- Publication number
- CN207359040U CN207359040U CN201721341325.1U CN201721341325U CN207359040U CN 207359040 U CN207359040 U CN 207359040U CN 201721341325 U CN201721341325 U CN 201721341325U CN 207359040 U CN207359040 U CN 207359040U
- Authority
- CN
- China
- Prior art keywords
- bar
- bearing
- prefabricated components
- placing multiple
- piling bin
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Pallets (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a kind of piling bin for placing multiple prefabricated components, the first bearing being arranged side by side including left and right, second bearing and front and rear two horizon bars being disposed side by side between the first bearing and the second bearing, the bearing of first bearing/second includes the bottom support bracket bar being arranged in parallel successively from top to bottom, intermediate support bar, upper seat bar, the horizon bar is equipped with a socket hole along its length, jack on two horizon bars corresponds and inserted with spacer bar, the spacer bar is stretched out from horizon bar and the position gap formed with positioning prefabricated components between adjacent two spacer bar.The utility model makes and simply, solves the problem that existing construction site prefabricated components stack difficulty, not only accomplishes to stack safety, but also can lift convenience.
Description
Technical field
It the utility model is related to technical field of building construction, and in particular to the special stacking adapter of prefabricated components.
Background technology
In some construction, prefabricated components are often used, and have concrete prefabricated element, steel member, aluminum member etc.,
Assembling construction is carried out using prefabricated components, can be accelerated the construction period, prefabricated components have been obtained for being widely applied.Constructing
Scene, prefabricated components should be accomplished to stack safety, and can lift conveniently, have certain difficulty, also brought not to construction
Just.
Utility model content
Technical problem to be solved in the utility model is just to provide a kind of piling bin for placing multiple prefabricated components, solution
Certainly existing construction site prefabricated components stack difficult problem.
In order to solve the above technical problems, the utility model adopts the following technical solution:One kind can place multiple prefabricated components
Piling bin, including left and right be arranged side by side the first bearing, the second bearing and front and rear be disposed side by side on the first bearing and second
Two horizon bars between bearing, the bearing of first bearing/second include the bottom support bracket being arranged in parallel successively from top to bottom
Bar, intermediate support bar, upper seat bar, the upper seat bar is concordant with intermediate support bar both ends and is shorter than bottom support bracket rod end
Portion, the upper seat bar and the both ends of intermediate support bar are connected the first bearing upright bar, the second bearing upright bar respectively, and described first
Bearing upright bar, the bottom of the second bearing upright bar are connected with bottom support bracket bar, the both ends of two horizon bars respectively with the first bearing
Upright bar, the upper end of the second bearing upright bar connect, and bottom supporting rod, the level are connected between two root bottom part seat bar of left and right
Bar is equipped with a socket hole along its length, and the jack on two horizon bars corresponds and inserted with spacer bar, the positioning
Reinforcing bar is stretched out from horizon bar and the position gap formed with positioning prefabricated components between adjacent two spacer bar.
Preferably, the both ends of the bottom support bracket bar are equipped between the first bearing upright bar, the second bearing upright bar respectively
First hound.
Preferably, the bottom supporting rod both ends stretch out bottom support bracket bar, and respectively with the first bearing, the second bearing
Upper seat bar between be equipped with the second hound.
Preferably, the bottom support bracket bar the first bearing upright bar, the second bearing upright bar inner side respectively with two levels
The 3rd hound is equipped between bar.
Preferably, a kind of piling bin for placing multiple prefabricated components is overall is made of channel steel welding.
The utility model uses above-mentioned technical proposal, and that brings has the beneficial effect that:, can be at the same time before prefabricated part hanging
Multiple prefabricated components are stacked, prefabricated components are fixed temporarily.The utility model makes simply, and it is pre- to solve existing construction site
Component processed stacks difficult problem, not only accomplishes to stack safety, but also can lift conveniently, high recycling rate.
Brief description of the drawings
The utility model is further described with reference to the accompanying drawings and detailed description:
Fig. 1 is the overall structure diagram of the utility model.
Fig. 2 is the schematic diagram of the utility model in actual use.
Embodiment
It should be noted that in the case where there is no conflict, the feature in embodiment and embodiment in the application can phase
Mutually combination.The utility model will be described in detail below with reference to the accompanying drawings and embodiments.
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.The description only actually at least one exemplary embodiment is illustrative to be never used as to this practicality below
New and its application or any restrictions used.Based on the embodiment in the utility model, those of ordinary skill in the art are not having
All other embodiments obtained under the premise of creative work are made, shall fall within the protection scope of the present invention.
As depicted in figs. 1 and 2, a kind of piling bin for placing multiple prefabricated components, including left and right be arranged side by side first
Bearing, the second bearing and front and rear two horizon bars (12,13) being disposed side by side between the first bearing and the second bearing), institute
State bottom support bracket bar (2,19), intermediate support bar that the bearing of the first bearing/second includes being arranged in parallel successively from top to bottom (7,
20), upper seat bar (9,23), the upper seat bar is concordant with intermediate support bar both ends and is shorter than bottom support bracket boom end,
The upper seat bar and the both ends of intermediate support bar be connected respectively the first bearing upright bar (6,22), the second bearing upright bar (8,
15), the first bearing upright bar, the bottom of the second bearing upright bar are connected with bottom support bracket bar, the two end portions of two horizon bars
Upper end not with the first bearing upright bar, the second bearing upright bar is connected, and bottom branch is connected between two root bottom part seat bar of left and right
Strut 3, the horizon bar are equipped with a socket hole along its length, and the jack on two horizon bars corresponds and inserted with positioning
Reinforcing bar 14, the spacer bar stretch out from horizon bar and between the positioning formed with positioning prefabricated components between adjacent two spacer bar
Gap.
It will be appreciated by those skilled in the art that be, can be according to the size and number for placing prefabricated components, regioselective steel
The bar spacing and quantity of muscle 14.
In order to strengthen a kind of overall construction intensity for the piling bin for placing multiple prefabricated components, the bottom support bracket bar
Both ends the first hound (1,4,16,18) is equipped between the first bearing upright bar, the second bearing upright bar respectively.The bottom
Bottom support bracket bar is stretched out at the both ends of supporting rod, and respectively with the first bearing, the second bearing upper seat bar between be equipped with the
Two hounds (5,21).The bottom support bracket bar the first bearing upright bar, the second bearing upright bar inner side respectively with two levels
The 3rd hound (10,11,17,28) is equipped between bar.
It is made in addition, a kind of piling bin for placing multiple prefabricated components is overall of channel steel welding, it is convenient to make, it is whole
Body is firm and light.
In bottom, the front and rear sides of supporting rod have respectively been laid side by side support board (26,27), are used to support prefabricated components bottom
Portion, in addition reinforces prefabricated components inserted with timber wedge (24,25) between the two sides of prefabricated components and reinforcing bar.
In addition to above preferred embodiment, the utility model also has other embodiments, and those skilled in the art can root
Made various changes and modifications according to the utility model, without departing from the spirit of the utility model, the utility model should all be belonged to
Scope as defined in the claims.
Claims (5)
- A kind of 1. piling bin for placing multiple prefabricated components, it is characterised in that:The first bearing for being arranged side by side including left and right, Two bearings and front and rear two horizon bars being disposed side by side between the first bearing and the second bearing, first bearing/the second Bearing includes bottom support bracket bar, intermediate support bar, the upper seat bar being arranged in parallel successively from top to bottom, the upper seat bar Concordant with intermediate support bar both ends and be shorter than bottom support bracket boom end, the both ends of the upper seat bar and intermediate support bar are distinguished Connect the first bearing upright bar, the second bearing upright bar, the first bearing upright bar, the bottom of the second bearing upright bar and bottom support bracket bar Connection, the upper end of the both ends of two horizon bars respectively with the first bearing upright bar, the second bearing upright bar are connected, two foundation of left and right It is connected with bottom supporting rod between portion's seat bar, the horizon bar is equipped with a socket hole along its length, on two horizon bars Jack corresponds and inserted with spacer bar, and the spacer bar is stretched out from horizon bar and formed between adjacent two spacer bar There is the position gap of positioning prefabricated components.
- A kind of 2. piling bin for placing multiple prefabricated components according to claim 1, it is characterised in that:The bottom branch The both ends of seat bar are equipped with the first hound between the first bearing upright bar, the second bearing upright bar respectively.
- A kind of 3. piling bin for placing multiple prefabricated components according to claim 1, it is characterised in that:The bottom branch Bottom support bracket bar is stretched out at the both ends of strut, and respectively with the first bearing, the second bearing upper seat bar between be equipped with second Hound.
- A kind of 4. piling bin for placing multiple prefabricated components according to claim 1, it is characterised in that:The bottom branch Seat bar is equipped with the 3rd hound between two horizon bars respectively in the inner side of the first bearing upright bar, the second bearing upright bar.
- A kind of 5. piling bin for placing multiple prefabricated components according to claim 1, it is characterised in that:Described one kind can Overall welded by channel steel of piling bin for placing multiple prefabricated components is made.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721341325.1U CN207359040U (en) | 2017-10-18 | 2017-10-18 | A kind of piling bin for placing multiple prefabricated components |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721341325.1U CN207359040U (en) | 2017-10-18 | 2017-10-18 | A kind of piling bin for placing multiple prefabricated components |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207359040U true CN207359040U (en) | 2018-05-15 |
Family
ID=62419640
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721341325.1U Expired - Fee Related CN207359040U (en) | 2017-10-18 | 2017-10-18 | A kind of piling bin for placing multiple prefabricated components |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207359040U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110434819A (en) * | 2019-08-01 | 2019-11-12 | 上海建工七建集团有限公司 | Vertical plate prefabricated member piling bin and its installation method |
CN113716171A (en) * | 2021-09-03 | 2021-11-30 | 四川华构建筑工程有限公司 | Pre-assembled roof truss stacking frame |
-
2017
- 2017-10-18 CN CN201721341325.1U patent/CN207359040U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110434819A (en) * | 2019-08-01 | 2019-11-12 | 上海建工七建集团有限公司 | Vertical plate prefabricated member piling bin and its installation method |
CN113716171A (en) * | 2021-09-03 | 2021-11-30 | 四川华构建筑工程有限公司 | Pre-assembled roof truss stacking frame |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102003066B (en) | Steering folded scaffold unit | |
CN207359040U (en) | A kind of piling bin for placing multiple prefabricated components | |
CN205046462U (en) | Foldable pier shaft template joins externally platform | |
CN107791226A (en) | More prefabricated components double-row vertical stacking adapters | |
CN208584137U (en) | Reinforced mesh welding support | |
CN208310149U (en) | Ramp slope bearing layer platform base | |
CN206752669U (en) | A kind of building frame | |
CN206987351U (en) | A kind of special workbench of I-beam | |
CN204983864U (en) | Concatenation formula tangent supension tower | |
CN206888517U (en) | A kind of cast-in-place support component for building | |
CN107380860A (en) | A kind of double-deck shelf for stacking Prefabricated stacking floor and preparation method thereof | |
CN209538625U (en) | A kind of scaffold | |
CN205282953U (en) | Assembled goods shelves of spatial structure of transformer substation | |
CN205089028U (en) | Weight type four -column communication base station tower | |
CN201214901Y (en) | Folding type steel tube stacking bracket | |
CN207593753U (en) | A kind of special piling bin of prefabricated components | |
CN207158082U (en) | A kind of double-deck shelf for stacking Prefabricated stacking floor | |
CN106996160A (en) | A kind of steel construction assembled wallboard | |
CN208582168U (en) | Insulating ladder hanger | |
CN205133079U (en) | Bracing device behind hanging flower basket support | |
CN204876756U (en) | But reuse's power transmission line iron tower | |
CN204197601U (en) | Stirrup stores lifting frame | |
CN213678396U (en) | Adjustable panel transportation equipment | |
CN204418186U (en) | Interim shaped steel lattice column fills with core apparatus | |
CN217501139U (en) | Hole cover plate for miniature pile foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||