CN209538625U - A kind of scaffold - Google Patents

A kind of scaffold Download PDF

Info

Publication number
CN209538625U
CN209538625U CN201822240357.3U CN201822240357U CN209538625U CN 209538625 U CN209538625 U CN 209538625U CN 201822240357 U CN201822240357 U CN 201822240357U CN 209538625 U CN209538625 U CN 209538625U
Authority
CN
China
Prior art keywords
vertical bar
scaffold
bar
crossbar
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201822240357.3U
Other languages
Chinese (zh)
Inventor
吴国保
吴振华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Rui Yun New Mstar Technology Ltd
Original Assignee
Jiangsu Rui Yun New Mstar Technology Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Rui Yun New Mstar Technology Ltd filed Critical Jiangsu Rui Yun New Mstar Technology Ltd
Priority to CN201822240357.3U priority Critical patent/CN209538625U/en
Application granted granted Critical
Publication of CN209538625U publication Critical patent/CN209538625U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of scaffold, the stand being vertically arranged including two and the multilayer pedal being overlapped between two stands;Each stand is spliced along the vertical direction by multiple scaffold units.By designing the scaffold unit and pedal, when building scaffold, the lower end of first vertical bar of top scaffold unit is set in the upper end of the first connecting rod of corresponding lower section scaffold unit, and it is inserted by the first locating part in the first through hole of corresponding first vertical bar lower end and the second through-hole of first connecting rod upper end, the two is attached, is fastened, stand is formed;Then pedal is overlapped in the first crossbar of corresponding scaffold unit by the hook at both ends, places pedal in different height, constructs multi-layer scaffold, used for construction, greatly improve and build efficiency, and improve applicability.

Description

A kind of scaffold
Technical field
The utility model relates to a kind of scaffolds.
Background technique
Scaffold is widely applied in building trade, has and is built using bamboo, wooden stick, also has and built using steel pipe.But Existing scaffold is temporarily spliced using single vertical bar and cross bar mostly to be built, time-consuming, laborious, low efficiency;If can design A kind of scaffold concatenation unit, it will greatly improve and build efficiency, improve applicability, therefore be badly in need of designing a kind of scaffold list Member.
Summary of the invention
The purpose of this utility model is to provide a kind of scaffold, solving the most of scaffold in the prior art is all to use The technical issues of single vertical bar and cross bar, which temporarily splice, to be built, time-consuming, laborious, low efficiency.
In order to solve the above-mentioned technical problem, the utility model is achieved through the following technical solutions:
A kind of scaffold, the stand being vertically arranged including two and the multilayer pedal being overlapped between two stands;Each Stand is spliced along the vertical direction by multiple scaffold units;
The scaffold unit includes two the first vertical bars disposed in parallel, and there are two for setting between two the first vertical bars One cross bar, the both ends of first crossbar are connected with corresponding first vertical bar respectively, and the first vertical bar is vertically arranged with first crossbar;Two Be provided with the second vertical bar between first crossbar, the both ends of the second vertical bar are connected with corresponding first crossbar respectively, the second vertical bar with First crossbar is vertically arranged;Second crossbar is provided between second vertical bar and the first vertical bar;It opens at the both ends of first vertical bar Equipped with first through hole, the first vertical bar is steel pipe, and the upper end of the first vertical bar is inserted with first connecting rod, and the both ends of first connecting rod are equal The second through-hole is offered, and is inserted under the first through hole and first connecting rod of corresponding first vertical bar upper end by the first locating part In second through-hole at end, first connecting rod and the first vertical bar are fastenedly connected;When building stand, by the of top scaffold unit The lower end of one vertical bar is set in the upper end of the first connecting rod of corresponding lower section scaffold unit, and is inserted by the first locating part In the first through hole of corresponding first vertical bar lower end and the second through-hole of first connecting rod upper end, by the of top scaffold unit First vertical bar of one vertical bar and lower section scaffold unit is attached, fastens.
The pedal includes rectangular frame and the steel wire that is fixed on rectangular frame, the both ends in lengths of frame direction It is provided with hook, pedal is overlapped in the first crossbar of corresponding scaffold unit by the hook at both ends.
By designing the scaffold unit and pedal, when building scaffold, by the first vertical bar of top scaffold unit Lower end be set in corresponding lower section scaffold unit first connecting rod upper end, and by the first locating part be inserted into it is corresponding In the first through hole of first vertical bar lower end and the second through-hole of first connecting rod upper end, the two is attached, is fastened, formed vertical Frame;Then pedal is overlapped in the first crossbar of corresponding scaffold unit by the hook at both ends, is stepped in different height placement Plate constructs multi-layer scaffold, uses for construction, greatly improves and build efficiency, and improves applicability.Wherein, scaffold list The second crossbar of member is climbed as ladder for the personnel of building.
It is further improved, the both ends of the first locating part of the scaffold unit are movable to be provided with the second locating part, prevents Only the first locating part and the first vertical bar, first connecting rod are detached from.
It is further improved, further includes brace, the both ends of brace are provided with third through-hole;The inside of first vertical bar There are two brace connection component, brace connection component includes third cross bar and third locating part for setting, and the one of third cross bar End is fixedly connected with the first vertical bar, and the other end and third locating part are rotatablely connected;Two brace connection components are located at two the Between one through-hole.
One end of brace is set on third cross bar by third through-hole, rotates third locating part, makes itself and third cross Bar is vertical;The other end of brace is connect with the brace connection component of the scaffold unit of sustained height in another stand.
By the way that oblique railing is arranged, two opposite scaffold units are connected as entirety, improve the structure of entire scaffold Stability enhances security performance, and easy to connect, firm.
It is further improved, one end of the third locating part is cambered surface, prevents wedge angle scuffing from building personnel.
It is further improved, second vertical bar is located on the perpendicular bisector of first crossbar, the second vertical bar and left side first crossbar Between be provided with a second crossbar, setting is there are two second crossbar between the second vertical bar and right side first crossbar.Pass through increase The quantity of second crossbar improves overall structure stability, while providing more climbing ladders for the personnel of building, and improves safety Energy.
It is further improved, multiple support rods is provided on the rectangular frame of the pedal, steel wire is located above support rod. By the way that support rod is arranged, the intensity of pedal is improved, bearing capacity is enhanced.
Compared with prior art, the utility model has the beneficial effects that
By designing the scaffold unit and pedal, when building scaffold, by the first vertical bar of top scaffold unit Lower end be set in corresponding lower section scaffold unit first connecting rod upper end, and by the first locating part be inserted into it is corresponding In the first through hole of first vertical bar lower end and the second through-hole of first connecting rod upper end, the two is attached, is fastened, formed vertical Frame;Then pedal is overlapped in the first crossbar of corresponding scaffold unit by the hook at both ends, is stepped in different height placement Plate constructs multi-layer scaffold, uses for construction, greatly improves and build efficiency, and improves applicability.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of stand.
Fig. 2 is the structural schematic diagram of the utility model scaffold unit.
Fig. 3 is the structural schematic diagram of pedal.
Fig. 4 is the top view of Fig. 3.
Specific embodiment
To keep the purpose of this utility model and technical solution clearer, below in conjunction with the utility model embodiment to this The technical solution of utility model is clearly and completely described.
As shown in Figs 1-4, a kind of scaffold, the stand being vertically arranged including two and is overlapped on more between two stands Layer pedal 30;Each stand is spliced along the vertical direction by multiple scaffold units 20.
The scaffold unit 20 includes two the first vertical bars 1 disposed in parallel, is provided with two between two the first vertical bars A first crossbar 2, the both ends of first crossbar are connected with corresponding first vertical bar respectively, and the first vertical bar is vertical with first crossbar to be set It sets.The second vertical bar 3 is provided between two first crossbars, the both ends of the second vertical bar 3 are connected with corresponding first crossbar 2 respectively, Second vertical bar is vertically arranged with first crossbar;Second crossbar 4 is provided between second vertical bar and the first vertical bar.First vertical bar 1 both ends offer first through hole 6, and the first vertical bar 1 is steel pipe, and the upper end of the first vertical bar is inserted with first connecting rod 5, and first The both ends of connecting rod offer the second through-hole 7, and are inserted into the first of corresponding first vertical bar upper end by the first locating part 8 and lead to In second through-hole 7 of hole 6 and first connecting rod lower end, first connecting rod and the first vertical bar are fastenedly connected.It, will when building stand The lower end of first vertical bar of top scaffold unit is set in the upper end of the first connecting rod of corresponding lower section scaffold unit, and It is inserted by the first locating part in the first through hole of corresponding first vertical bar lower end and the second through-hole of first connecting rod upper end, it will First vertical bar of top scaffold unit is attached with the first vertical bar of lower section scaffold unit, fastens.
The pedal 30 includes rectangular frame 31 and the steel wire 32 being fixed on rectangular frame 31, lengths of frame side To both ends be provided with hook 34, pedal 30 is overlapped on the first crossbar 2 of corresponding scaffold unit 20 by the hook 34 at both ends On.
By designing the scaffold unit and pedal, when building scaffold, by the first vertical bar of top scaffold unit Lower end be set in corresponding lower section scaffold unit first connecting rod upper end, and by the first locating part be inserted into it is corresponding In the first through hole of first vertical bar lower end and the second through-hole of first connecting rod upper end, the two is attached, is fastened, formed vertical Frame;Then pedal is overlapped in the first crossbar of corresponding scaffold unit by the hook at both ends, is stepped in different height placement Plate constructs multi-layer scaffold, uses for construction, greatly improves and build efficiency, and improves applicability.Wherein, scaffold list The second crossbar of member is climbed as ladder for the personnel of building.
In the present embodiment, the both ends of the first locating part 8 of the scaffold unit 20 are movable is provided with the second limit Part prevents the first locating part and the first vertical bar 1, first connecting rod 5 to be detached from.
It in the present embodiment, further include brace (not shown), the both ends of brace are provided with third through-hole;It is described There are two brace connection component, brace connection component includes third cross bar 9 and third limit for the inside setting of first vertical bar Part 10, one end of third cross bar are fixedly connected with the first vertical bar, and the other end and third locating part are rotatablely connected;Two braces connect Connected components are located between two first through hole.One end of brace is set on third cross bar by third through-hole, rotates third Locating part keeps it vertical with third cross bar;The scaffold unit of sustained height on the other end of brace and another stand The connection of brace connection component.
By the way that oblique railing is arranged, two opposite scaffold units are connected as entirety, improve the structure of entire scaffold Stability enhances security performance, and easy to connect, firm.
In the present embodiment, one end of the third locating part 10 is cambered surface, prevents wedge angle scuffing from building personnel.
In the present embodiment, second vertical bar 3 is located on the perpendicular bisector of first crossbar 2, the second vertical bar and left side first A second crossbar 4 is provided between cross bar, there are two second crossbars for setting between the second vertical bar and right side first crossbar.Pass through Increase the quantity of second crossbar, improves overall structure stability, while providing more climbing ladders for the personnel of building, improve peace Full performance.
In the present embodiment, multiple support rods 33 are provided on the rectangular frame 31 of the pedal 30, steel wire 32 is located at 33 top of support rod.By the way that support rod is arranged, the intensity of pedal is improved, bearing capacity is enhanced.
Do not done in the utility model illustrate be the prior art or can be realized by the prior art, Er Qieben Specific implementation case described in utility model is only the preferable case study on implementation of the utility model, is not used to limit practical Novel practical range.Equivalent changes and modifications made by i.e. all contents according to present utility model application the scope of the patents, should all make For the technology scope of the utility model.

Claims (6)

1. a kind of scaffold, which is characterized in that the stand being vertically arranged including two and the multilayer being overlapped between two stands Pedal;Each stand is spliced along the vertical direction by multiple scaffold units;
The scaffold unit includes two the first vertical bars disposed in parallel, and setting is horizontal there are two first between two the first vertical bars Bar, the both ends of first crossbar are connected with corresponding first vertical bar respectively, and the first vertical bar is vertically arranged with first crossbar;Two first The second vertical bar is provided between cross bar, the both ends of the second vertical bar are connected with corresponding first crossbar respectively, the second vertical bar and first Cross bar is vertically arranged;Second crossbar is provided between second vertical bar and the first vertical bar;The both ends of first vertical bar offer First through hole, the first vertical bar are steel pipe, and the upper end of the first vertical bar is inserted with first connecting rod, and the both ends of first connecting rod open up There is the second through-hole, and is inserted into first through hole and the first connecting rod lower end of corresponding first vertical bar upper end by the first locating part In second through-hole, first connecting rod and the first vertical bar are fastenedly connected;When building stand, the first of top scaffold unit is erected The lower end of bar is set in the upper end of the first connecting rod of corresponding lower section scaffold unit, and is corresponded to by the insertion of the first locating part The first through hole of the first vertical bar lower end and the second through-hole of first connecting rod upper end in, the first of top scaffold unit is erected First vertical bar of bar and lower section scaffold unit is attached, fastens;
The pedal includes rectangular frame and the steel wire that is fixed on rectangular frame, the both ends setting in lengths of frame direction There is hook, pedal is overlapped in the first crossbar of corresponding scaffold unit by the hook at both ends.
2. scaffold according to claim 1, which is characterized in that first locating part both ends are movable to be provided with second Locating part.
3. scaffold according to claim 1 or 2, which is characterized in that further include brace, the both ends of brace are provided with Third through-hole;
There are two brace connection component, brace connection component includes third cross bar and for the inside setting of first vertical bar Three locating parts, one end of third cross bar are fixedly connected with the first vertical bar, and the other end and third locating part are rotatablely connected;Two oblique pulls Bar connection component is located between two first through hole;
One end of brace is set on third cross bar by third through-hole, rotates third locating part, it is made to hang down with third cross bar Directly;The other end of brace is connect with the brace connection component of the scaffold unit of sustained height in another stand.
4. scaffold according to claim 3, which is characterized in that one end of the third locating part is cambered surface.
5. scaffold according to claim 4, which is characterized in that second vertical bar is located at the perpendicular bisector of first crossbar On, it is provided with a second crossbar between the second vertical bar and left side first crossbar, is set between the second vertical bar and right side first crossbar Second crossbar there are two setting.
6. scaffold according to claim 5, which is characterized in that be provided with multiple supports on the rectangular frame of the pedal Bar, steel wire are located above support rod.
CN201822240357.3U 2018-12-28 2018-12-28 A kind of scaffold Expired - Fee Related CN209538625U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822240357.3U CN209538625U (en) 2018-12-28 2018-12-28 A kind of scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822240357.3U CN209538625U (en) 2018-12-28 2018-12-28 A kind of scaffold

Publications (1)

Publication Number Publication Date
CN209538625U true CN209538625U (en) 2019-10-25

Family

ID=68267242

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822240357.3U Expired - Fee Related CN209538625U (en) 2018-12-28 2018-12-28 A kind of scaffold

Country Status (1)

Country Link
CN (1) CN209538625U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112942791A (en) * 2021-04-13 2021-06-11 北京天润建设有限公司 Small-space lifting scaffold and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112942791A (en) * 2021-04-13 2021-06-11 北京天润建设有限公司 Small-space lifting scaffold and construction method

Similar Documents

Publication Publication Date Title
CN201835512U (en) Turning folding scaffold unit
CN102003066A (en) Steering folded scaffold unit
CN209538625U (en) A kind of scaffold
CN219528334U (en) Scaffold for building construction
CN207359040U (en) A kind of piling bin for placing multiple prefabricated components
CN209523446U (en) A kind of scaffold unit
CN212295608U (en) System for stabilizing climbing scaffold
CN204960458U (en) Light -duty communication angle steel tower structure of acting as go -between
CN111550031A (en) System for stabilizing climbing scaffold
CN206753084U (en) The safe discharging platform of assembled for construction
CN201447906U (en) Safe guardrail
CN210563318U (en) Attached scaffold for constructional engineering
CN209163395U (en) The totally-enclosed scaffold system of console mode
CN216893369U (en) Scaffold structure for construction convenient to build
CN219548303U (en) Scaffold for civil engineering construction
CN207700648U (en) A kind of speed takes formula arched door type external scaffolding
CN205133079U (en) Bracing device behind hanging flower basket support
CN211286746U (en) Steady-supported scaffold protective net and scaffold
CN219100689U (en) Attachment structure suitable for super high floor attached lifting scaffold
CN213654187U (en) Attached support suitable for super high floor steel climbing frame
CN204781885U (en) Novel crown cornice shaped steel operation platform that encorbelments
CN216426559U (en) High tower crane adapter sleeve of security
CN211691396U (en) Lifting truss under attached lifting scaffold
CN211473315U (en) A simple and easy horizontal walking passageway of suspension type for piece formula truss
CN220620961U (en) Building construction has building construction frame of anti falling structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191025