CN207312847U - A kind of intelligent junction elevator - Google Patents
A kind of intelligent junction elevator Download PDFInfo
- Publication number
- CN207312847U CN207312847U CN201720828067.3U CN201720828067U CN207312847U CN 207312847 U CN207312847 U CN 207312847U CN 201720828067 U CN201720828067 U CN 201720828067U CN 207312847 U CN207312847 U CN 207312847U
- Authority
- CN
- China
- Prior art keywords
- elevator
- nacelle
- pressure sensor
- weight
- floor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Indicating And Signalling Devices For Elevators (AREA)
- Elevator Control (AREA)
Abstract
The utility model proposes a kind of intelligent junction elevator, including Hou Cang areas, nacelle, data acquisition device, intelligent scheduling device and elevator control gear, the Hou Cang areas include state of elevator display screen, uplink and downlink button and first pressure sensor;The nacelle includes confluence display screen, function button device, left side access door, right side access door and second pressure sensor.The weight of passenger in weight and nacelle of the utility model by gathering each landing elevator Hou Cang areas Waiting Passengers, the passenger in more idle nacelle is convergeed into a nacelle when needed, the carrying capacity of nacelle is made full use of, improves elevator utilization rate, while shorten overall latency.
Description
Technical field
The utility model belongs to elevator technology field, and in particular to a kind of intelligent junction elevator.
Background technology
Actual descending stair number after existing elevator does not account for the actual number of people boarding in each hall of elevator and arrives at a station, no
By whether can also be manned in lift car, if the state of full-load run can be reached, as long as calling out ladder instruction in hall simultaneously
And meeting the principle that elevator is forward run, elevator can all respond, and result in elevator and repeatedly stop even invalid stop hall
Phenomenon, causes the increase of elevator number of run and the extension of stand-by period, especially when floor is excessive, passenger waiting time
Can be very long.
Utility model content
In view of the deficiencies of the prior art, low in order to solve elevator utilization rate, passenger waiting time is long for the utility model
Technical problem, there is provided a kind of intelligent junction elevator.
Scheme provided by the utility model is as follows:
A kind of intelligent junction elevator, it is characterised in that including Hou Cang areas, nacelle, data acquisition device, intelligent scheduling device
And elevator control gear, the Hou Cang areas include state of elevator display screen, uplink and downlink button and first pressure sensor;The cabin
Body includes confluence display screen, function button device, left side access door, right side access door and second pressure sensor.
Further, the state of elevator display screen is used for the floor that indicating elevator is reached;
The first pressure sensor is located at the subsurface in front of gate, for gathering the first pressure sensor place
The weight of floor Waiting Passengers.
Further, the confluence display screen, indicating elevator enabling direction;
The function button device, realize floor selection and it is functionally selected;
The left side access door or the right side access door are opened under the control of elevator control gear when needing confluence,
To realize that passenger is converged;
The second pressure sensor is located at nacelle bottom, for gathering the weight of passenger in the nacelle.
Further, the data-signal of the data acquisition device collection from the Hou Cang areas and the nacelle, including
The signal from the uplink and downlink button is obtained, to obtain the elevator use demand from each floor, obtains and comes from described first
The signal of pressure sensor obtains the letter from multiple second pressure sensors to obtain the weight of each floor Waiting Passengers
Number to respectively obtain the weight of passenger in each nacelle.
Further, each item data that the intelligent scheduling device gets collection analyzes and processes, by elevator tune
Signal output is spent to the elevator control gear;The elevator control gear receives the elevator dispatching letter from intelligent scheduling device
Number, control the operation up and down of the switch and elevator of each door of elevator.
The weight of passenger in weight and nacelle of the utility model by gathering each landing elevator Hou Cang areas Waiting Passengers,
The passenger in more idle nacelle is convergeed into a nacelle when needed, the carrying capacity of nacelle is made full use of, improves electricity
Terraced utilization rate, while passenger's overall latency is shortened, the energy of elevator operation consumption is reduced, while reduce elevator parts
Abrasion, improve the service life of elevator.
Brief description of the drawings
The utility model is described in further detail below according to attached drawing.
Fig. 1 is intelligent junction elevator structure schematic diagram;
Fig. 2 is intelligent junction elevator dispatching flow chart.
Embodiment
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and implementation
Example, is further elaborated the utility model.It should be appreciated that specific embodiment described herein is only explaining this
Utility model, is not used to limit the utility model.
As shown in Figure 1, the utility model provides a kind of intelligent junction elevator, including Hou Cang areas, nacelle, data acquisition dress
Put, intelligent scheduling device and elevator control gear.The Hou Cang areas include state of elevator display screen, are reached for indicating elevator
Floor, uplink and downlink button, and in front of the gate subsurface first pressure sensor, for gathering the first pressure
The weight of floor Waiting Passengers where sensor;The nacelle includes confluence display screen, for indicating elevator enabling direction;Function
PBU pushbutton unit, be used for realization floor selection and it is functionally selected;Left side access door and right side access door, when needing confluence in electricity
The left side access door or the right side access door are opened under the control of terraced control device, to realize that passenger is converged;And it is located at
The second pressure sensor of nacelle bottom, for gathering the weight of passenger in the nacelle.
Further, the data-signal of the data acquisition device collection from the Hou Cang areas and the nacelle, including
The signal from the uplink and downlink button is obtained, to obtain the elevator use demand from each floor, obtains and comes from described first
The signal of pressure sensor obtains the letter from multiple second pressure sensors to obtain the weight of each floor Waiting Passengers
Number to respectively obtain the weight of passenger in each nacelle.
Further, each item data that the intelligent scheduling device gets collection analyzes and processes, by elevator tune
Signal output is spent to the elevator control gear;The elevator control gear receives the elevator dispatching letter from intelligent scheduling device
Number, control the operation up and down of the switch and elevator of each door of elevator.
As shown in Fig. 2, the scheduling process of intelligent junction elevator is as follows:
S1. all status datas of elevator, including passenger weight in place floor En.floor and cabin are read
En.weight;
S2. read in per floor waiting Passengen weight F.weight;
S3. judge whether to nacelle to converge, if desired converge, be transferred to step S5, otherwise all elevators press former scheme after
Reforwarding row, is transferred to step S6;
S4. carrying demand F.weiht++ on the way is responded;
S5. nacelle is converged;
S6. carrying demand F.weiht++ on the way is responded;
S7. end point layer is run to, terminates this scheduling.
Further, step S3 specifically includes:
S3.1 judges that certain two or more elevator travels direction is consistent, and is separated by number of floor levels and is less than first predetermined value
θ, | E.floorMax-E.floorMin |<θ, if then going to step S3.3, otherwise goes to step S3.2;
All elevators of S3.2 are continued to run with by former scheme, are transferred to step S8;
S3.3 judges whether previous step cabin inner capacities is much smaller than load En.weight<<E.max, if then continuing, otherwise
Go to step S3.2;
Wherein, E.floorMax is highest goal floor, and E.floorMin is minimum destination, and E.max is nacelle lotus
Loading capacity.
Further, step S6 specifically includes:
S5.1 obtains the number sequence for respectively converging nacelle;
S5.2 control nacelles open suitable access door, which nacelle confluence display screen instruction passenger should go to continue to multiply
Sit elevator, with make one few one or more nacelle A in passenger be transferred to the more nacelle B of counterpart;
S5.3 judges E.upLm for nacelle A>E.downm, it is then nacelle upstream request starting point layer to be, is otherwise nacelle
Downbound request starting point layer, goes to step S6;Manned nacelle B judges whether the E.weight that overloads by running in the original plan>E.max, if
It is to go to S7, otherwise goes to step S6;
Wherein, E.upLm is request quality summation upwards, and E.downm is down-call quality summation.
Three elevators E1, E2, E3 are suppose there is, E1 uplinks, E2, E3 downlink, converge elevator passenger after scheduled, then through meter
Calculate and understand, the utility model can shorten overall latency, and elevator utilization rate is got a promotion:
In formula, floor.max is maximum number of floor levels;
E3.floor the initial floor where E3 elevators;
E3.n.m it is owner's stand-by period summation in E3 elevator cabin bodies;
TnFor the stand-by period summation in n-layer crowd;
E2.floor the floor where E2 elevators;
E2.n.m it is owner's stand-by period summation in E2 elevator cabin bodies;
TeFor normal operation when by first floor time;
T is the stand-by period before improvement;
N for elevator this time run institute into mistake number of floor levels;
M is the equal weight of people.
Above-described embodiment, the purpose of this utility model, technical solution and beneficial effect have been carried out into
One step describes in detail, it should be understood that the foregoing is merely specific embodiment of the present utility model, is not used to limit
The utility model processed, where within the spirit and principles of the present invention, any modification, equivalent substitution, improvement and etc. done,
It should be included within the scope of protection of this utility model.
Claims (5)
- A kind of 1. intelligent junction elevator, it is characterised in that including Hou Cang areas, nacelle, data acquisition device, intelligent scheduling device and Elevator control gear, the Hou Cang areas include state of elevator display screen, uplink and downlink button and first pressure sensor;The nacelle Including confluence display screen, function button device, left side access door, right side access door and second pressure sensor.
- 2. a kind of intelligent junction elevator according to claim 1, it is characterised in that the state of elevator display screen is used to refer to Show the floor that elevator is reached;The first pressure sensor is located at the subsurface in front of gate, for gathering first pressure The weight of floor Waiting Passengers where force snesor.
- A kind of 3. intelligent junction elevator according to claim 1, it is characterised in thatThe confluence display screen, indicating elevator enabling direction;The function button device, realize floor selection and it is functionally selected;The left side access door or the right side access door are opened under the control of elevator control gear when needing confluence, with reality Existing passenger's confluence;The second pressure sensor is located at nacelle bottom, for gathering the weight of passenger in the nacelle.
- 4. a kind of intelligent junction elevator according to claim 1, it is characterised in that the data acquisition device collection comes from The Hou Cang areas and the data-signal of the nacelle, including the signal from the uplink and downlink button is obtained, to obtain from each The elevator use demand of floor, obtains the signal from the first pressure sensor to obtain the weight of each floor Waiting Passengers Amount, obtains the signal from multiple second pressure sensors to respectively obtain the weight of passenger in each nacelle.
- 5. a kind of intelligent junction elevator according to claim 1, it is characterised in that the intelligent scheduling device obtains collection Each item data got is analyzed and processed, by elevator dispatching signal output to the elevator control gear;The elevator controlling Device receives the elevator dispatching signal from intelligent scheduling device, controls the operation up and down of the switch and elevator of each door of elevator.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720828067.3U CN207312847U (en) | 2017-07-10 | 2017-07-10 | A kind of intelligent junction elevator |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720828067.3U CN207312847U (en) | 2017-07-10 | 2017-07-10 | A kind of intelligent junction elevator |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207312847U true CN207312847U (en) | 2018-05-04 |
Family
ID=62433504
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720828067.3U Expired - Fee Related CN207312847U (en) | 2017-07-10 | 2017-07-10 | A kind of intelligent junction elevator |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207312847U (en) |
-
2017
- 2017-07-10 CN CN201720828067.3U patent/CN207312847U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106586738B (en) | A kind of elevator with multiple compartments dispatching method of view-based access control model detection | |
CN105722780B (en) | destination control system | |
CN105967011B (en) | Elevator calling signal input apparatus, call system of elevator and its multiple lift control system | |
CN102765641B (en) | Elevator control system and control method thereof | |
CN110155827B (en) | Intelligent control system of group elevator | |
CN106006242A (en) | Building elevator scheduling control system | |
CN108249236A (en) | The method, apparatus and computer readable storage medium of Intelligent controlled elevator | |
CN106976766A (en) | Elevator sends method and device with charge free | |
CN107176510A (en) | Multiple lift control system and group control method | |
CN107098229A (en) | A kind of stop priority dispatching method based on elevator outer calling system | |
CN104724557A (en) | Elevator load carrying judgment system and method thereof | |
CN102674095A (en) | Energy-saving dispatching control method of elevator for passenger detection based on binocular vision | |
CN107176507B (en) | Intelligent confluence elevator and scheduling optimization method thereof | |
CN106241524B (en) | A kind of office building elevator regulating system | |
CN108408514A (en) | A kind of multi-connected machine team control type elevator scheduling method | |
CN207312847U (en) | A kind of intelligent junction elevator | |
CN207645554U (en) | Elevator multiple control device and multiple lift control system | |
CN103261070B (en) | Energy efficient elevator installation | |
CN109368425B (en) | Space three-dimensional interactive elevator calling system based on mobile terminal and working method | |
CN205274907U (en) | Automatic device of cancelling of elevator car mistake instruction | |
CN104150297B (en) | The control method of the control system of the many elevator devices of high-rise building | |
CN110422717B (en) | Intelligent elevator control method based on image acquisition | |
CN106006254A (en) | Building elevator stop control system | |
CN106379781B (en) | Call terraced method and system together | |
CN102040146A (en) | Method for preventing elevator from idling |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180504 Termination date: 20190710 |
|
CF01 | Termination of patent right due to non-payment of annual fee |