CN207453437U - A kind of triangular truss structure builder's jack structure - Google Patents

A kind of triangular truss structure builder's jack structure Download PDF

Info

Publication number
CN207453437U
CN207453437U CN201721188814.8U CN201721188814U CN207453437U CN 207453437 U CN207453437 U CN 207453437U CN 201721188814 U CN201721188814 U CN 201721188814U CN 207453437 U CN207453437 U CN 207453437U
Authority
CN
China
Prior art keywords
truss
brace
wall beam
frame linking
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721188814.8U
Other languages
Chinese (zh)
Inventor
李华
高昇伟
童红飞
殷杰
刘宇驰
顾晋源
张云云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
(group) Co Ltd Is Built In Pudong New Area Shanghai
Original Assignee
(group) Co Ltd Is Built In Pudong New Area Shanghai
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (group) Co Ltd Is Built In Pudong New Area Shanghai filed Critical (group) Co Ltd Is Built In Pudong New Area Shanghai
Priority to CN201721188814.8U priority Critical patent/CN207453437U/en
Application granted granted Critical
Publication of CN207453437U publication Critical patent/CN207453437U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model provides a kind of triangular truss structure builder's jack structure, including floor and the wall beam being connected on floor, being horizontally disposed on the wall beam has truss, truss and it is connected with brace between the wall beam of its lower floor, brace includes the company wall coil hinged with wall beam and the frame linking pipe hinged with truss, it even is provided with to adjust the regulating part of brace length between wall coil and frame linking pipe, scaffold is provided on truss, is connected between the scaffold and the wall beam by hard draw knot.Brace is connected to truss and between the wall beam of truss lower floor, form triangular truss structure, the structure is used to support the scaffold being positioned above, it is to be hinged and the length of brace can be adjusted by regulating device between brace and truss, brace and wall beam, for the adjacent floor deck of different spacing, brace can be by the connection that adjusts its own angle of inclination and length to realize between truss and wall beam so that brace may be mounted between the floor of different spacing.

Description

A kind of triangular truss structure builder's jack structure
Technical field
The utility model is related to technical field of building construction, more specifically, being a kind of triangular truss structure overhanging foot hand Frame structure.
Background technology
At present, in construction, road and bridge construction or shipping work, scaffold can all be used.Scaffold is to protect Demonstrate,prove the workbench that each work progress is smoothed out and sets up.Cantilever Beams structure scaffold is common a kind of foot hand in engineering Frame forms overhanging overhanging girder construction using the girder steel of connection on the wall, and the structure load-bearing is reliable, and construction period occupancy material is few, Use cost is low.
At present, the Chinese patent that application publication number is CN103243900A discloses a kind of steel pipe scaffold and connects wall component, Including the scaffold being mounted on wall, between wall and scaffold horizontal connection have a rod-type wall-connecting piece, scaffold and wall it Between brace be connected with brace bearing, rod-type wall-connecting piece includes joint steel pipe and connector, and connector is arranged at the main body of structures In structure, company's wall end of joint steel pipe is threadedly coupled with connector, and the upright bar between frame linking end and scaffold is fixed by fastener Connection.Brace bearing includes pedestal, the attaching means being fixed on pedestal and the connection bolt for inserting building main body, attaching means The setting of brace, pedestal and brace makes to form the English truss for being used to support scaffold overhanging unit in scaffold.
In above-mentioned technical proposal, brace both ends are fixedly connected between pedestal and scaffold, and length is equal with angle of inclination It is fixed, it can not be mounted between the floor of different spacing, there are improved shortcomings for the prior art.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of triangular truss structures to overhang foot Hand cradle structure makes brace may be mounted between the floor of different spacing.
The utility model provides following technical solution to achieve the above object:A kind of triangular truss structure builder's jack Structure, being horizontally disposed with including floor and the wall beam being connected on floor, on the wall beam has truss, and the truss is with being located at it Brace is connected between the wall beam of lower floor, brace includes the company wall coil hinged with wall beam and the frame linking pipe hinged with truss, described It even is provided with to adjust the regulating part of brace length between wall coil and frame linking pipe, scaffold is provided on the truss, it is described It is connected between scaffold and the wall beam by hard draw knot.
By using above-mentioned technical proposal, brace is connected to truss and between the wall beam of truss lower floor, forms triangle Truss structure, the structure are used to support the scaffold being positioned above, and are to be hinged between brace and truss, brace and wall beam And the length of brace can be adjusted by regulating part, for the adjacent floor deck of different spacing, brace can be by adjusting it certainly The angle of inclination of body and length realize the connection between truss and wall beam so that brace may be mounted at different spacing Between floor.
The utility model is further arranged to:The regulating part is the adjusting being connected between wall coil and frame linking pipe Pipe, regulation pipe are placed in the frame linking pipe close to frame linking pipe one end and coordinate with frame linking pipe screw thread.
By using above-mentioned technical proposal, regulation pipe is placed in frame linking pipe and thread fitting therewith, is installing the overhanging foot It, can be by rotating frame linking pipe or regulation pipe before hand cradle structure, the thread fitting to pass through between the two realizes the length of brace Degree is adjusted.
The utility model is further arranged to:It is arranged with to hide between the frame linking pipe and the even wall coil described The rubber sleeve of regulation pipe.
By using above-mentioned technical proposal, for regulation pipe due to needing threaded adjusting, surface is not easy mopping, scaffold installation After, regulation pipe expose in air, corrosion easily occurs, cause the length of brace be difficult to adjust and the intensity of brace drop Low, rubber sleeve can make regulation pipe isolation air and moisture, slow down the corrosion of regulation pipe.
The utility model is further arranged to:It is both provided with to fix the rubber on even wall coil and the frame linking pipe The retainer plate of set, the retainer plate are detachably connected with frame linking pipe.
By using above-mentioned technical proposal, rubber sleeve both ends are fixed on even wall coil and frame linking pipe, for completely cut off air and Moisture, rubber sleeve have centainly elasticity, and when the distance even between wall coil and frame linking pipe changes, rubber sleeve can be by stretching certainly Body is come the connection between the company's of realization wall coil and frame linking pipe, when adjusting height due to mutually being rotated between regulation pipe and frame linking pipe, One end rotation can occur with frame linking pipe for rubber sleeve, rubber sleeve be caused to damage, being detachably connected between retainer plate and frame linking pipe makes Obtaining rubber sleeve can again be installed after brace length adjustment, and rubber sleeve is prevented to be destroyed.
The utility model is further arranged to:The retainer plate includes carrying the annular resilient collar of opening and for adjusting The bolt of pitch circle shape elastic ring internal diameter.
By using above-mentioned technical proposal, the internal diameter of annular resilient collar can be adjusted by rotating bolt, passes through annular elastomeric The change of property circle internal diameter can realize dismounting of the rubber sleeve on brace.
The utility model is further arranged to:The wall beam on the truss with being both provided with for the hinged brace Articulated slab, the equal semicircular in shape in the articulated slab and brace both ends sets, and articulated slab on brace both ends with being equipped with connecting rod, even Fixing nut is provided on extension bar.
By using above-mentioned technical proposal, connecting rod, articulated slab brace both ends collective effect realize brace and wall beam, tiltedly The semicircle setting at being hinged between bar and truss, articulated slab and brace both ends can make the area smaller of articulated joint, make hinged The area of plate is also smaller, reduces articulated slab and the distance between truss and wall beam, add articulated slab and truss and wall beam it Between bonding strength.
The utility model is further arranged to:Be connected with firm anchor slab between the wall beam and articulated slab, articulated slab with just It is welded to connect between anchor slab.
By using above-mentioned technical proposal, the articulated slab being connected with wall beam can be subject in load-bearing it is larger it is vertical on cut Power, firm anchor slab can increase the contact area between articulated slab and wall beam, muscle are provided on firm anchor slab, can increase articulated slab pair The ability of shearing resistance.
The utility model is further arranged to:It is characterized in that, pass through chemical bolt between the firm anchor slab and wall beam Connection.
By using above-mentioned technical proposal, chemical bolt realizes the fixation of itself by gel, and anchor force is strong, Ke Yigeng The good firm anchor slab of fixation, while the service life of itself is long, ageing resistance is strong, can use in a humidity environment.
The utility model is further arranged to:The scaffold includes operation layer and the supporting rod being vertically arranged, institute It states and is welded to connect between supporting rod and truss.
By using above-mentioned technical proposal, supporting rod can be used for operation layer to be supported and fixed by welding In the fixation for realizing entire scaffold.
The utility model is further arranged to:The truss is located at supporting rod side and is welded with reinforcement steel in a ring Plate, the reinforcement steel plate wrap up the supporting rod.
By using above-mentioned technical proposal, strengthen steel plate can be by supporting to add supporting rod in supporting rod side By force, reduce it and the possibility of lateral deviation occurs.
In conclusion the utility model has the advantages that:
One:Pass through the setting of the regulating part on the hinged and brace between brace and truss, brace and wall beam, brace Angle of inclination and length it is adjustable, may be mounted between the floor of different spacing;
Secondly:The setting of rubber sleeve protects regulation pipe, enhances the intensity of brace, extends its service life.
Thirdly:Firm anchor slab and chemical bolt between articulated slab and wall beam are set, improve the ability of articulated slab shearing resistance, Triangular truss structure is reinforced.
Description of the drawings
Fig. 1 is the front view of triangular truss structure builder's jack system;
Fig. 2 is the connection diagram of truss and brace, the company of being hinged between major embodiment truss and brace, wall beam and brace Binding structure;
Fig. 3 is the exploded perspective view of brace, the structure of major embodiment brace;
Fig. 4 is the structure diagram of retainer plate;
Fig. 5 is the overall structure figure of triangular truss structure builder's jack system, between major embodiment truss and scaffold Connection mode.
In figure:1st, floor;2nd, wall beam;3rd, truss;31st, steel plate is strengthened;4th, brace;41st, wall coil is connected;42;Frame linking pipe;43、 Regulation pipe;5th, scaffold;51st, operation layer;52nd, supporting rod;6th, hard draw knot;7th, rubber sleeve;71st, retainer plate;711st, cyclic spring Circle;712nd, bolt;8th, firm anchor slab;81st, chemical bolt;9th, articulated slab;10th, connecting rod;101st, fixing nut.
Specific embodiment
Below in conjunction with attached drawing, the utility model is described in further detail.
As shown in Figure 1, a kind of triangular truss structure builder's jack structure, including floor 1 and is connected on floor 1 Wall beam 2, for wall beam 2 for installing scaffold 5, being horizontally disposed on wall beam 2 has truss 3, and scaffold 5, scaffold are provided on truss 3 5 for operating on it for worker, and truss 3 is used to support scaffold 5, truss 3 and is connected between the wall beam 2 of its lower floor Brace 4 due to the setting of brace 4, forms triangular truss structure, English truss knot between truss 3 and wall beam 2 and brace 4 The load-bearing capacity of structure is relatively strong and relatively stablizes, and ensure that the stabilization of scaffold 5.
As shown in Fig. 2, truss 3 is used to support scaffold 5, be subject to it is larger it is vertical on pressure, truss 3 and wall beam 2 it Between connection there are larger shearing, truss 3 is welded and connected with firm anchor slab 8 close to 2 one end of wall beam, and firm 8 bottom of anchor slab is arranged on On wall beam 2, firm anchor slab 8 shears for resisting, and enhances the bonding strength between truss 3 and wall beam 2, reduces truss 3 because being erected Straight shearing and generate loosening or the separated possibility with wall beam 2, pass through chemical bolt 81 between firm anchor slab 8 and wall beam 2 Connection, chemical bolt 81 realizes the fixation between firm anchor slab 8 and wall beam 2 by gel, and the anchor force of chemical bolt 81 is strong, can be with Firm anchor slab 8 is preferably fixed, while the service life of itself of chemical bolt 81 is long, can use in a humidity environment, just Anchor slab 8 realizes being fixedly connected between truss 3 and wall beam 2 with the collective effect of chemical bolt 81.
As shown in figure 3, brace 4 includes the company's wall coil 41 being connected with wall beam 2, the frame linking pipe 42 of grade is practiced with truss 3 and is connected Regulation pipe 43 between the company's of being connected on wall coil 41 and frame linking pipe 42 is even welded to connect, frame linking pipe 42 between wall coil 41 and regulation pipe 43 Close to 43 one end of regulation pipe in hollow setting, regulation pipe 43 close to frame linking pipe 42 be partially disposed in frame linking pipe 42 and the two screw thread Coordinate, rotation frame linking pipe 42, under the action of the thread fitting between frame linking pipe 42 and regulation pipe 43, regulation pipe 43 and frame linking pipe Relative displacement is sent out between 42 so that the length of brace 4 changes, and the length of brace 4 can be carried out by rotating frame linking pipe 42 It adjusts.
As shown in Fig. 2, all brushed with antirust paint on frame linking pipe 42 and wall coil 41, but 43 surface of regulation pipe is provided with screw thread, To ensure regulation pipe 43 and the threaded connection of frame linking pipe 42,43 surface of regulation pipe does not carry out mopping, and regulation pipe 43 is exposed to air In, corrosion easily occurs, it is strong that the difficult support that can reduce brace 4 simultaneously is adjusted between the regulation pipe 43 of corrosion and frame linking pipe 42 Degree, sets rubber sleeve 7 between frame linking pipe 42 and even wall coil 41, rubber sleeve 7 can make regulation pipe 43 completely cut off air and moisture, subtract The corrosion of slow regulation pipe 43, protects regulation pipe 43.
As shown in figure 3, since when adjusting 4 length of brace, regulation pipe 43 can relatively rotate with frame linking pipe 42, rubber Set 7 is connected to 42 one end of frame linking pipe and easily rotates, and rubber sleeve 7 is caused to damage.Even wall coil 41 on frame linking pipe 42 with being respectively provided with The retainer plate 71 of fixed rubber sleeve 7 is useful for, with reference to Fig. 4, retainer plate 71 includes annular resilient collar 711 and spiral shell with opening Bolt 712, for bolt 712 for changing the internal diameter of annular resilient collar 711, retainer plate 71 is used to implement rubber sleeve 7 and even wall coil 41, solid Surely being detachably connected between circle 71 and frame linking pipe 42.When adjusting frame linking pipe 42 with regulation pipe 43, by adjusting retainer plate 71 Rubber sleeve 7 is made to depart from the connection between frame linking pipe 42, is connected to after the length adjustment of brace 4, then by rubber sleeve 7 Between frame pipe 42 and frame linking pipe 42, be locked circle 71, and rubber sleeve 7 covers and protects regulation pipe 43.
As shown in Fig. 2, being provided with articulated slab 9 on truss 3 and on wall beam 2, articulated slab 9 is with frame linking pipe 42, articulated slab 9 with connecting Connecting rod 10 is equipped between wall coil 41, articulated slab 9 can relatively rotate between brace 4, realize being hinged for the two. Under the action of regulating device, brace 4 can adjust the length of itself;There are truss 3 and the hinged work of wall beam 2 at 4 both ends of brace Under, brace 4 can adjust the angle of inclination of itself so that brace 4 may be mounted between the floor 1 of different spacing.
As shown in Fig. 2, the equal semicircular in shape in both ends of articulated slab 9 and brace 4, makes the area smaller of articulated joint, makes hinged Plate 9 adds the bonding strength between articulated slab 9 and truss 3 and wall beam 2 closer to wall beam 2 or truss 3.Wall beam 2 and hinged Firm anchor slab 8 is provided between plate 9, firm anchor slab 8 is for connecting articulated slab 9 and enhancing its shearing resistance ability, firm anchor slab 8 and wall beam 2 Between connected by chemical bolt 81,8 collective effect of chemical bolt 81 and firm anchor slab so that wall beam 2 is connected more with articulated slab 9 Add stabilization.
As shown in figure 5, scaffold 5 includes operation layer 51 and supporting rod 52, supporting rod 52 in being vertically arranged, with support Operation layer 51 and truss frame for connecting 3, are connected with hard draw knot 6 between operation layer 51 and wall beam 2, hard draw knot 6 is used in upper level system Operation layer 51 prevents operation layer 51 from shifting.It is fixedly connected by welding between supporting rod 52 and truss 3, is located on truss 3 52 side of supporting rod be welded with strengthen steel plate 31, strengthen steel plate 31 set in a ring, for supporting rod 52 in level Support is provided, prevents supporting rod 52 and scaffold 5 from lateral deviation occurs.
Specific implementation process:When between the adjacent floor deck 1 for needing mounted on different spacing in scaffold 5, by calculating building Length and angle of inclination needed for 3 length computation brace 4 of 1 spacing of plate and truss, unscrew the bolt 712 on retainer plate 71, connect The fixation to rubber sleeve 7 is touched, frame linking pipe 42 is relatively rotated with regulation pipe 43, is adjusted under the thread fitting of the two to required length Rubber sleeve 7, using retainer plate 71 is fixed on brace 4, frame linking pipe 42 is connected on truss 3, passing through firm 8 He of anchor slab by degree Chemical bolt 81 completes the fixation of truss 3 and articulated slab 9 on wall beam 2, the installation of truss 3 and brace 4 is completed, on truss 3 Scaffold 5 is installed again.
This specific embodiment is only explanation to the utility model, is not the limitation to the utility model, ability Field technique personnel can as needed make the present embodiment the modification of no creative contribution after this specification is read, but As long as it is all protected in the right of the utility model be subject to Patent Law.

Claims (10)

1. a kind of triangular truss structure builder's jack structure, which is characterized in that including floor(1)And it is connected to floor(1) On wall beam(2), the wall beam(2)Upper be horizontally disposed with has truss(3), the truss(3)With the wall beam positioned at its lower floor(2)It Between be connected with brace(4), brace(4)Including with wall beam(2)Hinged company's wall coil(41)With with truss(3)Hinged frame linking pipe (42), the even wall coil(41)With frame linking pipe(42)Between be provided with to adjust the regulating part of brace length, the truss(3) On be provided with scaffold(5), the scaffold(5)With the wall beam(2)Between pass through hard draw knot(6)Connection.
A kind of 2. triangular truss structure builder's jack structure according to claim 1, which is characterized in that the regulating part To be connected to wall coil(41)With frame linking pipe(42)Between regulation pipe(43), regulation pipe(43)Close to frame linking pipe(42)It puts one end In the frame linking pipe(42)It is interior and with frame linking pipe(42)Thread fitting.
A kind of 3. triangular truss structure builder's jack structure according to claim 2, which is characterized in that the frame linking pipe (42)With the even wall coil(41)Between be arranged with to hide the regulation pipe(43)Rubber sleeve(7).
A kind of 4. triangular truss structure builder's jack structure according to claim 3, which is characterized in that the even wall coil (41)With frame linking pipe(42)On be both provided with to fix the rubber sleeve(7)Retainer plate(71), the retainer plate(71)With Frame linking pipe(42)It is detachably connected.
A kind of 5. triangular truss structure builder's jack structure according to claim 4, which is characterized in that the retainer plate (71)Annular resilient collar including carrying opening(711)And for adjusting the annular resilient collar(711)The bolt of internal diameter (712).
A kind of 6. triangular truss structure builder's jack structure according to claim 1, which is characterized in that the wall beam (2)With the truss(3)On be both provided with for the hinged brace(4)Articulated slab(9), the articulated slab(9)With brace (4)The equal semicircular in shape in both ends is set, articulated slab(9)With brace(4)Connecting rod is equipped on both ends(10), connecting rod(10)Upper company It is connected to fixing nut(101).
A kind of 7. triangular truss structure builder's jack structure according to claim 6, which is characterized in that the wall beam (2)With articulated slab(9)Between be connected with firm anchor slab(8), articulated slab(9)With firm anchor slab(8)Between be welded to connect.
A kind of 8. triangular truss structure builder's jack structure according to claim 7, which is characterized in that the firm anchor slab (8)With wall beam(2)Between pass through chemical bolt(81)Connection.
A kind of 9. triangular truss structure builder's jack structure according to claim 1, which is characterized in that the scaffold (5)Including operation layer(51)And the supporting rod being vertically arranged(52), the supporting rod(52)With truss(3)Between weld connect It connects.
A kind of 10. triangular truss structure builder's jack structure according to claim 9, which is characterized in that the truss (3)Positioned at supporting rod(52)Side is welded with reinforcement steel plate in a ring(31), the reinforcement steel plate(31)Wrap up the support Bar(52).
CN201721188814.8U 2017-09-16 2017-09-16 A kind of triangular truss structure builder's jack structure Expired - Fee Related CN207453437U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721188814.8U CN207453437U (en) 2017-09-16 2017-09-16 A kind of triangular truss structure builder's jack structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721188814.8U CN207453437U (en) 2017-09-16 2017-09-16 A kind of triangular truss structure builder's jack structure

Publications (1)

Publication Number Publication Date
CN207453437U true CN207453437U (en) 2018-06-05

Family

ID=62283244

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721188814.8U Expired - Fee Related CN207453437U (en) 2017-09-16 2017-09-16 A kind of triangular truss structure builder's jack structure

Country Status (1)

Country Link
CN (1) CN207453437U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110259087A (en) * 2019-06-04 2019-09-20 东莞市建筑科学研究所 Scaffold support structure and scaffold support system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110259087A (en) * 2019-06-04 2019-09-20 东莞市建筑科学研究所 Scaffold support structure and scaffold support system

Similar Documents

Publication Publication Date Title
CN207160539U (en) A kind of easy-to-dismount overhanging scaffold of high-mechanic
CN105804380A (en) Lifting portable scaffold
CN110374010B (en) Construction device for temporary vibration reduction of stay cable and use method thereof
CN207453437U (en) A kind of triangular truss structure builder's jack structure
CN210289598U (en) Inspection shaft ladder for municipal works construction
CN109235280A (en) The operation platform and construction method of bridge coping
CN105113781B (en) Device is set up in a kind of overhanging complete pre-buried installation in side of setting a roof beam in place
CN207469546U (en) A kind of glass curtain wall and steel structure of easy-to-mount glass
CN207420056U (en) A kind of quick correction type verticality of steel column device
CN110005203A (en) A kind of adaptive tool-type sloping core form bracing system and application method
CN202466923U (en) Suspended ceiling counter support
CN201753525U (en) Rotary operation platform
CN209194347U (en) The operation platform of bridge coping
CN214081146U (en) Fastening device of high-altitude nut
CN203924352U (en) Section steel concrete steel column base
CN206144127U (en) Simple and easy butt clamp integral type operation platform
CN212535068U (en) Formwork support device for building construction
CN105113776B (en) The support meanss and building method of pole inner top platform on a kind of spherical tank
CN211369217U (en) Pipe truss steel structure roof
CN205000249U (en) Cable -stay bridge king -tower cable pipe mounting adjustment support
CN209538695U (en) A kind of building template support device
CN208034966U (en) A kind of simple galling device of superimposed sheet
CN207959933U (en) A kind of support device
CN206693588U (en) A kind of quick assembling scaffold
CN206153437U (en) Steel bar truss string muscle work platform adjusting device that bends

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180605