CN207296862U - A kind of house hydropower installation folding device - Google Patents

A kind of house hydropower installation folding device Download PDF

Info

Publication number
CN207296862U
CN207296862U CN201721243593.XU CN201721243593U CN207296862U CN 207296862 U CN207296862 U CN 207296862U CN 201721243593 U CN201721243593 U CN 201721243593U CN 207296862 U CN207296862 U CN 207296862U
Authority
CN
China
Prior art keywords
folding device
main body
folding
device main
welded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721243593.XU
Other languages
Chinese (zh)
Inventor
路壮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Minle County State Installation LLC
Original Assignee
Minle County State Installation LLC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Minle County State Installation LLC filed Critical Minle County State Installation LLC
Priority to CN201721243593.XU priority Critical patent/CN207296862U/en
Application granted granted Critical
Publication of CN207296862U publication Critical patent/CN207296862U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Handcart (AREA)

Abstract

The utility model discloses a kind of house hydropower installation folding device, including folding device main body and support baseboard, vertical chute is installed on the left of the folding device main body, the side of the folding device main body away from vertical chute is welded with the left vertical bar of folding ladder, side away from the left vertical bar of folding ladder on the right side of the folding device main body is welded with the right vertical bar of folding ladder, some cross bars are installed between the left vertical bar of the folding ladder and the right vertical bar of folding ladder, the folding device body top is provided with socket, hinge is installed on the left of the folding device body surfaces, the side of the folding device body surfaces away from hinge is welded with control handle, side of the support baseboard away from folding device main body is provided with universal wheel.The house hydropower installation folding device, ensure that by components such as the left and right vertical bar of folding ladder, folding device main body and its internal batteries and house water power is installed, the use of person easy to operation.

Description

A kind of house hydropower installation folding device
Technical field
The utility model belongs to hydroelectric facility auxiliary device technical field, and in particular to a kind of house hydropower installation folds dress Put.
Background technology
It is exactly first the family of oneself to be fitted up first in living in house, wherein critically important one is exactly to occupying Family's water power is installed, must not in the thing that house hydropower installation carries out before being fine fitment indoors, and whole fitment process The link that can lack.If there is mistake in whole link, very big trouble will be brought to later finishing work.Water The finishing of this electric block is the most important thing, hydropower installation Exact Design scheme complete be finishing go into operation the primary condition that must possess it One.There is no detailed hydropower installation cabling scheme hastily to go into operation often blindness, while perturbed on one side carrying out Hydroelectric Project Construction It is uneasy to spend measured step back and forth which place is kept in mind and do something, as a result arrived just found when finishing finishes use it is ready-made Thing is not used, and the thing also much wanted is not done.House water power peace would generally be used in Hydroelectric Project Construction is carried out at the same time Fill folding device.
At present house hydropower installation folding device on the market be there are problems that, can not be moved freely, can be carried out Hydropower installation operation less and can not install eminence water power, be unfavorable for the use of operator, for it is above-mentioned the problem of, I A kind of be badly in need of house hydropower installation folding device to solve to move freely, can carry out hydropower installation operation less and nothing The problem of method installs eminence water power, the use of person easy to operation.
Utility model content
The purpose of this utility model is to provide a kind of house hydropower installation folding device, to solve in above-mentioned background technology The problem of proposition.
To achieve the above object, the utility model provides following technical solution:A kind of house hydropower installation folding device, bag Folding device main body and support baseboard are included, vertical chute, the folding device main body are installed on the left of the folding device main body Side away from vertical chute is welded with the left vertical bar of folding ladder, and the folding device main body right side is away from the left vertical bar of folding ladder Side be welded with the right vertical bar of folding ladder, some horizontal strokes are installed between the left vertical bar of the folding ladder and the right vertical bar of folding ladder Bar, the folding device body top are provided with socket, hinge, the folding are provided with the left of the folding device body surfaces Side of the stacking device body surfaces away from hinge is welded with control handle, side of the support baseboard away from folding device main body Universal wheel is installed.
Preferably, the folding device body interior bottom is provided with tool shelving rack one, on the tool shelving rack one Portion is provided with tool shelving rack two, and insulated column, the work are welded with inside the tool shelving rack one and tool shelving rack two Support isolation board two is welded between tool storage rack one and tool shelving rack two, two upper weld of tool shelving rack has support Isolation board one, one top of the support isolation board are provided with storage battery.
Preferably, left-handed shaft is installed in the middle part of the left vertical bar of the folding ladder, is pacified in the middle part of the right vertical bar of folding ladder Equipped with dextral shaft, the support baseboard upper right is provided with fixed Ingathering board.
Preferably, side of the vertical chute away from folding device main body is welded with connecting rod, the connecting rod lower part installation There is shaft, side of the connecting rod away from vertical chute is welded with clamp port.
Preferably, Three-hole socket is installed on the left of the socket plate surface, the socket plate surface is away from Three-hole socket Side is provided with Double-hole socket.
Preferably, universal wheel connecting rod is installed, the universal wheel connecting rod is right between the universal wheel and support baseboard Side is provided with brake fixed link.
The technique effect and advantage of the utility model:The house hydropower installation folding device, by installed in folding device The left vertical bar of folding ladder, the right vertical bar of folding ladder and cross bar on the right side of main body ensure that the installation to eminence house water power, described Left-handed shaft, dextral shaft and fixed Ingathering board ensure that the folding storage to folding ladder, ensure that by clamp port to water power The clamping of instrument in installation process, ensure that by shaft, connecting rod and vertical chute and clamp port is folded and ensure that Clamp port can be moved freely up and down, by hinge and control handle ensure that maintenance to folding device body interior component and Replace, the electricity to the instrument of electricity consumption during hydropower installation ensure that by storage battery, socket, Double-hole socket and Three-hole socket Power is supplied, by supporting isolation board one and supporting isolation board two to ensure that the isolation to folding device body interior component supports, Storage to hydropower installation instrument ensure that by tool shelving rack one and tool shelving rack two, ensure that by insulated column to work Isolation during tool storage, ensure that folding device can move freely by universal wheel, universal wheel connecting rod and brake fixed link, The house hydropower installation folding device, passes through the components such as the left and right vertical bar of folding ladder, folding device main body and its internal battery It ensure that and house water power is installed, the use of person easy to operation.
Brief description of the drawings
Fig. 1 is the dimensional structure diagram of the utility model;
Fig. 2 is the internal structure schematic diagram of the utility model.
In figure:1 folding device main body, 2 support baseboards, 3 vertical chutes, the left vertical bar of 4 folding ladders, 5 folding ladders are right vertical Bar, 6 cross bars, 7 universal wheels, 8 hinges, 9 control handles, 10 left-handed shafts, 11 dextral shafts, 12 fix Ingathering boards, 13 sockets, 14 shafts, 15 connecting rods, 16 clamp ports, 17 universal wheel connecting rods, 18 brake fixed links, 19 Double-hole sockets, 20 Three-hole sockets, 21 Support isolation board one, 22 and support isolation board two, 23 storage batteries, 24 tool shelving racks one, 25 tool shelving racks two, 26 insulated columns.
Embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are without making creative work All other embodiments obtained, shall fall within the protection scope of the present invention.
Referring to Fig. 1, Fig. 1 is the dimensional structure diagram of the utility model;A kind of house hydropower installation folding device, bag Folding device main body 1 and support baseboard 2 are included, the left side of folding device main body 1 is provided with vertical chute 3, the folding device Side of the main body 1 away from vertical chute 3 is welded with the left vertical bar 4 of folding ladder, and the right side of folding device main body 1 is away from folding ladder The side of left vertical bar 4 is welded with the right vertical bar 5 of folding ladder, between the left vertical bar 4 of the folding ladder and the right vertical bar 5 of folding ladder Some cross bars 6 are installed, the top of folding device main body 1 is provided with socket 13,1 surface of the folding device main body left side Hinge 8 is installed, side of 1 surface of folding device main body away from hinge 8 is welded with control handle 9, the support baseboard 2 Side away from folding device main body 1 is provided with universal wheel 7, and 1 inner bottom of folding device main body is provided with tool storage Frame 1, one 24 top of tool shelving rack are provided with tool shelving rack 2 25, and the tool shelving rack 1 and instrument are deposited Put and insulated column 26 is welded with inside frame 2 25, support is welded between the tool shelving rack 1 and tool shelving rack 2 25 Isolation board 2 22,2 25 upper weld of tool shelving rack have support isolation board 1, one 21 top of the support isolation board Storage battery 23 is installed, the left middle part of vertical bar 4 of folding ladder is provided with left-handed shaft 10, in the right vertical bar 5 of folding ladder Portion is provided with dextral shaft 11, and 2 upper right of support baseboard is provided with fixed Ingathering board 12, and the vertical chute 3 is remote The side of folding device main body 1 is welded with connecting rod 15, and 15 lower part of connecting rod is provided with shaft 14, and the connecting rod 15 is away from vertical The side of sliding slot 3 is welded with clamp port 16, and Three-hole socket 20,13 table of socket are provided with the left of 13 surface of socket Side of the face away from Three-hole socket 20 is provided with Double-hole socket 19, and universal wheel is provided between the universal wheel 7 and support baseboard 2 Connecting rod 17, the right side of universal wheel connecting rod 17 are provided with brake fixed link 18.
To house water power when folding ladder left vertical bar 4, the right vertical bar 5 of folding ladder and the cross bar 6 ensure that aloft Installation, the left-handed shaft 10, dextral shaft 11 and fixed Ingathering board 12 ensure that right to the left vertical bar of folding ladder 4, folding ladder The folding and storage of vertical bar 5 and cross bar 6, the hinge 8 and control handle 19 ensure that to 1 internal part of folding device main body Maintenance and replacement, the shaft 14, connecting rod 15, clamp port 16 and vertical chute 3 ensure that to instrument during hydropower installation Clamping and instrument be freely lifted, the universal wheel 7, universal wheel connecting rod 17 and brake fixed link 18 ensure that folding device It can move freely.
Referring to Fig. 2, Fig. 2 is the internal structure schematic diagram of the utility model.The socket 13, Double-hole socket 19, three Spring hole scoket 20 and storage battery 23 ensure that the supply of electric power to hydropower installation instrument, the insulated column 26, support isolation board 1 The isolation support to 1 internal part of folding device main body, one 25 He of tool shelving rack are ensure that with support isolation board 2 22 Tool shelving rack 2 26 ensure that the storage to hydropower installation instrument.
Operation principle:During using the house hydropower installation folding device, pass through the left vertical bar 4 of folding ladder, folding Installation when folded terraced right vertical bar 5 and cross bar 6 ensure that aloft to house water power, passes through left-handed shaft 10, dextral shaft 11 The folding and storage to the left vertical bar of folding ladder 4, the right vertical bar 5 of folding ladder and cross bar 6 are ensure that with fixed Ingathering board 12, at the same time Clamping to instrument during hydropower installation and instrument ensure that by shaft 14, connecting rod 15, clamp port 16 and vertical chute 3 It is freely lifted, the maintenance and replacement to 1 internal part of folding device main body ensure that by hinge 8 and control handle 19, pass through Socket 13, Double-hole socket 19, Three-hole socket 20 and storage battery 23 ensure that the supply of electric power to hydropower installation instrument, pass through work Tool storage rack 1 and tool shelving rack 2 26 ensure that the storage to hydropower installation instrument, while pass through insulated column 26, support Isolation board 1 and support isolation board 2 22 ensure that the isolation support to 1 internal part of folding device main body, pass through universal wheel 7th, universal wheel connecting rod 17 and brake fixed link 18 ensure that folding device can move freely.
Finally it should be noted that:The above descriptions are merely preferred embodiments of the present invention, is not limited to this Utility model, although the utility model is described in detail with reference to the foregoing embodiments, for those skilled in the art For, it can still modify the technical solution described in foregoing embodiments, or to which part technical characteristic Equivalent substitution is carried out, where within the spirit and principles of the present invention, any modification, equivalent replacement, improvement and so on, It should be included within the scope of protection of this utility model.

Claims (6)

1. a kind of house hydropower installation folding device, including folding device main body (1) and support baseboard (2), it is characterised in that:Institute State and vertical chute (3) is installed on the left of folding device main body (1), the one of the remote vertical chute (3) of the folding device main body (1) Side is welded with the left vertical bar of folding ladder (4), side of folding device main body (1) right side away from the left vertical bar of folding ladder (4) Be welded with the right vertical bar of folding ladder (5), the left vertical bar of folding ladder (4) and the right vertical bar of folding ladder (5) if between be provided with Dry cross bar (6), folding device main body (1) top are provided with socket (13), folding device main body (1) the surface left side Hinge (8) is installed, the side of folding device main body (1) surface away from hinge (8) is welded with control handle (9), described Side of the support baseboard (2) away from folding device main body (1) is provided with universal wheel (7).
A kind of 2. house hydropower installation folding device according to claim 1, it is characterised in that:The folding device main body (1) inner bottom is provided with tool shelving rack one (24), and described one (24) top of tool shelving rack is provided with tool shelving rack two (25), insulated column (26) is welded with inside the tool shelving rack one (24) and tool shelving rack two (25), the instrument is deposited Put and support isolation board two (22) is welded between frame one (24) and tool shelving rack two (25), on the tool shelving rack two (25) Portion is welded with support isolation board one (21), and described support isolation board one (21) top is provided with storage battery (23).
A kind of 3. house hydropower installation folding device according to claim 1, it is characterised in that:The folding ladder is left vertical Left-handed shaft (10) is installed in the middle part of bar (4), dextral shaft (11) is installed in the middle part of the right vertical bar of folding ladder (5), it is described Support baseboard (2) upper right is provided with fixed Ingathering board (12).
A kind of 4. house hydropower installation folding device according to claim 1, it is characterised in that:The vertical chute (3) Side away from folding device main body (1) is welded with connecting rod (15), and connecting rod (15) lower part is provided with shaft (14), the company Side of the bar (15) away from vertical chute (3) is welded with clamp port (16).
A kind of 5. house hydropower installation folding device according to claim 1, it is characterised in that:Socket (13) table Left side of face is provided with Three-hole socket (20), and the side of socket (13) surface away from Three-hole socket (20) is provided with diplopore and inserts Seat (19).
A kind of 6. house hydropower installation folding device according to claim 1, it is characterised in that:The universal wheel (7) and Universal wheel connecting rod (17) is installed between support baseboard (2), brake is installed on the right side of the universal wheel connecting rod (17) and is fixed Bar (18).
CN201721243593.XU 2017-09-26 2017-09-26 A kind of house hydropower installation folding device Expired - Fee Related CN207296862U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721243593.XU CN207296862U (en) 2017-09-26 2017-09-26 A kind of house hydropower installation folding device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721243593.XU CN207296862U (en) 2017-09-26 2017-09-26 A kind of house hydropower installation folding device

Publications (1)

Publication Number Publication Date
CN207296862U true CN207296862U (en) 2018-05-01

Family

ID=62439579

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721243593.XU Expired - Fee Related CN207296862U (en) 2017-09-26 2017-09-26 A kind of house hydropower installation folding device

Country Status (1)

Country Link
CN (1) CN207296862U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112405474A (en) * 2020-11-27 2021-02-26 广东电网有限责任公司 Smart power grids operation toolbox

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112405474A (en) * 2020-11-27 2021-02-26 广东电网有限责任公司 Smart power grids operation toolbox

Similar Documents

Publication Publication Date Title
CN207296862U (en) A kind of house hydropower installation folding device
CN207116967U (en) A kind of modularization distribution box
CN204838680U (en) Portable drawing frame for machine tooling
CN204349307U (en) Middle circuit breaker moves apparatus for examination and repair
CN207285324U (en) A kind of tailoring equipment cut suitable for straight line and curve
CN205493042U (en) Art design multifunctional workbench
CN209319752U (en) A kind of Moveable foldable tool rack
CN204800162U (en) Be used for circuit board welded weld holder
CN204719260U (en) A kind of operating means for optical fiber welding welding machine
CN203650468U (en) Portable working table
CN210878304U (en) Cable hook processing locater
CN205849094U (en) A kind of independent assortment cabinet
CN204392708U (en) A kind of combined cabinet
CN106695190B (en) A kind of safety-type welding machine
CN207156046U (en) A kind of making wood twig process equipment for being easy to regulation to use
CN213658943U (en) Safe grounding detection device
CN204273781U (en) Maintenance and production labor station
CN207083305U (en) A kind of electric appliance combined cabinet
CN205439797U (en) Formula fine arts drawing board is inhaled to wind
CN104473468A (en) Workbench for maintenance and production
CN215920366U (en) Workstation is used in warm logical installation of multi-use architecture
CN205882074U (en) Full -automatic battery kludge
CN216293472U (en) Locker for life management
CN207028683U (en) A kind of Multifunction fine arts drawing board
CN205125513U (en) Combined hall cabinet

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180501