CN207348217U CN201721323436.XU CN201721323436U CN207348217U CN 207348217 U CN207348217 U CN 207348217U CN 201721323436 U CN201721323436 U CN 201721323436U CN 207348217 U CN207348217 U CN 207348217U
Authority
CN
China
Prior art keywords
crossbeam
shear
reinforcing bar
pushing block
steel bars
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721323436.XU
Other languages
Chinese (zh)
Inventor
时晓利
闫超
李洪祯
孙延安
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Standard Construction Co Ltd
Original Assignee
Shandong Standard Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Standard Construction Co Ltd filed Critical Shandong Standard Construction Co Ltd
Priority to CN201721323436.XU priority Critical patent/CN207348217U/en
Application granted granted Critical
Publication of CN207348217U publication Critical patent/CN207348217U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses the assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used,Including crossbeam,One end of the crossbeam is provided with the first shear wall,The other end is provided with the second shear wall,Shaft is provided between first shear wall and crossbeam,The one end of the shaft away from crossbeam is provided with the second fixed steel bars and the first fixed steel bars,Second fixed steel bars are located at the side of the first fixed steel bars,Plug hole is provided with the top of the crossbeam,And the side of crossbeam is provided with pushing block and lower pushing block,The utility model is provided with upper shifting chute,Upper promotion reinforcing bar and upper pushing block,When user needs to transport crossbeam,Pushing block in promotion,Upper pushing block, which promotes, promotes reinforcing bar to be moved in upper shifting chute,Until income is into crossbeam completely,Make in crossbeam transportational process,Even if road bump,Make to promote reinforcing bar more firm,Increase the stability of crossbeam,Further improve the stability in house.

Description

The assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used
Technical field
The utility model belongs to prefabricated concrete structure technical field, and in particular to assembly concrete frame-shear structure is cut The assembled connection structure of power wall coupling beam.
Background technology
Fabricated construction is the abbreviation of prefabricated concrete structure, is to connect using prefabricated components as main bearing member through assembling The concrete structure connect, precast reinforced concrete structure are one of important directions of China's building structure development, it has Beneficial to the development of China's building industrialization, improve production efficiency and save the energy, develop Green environmental-protection building, and be conducive to improve With guarantee construction engineering quality, compared with cast-in-situ construction method, assembled reinforced concrete structure is conducive to green construction, because assembled is applied Work can more meet saving land, is energy saving, saving the requirement such as material, water-saving and environmental protection for green construction, reduce the negative effect to environment, Including reduce noise, prevent airborne dust, reduce environmental pollution, clean transport, reduce place disturb, saving water, electricity, the resource such as material And the energy, it then follows the principle of sustainable development, and also fabricated construction can continuously complete the multiple or complete of engineering in order Portion's process, so as to reduce the engineering machinery type and quantity marched into the arena, eliminate procedure connection rests the time, realizes that crossings on different level is made Industry, reduces construction personnel, so as to improve work efficiency, reduce supplies consumption, provide safeguard for green construction.
But the assembled connection structure of assembly concrete coupling beam currently on the market is not provided with promoting reinforcing bar easy to allow The device that can be stored, crossbeam promote reinforcing bar easily to bend, cause reinforcing bar to consolidate the reduction of effect, very in long-distance transport To allowing crossbeam to easily snap off, the stability in house is reduced, is not provided with the device being easy to and shear wall is fixed, crossbeam fixed form It is unstable, it is not easy to be poured during casting concrete during construction, reduces construction efficiency, extend the duration.
Utility model content
The purpose of this utility model is to provide the assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used, To solve the device proposed in the above background technology being not provided with easy to which promotion reinforcing bar can be stored, crossbeam is being transported for long-distance When promote reinforcing bar easily to bend, cause reinforcing bar to consolidate the reduction of effect, or even allow crossbeam to easily snap off, reduce the steady of house The problem of solidity.
To achieve the above object, the utility model provides following technical solution:Assembly concrete frame-shear structure shear wall The assembled connection structure of coupling beam, including crossbeam, one end of the crossbeam are provided with the first shear wall, and the other end of the crossbeam is set The second shear wall is equipped with, shaft, one end connection of the shaft away from crossbeam are provided between first shear wall and crossbeam There are the second fixed steel bars and the first fixed steel bars, second fixed steel bars are located at the side of the first fixed steel bars, the crossbeam Top be provided with plug hole, and the side of crossbeam is provided with pushing block and lower pushing block, and the lower pushing block is located at the one of upper pushing block Side, and middle pushing block is provided between lower pushing block and upper pushing block, the side of the upper pushing block is provided with promotion reinforcing bar, described above to push away Dynamic that shifting chute is provided between reinforcing bar and crossbeam, the side of the middle pushing block is provided with middle promotion reinforcing bar, the middle promotion steel Be provided with middle shifting chute between muscle and crossbeam, the side of the lower pushing block is provided with lower promotion reinforcing bar, the lower promotion reinforcing bar with Lower shifting chute is provided between crossbeam, be both provided with first shear wall and the second shear wall with it is upper promotion reinforcing bar, under push away Dynamic reinforcing bar and the corresponding link slot of middle promotion reinforcing bar.
Preferably, the plug hole is provided with three altogether, and three plug holes are located at the top of crossbeam.
Preferably, the shaft is provided with six altogether, and six shafts are separately mounted to the both sides of crossbeam.
Preferably, the height of first shear wall is equal with the second shear wall.
Compared with prior art, the beneficial effects of the utility model are:
(1)The utility model, which is provided with upper shifting chute, upper promotion reinforcing bar and upper pushing block, user, to be needed to transport crossbeam When defeated, pushing block in promotion, upper pushing block, which promotes, promotes reinforcing bar to be moved in upper shifting chute, until taking in completely to crossbeam In, make in crossbeam transportational process, even if road bump, upper promotion reinforcing bar will not bend, and make to promote reinforcing bar more steady Gu increasing the stability of crossbeam, the stability in house is further improved.
(2)The utility model is provided with the first fixed steel bars, the second fixed steel bars and shaft, and user needs to install crossbeam When, reinforcing bar will be promoted to be released from crossbeam, crossbeam will be attached respectively at the first shear wall and the second shear wall, and make first to consolidate Determine reinforcing bar and the second fixed steel bars turn to angle parallel to each other respectively around shaft, the stability that increase crossbeam is fixed, keeps away Exempt from crossbeam to come off in the case where earthquake occurs, improve the shock resistance in house.
Brief description of the drawings
Fig. 1 is the structure diagram of the utility model;
Fig. 2 is the top view of the utility model;
Fig. 3 is the cut-away view of the utility model crossbeam.
In figure:The first shear walls of 1-;2- crossbeams;The upper shifting chutes of 3-;Reinforcing bar is promoted on 4-;The upper pushing blocks of 5-;Pushing block under 6-;7- Lower shifting chute;The second shear walls of 8-;Reinforcing bar is promoted under 9-;Shifting chute in 10-;Pushing block in 11-;Reinforcing bar is promoted in 12-;13- One fixed steel bars;The second fixed steel bars of 14-;15- shafts;16- pouring holes.
Embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are without making creative work All other embodiments obtained, shall fall within the protection scope of the present invention.
- 3 are please referred to Fig.1, the utility model provides the assembled connection knot of assembly concrete frame-shear structure Shear-wall Connecting Beam Used Structure technical solution:The assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used, including crossbeam 2, crossbeam 2 are used to connect The first shear wall 1 and the second shear wall 8 are connect, one end of crossbeam 2 is provided with the first shear wall 1, and the other end is provided with the second shearing Wall 8, is connected with shaft 15 between the first shear wall 1 and crossbeam 2, shaft 15 plays the first fixed steel bars of rotation 13 and second and fixes The effect of reinforcing bar 14, the one end of shaft 15 away from crossbeam 2 connect the second fixed steel bars 14 and the first fixed steel bars 13, play connection The effect of first shear wall 1 and the second shear wall 8, the second fixed steel bars 14 are located at the side of the first fixed steel bars 13, crossbeam 2 Top pouring has plug hole 16, plays the role of easy to allow concrete to enter crossbeam 2, and the side of crossbeam 2 is provided with pushing block 5 With lower pushing block 6, lower pushing block 6 is located at the side of upper pushing block 5, and middle pushing block 11 is provided between lower pushing block 6 and upper pushing block 5, above pushes away The side of block 5, which is connected with, promotes reinforcing bar 4, and horizontal upper shifting chute 3, middle pushing block are offered between upper promotion reinforcing bar 4 and crossbeam 2 11 side be connected with it is middle promotion reinforcing bar 12, it is middle promotion reinforcing bar 12 and crossbeam 2 between offer horizontal middle shifting chute 10, under push away The side of block 6 is connected with lower promotion reinforcing bar 9, and horizontal lower shifting chute 7 is offered between lower promotion reinforcing bar 9 and crossbeam 2.
In order to make the first shear wall 1 and the second shear wall 8 are conveniently attached with crossbeam 2, in the present embodiment, the first shearing Offered on 1 and second shear wall 8 of wall and upper promotion reinforcing bar 4, lower promotion reinforcing bar 9 and middle promotion 12 corresponding connection of reinforcing bar Groove.
In order to make crossbeam 2 easy to pour, in the present embodiment, it is preferred that plug hole 16 is provided with three, and three cast altogether Hole 16 is located at the top of crossbeam 2.
In order to increase the stability of the fixation of crossbeam 2, in the present embodiment, it is preferred that shaft 15 is provided with six, and six altogether Shaft 15 is separately mounted to the both sides of crossbeam 2.
In order to be easily installed crossbeam 2, in the present embodiment, it is preferred that the height of the first shear wall 1 and the second shear wall 8 It is equal.
Operation principle:When user needs to transport crossbeam, upper pushing block 5, lower pushing block 6 and middle pushing block are promoted respectively 11, upper pushing block 5, which promotes, promotes reinforcing bar 4 to be moved in upper shifting chute 3, until income is into crossbeam 2 completely, middle pushing block 11 Promote reinforcing bar 12 to be moved in middle shifting chute 10 in promotion, lower pushing block 6 promote it is lower promote reinforcing bar 9 in lower shifting chute 7 into Row movement, when upper promotion reinforcing bar 4, middle promotion reinforcing bar 12 and lower promotion reinforcing bar 9 are taken in into crossbeam 2, shifting is carried to by crossbeam 2 On motor-car, crossbeam 2 is transported to infield using mobile vehicle, after reaching infield, by crossbeam 2 from mobile vehicle On unload, by it is upper promotion reinforcing bar 4, it is middle promotion reinforcing bar 12 and it is lower promotion reinforcing bar 9 released respectively from crossbeam 2, by crossbeam 2 respectively at First shear wall 1 and the second shear wall 8 are attached, and make the first fixed steel bars 13 and the second fixed steel bars 14 respectively around shaft 15 turn to angle parallel to each other, crossbeam 2 is engaged respectively at the first shear wall 1 with the second shear wall 8.
While there has been shown and described that the embodiment of the utility model, for the ordinary skill in the art, It is appreciated that these embodiments can be carried out with a variety of changes in the case where not departing from the principle of the utility model and spirit, repaiied Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.

Claims (4)

1. the assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used, including crossbeam(2), it is characterised in that:Institute State crossbeam(2)One end be provided with the first shear wall(1), the crossbeam(2)The other end be provided with the second shear wall(8), institute State the first shear wall(1)With crossbeam(2)Between be provided with shaft(15), the shaft(15)Away from crossbeam(2)One end connection There are the second fixed steel bars(14)With the first fixed steel bars(13), second fixed steel bars(14)Positioned at the first fixed steel bars(13) Side, the crossbeam(2)Top be provided with plug hole(16), and crossbeam(2)Side be provided with pushing block(5)Pushed away with Block(6), the lower pushing block(6)Positioned at upper pushing block(5)Side, and lower pushing block(6)With upper pushing block(5)Between be provided with middle pushing block (11), the upper pushing block(5)Side be provided with promotion reinforcing bar(4), the upper promotion reinforcing bar(4)With crossbeam(2)Between set It is equipped with shifting chute(3), the middle pushing block(11)Side be provided with middle promotion reinforcing bar(12), the middle promotion reinforcing bar(12)With Crossbeam(2)Between be provided with middle shifting chute(10), the lower pushing block(6)Side be provided with lower promotion reinforcing bar(9), pushed away under described Dynamic reinforcing bar(9)With crossbeam(2)Between be provided with lower shifting chute(7), first shear wall(1)With the second shear wall(8)It is upper equal It is provided with and upper promotion reinforcing bar(4), lower promotion reinforcing bar(9)With middle promotion reinforcing bar(12)Corresponding link slot.
2. the assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used according to claim 1, its feature It is:The plug hole(16)Three, and three plug holes are provided with altogether(16)Positioned at crossbeam(2)Top.
3. the assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used according to claim 1, its feature It is:The shaft(15)Six, and six shafts are provided with altogether(15)It is separately mounted to crossbeam(2)Both sides.
4. the assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used according to claim 1, its feature It is:First shear wall(1)Height and the second shear wall(8)It is equal.
CN201721323436.XU 2017-10-16 2017-10-16 The assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used Expired - Fee Related CN207348217U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721323436.XU CN207348217U (en) 2017-10-16 2017-10-16 The assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721323436.XU CN207348217U (en) 2017-10-16 2017-10-16 The assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used

Publications (1)

Publication Number Publication Date
CN207348217U true CN207348217U (en) 2018-05-11

Family

ID=62358309

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721323436.XU Expired - Fee Related CN207348217U (en) 2017-10-16 2017-10-16 The assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used

Country Status (1)

Country Link
CN (1) CN207348217U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227562A (en) * 2020-10-23 2021-01-15 温州大学瓯江学院 Assembled building anti-seismic wall

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227562A (en) * 2020-10-23 2021-01-15 温州大学瓯江学院 Assembled building anti-seismic wall

Similar Documents

Publication Publication Date Title
CN109868898B (en) A kind of assembled Self-resetting node
CN204849571U (en) Prefabricated assembly pier of posttension prestressing force tongue -and -groove plug -in type
CN203808292U (en) Assembly type gridded shear wall structure system
CN109295994B (en) Full-assembly type wind power tower cylinder foundation with combined structure
CN104695979B (en) A kind of method using tall and big chassis whole lateral moving high and big die plate
CN201609922U (en) Pull type prefabricated small box girder iron core
CN207348217U (en) The assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used
CN203603261U (en) Connecting structure for balcony slab and superposed beam
CN103866866B (en) Super High Core Walls Structure and housing water node after setting a roof beam in place
CN108756038A (en) Assembly concrete shear wall and floor support plate rigid connection node and construction method
CN206829463U (en) A kind of light steel insulation lightweight concrete floor construction
CN207660094U (en) A kind of Quick assembling structure of house foundation
CN2905894Y (en) Concrete prefabricated groove
CN109555268A (en) Prefabricated support column and its construction method based on H profile steel
CN206267169U (en) A kind of split blade type prestressing force anchor slab
CN103541435B (en) With the cross node of full assembling of steel plate concrete Cantilever Beams
CN108755949A (en) Assembly concrete girder and time beam connecting node and construction method
CN205530324U (en) Miniature stake of thin -walled cold -formed steel
CN204401829U (en) RPC compound shear wall is filled out in a kind of encased steel plate
CN209369026U (en) Assembly concrete beam column dry type connector
CN204282193U (en) A kind of steel-concrete combination beam
CN203428805U (en) Combined tower crane base
CN207484827U (en) A kind of efficiently measuring body roof truss beam precast concrete
CN103541434B (en) The complete cross Combined concrete node of assembled
CN208899639U (en) Assembly concrete girder and time beam connecting node

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180511

Termination date: 20201016