CN207453985U - A kind of high crag tunnel for the first time lining trolley one lining trolley device - Google Patents

A kind of high crag tunnel for the first time lining trolley one lining trolley device Download PDF

Info

Publication number
CN207453985U
CN207453985U CN201721177192.9U CN201721177192U CN207453985U CN 207453985 U CN207453985 U CN 207453985U CN 201721177192 U CN201721177192 U CN 201721177192U CN 207453985 U CN207453985 U CN 207453985U
Authority
CN
China
Prior art keywords
trolley
crag
tunnel
lining trolley
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721177192.9U
Other languages
Chinese (zh)
Inventor
黄高飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luoyang Gaofei Bridges And Tunnels Machinery Co ltd
Original Assignee
Luoyang Fly Bridge Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luoyang Fly Bridge Machinery Co Ltd filed Critical Luoyang Fly Bridge Machinery Co Ltd
Priority to CN201721177192.9U priority Critical patent/CN207453985U/en
Application granted granted Critical
Publication of CN207453985U publication Critical patent/CN207453985U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A kind of one lining trolley device of high crag tunnel lining trolley for the first time, lining trolley is arranged to leading portion, back segment for the first time in high crag tunnel, and high crag tunnel sets at least three door frames in the leading portion of lining trolley, back segment for the first time;The door pillar of door frame both sides is respectively arranged below two foundation framves, and two foundation frame rear ends set hydraulic lifting system respectively, and two foundation frame foreparts set hydraulic lifting system respectively, and hydraulic lifting system is respectively arranged below trolley running device;Longitudinally disposed two parallel guide rails between above the door frame of top trolley running device, the front upper of guide rail set top trolley running device, and guide rail rear upper sets hoist engine;The top of the utility model uses movable stand, entered by movable stand below the section excavated out and carry out carrying out tunnel wall lining reinforcement construction for the first time, ensure the soil is porous, the section in rubble location can be constructed safely, ensure the progress and quality of construction.

Description

A kind of high crag tunnel for the first time lining trolley one lining trolley device
Technical field
The utility model is related to the bench frame apparatus of high crag tunnel lining cutting for the first time, especially a kind of high crag tunnel serves as a contrast for the first time One lining trolley device of platform building cart.
Background technology
At present, the highway of China's infrastructure, railway are crossed over mountain after mountain, the construction of tunnel piercing run into loess soil property, dredge Song Yi cave in soil property, meet water and easily soften the construction end face in location, rubble location, have the danger of landslide, that is, excessive risk at any time High crag tunnel.The distance that the high crag tunnel of excessive risk once excavates is near, dig two meters it is necessary to reinforce immediately, supporting, serve as a contrast for the first time It builds, due to there is the danger of landslide, falling rocks, construction personnel cannot construct below open section, in order to avoid project progress Slowly, there is construction safety accident, improve construction technology;In view of the foregoing, it is proposed that a kind of high crag tunnel lining cutting for the first time One lining trolley device of trolley.
Utility model content
The purpose of this utility model is to overcome the constructions in tunnel piercing to run into loess soil property, the loose soil that easily caves in Matter meets the construction end face that water easily softens location, rubble location, has the danger of landslide at any time, the high crag tunnel of excessive risk is once opened The distance of digging is near, and two meters of digging it is necessary to reinforce immediately, supporting, for the first time lining cutting, due to there is the danger of landslide, falling rocks, construction personnel It cannot construct below open section, in case project progress is slow, construction safety accident occur, improves construction technology. By reasonably designing, an a kind of lining trolley device of high crag tunnel lining trolley for the first time is provided, the utility model is high-risk The top of lining trolley uses movable stand for the first time in rock tunnel, enters presence landslide by movable stand, the excavation of falling rocks goes out Section below carry out to tunnel wall carry out for the first time lining reinforcement construct, after being reinforced to tunnel wall, then to tunnel depths into Row driving;Ensure that high crag tunnel is for the first time under lining trolley the soil is porous, the section in rubble location can be constructed safely The upright often conveying cubic metre of earth and stone ensures the progress and quality of construction.
The utility model to achieve these goals, adopts the following technical scheme that:A kind of high crag tunnel lining cutting platform for the first time Vehicle one lining trolley device, be by:Trolley running device, hydraulic lifting system, door frame, screw, High molecular weight polyethylene are compound Template, top trolley running device, horizontal hydraulic pressure crossing system, top rack, strut, template jack, hoisting mechanism into;It is high Lining trolley is arranged to leading portion, back segment for the first time in crag tunnel, high crag tunnel set for the first time in the leading portion of lining trolley, back segment to Few three door frames;The door pillar of door frame both sides is respectively arranged below two foundation framves, and two foundation frame rear ends set hydraulic lifting system respectively System, two foundation frame foreparts set hydraulic lifting system respectively, and hydraulic lifting system is respectively arranged below trolley running device;
Longitudinally disposed two parallel guide rails between above the door frame of top trolley running device, the front upper of guide rail are set Top trolley running device is put, guide rail rear upper sets hoist engine;The door frame upper center of front end sets pulley, top trolley Symmetrical draw ring is reserved in front end, rear end respectively in the middle part of the crossbeam of running gear rear end;The draw ring of crossbeam front end and pulley, hoist engine Between steel wire rope is set, the steel wire rope other end is connected setting around hoist engine with the draw ring of crossbeam rear end;Dress is walked by upper stage garage Top is put with setting top rack, two longerons are symmetrical arranged between top trolley running device and top rack;A piece longeron Inside hinge ear is set, traversing hydraulic pressure cylinder seat is set above in the middle part of the trolley running device of top, hinge ear and traversing hydraulic pressure cylinder seat it Between set horizontal hydraulic pressure crossing system;
High molecular weight polyethylene composite shuttering, High molecular weight polyethylene compound die are set with door frame both sides above the rack of top Plate is arranged to arch, and template jack is set between High molecular weight polyethylene composite shuttering both sides lower end and ground;
The screw that spacing sets different length respectively is corresponded between door frame both sides and High molecular weight polyethylene composite shuttering;It is high After the lining trolley removal for the first time of crag tunnel, screw support, which is replaced, to be arranged to:Ground and High molecular weight polyethylene composite shuttering it Between strut is set.
Operation principle:In high crag tunnel excavating process, lining trolley is walked by upper stage garage for the first time in high crag tunnel Device moves the top rack on top, and top rack drives High molecular weight polyethylene composite shuttering, answers High molecular weight polyethylene Shuttering end is docked with high crag constructing tunnel section, and construction personnel passes through pick below High molecular weight polyethylene composite shuttering Construction section is inwardly excavated into equipment;
Tap into construction section after, depth distance High molecular weight polyethylene composite shuttering end rice 2 meters~2.5 meters when, Observation construction section passes through trolley running device or the macromolecule of top trolley running device drive equipment without native stone loose phenomenon Weight northylen composite shuttering is walked into the construction section newly excavated, and makes the end of High molecular weight polyethylene composite shuttering Dock new construction section;
After docking new construction section, by working window prefabricated on High molecular weight polyethylene composite shuttering to newly excavating Construction section tunnel wall carry out a construction of concrete lining;
Construction of concrete lining is completed after solidifying, and High molecular weight polyethylene composite shuttering is propped up by strut Support;
After High molecular weight polyethylene composite shuttering firm supporting, screw is removed, passes through hydraulic lifting system, template jack It shrinks, reduces trolley running device and depart from High molecular weight polyethylene composite shuttering, the concrete lining of construction section is completed; The High molecular weight polyethylene composite shuttering more renewed above trolley running device, repeat last time method excavate construction and Concrete lining.
Advantageous effect:The top of lining trolley uses movable stand to the utility model for the first time in high crag tunnel, passes through Movable stand, which enters to exist, to cave in, carries out carrying out tunnel wall lining reinforcement construction for the first time below the section excavated out of falling rocks, After being reinforced to tunnel wall, then tunneled to tunnel depths;Ensure the soil is porous, the section in rubble location can be safe It constructs, high crag tunnel normally conveys the cubic metre of earth and stone in lining trolley lower section for the first time, ensures the progress and quality of construction.
Description of the drawings
The utility model is described in further detail below in conjunction with the accompanying drawings:
Fig. 1 is general assembly structure diagram;
Fig. 2 is side structure schematic view;
In Fig. 1,2:Trolley running device 1, hydraulic lifting system 2, door frame 3, screw 4, High molecular weight polyethylene compound die Plate 5, top trolley running device 6, horizontal hydraulic pressure crossing system 7, top rack 8, strut 9, template jack 10, hoist engine 11。
Specific embodiment
The utility model is described in further detail with specific embodiment below in conjunction with the accompanying drawings:
Lining trolley is arranged to leading portion, back segment for the first time in high crag tunnel, high crag tunnel for the first time the leading portion of lining trolley, after At least three door frames 3 are set in section;The door pillar of 3 both sides of door frame is respectively arranged below two foundation framves, and two foundation frame rear ends are set respectively Hydraulic lifting system 2 is put, two foundation frame foreparts set hydraulic lifting system 2 respectively, and hydraulic lifting system 2 is respectively arranged below platform Garage's walking apparatus 1;
Longitudinally disposed two parallel guide rails between 3 top of door frame of top trolley running device 6, the front upper of guide rail Top trolley running device 6 is set, and guide rail rear upper sets hoist engine 11;3 upper center of door frame of front end sets pulley, on Symmetrical draw ring is reserved in front end, rear end respectively in the middle part of the crossbeam of 6 rear end of portion's trolley running device;The draw ring and cunning of crossbeam front end Steel wire rope is set between wheel, hoist engine 11, and the steel wire rope other end is connected setting around hoist engine 11 with the draw ring of crossbeam rear end;On Trolley running device 6 top in portion's is symmetrical arranged two with setting top rack 8 between top trolley running device 6 and top rack 8 Root longeron;The inside of a piece longeron sets hinge ear, and trolley running device 6 middle part in top sets traversing hydraulic pressure cylinder seat, cuts with scissors ear above Horizontal hydraulic pressure crossing system 7 is set between traversing hydraulic pressure cylinder seat;
Rack 8 top in top sets High molecular weight polyethylene composite shuttering 5 with 3 both sides of door frame, and High molecular weight polyethylene is multiple Shuttering 5 is arranged to arch, and template jack 10 is set between 5 both sides lower end of High molecular weight polyethylene composite shuttering and ground;
The screw that spacing sets different length respectively is corresponded between 3 both sides of door frame and High molecular weight polyethylene composite shuttering 5 4;After the lining trolley removal for the first time of high crag tunnel, the support of screw 4, which is replaced, to be arranged to:Ground and High molecular weight polyethylene compound die Strut 9 is set between plate 5.

Claims (4)

1. a kind of high crag tunnel for the first time lining trolley one lining trolley device, be by:Trolley running device (1), hydraulic lifting System (2), door frame (3), screw (4), High molecular weight polyethylene composite shuttering (5), top trolley running device (6), horizontal liquid Crossing system (7), top rack (8), strut (9), template jack (10), hoist engine (11) is pressed to form;It is characterized in that:It is high Lining trolley is arranged to leading portion, back segment for the first time in crag tunnel, high crag tunnel set for the first time in the leading portion of lining trolley, back segment to Few three door frames (3);The door pillar of door frame (3) both sides is respectively arranged below two foundation framves, and two foundation frame rear ends set hydraulic pressure respectively Jacking system (2), two foundation frame foreparts set hydraulic lifting system (2) respectively, and hydraulic lifting system (2) is respectively arranged below platform Garage's walking apparatus (1).
2. a kind of high crag tunnel according to claim 1 for the first time lining trolley one lining trolley device, it is characterised in that: Longitudinally disposed two parallel guide rails between above the door frame (3) of top trolley running device (6), the front upper of guide rail are set Top trolley running device (6), guide rail rear upper set hoist engine (11);Door frame (3) upper center of front end sets pulley, Symmetrical draw ring is reserved in front end, rear end respectively in the middle part of the crossbeam of top trolley running device (6) rear end;The draw ring of crossbeam front end with Steel wire rope is set between pulley, hoist engine (11), and the steel wire rope other end is connected around hoist engine (11) with the draw ring of crossbeam rear end It sets;With setting top rack (8), top trolley running device (6) and top rack above top trolley running device (6) (8) two longerons are symmetrical arranged between;The inside of a piece longeron sets hinge ear, is set above in the middle part of top trolley running device (6) Traversing hydraulic pressure cylinder seat is put, cuts with scissors and horizontal hydraulic pressure crossing system (7) is set between ear and traversing hydraulic pressure cylinder seat.
3. a kind of high crag tunnel according to claim 1 for the first time lining trolley one lining trolley device, it is characterised in that: High molecular weight polyethylene composite shuttering (5) is set with door frame (3) both sides above top rack (8), High molecular weight polyethylene is compound Template (5) is arranged to arch, and template jack is set between High molecular weight polyethylene composite shuttering (5) both sides lower end and ground (10)。
4. a kind of high crag tunnel according to claim 1 for the first time lining trolley one lining trolley device, it is characterised in that: The screw (4) that spacing sets different length respectively is corresponded between door frame (3) both sides and High molecular weight polyethylene composite shuttering (5); After the lining trolley removal for the first time of high crag tunnel, screw (4) support, which is replaced, to be arranged to:Ground and High molecular weight polyethylene compound die Strut (9) is set between plate (5).
CN201721177192.9U 2017-09-14 2017-09-14 A kind of high crag tunnel for the first time lining trolley one lining trolley device Active CN207453985U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721177192.9U CN207453985U (en) 2017-09-14 2017-09-14 A kind of high crag tunnel for the first time lining trolley one lining trolley device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721177192.9U CN207453985U (en) 2017-09-14 2017-09-14 A kind of high crag tunnel for the first time lining trolley one lining trolley device

Publications (1)

Publication Number Publication Date
CN207453985U true CN207453985U (en) 2018-06-05

Family

ID=62283050

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721177192.9U Active CN207453985U (en) 2017-09-14 2017-09-14 A kind of high crag tunnel for the first time lining trolley one lining trolley device

Country Status (1)

Country Link
CN (1) CN207453985U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756956A (en) * 2018-07-30 2018-11-06 洛阳高飞桥隧机械有限公司 A kind of anchor bar of waterproof plate in tunnels reinforcement trolley is laid with the application method of positioning device
CN109538268A (en) * 2018-11-15 2019-03-29 河南工程学院 What a kind of mine laneway expanded when repairing interim moves suspension device
CN111963217A (en) * 2020-07-30 2020-11-20 中铁十七局集团第三工程有限公司 Assembled tunnel trolley
CN114060064A (en) * 2021-11-11 2022-02-18 武汉二航路桥特种工程有限责任公司 Numerical control steel strip reinforcing trolley for damaged highway tunnel

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108756956A (en) * 2018-07-30 2018-11-06 洛阳高飞桥隧机械有限公司 A kind of anchor bar of waterproof plate in tunnels reinforcement trolley is laid with the application method of positioning device
CN109538268A (en) * 2018-11-15 2019-03-29 河南工程学院 What a kind of mine laneway expanded when repairing interim moves suspension device
CN111963217A (en) * 2020-07-30 2020-11-20 中铁十七局集团第三工程有限公司 Assembled tunnel trolley
CN114060064A (en) * 2021-11-11 2022-02-18 武汉二航路桥特种工程有限责任公司 Numerical control steel strip reinforcing trolley for damaged highway tunnel
CN114060064B (en) * 2021-11-11 2024-04-16 中交特种工程有限公司 Defective highway tunnel numerical control steel belt reinforcing trolley

Similar Documents

Publication Publication Date Title
CN207453985U (en) A kind of high crag tunnel for the first time lining trolley one lining trolley device
CN103850684B (en) A kind of shaft excavation machine expands the sinking shaft technique of anti-well rig pilot shaft
CN104989272B (en) Upward inverse well drilling process
CN106761763A (en) A kind of novel silo development machine and its construction method
CN206267851U (en) A kind of novel silo development machine
CN101832103B (en) Movable two-arm hanging wall anchor rod and anchor cable construction drill carriage
CN106979021B (en) Large-section loess tunnel excavates and preliminary bracing quick closure cyclization method
CN109113745B (en) Method for carrying out large-inclination-angle large-section mountain-down construction cutting by using fully-mechanized excavating machine
CN103758522B (en) A kind of temporary support for drivage face method and equipment thereof
WO2018166518A1 (en) Foundation construction device and construction method therefor
CN105041204A (en) Movable upward raise boring machine
CN204782750U (en) To raise boring machine in movable type
CN106437741A (en) Tunneling machine by new Austrian tunneling method
CN201826837U (en) Movable double-platform partitioned four-arm drill carriage for construction of hangwall anchor rods and anchor cables
CN104632227A (en) Subway station excavation technology of single-layer beam arch structure
CN109629576A (en) Cross foundation pit feed pipe suspension protection system and construction method
CN104196072A (en) Plateau mountain foundation pit excavation construction device
CN104712356B (en) A kind of hydraulic pressure supports tunnel sectional shelf-unit and construction method from moving circulation
CN105736012B (en) A kind of tunnel lining concrete grouting device
CN108643193A (en) A kind of pattern foundation pit supporting structure prestress anchorage cable Drilling draw out method
CN210370741U (en) Scalable tunnel support bow member
CN211115999U (en) Rock mining device for penetrating through surrounding rock of broken zone
RU2141030C1 (en) Device for construction of mine shafts
CN209941704U (en) Side slope or retaining wall construction trolley
CN107503769A (en) A kind of high crag tunnel first lining trolley one serve as a contrast trolley device construction technology

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 471000 No. 16, Longteng North Road, Xiagou Village, Hongshan Township, Xigong District, Luoyang City, Henan Province

Patentee after: Luoyang Gaofei Bridges and Tunnels Machinery Co.,Ltd.

Address before: 471000 No. 16, Longteng North Road, Xiagou Village, Hongshan Township, Xigong District, Luoyang City, Henan Province

Patentee before: LUOYANG GAOFEI BRIDGE AND TUNNEL MACHINERY Co.,Ltd.