CN207339216U - A kind of power cable comb laying structure - Google Patents

A kind of power cable comb laying structure Download PDF

Info

Publication number
CN207339216U
CN207339216U CN201721391475.3U CN201721391475U CN207339216U CN 207339216 U CN207339216 U CN 207339216U CN 201721391475 U CN201721391475 U CN 201721391475U CN 207339216 U CN207339216 U CN 207339216U
Authority
CN
China
Prior art keywords
cable
laying structure
concrete layer
heat dissipation
power cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721391475.3U
Other languages
Chinese (zh)
Inventor
刘旭
姜帅
黎金毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Zhihua Construction Project Co Ltd
Original Assignee
Guizhou Zhihua Construction Project Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Zhihua Construction Project Co Ltd filed Critical Guizhou Zhihua Construction Project Co Ltd
Priority to CN201721391475.3U priority Critical patent/CN207339216U/en
Application granted granted Critical
Publication of CN207339216U publication Critical patent/CN207339216U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Laying Of Electric Cables Or Lines Outside (AREA)

Abstract

It the utility model is related to technical field of civil engineering, disclose a kind of power cable comb laying structure, including cable tubing, pipe pillow, blinding layer, heat dissipation duct, ground wire, earthing pole and concrete layer, blinding layer is arranged on comb laying structure bottom, cable tubing is set in pipe pillow and is positioned over above blinding layer, ground wire is laid along cable tubing bottom, earthing pole is welded to connect with ground wire, pipe pillow periphery concrete layer encapsulating is tamped, and some heat dissipation ducts are set inside the left and right sides of concrete layer.A kind of power cable comb laying structure provided by the utility model; by setting some heat dissipation ducts inside the left and right sides of concrete layer; improve the heat dissipation performance of concrete layer; current-carrying capacity of cable is improved, and sets heat dissipation duct not weaken protective effect of the concrete layer to pipeline inside the left and right sides.

Description

A kind of power cable comb laying structure
Technical field
Technical field of civil engineering is the utility model is related to, particularly a kind of power cable comb laying structure.
Background technology
Continuous with national urbanization process promotes, and the development in city is getting faster, also more next for the demand of electricity consumption It is higher, therefore, it is necessary to strengthen the construction of urban electric power power grid.The system of laying of power cable has a variety of, can be divided into direct burial, tunnel Road formula, cable duct type, calandria, vertical shaft type, bridge, water-bed laying etc..Wherein cable duct bank laying is that cable laying exists A kind of system of laying of the pre-plugged in the pipe of underground.Intersect commonly used in buried cable with highway, railway, buried cable Pass through the more crowded locations such as house, square, frequent, the industrial and mining enterprises' subterranean corridor of traffic.Compared to other system of laying, comb System of laying has the advantages that to be not easy by environmental damage, space is small, safety and stability, can effectively insect-pest, moisture-proof.It is but same When, for cable duct bank system of laying there is also the shortcomings that poor radiation, this directly results in the current-carrying capacity of cable in the case of multiloop Decline.
The content of the invention
The purpose of this utility model is to provide a kind of power cable comb laying structure, by improving comb laying knot Structure, sets heat dissipation duct inside the left and right sides of concrete layer, improves the heat dissipation performance of concrete layer, improves cable load Flow.
To realize above-mentioned technical purpose and the technique effect, the utility model discloses a kind of power cable comb Laying structure, including cable tubing, pipe pillow, blinding layer, heat dissipation duct, ground wire, earthing pole and concrete layer, the basis Bed course is arranged on comb laying structure bottom, and the cable tubing is set in the pipe pillow and is positioned over above blinding layer, The ground wire is laid along cable tubing bottom, and the earthing pole is welded to connect with ground wire, and the pipe rests the head on periphery concrete Layer encapsulating is tamped, and some heat dissipation ducts are set inside the left and right sides of the concrete layer.
Further, the cable tubing is single-wall corrugated pipe, thickness of pipe wall 5mm.
Further, the internal diameter in the heat dissipation duct is not more than the 1/4 of cable pipe internal diameter.
Further, back fill course is also set up at the top of the concrete layer, the thickness pavement of backfill is not less than 0.6m, driveway are not less than 0.7m.
Further, the ground wire uses 50x5 zinc-coated flat steel sheets.
Further, the earthing pole uses L50x5 Zinc-coated angle steels, length 1.5m.
The utility model has the advantages that:
A kind of power cable comb laying structure provided by the utility model, by inside the left and right sides of concrete layer Some heat dissipation ducts are set, the heat dissipation performance of concrete layer is improved, improves current-carrying capacity of cable, and inside the left and right sides Heat dissipation duct is set not weaken protective effect of the concrete layer to pipeline.Since cable pipeline needs to bear overburden layer and the external world Additional loading, therefore should avoid setting heat dissipation duct inside both sides above and below concrete layer, in order to avoid influence cable pipeline load-bearing.Together When, a kind of power cable comb laying structure provided by the utility model, by setting blinding layer, can prevent cable tubing It is subjected to displacement and stress raisers phenomenon occurs, and sets pipe to rest the head on to fix tube layer and branch by longitudinally spaced appropriate spacing Support.
Brief description of the drawings
Fig. 1 is the structure diagram of existing the utility model.
Critical piece symbol description:
1:Cable tubing, 2:Pipe is rested the head on, and 3:Blinding layer, 4:Heat dissipation duct, 5:Ground wire, 6:Earthing pole, 7:Concrete layer, 8:Back fill course.
Embodiment
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and implementation Example, is further elaborated the utility model.
It is a kind of power cable comb laying structure as shown in Figure 1, including cable tubing 1, pipe pillow 2, blinding layer 3, dissipates Hot hole road 4, ground wire 5, earthing pole 6 and concrete layer 7.Blinding layer 3 is arranged on comb laying structure bottom.Cable tube is route In overburden layer to be born and extraneous additional loading, it is therefore desirable to carry out based process to comb laying structure bottom, pass through setting Blinding layer, can prevent that cable tubing is subjected to displacement and stress raisers phenomenon occurs.Cable tubing 1 is set in the pipe In pillow 2 and it is positioned over above blinding layer 3.Set in the present embodiment using eight cable tubing, bilayer, four every layer Stacked arrangement mode arranged side by side, in order to fix tube layer and support, longitudinally spaced appropriate spacing sets pipe to rest the head on.Pipe pillow spacing according to Above pipeline earthing layer thickness and road surface bogie by when comprehensive load set.Ground wire 5 is applied along 1 bottom of cable tubing If earthing pole 65 is welded to connect with ground wire, it is desirable to which all ironwares are connected with ground wire in pipeline, the Ω of ground connection internal resistance R≤10. Pipe is rested the head on the encapsulating of 2 periphery concrete layers 7 and is tamped, and can effectively prevent external world, and can be effectively moisture-proof, and increase cable uses Service life.Some heat dissipation ducts 4 are set inside the left and right sides of concrete layer 7, the heat dissipation performance of concrete layer is improved, improves electricity Cable current-carrying capacity, and set heat dissipation duct not weaken protective effect of the concrete layer to pipeline inside the left and right sides.Due to Cable pipeline needs to bear overburden layer and extraneous additional loading, therefore should avoid setting heat dissipation inside both sides above and below concrete layer Duct, in order to avoid influence cable pipeline load-bearing.
Cable tubing 1 is single-wall corrugated pipe, thickness of pipe wall 5mm.Joint should be strictly aligned, and be covered with glue, prevent water Permeate in inlet pipe.
The internal diameter in heat dissipation duct 4 is not more than the 1/4 of 1 internal diameter of cable tubing, and heat dissipation duct within this range can play While heat dissipation effect, the compressive resistance of concrete layer is not destroyed.
The top of concrete layer 7 also sets up back fill course 8, and the thickness pavement of backfill is not less than 0.6m, and driveway is not small In 0.7m.
Ground wire 5 uses 50x5 zinc-coated flat steel sheets.
Earthing pole 6 uses L50x5 Zinc-coated angle steels, length 1.5m.
The above, is only the preferable embodiment of the utility model, but the scope of protection of the utility model is not This is confined to, any one skilled in the art can readily occur in the technical scope that the utility model discloses Change or replacement, should be covered within the scope of the utility model.

Claims (6)

  1. A kind of 1. power cable comb laying structure, it is characterised in that including cable tubing, pipe pillow, blinding layer, heat dissipation duct, Ground wire, earthing pole and concrete layer, the blinding layer are arranged on comb laying structure bottom, and the cable tubing is set in In the pipe pillow and it is positioned over above blinding layer, the ground wire is laid along cable tubing bottom, the earthing pole and ground connection Wire bonding connects, and the pipe pillow periphery concrete layer encapsulating is tamped, and is set inside the left and right sides of the concrete layer some Heat dissipation duct.
  2. A kind of 2. power cable comb laying structure as claimed in claim 1, it is characterised in that:The cable tubing is single Wall bellows, thickness of pipe wall 5mm.
  3. A kind of 3. power cable comb laying structure as claimed in claim 2, it is characterised in that:The interior of duct that radiate Footpath is not more than the 1/4 of cable pipe internal diameter.
  4. A kind of 4. power cable comb laying structure as claimed in claim 1, it is characterised in that:At the top of the concrete layer Back fill course is also set up, the thickness pavement of backfill is not less than 0.6m, and driveway is not less than 0.7m.
  5. A kind of 5. power cable comb laying structure as claimed in claim 1, it is characterised in that:The ground wire uses 50x5 zinc-coated flat steel sheets.
  6. A kind of 6. power cable comb laying structure as claimed in claim 1, it is characterised in that:The earthing pole uses L50x5 Zinc-coated angle steels, length 1.5m.
CN201721391475.3U 2017-10-26 2017-10-26 A kind of power cable comb laying structure Expired - Fee Related CN207339216U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721391475.3U CN207339216U (en) 2017-10-26 2017-10-26 A kind of power cable comb laying structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721391475.3U CN207339216U (en) 2017-10-26 2017-10-26 A kind of power cable comb laying structure

Publications (1)

Publication Number Publication Date
CN207339216U true CN207339216U (en) 2018-05-08

Family

ID=62362740

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721391475.3U Expired - Fee Related CN207339216U (en) 2017-10-26 2017-10-26 A kind of power cable comb laying structure

Country Status (1)

Country Link
CN (1) CN207339216U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111817199A (en) * 2020-06-23 2020-10-23 中国五冶集团有限公司 Construction method for changing electric U-shaped groove into calandria
CN111984909A (en) * 2020-08-11 2020-11-24 合肥电力规划设计院 Method for rapidly calculating civil engineering quantity in power distribution network cable engineering

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111817199A (en) * 2020-06-23 2020-10-23 中国五冶集团有限公司 Construction method for changing electric U-shaped groove into calandria
CN111984909A (en) * 2020-08-11 2020-11-24 合肥电力规划设计院 Method for rapidly calculating civil engineering quantity in power distribution network cable engineering

Similar Documents

Publication Publication Date Title
CN203702166U (en) Segment lining ring structure applicable to rectangular tunnel
CN103557014B (en) A kind of tunnel segment structure and its assembling method suitable for Rectangular Tunnel
CN207339216U (en) A kind of power cable comb laying structure
CN201599040U (en) Prefabricated segments for shield tunneling
CN104514218A (en) Energy pile and system thereof
CN106558862A (en) Assembled cable duct bank mounting structure
CN202678908U (en) High-toughness power cable protection tube
CN102704388A (en) Anti-seismic and anti-flood semi-integral abutment seamless bridge and construction method thereof
CN202194159U (en) Square pipe gallery bracket and square pipe gallery
CN201696055U (en) Multi-span flat arch tunnel structure
CN211571784U (en) Assembled underground pipe gallery
CN209293067U (en) Integrated pipe shelter bridge structure
CN206099263U (en) Assembled cable duct bank mounting structure
CN206635812U (en) A kind of U-shaped Combined type concrete prefabricated box culvert
CN204266666U (en) A kind of street lamp
CN211948676U (en) Major diameter municipal administration steel pipe underground installation structure
CN204886076U (en) Simple and easy indoor cable tray
CN204435209U (en) A kind of semi-rigid joint Integral Abutment Bridge of concrete pile supporting
CN204570718U (en) A kind of raft foundation with fluid pipeline path
CN207775648U (en) A kind of precast concrete block road
CN113629647A (en) Large-span ultrahigh-voltage power pipe trench suspension device and method in subway station foundation pit
CN207646606U (en) A kind of bridge cable protective device for municipal science of bridge building
CN203184551U (en) Steel wire woven mesh
CN207047681U (en) Bridge assembly
CN105088916A (en) Road pipeline crossing node protection structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Liu Xu

Inventor after: Jiang Shuai

Inventor after: Li Jinyi

Inventor after: Liu Lingyun

Inventor after: Zhou Daoqing

Inventor after: Lu Guirong

Inventor after: Zhang Fei

Inventor after: Gong Zhipeng

Inventor before: Liu Xu

Inventor before: Jiang Shuai

Inventor before: Li Jinyi

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180508

Termination date: 20201026