intervals; a first quick joint and a first leakage point are respectively arranged on the vertical pipe section between the upper blind plate and the lower blind plate; the upper end of one vertical pipe is connected with a first horizontal pipe and a second horizontal pipe through a tee joint, the upper end of the other vertical pipe is welded with a third horizontal pipe, a left blind plate is arranged in the first horizontal pipe, and a right blind plate is arranged in the third horizontal pipe; the first horizontal pipe and the third horizontal pipe are connected with a valve through a connecting flange; a second quick joint is arranged on the horizontal pipe section between the left blind plate and the right blind plate; a pressure container is welded on the outer side of the third horizontal pipe, a second leakage point is arranged on the pressure container, and one end of the pressure container is connected with a third quick coupling; the second horizontal pipe is connected with the reducing straight pipe through an elbow, and a fourth quick connector is arranged on the reducing straight pipe; and a third leakage point is arranged on the second horizontal pipe between the elbow and the tee joint.
And one side of the valve is provided with a flange clamp, and the other side of the valve is provided with a steel wire which is locked by a flange nut and is locked by a screw hole injection valve which is arranged on a flange stud through threaded connection.
The tee joint is provided with a tee joint clamp, the elbow is provided with an elbow clamp, the reducing part of the reducing straight pipe is provided with a reducing straight pipe clamp, and the third leakage point on the second horizontal pipe is provided with a straight pipe clamp.
And the three-way clamp, the elbow clamp, the straight pipe clamp and the reducing straight pipe clamp are respectively provided with an agent injection hole.
The utility model discloses emergent leaking stoppage teaching aid, through with the tee junction for the pipeline section, connect the reducing straight tube with the elbow, the straight tube passes through flange joint with pressure vessel welding and valve to setting up corresponding simulation leakage point and setting up corresponding anchor clamps at corresponding leakage point, and set up a plurality of blind plates in the pipeline section, independently cut apart each leakage point, thereby realize with the omnidirectional leaking stoppage teaching training that meets an urgent need.
Drawings
Fig. 1 shows the schematic diagram of the emergency leak stoppage teaching aid of the utility model.
Detailed Description
The present invention will be described in further detail with reference to the following drawings and specific embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
As shown in fig. 1, an emergency leak stoppage teaching aid comprises a base plate 1 and two stand pipes 2 arranged on the base plate, wherein an upper blind plate 31 and a lower blind plate 32 are arranged in each stand pipe at intervals; a first quick joint 3 and a first leakage point 2 are respectively arranged on the vertical pipe section between the upper blind plate and the lower blind plate; the upper end of one vertical pipe is connected with a first horizontal pipe 5 and a second horizontal pipe 20 through a tee joint 18, the upper end of the other vertical pipe is welded with a third horizontal pipe 6, a left blind plate 7 is arranged in the first horizontal pipe, and a right blind plate 8 is arranged in the third horizontal pipe; the first horizontal pipe and the third horizontal pipe are connected with a valve 10 through a connecting flange 9; a second quick joint 14 is arranged on the horizontal pipe section between the left blind plate and the right blind plate; a pressure container 15 is welded on the outer side of the third horizontal pipe, a second leakage point 16 is arranged on the pressure container, and one end of the pressure container is connected with a third quick joint 17; the second horizontal pipe is connected with a reducing straight pipe 25 through an elbow 23, and a fourth quick joint 26 is arranged on the reducing straight pipe; and a third leakage point 21 is arranged on a second horizontal pipe between the elbow and the tee joint, and the diameter of the upper pipe section of the reducing straight pipe is larger than that of the lower pipe section 29.
A flange leakage stopping clamp 11 is mounted on a connecting flange on one side of the valve, a steel wire rope lock leakage stopping clamp 13 is mounted on a connecting flange on the other side of the valve, and a special screw hole injection valve 12 is rotationally locked on a flange screw through a flange connecting nut.
Wherein, install tee bend anchor clamps 19 on the tee bend, install elbow anchor clamps 24 on the elbow, reducing portion 27 department of reducing straight pipe installs reducing straight pipe anchor clamps 28, the third leak point department on the second horizontal pipe installs straight pipe anchor clamps 22.
It should be noted that, in the utility model, a corresponding blind plate is also arranged in the pipe section between the three-way clamp 19 and the straight pipe clamp 22 and connected with a quick coupling, and a leakage point is arranged at the joint of the three-way and the pipe section, so that the teaching demonstration of realizing the leakage point leakage stoppage of the three-way can be realized; similarly, a blind plate is arranged in the pipe section between the straight pipe clamp 22 and the elbow clamp 24 and connected with a quick connector, so that teaching demonstration for realizing straight pipe leakage point leakage stoppage can be realized; similarly, a blind plate is arranged in the reducing straight pipe 25, pressure water or pressure gas is introduced by using a fourth quick connector to realize teaching demonstration of emergency leakage stoppage of the leakage point of the elbow, and the pressure water or the pressure gas is introduced at the free end of the reducing straight pipe to realize teaching demonstration of emergency leakage stoppage of the leakage point of the reducing part of the reducing straight pipe.
The three-way clamp, the elbow clamp, the straight pipe clamp and the reducing straight pipe clamp are respectively provided with an injection hole 30.
To sum up, can see, the utility model discloses emergent leaking stoppage teaching aid through with tee junction for the pipeline section, connects the reducing straight tube with the elbow, and the straight tube passes through flange joint with pressure vessel welding and valve to setting up corresponding simulation leak point and setting up the anchor clamps that correspond at corresponding leak point, and set up a plurality of blind plates in the pipeline section, independently cutting apart each leak point, thereby realize with the omnidirectional leaking stoppage teaching training that meets an urgent need.
The foregoing is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, a plurality of improvements and decorations can be made without departing from the principle of the present invention, and these improvements and decorations should also be regarded as the protection scope of the present invention.

Claims (4)

1. An emergency leakage stoppage teaching aid is characterized by comprising a bottom plate and two vertical pipes arranged on the bottom plate, wherein an upper blind plate and a lower blind plate are arranged in each vertical pipe at intervals; a first quick joint and a first leakage point are respectively arranged on the vertical pipe section between the upper blind plate and the lower blind plate; the upper end of one vertical pipe is connected with a first horizontal pipe and a second horizontal pipe through a tee joint, the upper end of the other vertical pipe is welded with a third horizontal pipe, a left blind plate is arranged in the first horizontal pipe, and a right blind plate is arranged in the third horizontal pipe; the first horizontal pipe and the third horizontal pipe are connected with a valve through a connecting flange; a second quick joint is arranged on the horizontal pipe section between the left blind plate and the right blind plate; a pressure container is welded on the outer side of the third horizontal pipe, a second leakage point is arranged on the pressure container, and one end of the pressure container is connected with a third quick coupling; the second horizontal pipe is connected with the reducing straight pipe through an elbow, and a fourth quick connector is arranged on the reducing straight pipe; and a third leakage point is arranged on the second horizontal pipe between the elbow and the tee joint.
2. The emergency leak stoppage teaching aid according to claim 1, wherein a flange leak stoppage jig is mounted on a connecting flange on one side of the valve, a wire rope lock leak stoppage jig is mounted on a connecting flange on the other side of the valve, and a special screw hole injection valve which is locked on a flange screw in a rotating manner through a flange connecting nut is provided.
3. The teaching aid for emergency leak stoppage according to claim 2, wherein a tee clamp is installed on the tee, an elbow clamp is installed on the elbow, a reducing portion of the reducing straight pipe is provided with a reducing straight pipe clamp, and a third leakage point on the second horizontal pipe is provided with a straight pipe clamp.
4. An emergency leak stoppage teaching aid as set forth in claim 3, wherein the three-way clamp, the elbow clamp, the straight pipe clamp and the reducing straight pipe clamp are respectively provided with an agent injection hole.
CN202020818128.XU 2020-05-15 2020-05-15 Emergency leakage stoppage teaching aid Active CN211906604U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020818128.XU CN211906604U (en) 2020-05-15 2020-05-15 Emergency leakage stoppage teaching aid

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020818128.XU CN211906604U (en) 2020-05-15 2020-05-15 Emergency leakage stoppage teaching aid

Publications (1)

Publication Number Publication Date
CN211906604U true CN211906604U (en) 2020-11-10

Family

ID=73270279

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020818128.XU Active CN211906604U (en) 2020-05-15 2020-05-15 Emergency leakage stoppage teaching aid

Country Status (1)

Country Link
CN (1) CN211906604U (en)

Similar Documents

Publication Publication Date Title
CN103574215B (en) PE pipeline pressure test blind plate
CN201129586Y (en) Polyethylene, steel bushing flange and pipeline connecting structure
WO2018000538A1 (en) Unmanned shipborne pipeline maintenance fixture
CN2731237Y (en) Device for repairing damaged pipe line
CN205748841U (en) A kind of pressure tester for tubes
CN211906604U (en) Emergency leakage stoppage teaching aid
CN201765743U (en) Chemical pipeline blocking leakage under pressure test training integrated equipment
RU178729U1 (en) CUTTED TEE WITH STAMPED TUBE
CN203757286U (en) Hough type pipeline connecting and repairing device
CN211779518U (en) Inclined neck type welding neck flange
CN111462569A (en) Emergency leakage stoppage teaching aid
CN212616918U (en) Expansion joint for connecting pump test pipeline
CN211232020U (en) Three-way joint convenient and rapid to insert
WO2017070987A1 (en) Construction method for gas pipeline system
CN210830890U (en) Connecting piece for pipeline
KR20180124665A (en) No-welding flange structure for piping
CN201032036Y (en) Pipe fitting dedicated for pipeline non-stop transport construction
CN201748105U (en) Novel online keeping-gas pressed plugging sealing clamp
CN207514460U (en) A kind of generator bilayer for LNG surface units supplies tube-connecting part
CN202901691U (en) Flange leaking stoppage device
RU116953U1 (en) PIPE CUTTING WELDING TEE
CN105841901A (en) Pipe pressure testing apparatus
CN109141850A (en) A kind of pipe positioning pressure testing platform
CN206583582U (en) A kind of complete fast pressure testing device of piping lane pipeline
US20120049515A1 (en) Boltless Pipe Joint Assembly

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant