CN207259384U - For bridge bearing platform and the automation curing system of pier stud - Google Patents

For bridge bearing platform and the automation curing system of pier stud Download PDF

Info

Publication number
CN207259384U
CN207259384U CN201721147616.7U CN201721147616U CN207259384U CN 207259384 U CN207259384 U CN 207259384U CN 201721147616 U CN201721147616 U CN 201721147616U CN 207259384 U CN207259384 U CN 207259384U
Authority
CN
China
Prior art keywords
water
water tank
bearing platform
pier stud
bridge bearing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721147616.7U
Other languages
Chinese (zh)
Inventor
蒋豪
田苏云
刘佳皓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Transportation Construction Engineering Group Co ltd
Original Assignee
Wuxi Traffic Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Traffic Engineering Co Ltd filed Critical Wuxi Traffic Engineering Co Ltd
Priority to CN201721147616.7U priority Critical patent/CN207259384U/en
Application granted granted Critical
Publication of CN207259384U publication Critical patent/CN207259384U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of automation curing system for being used for bridge bearing platform and pier stud,Including water tank,Arranged on the spraying mechanism of water tank bottom,The inlet channel and the water supply pump arranged on inlet channel water supply point one end being connected with water tank,In the water tank partition plate is equipped with close to spraying mechanism side,Water tank partition is water storage accommodating cavity and water outlet drainage lumens by the partition plate,The partition plate center is equipped with a vertical tube,The top of the vertical tube is equipped with flow control device,The flow control device is fixed on the tank inner wall,The flow control device is equipped with the time schedule controller of control spray,Lowest water level detector and peak level detector are additionally provided with the water tank,It can realize full-automatic maintenance continual to bridge bearing platform and pier stud timing,Be conducive to the quality of control bridge bearing platform and pier stud,Save manpower and water resource at the same time.

Description

For bridge bearing platform and the automation curing system of pier stud
Technical field
Bridge construction care field is the utility model is related to, more specifically, it relates to which a kind of be used for bridge bearing platform and pier The automation curing system of column.
Background technology
In bridge construction, cushion cap and pier stud carry out maintenance after pouring be one very heavy in bridge construction project The work wanted.The maintenance work of concrete mainly allows concrete to be in suitable environment, can easily control concrete Temperature, the sign that can occur crack to concrete makes the measure of reply, prevents the appearance of crack problem in time.Normally Maintenance be after concrete final set, watering is responsible for by special messenger daily, but the original such as concrete temperature in itself, humidity, hardness Because that can produce outside crack, maintenance work of the construction personnel to concrete surface do it is not in place, cause its surface not in time Moisture evaporation is too fast but cannot timely supplement moisture, also easily causes concrete and occurs dry and cracked show because of water shortage As.
Notification number is that the Chinese patent of 105133502 A of CN discloses a kind of bridge bearing platform and pier stud regarding to the issue above Curing means, including tank, water inlet switch, controlling switch, effluent switch and maintenance sparge pipe;Tank is airtight Container, the top of tank are equipped with the inlet channel and water inlet switch that are connected with pressure water source, and the top of tank is equipped with The control pipeline and controlling switch communicated with air, tank lower part are equipped with the effluent switch being connected with maintenance sparge pipe;Storage Water container is placed in the top surface of bridge pier column, and maintenance sparge pipe is looped around the surrounding of bridge pier column top surface, conserves sparge pipe along length Uniformly distributed a plurality of hole for water sprayings.By the maintenance sparge pipe of annular, the whole top surface of bridge pier column can uniformly, be constantly sprayed, Water consumption is saved compared to more artificial water seasoning, but this scheme still has the problem of demand of human resources is big, Wu Fashi Existing automatic control, be difficult to realize 24 it is small when uninterrupted maintenance or timing conserve.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model is to provide one kind to be used for bridge bearing platform and pier stud Automation curing system, make the degree of automation higher of bridge bearing platform and pier stud concrete curing, realize the complete of maintenance processes Automated control, to meet the quality control to bridge bearing platform and pier stud.
The above-mentioned technical purpose of the utility model technical scheme is that:One kind is used for bridge bearing platform And the automation curing system of pier stud, including water tank, some spraying mechanisms arranged on water tank bottom, the water inlet being connected with water tank Pipeline and the water supply pump arranged on inlet channel water supply point one end, are equipped with partition plate in the water tank close to spraying mechanism side, described Water tank partition is water storage accommodating cavity and water outlet drainage lumens by partition plate, and the partition plate center is equipped with vertical tube connection water storage and houses Chamber and water outlet drainage lumens, the water outlet drainage lumens connect with spraying mechanism, and the top of the vertical tube is equipped with flow control device, The flow control device is fixed on the tank inner wall.
By using above technical scheme, overcoming traditional bridge pier column to conserve, the degree of automation is low, is difficult to periodically conserve And the shortcomings that labor intensive, water storage and drainage when the water storage accommodating cavity and water outlet drainage lumens that partition plate is separated out are easy to maintenance, stream The installation of amount adjusting mechanism can greatly save the water resource used in maintenance processes.
Further, the spraying mechanism includes plastic water pipe and shower nozzle, and the plastic water pipe is placed in water tank bottom Periphery, the corresponding shower nozzle are placed in described plastic water pipe water outlet one end.
By using above technical scheme, using the gravity of water, the large area water spray that shower nozzle is uniform, lasting can be made.
Further, the flow control device include be set up on tank inner wall supporting rack, be fixed in supporting rack Waterproof hydraulic pump, the waterproof hydraulic pump lower end is sequentially connected with drive link, the central axis phase of drive link and both vertical tubes Overlap, waterproof hydraulic pump can control drive link vertically to move, and the waterproof hydraulic pump upper end is equipped with hydraulic pipeline and prolongs Extend outside water tank, one end that the hydraulic pipeline is located at outside water tank is equipped with hydraulic valve.
By using above technical scheme, the transmission of hydraulic pump accurately and reliably, can be accurately held between vertical tube and drive link Away from external environment change influences transmission small.
Further, the hydraulic valve is equipped with time schedule controller, and the hydraulic valve is mutually electrically connected with time schedule controller.
By using above technical scheme, time schedule controller can realize the maintenance spray of full-automatic bridge bearing platform, according to The maintenance effect at initial stage, the pipe diameter size of plastic water pipe and weather conditions etc., adjust the time interval of time schedule controller, further Accomplish to reduce water consumption.
Further, the flow control device further includes the conical head arranged on drive link bottom, and the conical head is circle Cone, and its bottom surface is connected with the drive link, the conical head scarf matches with vertical tube.
By using above technical scheme, the clearance distance of conical head scarf and vertical tube is adjusted, so that water flow is limited, The carry out wet curing of realization while at the uniform velocity large area.
Further, the basal diameter of the conical head and vertical tube internal diameter are equal in magnitude.
By using above technical scheme, when conical head abuts completely to be placed in vertical tube, water flow zero.
Further, the conical head perisporium is coated with one layer of rubber sleeve.
By using above technical scheme, become the hard contact between conical head and vertical tube as Elastic Contact, both protections It is without damage, and can largely reduce the phenomenon of leak.
Further, the partition plate upper surface is equipped with lowest water level detector, and the tank top madial wall is equipped with most Wireless transport module is equipped with high water level detector, the lowest water level detector and the peak level detector.
By using above technical scheme, the moment detects the moisture storage capacity in water tank, realizes automatic control during water inlet.
In conclusion the utility model has the advantages that:
1st, by spraying mechanism complete uniform large-area spray conserve, have it is simple in structure, manufacture cost it is low, save water The advantages of resource;
2nd, by the regulating power of flow control device, bridge bearing platform and the degree of automation of pier stud concrete curing are made more Height, to meet the quality control to bridge bearing platform and pier stud;
3rd, by time schedule controller, lowest water level detector and peak level detector realize water inlet, maintenance processes it is complete Automation and curing time and cycle are controllable, have the advantages that intelligent, automation, green energy conservation.
Brief description of the drawings
Fig. 1 is a kind of overall structure signal for bridge bearing platform and the automation curing system of pier stud of the utility model Figure;
Fig. 2 is structure sectional view of the tank parts along B directions in Fig. 1;
Fig. 3 is the close-up schematic view of part A in Fig. 2, shows the position relationship of flow control device and vertical tube.
In figure:1st, water tank;11st, partition plate;12nd, water storage accommodating cavity;13rd, water outlet drainage lumens;14th, vertical tube;2nd, spraying mechanism; 21st, plastic water pipe;22nd, shower nozzle;3rd, inlet channel;4th, water supply pump;5th, flow control device;51st, supporting rack;52nd, Water-proof liquid Press pump;53rd, hydraulic pipeline;54th, hydraulic valve;55th, time schedule controller;56th, drive link;57th, conical head;58th, rubber sleeve;6th, it is minimum Level switch;7th, peak level detector;8th, wireless transport module;9th, water conservation layer is contained.
Embodiment
With reference to the accompanying drawings and examples, the utility model is described in detail.
A kind of automation curing system for bridge bearing platform and pier stud, as shown in Figure 1, including water tank 1, spraying mechanism 2, Inlet channel 3 and water supply pump 4, pour after completion reaches final set in cushion cap or pier stud, are hung water tank 1 in pier stud branch with truck crane At the embedded bar of seat, the bottom of water tank 1 is equipped with some spraying mechanisms 2, persistently sprays water in the maintenance work of bridge, prevents from mixing Solidifying soil occurs dry and cracked phenomenon because of water shortage, and inlet channel 3 is installed on 1 side of water tank, and one end of 3 water supply point of inlet channel is equipped with Water supply pump 4, water supply pump 4 persistently supply water for spraying mechanism 2.
As depicted in figs. 1 and 2, spraying mechanism 2 includes plastic water pipe 21 and the shower nozzle 22 being connected with plastic water pipe 21, this In embodiment, a plastic water pipe 21 is equipped in four sidewall bottoms of water tank 1, the shower nozzle 22 being mutually equipped with is positioned on plastic water pipe One end of 21 water outlets, using the gravity of water, can make shower nozzle 22 continue the water spray of large area.
As shown in Figure 1, Figure 2 and Figure 3, partition plate 11 is welded with close to the side of spraying mechanism 2 in water tank 1, partition plate 11 will be whole Water tank 1 is divided into water storage accommodating cavity 12 and water outlet drainage lumens 13, and 11 center of partition plate is equipped with a vertical tube 14 connection water storage and houses Chamber 12 and water outlet drainage lumens 13, plastic water pipe 21 connect with water outlet drainage lumens 13, water storage during easy to conserve bridge and pier stud With drainage.As shown in Figures 2 and 3, the top of vertical tube 14 sets a flow control device 5, and flow control device 5 includes supporting rack 51st, waterproof hydraulic pump 52, hydraulic pipeline 53 and hydraulic valve 54, supporting rack 51 are set up on 1 middle part inner wall of water tank, for fixed anti- Water Hydraulic Pump 52,52 lower end of waterproof hydraulic pump are sequentially connected with drive link 56, both central axis of drive link 56 and vertical tube 14 Coincide, waterproof hydraulic pump 52 can control 56 vertical direction of drive link to move, and 52 upper end of waterproof hydraulic pump is connected with hydraulic pipeline 53, and extend to outside water tank 1, one end that hydraulic pipeline 53 is located at outside water tank 1 is equipped with hydraulic valve 54 and is used to control waterproof hydraulic pump 52 running.Time schedule controller 55 is also powered with the junction of hydraulic valve 54 and water tank 1, can be realized by time schedule controller 55 The maintenance spray of full-automatic bridge bearing platform, it is only necessary to finish the interval setting of time schedule controller 55, it becomes possible to according to design Good time interval continuous water supply, conserves bridge bearing platform or pier stud, meanwhile, according to the maintenance effect at initial stage, plastics water The pipe diameter size of pipe 21 and weather conditions etc., adjustment time interval, further accomplishes to reduce water consumption.
As shown in figure 3, flow control device 5 further includes the conical head 57 arranged on 56 bottom of drive link, conical head 57 is chamfer Face matches with vertical tube 14, and 57 basal diameter of conical head and 14 internal diameter of vertical tube are equal in magnitude, and is put when conical head 57 abuts completely In in vertical tube 14, water flow zero, therefore, the spacing of conical head 57 and vertical tube 14 is adjusted by controlling waterproof hydraulic pump 52, So as to limit water flow.As shown in Figures 2 and 3, the valve that four plastic water pipes 21 add manual adjustment flow is compared to, this Automatic management that structure is simple and easy to implement, the flow that plastic water pipe 21 can be adjusted by the water yield of adjusting water outlet drainage lumens 13 are big It is small, realize the wet curing of the at the uniform velocity large area of spraying mechanism 2.In this embodiment, in order to protect conical head 57, vertical tube 14 to contact It is without damage, one layer of rubber sleeve 58 is coated in 57 perisporium of conical head, change hard contact, and can be largely into Elastic Contact On can reduce the phenomenon of leak.
As shown in Figures 2 and 3, vertical tube 14 is mounted with lowest water level detector 6, the water beyond the convex edge part of partition plate 11 Case 1 is mounted with peak level detector 7, lowest water level detector 6 and the peak level detector 7 close to one end of top case lid Inside it is respectively arranged with wireless transport module 8.When lowest water level detector 6 detects that the water surface is less than lowest water level, wireless transport module 8 By this signal transmission at staff, water supply pump 4 is opened to 1 water filling of water tank;The water surface at 7 detection of peak level detector During higher than highest water filling position, monitoring signals are then transferred to staff, water supply pump 4 is closed and stops water filling.
As shown in Figure 1, the surface of bridge bearing platform is contained covered with water conservation layer 9 is contained in the present embodiment using continuous be used as of acrylic Water conservation layer 9, can also use other materials with enough water imbibitions, water-retaining property and flexibility, such as sponge, it is therefore an objective to first Outside moisture gradually absorbs, and is gradually discharged during concrete curing, so as to ensure the humidity of concrete surface.
The course of work:After water tank 1 is connected according to the size of bridge bearing platform or pier stud, inlet channel 3 and water source are connected Connect, when the water surface is less than lowest water level, opens water supply pump 4 to 1 water filling of water tank, when the water surface is higher than highest water filling position, closes and supply Water pump 4 stops water filling;Then according to curing requirements, the interval of time schedule controller 55 is set, and automatic switch waterproof hydraulic pump 52, is adjusted Pitch cone forming head 57 and the spacing control uninterrupted of vertical tube 14, are finally uniformly sprayed to whole platform via shower nozzle 22.
The above is only the preferred embodiment of the utility model, and the scope of protection of the utility model is not limited merely to Above-described embodiment, all technical solutions belonged under the utility model thinking belong to the scope of protection of the utility model.It should refer to Go out, for those skilled in the art, some improvement under the premise of the utility model principle is not departed from and Retouching, these improvements and modifications also should be regarded as the scope of protection of the utility model.

Claims (8)

1. a kind of automation curing system for being used for bridge bearing platform and pier stud, including water tank(1), some be arranged on water tank(1)Bottom Spraying mechanism(2)With water tank(1)The inlet channel being connected(3)And arranged on inlet channel(3)The water supply pump of water supply point one end (4), it is characterised in that:The water tank(1)Interior close spraying mechanism(2)Side is equipped with partition plate(11), the partition plate(11)By water Case(1)Separate for water storage accommodating cavity(12)With water outlet drainage lumens(13), the partition plate(11)Center is equipped with a vertical tube(14) Connect water storage accommodating cavity(12)With water outlet drainage lumens(13), the water outlet drainage lumens(13)With spraying mechanism(2)Connect, it is described Vertical tube(14)Top be equipped with flow control device(5), the flow control device(5)It is fixed on the water tank(1)Inner wall.
2. the automation curing system according to claim 1 for being used for bridge bearing platform and pier stud, it is characterised in that:The spray Drench mechanism(2)Including plastic water pipe(21)And shower nozzle(22), the plastic water pipe(21)Be placed in water tank(1)Bottom periphery, The corresponding shower nozzle(22)It is placed in the plastic water pipe(21)Water outlet one end.
3. the automation curing system according to claim 2 for being used for bridge bearing platform and pier stud, it is characterised in that:The stream Measure adjusting mechanism(5)Including being set up in water tank(1)Supporting rack on inner wall(51), be fixed on supporting rack(51)Interior waterproof hydraulic pressure Pump(52), the waterproof hydraulic pump(52)Lower end is sequentially connected with drive link(56), drive link(56)With vertical tube(14)Both Central axis coincides, waterproof hydraulic pump(52)Control drive link(56)Vertically stretch, the waterproof hydraulic pump(52) Upper end is equipped with hydraulic pipeline(53)And extend to water tank(1)Outside, the hydraulic pipeline(53)Positioned at water tank(1)Outer one end is equipped with Hydraulic valve(54).
4. the automation curing system according to claim 3 for being used for bridge bearing platform and pier stud, it is characterised in that:The liquid Pressure valve(54)It is equipped with time schedule controller(55), the hydraulic valve(54)With time schedule controller(55)Mutually it is electrically connected.
5. the automation curing system according to claim 4 for being used for bridge bearing platform and pier stud, it is characterised in that:The stream Measure adjusting mechanism(5)Further include and be arranged on drive link(56)The conical head of bottom(57), the conical head(57)For cone, and its Bottom surface and the drive link(56)Connection, the conical head(57)Scarf and vertical tube(14)Match.
6. the automation curing system according to claim 5 for being used for bridge bearing platform and pier stud, it is characterised in that:The cone Forming head(57)Basal diameter and vertical tube(14)Internal diameter is equal in magnitude.
7. the automation curing system according to claim 6 for being used for bridge bearing platform and pier stud, it is characterised in that:The cone Forming head(57)Perisporium is coated with one layer of rubber sleeve(58).
8. the automation curing system according to claim 7 for being used for bridge bearing platform and pier stud, it is characterised in that:It is described every Plate(11)Upper surface is equipped with lowest water level detector(6), the water tank(1)Inside top wall is equipped with peak level detector (7), the lowest water level detector(6)With the peak level detector(7)Inside it is equipped with wireless transport module(8).
CN201721147616.7U 2017-09-08 2017-09-08 For bridge bearing platform and the automation curing system of pier stud Active CN207259384U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721147616.7U CN207259384U (en) 2017-09-08 2017-09-08 For bridge bearing platform and the automation curing system of pier stud

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721147616.7U CN207259384U (en) 2017-09-08 2017-09-08 For bridge bearing platform and the automation curing system of pier stud

Publications (1)

Publication Number Publication Date
CN207259384U true CN207259384U (en) 2018-04-20

Family

ID=61920746

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721147616.7U Active CN207259384U (en) 2017-09-08 2017-09-08 For bridge bearing platform and the automation curing system of pier stud

Country Status (1)

Country Link
CN (1) CN207259384U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110480815A (en) * 2018-05-31 2019-11-22 杭州萧宏建设环境集团有限公司 A kind of high pier stud concrete surface automatic maintenance device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110480815A (en) * 2018-05-31 2019-11-22 杭州萧宏建设环境集团有限公司 A kind of high pier stud concrete surface automatic maintenance device

Similar Documents

Publication Publication Date Title
CN208981168U (en) A kind of bridge pier abutment body intelligent spray curing system
CN105104010B (en) Water and fertilizer automatic irrigation greening wall
CN201221056Y (en) Concrete bridge pier spray curing means
CN202021683U (en) Automatic spray curing system for concrete
CN207259384U (en) For bridge bearing platform and the automation curing system of pier stud
CN206173810U (en) Concrete maintenance spraying system
CN204929795U (en) A kind of liquid manure automatic irrigation greening wall
CN103718849A (en) Vertical greening device for building walls
CN102375421A (en) Solar energy and wind energy golf course automatic water-saving sprinkling irrigation control system
CN103147575B (en) A kind of concrete column automatic spraying device and method
CN103290857A (en) Conservation method of basic on-site concrete of transmission tower in desert areas
CN110486035A (en) A kind of shield machine working shaft lining wall trickle irrigation maintenance process
CN107347589A (en) A kind of high-efficiency solar treegarden irrigation device
CN208965377U (en) A kind of high temperature and drought area road maintenance system
CN204579373U (en) A kind of automatic flower-watering device
CN215801063U (en) Pier body health preserving device
CN211498503U (en) High pier stud concrete maintenance controlling means of bridge
CN206170299U (en) Intelligent spraying maintenance device of precast concrete bridge
CN203885387U (en) Washbasin with sprinkler structure
CN208462627U (en) A kind of energy saving and environment friendly treegarden irrigation device
CN208227940U (en) One kind being used for afforestation Domestic waste water reutilizing apparatus
CN206993825U (en) A kind of automatic irrigation feature wall
CN208428451U (en) A kind of vertical concrete component automatic maintenance device
CN206760135U (en) A kind of mushroom watering device
CN209703308U (en) A kind of automatic spray maintenance of equipment for high-speed railway bridge pier

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 214000 Room 608, building B, No. 35, Changjiang South Road, Wuxi City, Jiangsu Province

Patentee after: Wuxi Traffic Construction Engineering Group Co.,Ltd.

Address before: No. 805 Jianghai West Road, Wuxi, Jiangsu Province

Patentee before: WUXI TRAFFIC ENGINEERING Co.,Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: Room 521, No. 188 Guangyi Road, Liangxi District, Wuxi City, Jiangsu Province, 214000

Patentee after: Wuxi Transportation Construction Engineering Group Co.,Ltd.

Country or region after: China

Address before: Room 608, building B, 35 Changjiang South Road, Wuxi, Jiangsu 214000

Patentee before: Wuxi Traffic Construction Engineering Group Co.,Ltd.

Country or region before: China