- CN207348217U CN207348217U CN201721323436.XU CN201721323436U CN207348217U CN 207348217 U CN207348217 U CN 207348217U CN 201721323436 U CN201721323436 U CN 201721323436U CN 207348217 U CN207348217 U CN 207348217U
- Authority
- CN
- China
- Prior art keywords
- crossbeam
- shear
- reinforcing bar
- pushing block
- steel bars
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses the assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used,Including crossbeam,One end of the crossbeam is provided with the first shear wall,The other end is provided with the second shear wall,Shaft is provided between first shear wall and crossbeam,The one end of the shaft away from crossbeam is provided with the second fixed steel bars and the first fixed steel bars,Second fixed steel bars are located at the side of the first fixed steel bars,Plug hole is provided with the top of the crossbeam,And the side of crossbeam is provided with pushing block and lower pushing block,The utility model is provided with upper shifting chute,Upper promotion reinforcing bar and upper pushing block,When user needs to transport crossbeam,Pushing block in promotion,Upper pushing block, which promotes, promotes reinforcing bar to be moved in upper shifting chute,Until income is into crossbeam completely,Make in crossbeam transportational process,Even if road bump,Make to promote reinforcing bar more firm,Increase the stability of crossbeam,Further improve the stability in house.
Description
Technical field
The utility model belongs to prefabricated concrete structure technical field, and in particular to assembly concrete frame-shear structure is cut
The assembled connection structure of power wall coupling beam.
Background technology
Fabricated construction is the abbreviation of prefabricated concrete structure, is to connect using prefabricated components as main bearing member through assembling
The concrete structure connect, precast reinforced concrete structure are one of important directions of China's building structure development, it has
Beneficial to the development of China's building industrialization, improve production efficiency and save the energy, develop Green environmental-protection building, and be conducive to improve
With guarantee construction engineering quality, compared with cast-in-situ construction method, assembled reinforced concrete structure is conducive to green construction, because assembled is applied
Work can more meet saving land, is energy saving, saving the requirement such as material, water-saving and environmental protection for green construction, reduce the negative effect to environment,
Including reduce noise, prevent airborne dust, reduce environmental pollution, clean transport, reduce place disturb, saving water, electricity, the resource such as material
And the energy, it then follows the principle of sustainable development, and also fabricated construction can continuously complete the multiple or complete of engineering in order
Portion's process, so as to reduce the engineering machinery type and quantity marched into the arena, eliminate procedure connection rests the time, realizes that crossings on different level is made
Industry, reduces construction personnel, so as to improve work efficiency, reduce supplies consumption, provide safeguard for green construction.
But the assembled connection structure of assembly concrete coupling beam currently on the market is not provided with promoting reinforcing bar easy to allow
The device that can be stored, crossbeam promote reinforcing bar easily to bend, cause reinforcing bar to consolidate the reduction of effect, very in long-distance transport
To allowing crossbeam to easily snap off, the stability in house is reduced, is not provided with the device being easy to and shear wall is fixed, crossbeam fixed form
It is unstable, it is not easy to be poured during casting concrete during construction, reduces construction efficiency, extend the duration.
Utility model content
The purpose of this utility model is to provide the assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used,
To solve the device proposed in the above background technology being not provided with easy to which promotion reinforcing bar can be stored, crossbeam is being transported for long-distance
When promote reinforcing bar easily to bend, cause reinforcing bar to consolidate the reduction of effect, or even allow crossbeam to easily snap off, reduce the steady of house
The problem of solidity.
To achieve the above object, the utility model provides following technical solution:Assembly concrete frame-shear structure shear wall
The assembled connection structure of coupling beam, including crossbeam, one end of the crossbeam are provided with the first shear wall, and the other end of the crossbeam is set
The second shear wall is equipped with, shaft, one end connection of the shaft away from crossbeam are provided between first shear wall and crossbeam
There are the second fixed steel bars and the first fixed steel bars, second fixed steel bars are located at the side of the first fixed steel bars, the crossbeam
Top be provided with plug hole, and the side of crossbeam is provided with pushing block and lower pushing block, and the lower pushing block is located at the one of upper pushing block
Side, and middle pushing block is provided between lower pushing block and upper pushing block, the side of the upper pushing block is provided with promotion reinforcing bar, described above to push away
Dynamic that shifting chute is provided between reinforcing bar and crossbeam, the side of the middle pushing block is provided with middle promotion reinforcing bar, the middle promotion steel
Be provided with middle shifting chute between muscle and crossbeam, the side of the lower pushing block is provided with lower promotion reinforcing bar, the lower promotion reinforcing bar with
Lower shifting chute is provided between crossbeam, be both provided with first shear wall and the second shear wall with it is upper promotion reinforcing bar, under push away
Dynamic reinforcing bar and the corresponding link slot of middle promotion reinforcing bar.
Preferably, the plug hole is provided with three altogether, and three plug holes are located at the top of crossbeam.
Preferably, the shaft is provided with six altogether, and six shafts are separately mounted to the both sides of crossbeam.
Preferably, the height of first shear wall is equal with the second shear wall.
Compared with prior art, the beneficial effects of the utility model are:
(1)The utility model, which is provided with upper shifting chute, upper promotion reinforcing bar and upper pushing block, user, to be needed to transport crossbeam
When defeated, pushing block in promotion, upper pushing block, which promotes, promotes reinforcing bar to be moved in upper shifting chute, until taking in completely to crossbeam
In, make in crossbeam transportational process, even if road bump, upper promotion reinforcing bar will not bend, and make to promote reinforcing bar more steady
Gu increasing the stability of crossbeam, the stability in house is further improved.
(2)The utility model is provided with the first fixed steel bars, the second fixed steel bars and shaft, and user needs to install crossbeam
When, reinforcing bar will be promoted to be released from crossbeam, crossbeam will be attached respectively at the first shear wall and the second shear wall, and make first to consolidate
Determine reinforcing bar and the second fixed steel bars turn to angle parallel to each other respectively around shaft, the stability that increase crossbeam is fixed, keeps away
Exempt from crossbeam to come off in the case where earthquake occurs, improve the shock resistance in house.
Brief description of the drawings
Fig. 1 is the structure diagram of the utility model;
Fig. 2 is the top view of the utility model;
Fig. 3 is the cut-away view of the utility model crossbeam.
In figure:The first shear walls of 1-;2- crossbeams;The upper shifting chutes of 3-;Reinforcing bar is promoted on 4-;The upper pushing blocks of 5-;Pushing block under 6-;7-
Lower shifting chute;The second shear walls of 8-;Reinforcing bar is promoted under 9-;Shifting chute in 10-;Pushing block in 11-;Reinforcing bar is promoted in 12-;13-
One fixed steel bars;The second fixed steel bars of 14-;15- shafts;16- pouring holes.
Embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are without making creative work
All other embodiments obtained, shall fall within the protection scope of the present invention.
- 3 are please referred to Fig.1, the utility model provides the assembled connection knot of assembly concrete frame-shear structure Shear-wall Connecting Beam Used
Structure technical solution:The assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used, including crossbeam 2, crossbeam 2 are used to connect
The first shear wall 1 and the second shear wall 8 are connect, one end of crossbeam 2 is provided with the first shear wall 1, and the other end is provided with the second shearing
Wall 8, is connected with shaft 15 between the first shear wall 1 and crossbeam 2, shaft 15 plays the first fixed steel bars of rotation 13 and second and fixes
The effect of reinforcing bar 14, the one end of shaft 15 away from crossbeam 2 connect the second fixed steel bars 14 and the first fixed steel bars 13, play connection
The effect of first shear wall 1 and the second shear wall 8, the second fixed steel bars 14 are located at the side of the first fixed steel bars 13, crossbeam 2
Top pouring has plug hole 16, plays the role of easy to allow concrete to enter crossbeam 2, and the side of crossbeam 2 is provided with pushing block 5
With lower pushing block 6, lower pushing block 6 is located at the side of upper pushing block 5, and middle pushing block 11 is provided between lower pushing block 6 and upper pushing block 5, above pushes away
The side of block 5, which is connected with, promotes reinforcing bar 4, and horizontal upper shifting chute 3, middle pushing block are offered between upper promotion reinforcing bar 4 and crossbeam 2
11 side be connected with it is middle promotion reinforcing bar 12, it is middle promotion reinforcing bar 12 and crossbeam 2 between offer horizontal middle shifting chute 10, under push away
The side of block 6 is connected with lower promotion reinforcing bar 9, and horizontal lower shifting chute 7 is offered between lower promotion reinforcing bar 9 and crossbeam 2.
In order to make the first shear wall 1 and the second shear wall 8 are conveniently attached with crossbeam 2, in the present embodiment, the first shearing
Offered on 1 and second shear wall 8 of wall and upper promotion reinforcing bar 4, lower promotion reinforcing bar 9 and middle promotion 12 corresponding connection of reinforcing bar
Groove.
In order to make crossbeam 2 easy to pour, in the present embodiment, it is preferred that plug hole 16 is provided with three, and three cast altogether
Hole 16 is located at the top of crossbeam 2.
In order to increase the stability of the fixation of crossbeam 2, in the present embodiment, it is preferred that shaft 15 is provided with six, and six altogether
Shaft 15 is separately mounted to the both sides of crossbeam 2.
In order to be easily installed crossbeam 2, in the present embodiment, it is preferred that the height of the first shear wall 1 and the second shear wall 8
It is equal.
Operation principle:When user needs to transport crossbeam, upper pushing block 5, lower pushing block 6 and middle pushing block are promoted respectively
11, upper pushing block 5, which promotes, promotes reinforcing bar 4 to be moved in upper shifting chute 3, until income is into crossbeam 2 completely, middle pushing block 11
Promote reinforcing bar 12 to be moved in middle shifting chute 10 in promotion, lower pushing block 6 promote it is lower promote reinforcing bar 9 in lower shifting chute 7 into
Row movement, when upper promotion reinforcing bar 4, middle promotion reinforcing bar 12 and lower promotion reinforcing bar 9 are taken in into crossbeam 2, shifting is carried to by crossbeam 2
On motor-car, crossbeam 2 is transported to infield using mobile vehicle, after reaching infield, by crossbeam 2 from mobile vehicle
On unload, by it is upper promotion reinforcing bar 4, it is middle promotion reinforcing bar 12 and it is lower promotion reinforcing bar 9 released respectively from crossbeam 2, by crossbeam 2 respectively at
First shear wall 1 and the second shear wall 8 are attached, and make the first fixed steel bars 13 and the second fixed steel bars 14 respectively around shaft
15 turn to angle parallel to each other, crossbeam 2 is engaged respectively at the first shear wall 1 with the second shear wall 8.
While there has been shown and described that the embodiment of the utility model, for the ordinary skill in the art,
It is appreciated that these embodiments can be carried out with a variety of changes in the case where not departing from the principle of the utility model and spirit, repaiied
Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.
Claims (4)
1. the assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used, including crossbeam(2), it is characterised in that:Institute
State crossbeam(2)One end be provided with the first shear wall(1), the crossbeam(2)The other end be provided with the second shear wall(8), institute
State the first shear wall(1)With crossbeam(2)Between be provided with shaft(15), the shaft(15)Away from crossbeam(2)One end connection
There are the second fixed steel bars(14)With the first fixed steel bars(13), second fixed steel bars(14)Positioned at the first fixed steel bars(13)
Side, the crossbeam(2)Top be provided with plug hole(16), and crossbeam(2)Side be provided with pushing block(5)Pushed away with
Block(6), the lower pushing block(6)Positioned at upper pushing block(5)Side, and lower pushing block(6)With upper pushing block(5)Between be provided with middle pushing block
(11), the upper pushing block(5)Side be provided with promotion reinforcing bar(4), the upper promotion reinforcing bar(4)With crossbeam(2)Between set
It is equipped with shifting chute(3), the middle pushing block(11)Side be provided with middle promotion reinforcing bar(12), the middle promotion reinforcing bar(12)With
Crossbeam(2)Between be provided with middle shifting chute(10), the lower pushing block(6)Side be provided with lower promotion reinforcing bar(9), pushed away under described
Dynamic reinforcing bar(9)With crossbeam(2)Between be provided with lower shifting chute(7), first shear wall(1)With the second shear wall(8)It is upper equal
It is provided with and upper promotion reinforcing bar(4), lower promotion reinforcing bar(9)With middle promotion reinforcing bar(12)Corresponding link slot.
2. the assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used according to claim 1, its feature
It is:The plug hole(16)Three, and three plug holes are provided with altogether(16)Positioned at crossbeam(2)Top.
3. the assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used according to claim 1, its feature
It is:The shaft(15)Six, and six shafts are provided with altogether(15)It is separately mounted to crossbeam(2)Both sides.
4. the assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used according to claim 1, its feature
It is:First shear wall(1)Height and the second shear wall(8)It is equal.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721323436.XU CN207348217U (en) | 2017-10-16 | 2017-10-16 | The assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721323436.XU CN207348217U (en) | 2017-10-16 | 2017-10-16 | The assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207348217U true CN207348217U (en) | 2018-05-11 |
Family
ID=62358309
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721323436.XU Expired - Fee Related CN207348217U (en) | 2017-10-16 | 2017-10-16 | The assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207348217U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112227562A (en) * | 2020-10-23 | 2021-01-15 | 温州大学瓯江学院 | Assembled building anti-seismic wall |
-
2017
- 2017-10-16 CN CN201721323436.XU patent/CN207348217U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112227562A (en) * | 2020-10-23 | 2021-01-15 | 温州大学瓯江学院 | Assembled building anti-seismic wall |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109868898B (en) | A kind of assembled Self-resetting node | |
CN204849571U (en) | Prefabricated assembly pier of posttension prestressing force tongue -and -groove plug -in type | |
CN203808292U (en) | Assembly type gridded shear wall structure system | |
CN109295994B (en) | Full-assembly type wind power tower cylinder foundation with combined structure | |
CN104695979B (en) | A kind of method using tall and big chassis whole lateral moving high and big die plate | |
CN201609922U (en) | Pull type prefabricated small box girder iron core | |
CN207348217U (en) | The assembled connection structure of assembly concrete frame-shear structure Shear-wall Connecting Beam Used | |
CN203603261U (en) | Connecting structure for balcony slab and superposed beam | |
CN103866866B (en) | Super High Core Walls Structure and housing water node after setting a roof beam in place | |
CN108756038A (en) | Assembly concrete shear wall and floor support plate rigid connection node and construction method | |
CN206829463U (en) | A kind of light steel insulation lightweight concrete floor construction | |
CN207660094U (en) | A kind of Quick assembling structure of house foundation | |
CN2905894Y (en) | Concrete prefabricated groove | |
CN109555268A (en) | Prefabricated support column and its construction method based on H profile steel | |
CN206267169U (en) | A kind of split blade type prestressing force anchor slab | |
CN103541435B (en) | With the cross node of full assembling of steel plate concrete Cantilever Beams | |
CN108755949A (en) | Assembly concrete girder and time beam connecting node and construction method | |
CN205530324U (en) | Miniature stake of thin -walled cold -formed steel | |
CN204401829U (en) | RPC compound shear wall is filled out in a kind of encased steel plate | |
CN209369026U (en) | Assembly concrete beam column dry type connector | |
CN204282193U (en) | A kind of steel-concrete combination beam | |
CN203428805U (en) | Combined tower crane base | |
CN207484827U (en) | A kind of efficiently measuring body roof truss beam precast concrete | |
CN103541434B (en) | The complete cross Combined concrete node of assembled | |
CN208899639U (en) | Assembly concrete girder and time beam connecting node |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180511 Termination date: 20201016 |