CN207392240U - For the full bag water proof structure structure of contrary sequence method building - Google Patents

For the full bag water proof structure structure of contrary sequence method building Download PDF

Info

Publication number
CN207392240U
CN207392240U CN201721403084.9U CN201721403084U CN207392240U CN 207392240 U CN207392240 U CN 207392240U CN 201721403084 U CN201721403084 U CN 201721403084U CN 207392240 U CN207392240 U CN 207392240U
Authority
CN
China
Prior art keywords
connecting portion
foundation pit
pit enclosure
floor
interim
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201721403084.9U
Other languages
Chinese (zh)
Inventor
徐正良
张中杰
李太文
张擎宇
刘妮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Group Co Ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Group Co Ltd filed Critical Shanghai Urban Construction Design Research Institute Group Co Ltd
Priority to CN201721403084.9U priority Critical patent/CN207392240U/en
Application granted granted Critical
Publication of CN207392240U publication Critical patent/CN207392240U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model discloses the full bag water proof structure structure for contrary sequence method building, including floor and foundation pit enclosure structure, floor edge be equipped with treat the connecting portion being connected with exterior wall and with the symmetrically arranged interim construction beam of connecting portion;The outside one side of interim construction beam and connecting portion are coplanar, and are connected with foundation pit enclosure structure, and equipped with waterproof roll;Extend the lower end of connecting portion, the latter half of the interim construction beam of upper end covering in the lower end of the laying scope of waterproof roll;In construction, interim construction beam is first added on floor, it is made to be connected with foundation pit enclosure structure, and waterproof roll is overlay in floor and foundation pit enclosure structure joint, and reserve certain lap of splice;After lower part external wall structure is returned and built, the completion of vertical supporting system underpins, and cuts the concrete for the interim construction beam added;It is carried out in construction afterwards and carries out overlap joint with waterproof roll.The utility model is realized in being built using contrary sequence method, floor and the outside waterproofing of supporting construction junction.

Description

For the full bag water proof structure structure of contrary sequence method building
Technical field
The utility model is related to building top-down method building technology fields, the more particularly to full bag for contrary sequence method building Water proof structure structure.
Background technology
In underground engineering, reinforced concrete structure is still occupied an leading position.Although underground waterproof concrete takes certain technical measures, add Add various additives, but crack after constructing still is difficult to avoid that, therefore《Technical code for water proof in underground engineering》 Clear stipulaties in the 4.1.7 articles of GB50108-2008 specifications:" fracture width is not greater than 0.2mm, and must not penetrate through ".Notice this A provision regulation is safe in engineering structure, but such as without considering other waterproof measures, consequence is also to be difficult to imagine.Therefore To inhibit and reducing the leakage of concrete, and concrete is effectively avoided or reduced by carbonate in underground water and chlorion etc. Full bag waterproofing design is taken in corrosion, more and more underground engineering project considerations.
Traditional deep basal pit is generally constructed from bottom to top using open type Open Cut Method, with subway and underground engineering Large scale construction, underground engineering contrary sequence method can effectively control surrounding enviroment deformation, reduction to make it to the characteristics of ground time effects Gradually promoted in the whole nation.Contrary sequence method refers to that each layer basement of below ground using top-down sequence of construction, is gone downstairs by ground The horizontal rigidity and compression strength of harden structure generate support action to foundation pit, ensure the earth excavation of foundation pit.
Since basement floor construction is constructed from top to down, the earthwork at this time is not yet excavated, the exterior wall and structural column of basement Completion cannot be poured before floor construction construction, it is therefore necessary to it is the vertical temporary support pile foundation of structural column setting, and exterior wall Supporting construction of the floor at place then directly with foundation pit both sides is connected, using supporting construction as vertical supporting.
Since inverse floor of making is connected by reinforcing bar with supporting construction, the waterproof material at this node is cut by reinforcing bar tunneling boring It is disconnected, it can not really realize full bag waterproof.
Therefore, how effectively to solve the above problems, the full bag waterproof that underground structure is further realized in contrary sequence method is mesh Preceding engineering circles thorny problem urgently to be resolved hurrily.
Utility model content
In view of the drawbacks described above of the prior art, the utility model provides the full bag water proof structure for contrary sequence method building Structure, the first purpose of realization is in the case of using contrary sequence method construction of buildings underground structure, realizes floor and supporting knot The outside waterproofing of structure junction.
To achieve the above object, the utility model discloses the full bag water proof structure structure for contrary sequence method building, bags Floor and foundation pit enclosure structure are included, is equipped with below the floor edge and treats the connecting portion being connected with exterior wall, the connecting portion Vertical with the floor, the outside one side of the connecting portion is connected with the foundation pit enclosure structure.
Wherein, described floor edge the upper surface of symmetrically constructs beam temporarily with the connecting portion equipped with together with;It is described to face When construct the outside one side of beam and the connecting portion is coplanar, and the outside one side of the interim construction beam and the foundation pit enclosure knot Structure connects.
Waterproof roll is equipped between the interim construction beam and the connecting portion and the foundation pit enclosure structure;It is described anti- The lower end of the connecting portion is extended in the lower end of the laying scope of water coiled material, and upper end covers the lower half of the interim construction beam Point.
When the underground structure completion of the building, after the floor external wall structure time is built, the interim construction beam is removed Concrete parts, expose the upper end that the waterproof roll covers the interim construction beam the latter half, for being built with follow-up It is overlapped in the process with other waterproof constructions.
Preferably, if the position that the foundation pit enclosure structure corresponds to the interim construction beam is equipped with the L-shaped reinforcing bar in arterial highway, One end of " L " the shape reinforcing bar bending, which is buried, builds in the foundation pit enclosure structure, and the other end is horizontal to the interim construction beam direction To the stretching foundation pit enclosure structure;" L " the shape reinforcing bar stretches out one end of the foundation pit enclosure structure and the interim construction Bar construction connection in beam.
Preferably, it is to build that the reinforcing bar in the connecting portion, which is connected with the bar construction in the interim construction beam in an entirety, Build the vertical reinforcement of beyond the region of objective existence wall.
Preferably, the lower end of the connecting portion is equipped with reinforcing bar connector and is cast in bar connecting inside the connecting portion.
The beneficial effects of the utility model:
1) structure stress is clear.
Pre-buried U-typed reinforcing bar in supporting construction, breaks U-typed reinforcing bar one end during construction straight L-shaped, makees with inverse at floor Newly-increased interim construction beam connection, with contentedly downstairs harden structure bears horizontal loading, supporting construction shares floor vertical load Requirement.
2) waterproof measure simple structure.
Waterproof roll is overlay with supporting construction joint in inverse floor of making, and reserves certain lap of splice, in order to the later stage Return the connection for building stage waterproof roll.Waterproof material and construction, easy for construction, input cost base consistent with standard paragraphs external wall waterproof This is without increase.
3) construction on internal structure and design are without influence.
Exterior wall vertical reinforcement is set in newly-increased interim construction beam, this reinforcing bar is retained when the later stage cuts, External Wall pours It builds and designs without influence.
This waterproofing node has effectively expanded the construction means of underground engineering, has promoted technical progress of industry, has good warp Ji, social benefit.The technique effect of the design of the utility model, concrete structure and generation is made below with reference to attached drawing further Illustrate, to be fully understood from the purpose of this utility model, feature and effect.
Description of the drawings
Fig. 1 shows the structure diagram of one embodiment of the utility model.
Specific embodiment
Embodiment
As shown in Figure 1, for the full bag water proof structure structure of contrary sequence method building, including floor 1 and foundation pit enclosure structure 3, it is equipped with below 1 edge of floor and treats connecting portion be connected with exterior wall 2, connecting portion 2 is vertical with floor 1, and connecting portion 2 is outwards It is connected on one side with foundation pit enclosure structure 3.
Wherein, 1 edge of floor the upper surface of symmetrically constructs beam 5 temporarily with connecting portion 2 equipped with together with;Interim construction beam 5 Outside one side and connecting portion 2 are coplanar, and the interim outside one side of beam 5 that constructs is connected with foundation pit enclosure structure 3.
Waterproof roll 4 is equipped between interim construction beam 5 and connecting portion 2 and foundation pit enclosure structure 3;The paving of waterproof roll 4 If the lower end of connecting portion 2, the latter half of the interim construction beam 5 of upper end covering are extended in the lower end of scope.
When the underground structure of building is completed, after floor 1 external wall structure time is built, removal constructs the concrete section of beam 5 temporarily Point, expose the upper end that waterproof roll 4 covers 5 the latter half of interim construction beam, for in follow-up building course with other waterproofs Structure overlaps.
In certain embodiments, if the position that foundation pit enclosure structure 3 corresponds to interim construction beam 5 is equipped with the L-shaped steel in arterial highway Muscle 31, one end that " L " shape reinforcing bar 31 is bent, which is buried, builds in foundation pit enclosure structure 3, and the other end is laterally stretched to 5 direction of interim construction beam Go out foundation pit enclosure structure 3;One end and the bar construction 51 in interim construction beam 5 that " L " shape reinforcing bar 31 stretches out foundation pit enclosure structure 3 Connection.
In certain embodiments, the reinforcing bar in connecting portion 2 is connected whole in one with the bar construction 51 in interim construction beam 5 It is the vertical reinforcement of skin.
In certain embodiments, the lower end of connecting portion 2 is equipped with reinforcing bar connector 21 and is cast in 2 inside reinforcing bar of connecting portion and connects It connects.
The utility model also provides a kind of construction method of the full bag water proof structure structure for contrary sequence method building, step It is as follows:
A, it will go back to the edge for building exterior wall in the excavation of foundation pit stage and add interim construction beam 5 together in being located on floor 1, And the lateral surface of the lateral surface and the connecting portion 2 of floor 1 of interim construction beam 5 is coplanar.
B, waterproof roll 4, the covering of waterproof roll 4 are set on coplanar lateral surface of the construction beam 5 with connecting portion 2 temporarily Scope is more than the lateral surface of connecting portion 2, and 4 upper end of waterproof roll covers the latter half of interim construction 5 lateral surface of beam.
In construction, add interim construction beam 5 together above floor 1 in the excavation of foundation pit stage first, make itself and foundation pit Building enclosure 3 connects, and overlays waterproof roll 4 in floor 1 and 3 joint of foundation pit enclosure structure, and reserves certain lap of splice.
C, foundation pit enclosure structure is built, is connected with the coplanar lateral surface of interim construction beam 5 and connecting portion 2.
D, foundation pit is excavated, after the underground structure for completing construction of buildings, returns and builds exterior wall, complete the support of vertical supporting system It changes.
After lower part external wall structure is returned and built, the completion of vertical supporting system underpins, and cuts the coagulation for the interim construction beam 5 added Soil.
E, interim construction beam 5 is cut, what formation was flushed with floor cuts face 52, when making waterproof layer, extends with exposing Waterproof roll 4 outside connecting portion 2 carries out overlap joint.
Finally, overlap joint is carried out with reserved waterproof roll 4 in construction, realizes the full bag waterproof of this node.
In certain embodiments, in step E, the concrete parts of interim construction beam 5 is cut, will temporarily be constructed in beam 5 Vertical reinforcement use as returning the vertical reinforcement of exterior wall built.
The preferred embodiment of the utility model described in detail above.It should be appreciated that the ordinary skill people of this field Member according to the present utility model can conceive without creative work makes many modifications and variations.Therefore, all this technology necks Technical staff passes through logic analysis, reasoning or limited reality on the basis of existing technology according to the design of the utility model in domain Available technical solution is tested, it all should be in the protection domain being defined in the patent claims.

Claims (4)

1. for the full bag water proof structure structure of contrary sequence method building, including floor (1) and foundation pit enclosure structure (3), the building It being equipped with below plate (1) edge and treats the connecting portion being connected with exterior wall (2), the connecting portion (2) is vertical with the floor (1), The outside one side of the connecting portion (2) is connected with the foundation pit enclosure structure (3);It is characterized in that:
Described floor (1) edge the upper surface of symmetrically constructs beam (5) temporarily with the connecting portion (2) equipped with together with;It is described to face When construct beam (5) outside one side and the connecting portion (2) is coplanar, and the outside one side of the interim construction beam (5) with it is described Foundation pit enclosure structure (3) connects;
Waterproof roll is equipped between the interim construction beam (5) and the connecting portion (2) and the foundation pit enclosure structure (3) (4);The lower end of the connecting portion (2) is extended in the lower end of the laying scope of the waterproof roll (4), and upper end covering is described interim Construct the latter half of beam (5);
When the underground structure completion of the building, after floor (1) external wall structure time is built, the interim construction beam is removed (5) concrete parts expose the upper end that the waterproof roll (4) covers interim construction beam (5) the latter half, for It is overlapped in follow-up building course with other waterproof constructions.
2. the full bag water proof structure structure according to claim 1 for contrary sequence method building, it is characterised in that:The base The corresponding interim construction beam (5) of pit enclosure structure (3) if position be equipped with the L-shaped reinforcing bar in arterial highway (31), " L " the shape steel One end of muscle (31) bending, which is buried, builds in the foundation pit enclosure structure (3), and the other end is horizontal to interim construction beam (5) direction Stretch out the foundation pit enclosure structure (3);" L " the shape reinforcing bar (31) stretch out one end of the foundation pit enclosure structure (3) with it is described Bar construction (51) connection in interim construction beam (5).
3. the full bag water proof structure structure according to claim 2 for contrary sequence method building, it is characterised in that:The company It is skin that reinforcing bar in socket part (2), which is connected with the bar construction (51) in the interim construction beam (5) in an entirety, Vertical reinforcement.
4. the full bag water proof structure structure according to claim 1 for contrary sequence method building, it is characterised in that:The company The lower end of socket part (2) is equipped with reinforcing bar connector (21) and is cast in the internal bar connecting of the connecting portion (2).
CN201721403084.9U 2017-10-27 2017-10-27 For the full bag water proof structure structure of contrary sequence method building Withdrawn - After Issue CN207392240U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721403084.9U CN207392240U (en) 2017-10-27 2017-10-27 For the full bag water proof structure structure of contrary sequence method building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721403084.9U CN207392240U (en) 2017-10-27 2017-10-27 For the full bag water proof structure structure of contrary sequence method building

Publications (1)

Publication Number Publication Date
CN207392240U true CN207392240U (en) 2018-05-22

Family

ID=62326658

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721403084.9U Withdrawn - After Issue CN207392240U (en) 2017-10-27 2017-10-27 For the full bag water proof structure structure of contrary sequence method building

Country Status (1)

Country Link
CN (1) CN207392240U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107653905A (en) * 2017-10-27 2018-02-02 上海市城市建设设计研究总院(集团)有限公司 Full bag water proof structure structure and its construction method for contrary sequence method building
CN113482021A (en) * 2021-08-19 2021-10-08 中铁第六勘察设计院集团有限公司 Half-pile supporting structure for excavating shallow foundation pit above underground structure floor and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107653905A (en) * 2017-10-27 2018-02-02 上海市城市建设设计研究总院(集团)有限公司 Full bag water proof structure structure and its construction method for contrary sequence method building
CN107653905B (en) * 2017-10-27 2023-03-10 上海市城市建设设计研究总院(集团)有限公司 Full-package waterproof structure for reverse construction method building and construction method thereof
CN113482021A (en) * 2021-08-19 2021-10-08 中铁第六勘察设计院集团有限公司 Half-pile supporting structure for excavating shallow foundation pit above underground structure floor and construction method

Similar Documents

Publication Publication Date Title
CN102536273B (en) One-step forming construction method for 26m large-span space
CN111898184B (en) Analysis method for influence of shallow-buried underground tunnel pipe curtain reinforcement on ground and pile foundation
CN104652443B (en) Construction method of the interim horizontal support of deep basal pit as permanent structure beam
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN106703814A (en) Mined metro station hole pile construction method
CN106400811B (en) Frame is inverse to make foldable assembled foundation pit structure construction method
CN207092107U (en) A kind of anti-subsidence structure using diaphram wall
CN105239578B (en) Water-rich sand layer deep foundation pit underwater construction method
CN107542115A (en) Underground project waterproof structure and its construction method
CN106013053A (en) Steel sheet pile support construction method for building underground garage open caisson
CN108343059A (en) The two walls unification half that underground pipe gallery combines prefabricated socket inverse makees method of construction
CN104652418A (en) Continuous wall underground pipeline position construction method
CN109441456A (en) A kind of the tunnel structure and its construction method of weakness Facility-sliding strata
CN109183838B (en) A kind of high anti-floating cracking resistance basement floor constructions and its design method
CN207392240U (en) For the full bag water proof structure structure of contrary sequence method building
CN108797637A (en) Prefabricated board combined cast-in-situ concrete considers the underground pipe gallery construction method of structure and ground
CN106837341A (en) A kind of construction method of Metro construction shaft wall
CN109056810A (en) The transverse direction that open cut or lid dig underground main structure below existing building digs construction and its construction method
CN106498951B (en) A kind of shaft excavation construction method
CN102410031A (en) Underground space structure constructed by pile wall construction method
CN105735383A (en) Partial underground obstacle removing construction method capable of reserving structural system
CN110939139B (en) Pile plate wall structure based on rigid contact of post-pile special-shaped retaining wall and construction method thereof
CN107905795A (en) Subway station is inverse under a kind of operation condition widens method
CN209066508U (en) Cross the existing electric power piping lane protection structure of tunnel foundation pit
CN204851265U (en) Bearing structure in work well under high water pressure condition

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20180522

Effective date of abandoning: 20230310

AV01 Patent right actively abandoned

Granted publication date: 20180522

Effective date of abandoning: 20230310