CN207296416U CN201721080012.5U CN201721080012U CN207296416U CN 207296416 U CN207296416 U CN 207296416U CN 201721080012 U CN201721080012 U CN 201721080012U CN 207296416 U CN207296416 U CN 207296416U
Authority
CN
China
Prior art keywords
plank sheathing
component
nail
substrate
wedge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721080012.5U
Other languages
Chinese (zh)
Inventor
谢军龙
龙涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Jingye Construction Technology Co Ltd
Original Assignee
Guangzhou Jingye Construction Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Jingye Construction Technology Co Ltd filed Critical Guangzhou Jingye Construction Technology Co Ltd
Application granted granted Critical
Publication of CN207296416U publication Critical patent/CN207296416U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G9/00Forming or shuttering elements for general use
    • E04G9/08Forming boards or similar elements, which are collapsible, foldable, or able to be rolled up
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/02Connecting or fastening means for non-metallic forming or stiffening elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/04Connecting or fastening means for metallic forming or stiffening elements, e.g. for connecting metallic elements to non-metallic elements
    • E04G17/047Connecting or fastening means for metallic forming or stiffening elements, e.g. for connecting metallic elements to non-metallic elements simultaneously tying two facing forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G19/00Auxiliary treatment of forms, e.g. dismantling; Cleaning devices

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a kind of for Combined formwork and the connection component of plank sheathing assembly and disassembly, including first component and second component, first component includes substrate and wedge, the two sides of substrate are respectively configured as bearing surface and supporting surface, the entrance hole of connection bearing surface and supporting surface is provided with substrate, wedge is fixed on supporting surface and is provided with to be connected and the gradual increased straight slot of height with entrance hole, the opening that the slot bottom of connection entrance hole and straight slot is also provided with substrate and is passed through for second component;The annular abutment part that second component includes nail body, is fixed on the head of a nail for the tail end for following closely body and is socketed on the nail, is configured as installing zone between annular abutment part and the head of a nail, annular abutment part is used for the surface snug fit with plank sheathing, and entrance hole is passed through for the head of a nail.The utility model can realize the simple assembly and disassembly of plank sheathing and Combined formwork, and plank sheathing will not be caused to damage.

Description

For Combined formwork and the connection component of plank sheathing assembly and disassembly
Technical field
Technical field of building construction is the utility model is related to, be used for Combined formwork more particularly to one kind fills with plank sheathing The connection component torn open.
Background technology
Building template is made by design requirement as a kind of temporary supporting structure, makes concrete structure, component by regulation Position, physical dimension shaping, keep its correct position, and removed after concrete structure shaping.For example, skyscraper In work progress, usually already installed building template is removed after completing one layer and is acted in lower floor, repeatedly to follow Ring utilizes.
Because of the cuttability of plank sheathing, it can flexibly be deformed as needed when implementing work process-field, therefore, It is in traditional architecture to use plank sheathing more.And plank sheathing is although easy to make, but its overall stiffness is poor, thus, as high level is built The template such as the appearance built, Combined formwork, such as aluminum alloy mould plate or plastic formwork is applied widely.Combined formwork leads to It is often that transport to construction site is installed after factory completes processing.Although the overall stiffness and precision of Combined formwork all compare It is higher, and install simply, but the requirement for some shapes specially component is difficult to meet again.Therefore, by by combined type mould Plate is used in combination with plank sheathing, can overcome the shortcomings that respective, improves construction efficiency.
At present, when Combined formwork is combined with plank sheathing, it will usually using connection component (such as the metal of bending Plate) both are connected, and iron nail or screw etc. would generally be used to be fixed between plank sheathing and connection component.Specifically, even Connecting hole can be provided with connected components, in order to which iron nail or screw are knocked in along connecting hole and the perforate through on Combined formwork In plank sheathing, and the cap head of iron nail or screw can be stuck in the edge of connecting hole, in this way, being torn open by the plank sheathing on Combined formwork Except when, it is necessary to the iron nail clenched or screw etc. are gone out from plank sheathing.Although the setting of above-mentioned connection component can be with Plank sheathing is connected with Combined formwork, but it also make it that the dismounting of plank sheathing is difficult, and during assembling and disassembling repeatedly Plank sheathing is damaged, so as to not only influence the bonding strength between plank sheathing and Combined formwork, but also is also required to periodic replacement wood Template, improves construction cost.
Utility model content
To solve the above-mentioned problems, the utility model provides a kind of for Combined formwork and the connection group of plank sheathing assembly and disassembly Part, including:First component and the second component in spike-like structures, the first component include substrate and wedge, the substrate Two sides be respectively configured as bearing surface and supporting surface, the connection bearing surface and the supporting surface are provided with the substrate Entrance hole, the wedge is fixed on the supporting surface and is provided with to be connected and height is gradually increased logical with the entrance hole Groove, the slot bottom for connecting the entrance hole and the straight slot and the opening passed through for the second component are also provided with the substrate; The second component includes nail body, the head of a nail for being fixed on the tail end for following closely body and the annular abutment being socketed on the nail Part, is configured as installing zone between the annular abutment part and the head of a nail, the annular abutment part is used for the table with plank sheathing Face snug fit, the entrance hole are passed through for the head of a nail, and the head of a nail is used to contact with the notch of the straight slot.
Preferably, the substrate and the wedge are axially symmetric structure, the central axes of the wedge with On same straight line, the straight slot extends along the central axes of the wedge for the central axes of the substrate.
Preferably, the notch of the straight slot is string configuration.
Preferably, the surface of the wedge is arcwall face.
Preferably, the arcwall face is configured as friction portion with the position that the notch of the straight slot is connected.
Preferably, the substrate is integrally formed with the wedge.
Preferably, integrative-structure is formed by impact style between the substrate and the wedge.
Preferably, the both ends of the substrate are respectively equipped with the first hit piece and the second hit piece.
Preferably, first hit piece and second hit piece are bending plate.
Preferably, the substrate, the wedge and the bending plate are integrally formed.
Compared with prior art, the beneficial effects of the utility model are:
1st, can be followed closely when in use on plank sheathing in the second component of spike-like structures, to coordinate with first component, so that Simply and easily realize the assembly and disassembly of plank sheathing and Combined formwork, and the need not be removed during plank sheathing is assembled and disassembled repeatedly Two components, can also so avoid the damage of plank sheathing, reduce construction cost;
2nd, the annular abutment part in second component nail body hammer into after plank sheathing can with the surface snug fit of plank sheathing, one Aspect can ensure during first component is assembled and disassembled, that is, during impacting substrate, the surface force part of plank sheathing by Power is balanced, avoids damage plank sheathing;On the other hand, the installing zone formed between annular abutment part and the head of a nail, can also fill To forming position-limiting action well between plank sheathing, Combined formwork and first component during tearing open, so as to plank sheathing shape Into protection;
3rd, first component is by setting substrate and wedge, and the entrance hole that makes to be opened on wedge on substrate connects Straight slot, and the slot bottom of straight slot is to be connected by the opening on substrate with entrance hole, in this way, can be in second component opposite the When one component moves, guiding role well is played;
4th, entrance hole can for first component the head of a nail by the way that and the head of a nail of first component is for the notch with straight slot Contact, so, it is ensured that by the cooperation of first component and second component, plank sheathing can be lock onto combined type In template.
Brief description of the drawings
Fig. 1 is the top view of the first component in the utility model embodiment;
Fig. 2 is the front view of the first component in the utility model embodiment;
Fig. 3 is the structure diagram of the second component in the utility model embodiment.
Wherein, 100, first component;200th, second component;1st, substrate;11st, entrance hole;2nd, wedge;21st, straight slot;3rd, One hit piece;4th, the second hit piece;5th, body is followed closely;6th, the head of a nail;7th, annular abutment part.
Embodiment
With reference to the accompanying drawings and examples, specific embodiment of the present utility model is described in further detail.Below Embodiment is used to illustrate the utility model, but is not intended to limit the scope of the present invention.
As shown in Figure 1 to Figure 3, the preferred embodiment in the utility model is a kind of for Combined formwork and plank sheathing assembly and disassembly Connection component, including:First component 100 and the second component 200 in spike-like structures.
The first component 100 includes substrate 1 and wedge 2, and the two sides of the substrate 1 are respectively configured as bearing surface And supporting surface, the entrance hole 11 for connecting the bearing surface and the supporting surface is provided with the substrate 1, the wedge 2 is fixed In on the supporting surface and being provided with and being connected with the entrance hole 11 and the gradual increased straight slot 21 of height, also open on the substrate 1 There is the opening for connecting the entrance hole 11 and the slot bottom of the straight slot 21, which passes through for the second component 200.
The wedge 2 is thickness gradually increased block structure, can be added using metallic plate by cutting, punching press etc. The metalwork with gradient that work technique is formed.The second component 200 is affixed on plank sheathing when in use, it includes nail Body 5, the head of a nail 6 for being fixed on the tail end for following closely body 5 and the annular abutment part 7 being socketed on the nail body 5.
Screw thread can be equipped with the nail body 5 with both connections of enhancing after the nail body 5 to be hammered into the plank sheathing Intensity, takes the second component 200 out of when avoiding subsequently removing the first component 100.
Surface snug fit of the annular abutment part 7 when the nail body 5 hammers into the plank sheathing with the plank sheathing. Installing zone is configured as between the annular abutment part 7 and the head of a nail 6, and when the plank sheathing and the Combined formwork are pacified After installing, the Combined formwork is to be clamped in the installation by the plank sheathing and the head of a nail 6 with the first component 100 In area, therefore, the annular abutment part 7 can also by the first component 100 by the plank sheathing and Combined formwork With reference to during, protection is formed to the surface of the plank sheathing.
The entrance hole 11 is used to pass through for the head of a nail 6, in order to the follow-up second component 200 and first structure The connection of part 100.
Specifically, the connection component in the utility model embodiment is being combined the plank sheathing with the Combined formwork When, only the nail body 5 of the second component 200 need to be hammered into the plank sheathing, make the tail end for being fixed on the nail body 5 afterwards The head of a nail 6 sequentially pass through entrance hole 11 in perforate and the substrate 1 on Combined formwork, and finally by the importing Hole 11 is pierced by.Then the nail body 5 is set to enter the straight slot 21 along the entrance hole 11 by impacting one end of the substrate 1, Since the height of the straight slot 21 is gradually increased, and the minimum end of height corresponding to the straight slot 21 is again and institute The connection of entrance hole 11 is stated, thus when the nail body 5 is moved relative to the straight slot 21, the head of a nail 6 of nail 5 tail end of body Eventually the notch with the straight slot 21 contacts, and at this time, the head of a nail 6 is brought pressure to bear on described by the wedge 2 On substrate 1, and the plank sheathing can be lock onto on the Combined formwork by the bearing surface.
When needing to remove the plank sheathing from the Combined formwork, it is only necessary to impact the another of the substrate 1 End, makes the nail body 5 be moved relative to the wedge 2, and when the nail body 5 enters the entrance hole 11 along the straight slot 21 When, the coupling mechanism force that the bearing surface is put between the plank sheathing and the Combined formwork will disappear, at this time, you can will The second component 200 being fixed on the plank sheathing is extracted out from the entrance hole 11, so that simply and easily by the wood Template is removed from the Combined formwork, without the second component 200 being fixed on the plank sheathing is extracted, such as This, not only conveniently and efficiently realizes the assembly and disassembly operation between the plank sheathing and the Combined formwork, but also repeatedly Plank sheathing will not be damaged during assembly and disassembly, so that the connection not interfered with not only between plank sheathing and Combined formwork is strong Degree, and also reduce construction cost.
Passed through it is understood that the aperture of the perforate on the Combined formwork is enough the second component 200. And the second component 200 can be used has a higher mechanical strength, such as the material making of steel or iron etc..The opening It is enough the annular abutment part 7 and the head of a nail 6 to pass through.
In order to ensure that, in force, the substrate 1 and the wedge 2 can be exemplary with stress equalization, can be by institute State substrate 1 and be disposed as axially symmetric structure with the wedge 2, and make in central axes and the substrate 1 of the wedge 2 Axis is on same straight line, and the straight slot 21 extends along the central axes of the wedge 2, in this way, impacting the substrate 1 When, during the substrate 1 drives the movement of wedge 2, it can make on the plank sheathing of the straight slot 21 The nail body 5 successfully moves in the straight slot 21.It is preferred that the notch of the straight slot 21 could be provided as strip knot Structure, is acted on forming spacing priming well to the nail body 5.
The surface of the wedge 2 could be provided as arcwall face, to strengthen the intensity of the wedge 2, with guarantee and institute When stating the head of a nail 6 and abutting, situations such as being not in deformation, to extend the service life of the connection component.Further, can be with The arcwall face is configured to friction portion with the position that the notch of the straight slot 21 is connected, and the friction portion can be with the head of a nail Frictional force well is formed between 6, so that after the plank sheathing is assembled with the Combined formwork, the second component 200 Be not in opposite slip between the wedge 2, applied so as to improve the plank sheathing with the Combined formwork in building Bonding strength during work.
Furthermore, it is possible to make to form one knot between the substrate 1 and the wedge 2 using punching press or other modes Structure, to strengthen the intensity of connection component, and reduces production cost.
It is exemplary for the ease of exerting a force to the substrate 1, first hit piece 3 can be set at the both ends of the substrate 1 With the second hit piece 4.Preferably, first hit piece 3 uses bending plate with second hit piece 4, to increase force Area, makes 1 stress equalization of substrate, so as to move well the relatively described straight slot 21 of the nail body 5 on the plank sheathing It is dynamic.
It is of course also possible to use punching press or other modes are by the substrate 1, the wedge 2 and the bending plate Setting is an integral molding structure, so as to improve the intensity of connection component, and reduces overall production cost.
It is used for Combined formwork and the connection component of plank sheathing assembly and disassembly in the utility model embodiment, due to assembly and disassembly Simplicity, and the characteristic of the plank sheathing will not be destroyed, therefore, can be in construction, such as the construction of floor, shear wall etc. In, plank sheathing is assembled and disassembled well with Combined formwork, to obtain preferably construction effect.
The above is only the preferred embodiment of the utility model, it is noted that for the common skill of the art For art personnel, on the premise of the utility model technical principle is not departed from, some improvement and replacement can also be made, these change The scope of protection of the utility model is also should be regarded as into replacement.

Claims (10)

  1. It is 1. a kind of for Combined formwork and the connection component of plank sheathing assembly and disassembly, it is characterised in that including:First component and in nail The second component of shape structure, the first component include substrate and wedge, the two sides of the substrate be respectively configured as to Junction and supporting surface, the entrance hole for connecting the bearing surface and the supporting surface is provided with the substrate, and the wedge is fixed In on the supporting surface and being provided with and being connected with the entrance hole and the gradual increased straight slot of height, connection is also provided with the substrate The slot bottom of the entrance hole and the straight slot and the opening passed through for the second component;The second component includes nail body, consolidates Due to the head of a nail and the annular abutment part that is socketed on the nail, the annular abutment part and the nail of the tail end of the nail body Installing zone is configured as between cap, the annular abutment part is used for the surface snug fit with plank sheathing, and the entrance hole supplies institute State the head of a nail to pass through, the head of a nail is used to contact with the notch of the straight slot.
  2. 2. as claimed in claim 1 for Combined formwork and the connection component of plank sheathing assembly and disassembly, it is characterised in that the base Plate and the wedge are axially symmetric structure, and the central axes of the central axes of the wedge and the substrate are in same straight line On, the straight slot extends along the central axes of the wedge.
  3. 3. as claimed in claim 2 for Combined formwork and the connection component of plank sheathing assembly and disassembly, it is characterised in that described logical The notch of groove is string configuration.
  4. 4. as claimed in claim 3 for Combined formwork and the connection component of plank sheathing assembly and disassembly, it is characterised in that the wedge The surface of shape part is arcwall face.
  5. 5. as claimed in claim 4 for Combined formwork and the connection component of plank sheathing assembly and disassembly, it is characterised in that the arc Shape face is configured as friction portion with the position that the notch of the straight slot is connected.
  6. 6. such as the connection component that claim 1-5 any one of them is assembled and disassembled for Combined formwork with plank sheathing, its feature exists In the substrate is integrally formed with the wedge.
  7. 7. as claimed in claim 6 for Combined formwork and the connection component of plank sheathing assembly and disassembly, it is characterised in that the base Integrative-structure is formed by impact style between plate and the wedge.
  8. 8. such as the connection component that claim 1-5 any one of them is assembled and disassembled for Combined formwork with plank sheathing, its feature exists In the both ends of the substrate are respectively equipped with the first hit piece and the second hit piece.
  9. 9. the connection component for the assembly and disassembly of Combined formwork and plank sheathing as claimed in claim 8, it is characterised in that described the One hit piece and second hit piece are bending plate.
  10. 10. as claimed in claim 9 for Combined formwork and the connection component of plank sheathing assembly and disassembly, it is characterised in that described Substrate, the wedge and the bending plate are integrally formed.
CN201721080012.5U 2016-12-09 2017-08-25 For Combined formwork and the connection component of plank sheathing assembly and disassembly Active CN207296416U (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201621349899 2016-12-09
CN2016213498999 2016-12-09

Publications (1)

Publication Number Publication Date
CN207296416U true CN207296416U (en) 2018-05-01

Family

ID=60228358

Family Applications (6)

Application Number Title Priority Date Filing Date
CN201710741401.6A Active CN107476570B (en) 2016-12-09 2017-08-25 Connection component and mounting and dismounting method for Combined formwork and plank sheathing assembly and disassembly
CN201710742139.7A Active CN107386644B (en) 2016-12-09 2017-08-25 Locking piece for assembling and disassembling combined type formwork and wood formwork and assembling and disassembling method
CN201721079958.XU Active CN207296405U (en) 2016-12-09 2017-08-25 For Combined formwork and the locking member of plank sheathing assembly and disassembly
CN201721080012.5U Active CN207296416U (en) 2016-12-09 2017-08-25 For Combined formwork and the connection component of plank sheathing assembly and disassembly
CN201721080206.5U Active CN207296406U (en) 2016-12-09 2017-08-25 The connection component that a kind of Combined formwork is used in combination with plank sheathing
CN201710742219.2A Active CN107327136B (en) 2016-12-09 2017-08-25 A kind of installation that Combined formwork is used in combination with plank sheathing and method for dismounting

Family Applications Before (3)

Application Number Title Priority Date Filing Date
CN201710741401.6A Active CN107476570B (en) 2016-12-09 2017-08-25 Connection component and mounting and dismounting method for Combined formwork and plank sheathing assembly and disassembly
CN201710742139.7A Active CN107386644B (en) 2016-12-09 2017-08-25 Locking piece for assembling and disassembling combined type formwork and wood formwork and assembling and disassembling method
CN201721079958.XU Active CN207296405U (en) 2016-12-09 2017-08-25 For Combined formwork and the locking member of plank sheathing assembly and disassembly

Family Applications After (2)

Application Number Title Priority Date Filing Date
CN201721080206.5U Active CN207296406U (en) 2016-12-09 2017-08-25 The connection component that a kind of Combined formwork is used in combination with plank sheathing
CN201710742219.2A Active CN107327136B (en) 2016-12-09 2017-08-25 A kind of installation that Combined formwork is used in combination with plank sheathing and method for dismounting

Country Status (1)

Country Link
CN (6) CN107476570B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476570A (en) * 2016-12-09 2017-12-15 广州兢业建筑结构技术有限公司 For Combined formwork and the connection component and mounting and dismounting method of plank sheathing assembly and disassembly

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109629828A (en) * 2018-12-03 2019-04-16 筑梦高科建筑有限公司 A kind of quick rigging mechanism of semi-solid-state shaping
CN111287454A (en) * 2020-03-05 2020-06-16 上海建工集团股份有限公司 Mold opening and closing device and using method thereof

Family Cites Families (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100633347B1 (en) * 2004-01-16 2006-10-12 (주)삼아테크 A bar for having the cutoff-slot, and an apparatus for forming the form of having it
CN1769622B (en) * 2005-03-28 2010-12-08 孙长顺 Template engineering construction technology employing coiled material
CN2801962Y (en) * 2005-04-14 2006-08-02 冈建企业股份有限公司 Improved structure of template pressing stripe for grout
KR100799609B1 (en) * 2006-05-29 2008-01-30 이현 Form hook
CN201169918Y (en) * 2008-02-27 2008-12-24 郑国良 Opposed-pulling bolt fixed pin
CN201598829U (en) * 2009-11-10 2010-10-06 郑大彤 Double-cap steel nail for building formwork
CN202139849U (en) * 2011-06-30 2012-02-08 深圳汇林达科技有限公司 Back ridge clamping mechanism
CN202391125U (en) * 2011-12-27 2012-08-22 绍兴县明煌建材科技有限公司 Special connecting member for combined template
CN203213581U (en) * 2013-02-19 2013-09-25 毛国海 Building template assembly
CN203188621U (en) * 2013-04-03 2013-09-11 福建安厦新型建筑模板制造有限公司 Template inserted pin
US9340933B2 (en) * 2013-11-19 2016-05-17 Kevin Parr Telescoping concrete form assembly
CN203669365U (en) * 2014-01-21 2014-06-25 福建江南铝合金模板有限公司 Aluminum alloy template and wood template connecting piece
EP3002392A1 (en) * 2014-09-30 2016-04-06 Nicolae Popescu Covering element for a formwork for solid ceilings
CN205330165U (en) * 2015-11-28 2016-06-22 福建省二建建设集团有限公司 Novel concrete form installs inseparable ware and mounting structure thereof
CN205558273U (en) * 2016-01-28 2016-09-07 李木林 Template connecting piece
CN107476570B (en) * 2016-12-09 2019-11-01 广州兢业建筑结构技术有限公司 Connection component and mounting and dismounting method for Combined formwork and plank sheathing assembly and disassembly

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107476570A (en) * 2016-12-09 2017-12-15 广州兢业建筑结构技术有限公司 For Combined formwork and the connection component and mounting and dismounting method of plank sheathing assembly and disassembly
CN107476570B (en) * 2016-12-09 2019-11-01 广州兢业建筑结构技术有限公司 Connection component and mounting and dismounting method for Combined formwork and plank sheathing assembly and disassembly

Also Published As

Publication number Publication date
CN207296406U (en) 2018-05-01
CN107476570A (en) 2017-12-15
CN107386644B (en) 2020-05-19
CN107327136B (en) 2019-05-24
CN107386644A (en) 2017-11-24
CN107476570B (en) 2019-11-01
CN207296405U (en) 2018-05-01
CN107327136A (en) 2017-11-07

Similar Documents

Publication Publication Date Title
CN207296416U (en) For Combined formwork and the connection component of plank sheathing assembly and disassembly
JP2015045412A (en) Clinch pin-type panel fastener
WO2006044829A3 (en) Rivet tool for steel studs
JP4351710B2 (en) Screws with bit engagement holes and a group of bit engagement hole screws and driver bits
CN205400053U (en) Pop out formula coupling assembling
CN112663951A (en) Beam formwork and beam formwork combination
JP2006274775A (en) Method of mounting and dismounting a surface wood/joint bar on mold form with separate nail
CN206143985U (en) Curtain wall beam spring pin
US8458881B1 (en) Die with multi-sided cavity for self-piercing riveting process
CN201982426U (en) Plane hermetic riveting structure
CN211447760U (en) Aluminum alloy wall template reinforcing and quick assembling and disassembling structure
CN208056333U (en) A kind of bearing type flooring deformation joint deckboard construction
CN210949405U (en) Connecting mechanism for connecting a plurality of plates
CN203533173U (en) Wedge-shaped connection plate
CN108891715B (en) Logistics tray
CN207138937U (en) A kind of novel embedded drill bushing
CN219575048U (en) Buckle integrated nameplate
CN1935620A (en) Steel crane beam end portion heightening device
KR200443369Y1 (en) A construction connector
CN207308709U (en) Repair punch die in the side of energy fast assembling-disassembling insert
CN218117208U (en) Outer wall aluminum alloy template reinforcing apparatus
CN103089777B (en) Safety locking pin with own locking piece and machining process for safety locking pin
KR200377146Y1 (en) Nail that have taper in head department
CN210082035U (en) Tongue-and-groove magnetic side mould
KR101827382B1 (en) Combination structure between deck-plate and spacer for preventing sag

Legal Events