CN207247407U - A kind of building intellectualization building - Google Patents

A kind of building intellectualization building Download PDF

Info

Publication number
CN207247407U
CN207247407U CN201721193922.4U CN201721193922U CN207247407U CN 207247407 U CN207247407 U CN 207247407U CN 201721193922 U CN201721193922 U CN 201721193922U CN 207247407 U CN207247407 U CN 207247407U
Authority
CN
China
Prior art keywords
valve
air
building
connecting tube
export
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721193922.4U
Other languages
Chinese (zh)
Inventor
祁军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Cxs Cleaning Technology Co Ltd
Original Assignee
Shenzhen Cxs Cleaning Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Cxs Cleaning Technology Co Ltd filed Critical Shenzhen Cxs Cleaning Technology Co Ltd
Priority to CN201721193922.4U priority Critical patent/CN207247407U/en
Application granted granted Critical
Publication of CN207247407U publication Critical patent/CN207247407U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Filtering Of Dispersed Particles In Gases (AREA)

Abstract

The utility model provides a kind of building intellectualization building, including:Filter, air intake equipment, purifier, air vessel, pipeline, solar converter, solar collecting device, negative aeroion device, return air equipment, dust-extraction unit, multiple floors, valve, connecting tube and check valve, there is no air purification and dedusting function relative to prior art Ground Connection in Intelligent Building ventilating system, at the same time, ventilating system uses single pipeline, there are function it is single the problems such as.Building intellectualization building provided by the utility model, it is divided into air inlet system, air return system, cleaning system and energy resource system, air return system has dedusting function, and it can effectively avoid energy waste, cleaning system has purification function, and air is purified three times, and energy resource system can convert solar energy into electrical energy supply exhaust equipment and return air equipment, the energy is saved, while air inlet system, air return system and cleaning system can need switching flow using multipaths according to user.

Description

A kind of building intellectualization building
Technical field
It the utility model is related to building field, more particularly to a kind of building intellectualization building.
Background technology
With the high speed development of social economy, people's living standard is continuously improved, and modernizes large-scale commercial building and intelligence Change house is also more and more, these large-scale commercial buildings and intelligent residence have the function of that numerous, industry situation is complicated, indoor environment product Matter requires the features such as high, greatly improves appearance of city and the people live condition.
People are to be different from common building notable feature in the preferable comfort level that intelligence obtains.People have just enter into building Interior, what is breathed first is the air in building, therefore the ventilating system in Ground Connection in Intelligent Building should be paid much attention to.
At present, Ground Connection in Intelligent Building ventilating system uses conventional means of ventilation, without air purification and dedusting function, meanwhile, Ventilating system uses single pipeline, there are function it is single the problems such as.
Utility model content
This application provides a kind of building intellectualization building, there is no the air net to solve existing Ground Connection in Intelligent Building ventilating system Change and dedusting function, meanwhile, ventilating system uses single pipeline, there are function it is single the problems such as.
In order to solve the above-mentioned technical problem, the utility model provides following technical solution:
A kind of building intellectualization building, it is characterised in that:Including:Filter, air intake equipment, purifier, air vessel, Pipeline, solar converter, solar collecting device, negative aeroion device, return air equipment, dust-extraction unit, multiple floors, One valve, the second valve, the 3rd valve, the 4th valve, connecting tube, the first check valve and the second check valve;
The air intake equipment input end is connected by the connecting tube with first valve one end
The first valve other end is connected by the connecting tube with the filter outlet end;
The air intake equipment port of export is connected by the connecting tube with the first check valve inlet end;
The first one-way valved outlet end is connected by the connecting tube with the purifier input end;
The second valve export end is connected by the connecting tube with the second check valve inlet end;
The second valve inlet end is connected by the connecting tube with the filter outlet end;
The second one-way valved outlet end is connected by the connecting tube with the purifier input end;
The purifier outlet is connected by the connecting tube with the air vessel input end;The air vessel goes out Mouth end is connected with described pipeline one end;
The pipeline other end is connected with the negative aeroion device input end;
Described floor one end is connected with the negative aeroion device port of export;
The floor other end is connected by the connecting tube with the dust-extraction unit input end, the dust-extraction unit outlet End is connected by the connecting tube with described 3rd valve one end;
The 3rd valve other end is connected by the connecting tube with the return air equipment importation end;
The return air equipment port of export is connected by the connecting tube with described 4th valve one end;
The air return system port of export is connected with the 5th valve;
The 4th valve other end is connected by the connecting tube with the purifier input end.
Top and bottom are additionally provided with crystal gypsum lamp in the air vessel;
The pipeline includes the first conduit entrance valve, the first pipeline, the first pipe outlet valve, second pipe inlet valve Door, second pipe, second pipe outlet valve;
First pipe head is connected with described first conduit entrance valve one end;First pipe outlet with First pipe outlet valve one end connection;
The second pipe input end is connected with described second pipe imported valve one end;The second pipe port of export with Second pipe outlet valve one end connection;
The first conduit entrance valve other end is connected with the second pipe imported valve other end;
The first pipe outlet valve other end is connected with the second pipe outlet valve other end;
First pipeline is tapered pipeline, and the first pipe head radius is less than first pipe outlet half Footpath;
The second pipe is tapered pipeline, and the second pipe input end radius is more than the second pipe port of export half Footpath.
Alternatively, the solar converter is connected with the crystal gypsum lamp.
Alternatively, the solar converter is connected with the purifier.
Alternatively, the 4th valve uses check valve.
Alternatively, the air vessel uses horizontal tank, and the air vessel outer wall is provided with insulating layer.
From above technical scheme, the utility model provides a kind of building intellectualization building, relative to the prior art Ground Connection in Intelligent Building ventilating system does not have air purification and dedusting function, meanwhile, ventilating system uses single pipeline, and there are function list One the problems such as.Building intellectualization building provided by the utility model, are divided into air inlet system, air return system, cleaning system and energy Source system, air return system has dedusting function, and can effectively avoid energy waste, and cleaning system has purification function, to sky Gas is purified three times, and energy resource system can convert solar energy into electrical energy supply exhaust equipment and return air equipment, saves the energy, together When air inlet system, air return system and cleaning system switching flow can be needed according to user using multipaths.
Brief description of the drawings
In order to illustrate more clearly of the technical solution of the application, letter will be made to attached drawing needed in the embodiment below Singly introduce, it should be apparent that, for those of ordinary skills, without having to pay creative labor, Other attached drawings can also be obtained according to these attached drawings.
Fig. 1 is the application building intellectualization building example structure schematic diagram.
Fig. 2 flows to schematic diagram for the application building intellectualization building air.
Description of reference numerals:
1- filters;2- air intake equipments;3- purifiers;4- air vessels;41- crystal gypsum lamps;5- air-conditionings;The 6- sun Can converter;7- solar collecting devices;8- negative aeroion devices;9- return air equipment;10- dust-extraction units;11- floors; 100- connecting tubes;The first valves of 101-;The second valves of 102-;The 3rd valves of 103-;The 4th valves of 104-;201- first is unidirectional Valve;The second check valves of 202-;The first pipelines of 51-;52- second pipes;501- the first conduit entrance valves;The first pipelines of 502- go out Mouth valve;503- second pipe imported valves;504- second pipe outlet valves.
Embodiment
For the utility model embodiment, specific application scenarios can be as follows, but not limited to this, as shown in Figure 1, The application building intellectualization building example structure schematic diagram.
A kind of building intellectualization building, it is characterised in that:Including:Filter 1, air intake equipment 2, purifier 3, air hold Device 4, pipeline 5, solar converter 6, solar collecting device 7, negative aeroion device 8, return air equipment 9, dust-extraction unit 10, Multiple floors 11, the first valve 101, the second valve 102, the 3rd valve 103, the 4th valve 104, connecting tube 100, first are unidirectional 201 and second check valve 202 of valve;
2 input end of air intake equipment is connected by the connecting tube 100 with 101 one end of the first valve;
First valve, 101 other end is connected by the connecting tube 100 with 1 port of export of filter;
2 port of export of air intake equipment is connected by the connecting tube 100 with 201 input end of the first check valve;
First check valve, 201 port of export is connected by the connecting tube 100 with 3 input end of purifier;
Second valve, 102 port of export is connected by the connecting tube 100 with 202 input end of the second check valve;
Second valve, 102 input end is connected by the connecting tube 100 with 1 port of export of filter;
Second check valve, 202 port of export is connected by the connecting tube 100 with 3 input end of purifier;
The outlet of purifier 3 is connected by the connecting tube 100 with 4 input end of air vessel;The air 4 port of export of container is connected with described 5 one end of pipeline;
5 other end of pipeline is connected with 8 input end of negative aeroion device;
Described 11 one end of floor is connected with 8 port of export of negative aeroion device;
11 other end of floor is connected by the connecting tube 100 with 10 input end of dust-extraction unit, the dedusting 10 port of export of device is connected by the connecting tube with described 3rd valve, 103 one end;
3rd valve, 103 other end is connected by the connecting tube 100 with 9 input end of return air equipment;
9 port of export of return air equipment is connected by the connecting tube 100 with described 4th valve, 104 one end;
9 port of export of return air equipment is connected with the 5th valve 105;
4th valve, 104 other end is connected by the connecting tube 100 with 3 input end of purifier;
Top and bottom are additionally provided with crystal gypsum lamp 41 in the air vessel 4;
The pipeline 5 includes the first conduit entrance valve 501, the first pipeline 51, the first pipe outlet valve 502, second Conduit entrance valve 503, second pipe 52, second pipe outlet valve 504;
First pipeline, 51 input end is connected with described first conduit entrance valve, 501 one end;First pipeline 51 The port of export is connected with described first pipe outlet valve, 502 one end;
52 input end of second pipe is connected with described 503 one end of second pipe imported valve;The second pipe 52 The port of export is connected with described 504 one end of second pipe outlet valve;
First conduit entrance valve, 501 other end is connected with 503 other end of second pipe imported valve;
First pipe outlet valve, 502 other end is connected with 504 other end of second pipe outlet valve;
First pipeline 51 is tapered pipeline, and the 51 input end radius of the first pipeline goes out less than first pipeline 51 Mouth end radius;
The second pipe 52 is tapered pipeline, and the 52 input end radius of second pipe goes out more than the second pipe 52 Mouth end radius.
The application utility model embodiment operation principle is:The building intellectualization building ventilating system can be divided into air inlet system System, air return system, cleaning system and energy resource system.As shown in Fig. 2, it is the flow direction signal of the application building intellectualization building air Scheme, arrow represents air-flow direction in figure.
Specifically, air inlet system includes two flows, and first flow is by first valve 101, the connecting tube 100, the air intake equipment 2 and first check valve 201 form, which provides wind-force by the air intake equipment 2;Second A flow is made of second valve 102, connecting tube 100 and second check valve 202, which is provided by natural wind Wind-force.First flow may be selected as needed wind-force or second flow offer wind-force are provided.
Specifically, air return system includes three flows, and first flow is by the dust-extraction unit (10), the 3rd valve 103rd, the connecting tube 100, the return air equipment 9 and the 4th valve 104 form, and when indoor/outdoor temperature-difference is larger, adopt With the flow, energy loss can be reduced, for example, when indoor temperature is much larger than outdoor temperature, indoor hot-air outwards flows damage Loss of heat amount, outdoor cold air cause temperature in the floor 11 to decline, therefore can avoid heat using the flow to indoor conveying Loss.Second flow is by the dust-extraction unit (10), the 3rd valve 103, the connecting tube 100, the return air equipment 9 And the 5th valve 105 forms, which, which can be, makes air in the floor 11 continue to exchange with the external world.3rd flow By the dust-extraction unit (10), the 3rd valve 103, the connecting tube 100, the return air equipment 9, the 4th valve 104 and the 5th valve 105 form, which can make the 11 inside points air return of floor be delivered to the layer again In building 11, partial air enters extraneous.It should be noted that three flows of air return system are respectively provided with dedusting function.
Specifically, cleaning system includes the purifier 3, the air vessel 4, the pipeline 5 and the air Negative ion device 8.The purifier 3 is completed to air primary purification, passes through the crystal gypsum in the air vessel 4 Lamp 41 completes double purification, and finally by the negative aeroion device 8, production capacity negative aeroion, completion purifies three times.Need Illustrate, cleaning system also has two flows, and first flow includes purifier 3, the air vessel 4, the sky Gas negative ion device 8, first pipeline 51, the first conduit entrance valve 501 and the first pipe outlet valve 502, which is mainly used for winter, since reducing causes air pressure in pipeline to change, can improve gas in pipelines temperature;Second Flow includes purifier 3, the air vessel 4, the negative aeroion device 8, the second pipe 52, second pipe Road imported valve 503 and the second pipe outlet valve 504, the flow are mainly used for summer, since reducing causes pipeline Interior air pressure changes, and can reduce gas in pipelines temperature;Above-mentioned two flow is spare each other at the same time.
Specifically, energy resource system mainly includes the solar converter 6 and the solar collecting device 7, it is described too Positive energy 7 major function of collection device is collection solar energy, then converts solar energy into electricity by the solar converter 6 Energy.The air intake equipment 2 and the return air equipment 9 are connected with the solar converter 6, i.e., described air intake equipment 2 and described Return air equipment 9 provides electric energy by the solar converter 6.
This application provides a kind of building intellectualization building, there is no the air net to solve existing Ground Connection in Intelligent Building ventilating system Change and dedusting function, meanwhile, ventilating system uses single pipeline, there are function it is single the problems such as.
Further, the solar converter 6 is connected with the crystal gypsum lamp 41.The solar converter 6 can Electric energy is provided to the crystal gypsum lamp 41.
Further, the solar converter 6 is connected with the purifier 3.The solar converter 6 can give institute State purifier 3 and electric energy is provided.
Further, the 4th valve 104 uses check valve.Check valve can place gas backstreaming.
Further, the air vessel 4 uses horizontal tank, and 4 outer wall of the air vessel is provided with insulating layer.It is sleeping Formula tank water plane is longer, air can be made relatively long in the air vessel 4, improves the crystal gypsum lamp 41 to sky Gas clean-up effect.Heat scatters and disappears in order to prevent, 4 outer wall of air vessel need to be provided with insulating layer.
From above technical scheme, the utility model provides a kind of building intellectualization building, relative to the prior art Ground Connection in Intelligent Building ventilating system does not have air purification and dedusting function, meanwhile, ventilating system uses single pipeline, and there are function list One the problems such as.Building intellectualization building provided by the utility model, are divided into air inlet system, air return system, cleaning system and energy Source system, air return system has dedusting function, and can effectively avoid energy waste, and cleaning system has purification function, to sky Gas is purified three times, and energy resource system can convert solar energy into electrical energy supply exhaust equipment and return air equipment, saves the energy, together When air inlet system, air return system and cleaning system switching flow can be needed according to user using multipaths.
It should be appreciated that the accurate knot that the utility model is not limited to be described above and is shown in the drawings Structure, and various modifications and changes may be made without departing from the scope thereof.The scope of the utility model only will by appended right Ask to limit.

Claims (5)

  1. A kind of 1. building intellectualization building, it is characterised in that:Including:Filter (1), air intake equipment (2), purifier (3), sky Gas container (4), pipeline (5), solar converter (6), solar collecting device (7), negative aeroion device (8), return air are set Standby (9), dust-extraction unit (10), multiple floors (11), the first valve (101), the second valve (102), the 3rd valve (103), the Four valves (104), the 5th valve (105), connecting tube (100), the first check valve (201) and the second check valve (202);
    Air intake equipment (2) input end is connected by the connecting tube (100) with the first valve (101) one end;
    First valve (101) other end is connected by the connecting tube (100) with the filter (1) port of export;
    Air intake equipment (2) port of export is connected by the connecting tube (100) with the first check valve (201) input end;
    First check valve (201) port of export is connected by the connecting tube (100) with the purifier (3) input end;
    Second valve (102) port of export is connected by the connecting tube (100) and the second check valve (202) input end Connect;
    Second valve (102) input end is connected by the connecting tube (100) with the filter (1) port of export;
    Second check valve (202) port of export is connected by the connecting tube (100) with the purifier (3) input end;
    Purifier (3) outlet is connected by the connecting tube (100) with the air vessel (4) input end;The sky Gas container (4) port of export is connected with the pipeline (5) one end;
    Pipeline (5) other end is connected with negative aeroion device (8) input end;
    Described floor (11) one end is connected with negative aeroion device (8) port of export;
    Floor (11) other end is connected by the connecting tube (100) with the dust-extraction unit (10) input end, described to remove Dirt device (10) port of export is connected by the connecting tube with described 3rd valve (103) one end;
    3rd valve (103) other end is connected by the connecting tube (100) with return air equipment (9) input end;
    Return air equipment (9) port of export is connected by the connecting tube (100) with described 4th valve (104) one end;
    Return air equipment (9) port of export is connected with the 5th valve (105);
    4th valve (104) other end is connected by the connecting tube (100) with the purifier (3) input end;
    The interior top of the air vessel (4) and bottom are additionally provided with crystal gypsum lamp (41);
    The pipeline (5) include the first conduit entrance valve (501), the first pipeline (51), the first pipe outlet valve (502), Second pipe imported valve (503), second pipe (52), second pipe outlet valve (504);
    First pipeline (51) input end is connected with described first conduit entrance valve (501) one end;First pipeline (51) port of export is connected with described first pipe outlet valve (502) one end;
    Second pipe (52) input end is connected with described second pipe imported valve (503) one end;The second pipe (52) port of export is connected with described second pipe outlet valve (504) one end;
    First conduit entrance valve (501) other end is connected with second pipe imported valve (503) other end;
    First pipe outlet valve (502) other end is connected with second pipe outlet valve (504) other end;
    First pipeline (51) is tapered pipeline, and the first pipeline (51) input end radius is less than first pipeline (51) Port of export radius;
    The second pipe (52) is tapered pipeline, and second pipe (52) the input end radius is more than the second pipe (52) Port of export radius.
  2. 2. building intellectualization building as claimed in claim 1, it is characterised in that:The solar converter (6) and the crystalline substance Body gypsum lamp (41) connects.
  3. 3. building intellectualization building as claimed in claim 2, it is characterised in that:The solar converter (6) with it is described net (3) connection is put in makeup.
  4. 4. the building intellectualization building as described in claim 1-3 any one, it is characterised in that:4th valve (104) Using check valve.
  5. 5. the building intellectualization building as described in claim 1-3 any one, it is characterised in that:The air vessel (4) is adopted With horizontal tank, and the air vessel (4) outer wall is provided with insulating layer.
CN201721193922.4U 2017-09-18 2017-09-18 A kind of building intellectualization building Active CN207247407U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721193922.4U CN207247407U (en) 2017-09-18 2017-09-18 A kind of building intellectualization building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721193922.4U CN207247407U (en) 2017-09-18 2017-09-18 A kind of building intellectualization building

Publications (1)

Publication Number Publication Date
CN207247407U true CN207247407U (en) 2018-04-17

Family

ID=61889077

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721193922.4U Active CN207247407U (en) 2017-09-18 2017-09-18 A kind of building intellectualization building

Country Status (1)

Country Link
CN (1) CN207247407U (en)

Similar Documents

Publication Publication Date Title
CN201206901Y (en) Integration energy-conserving system for solar construction
CN202465426U (en) Energy-saving residence water treatment system
CN206398895U (en) The composite heating air-conditioning system of air source heat pump and water source heat pump combining
CN207247407U (en) A kind of building intellectualization building
CN207469821U (en) A kind of ventilated building structure
CN111392932A (en) Green building water circulating system
CN105783153A (en) System based on ground temperature structure ratio/hybrid air pump/multi-pipe temperature taking/water penetration purification
CN207570698U (en) A kind of intelligence joins Temperature Control Type ultrasonic wave hotlist system
CN202868844U (en) Modularized radiation heat transfer terminal and waste heat recovery radiation pipe network heat pump system
CN104728853B (en) boiler flue gas cooler
CN203083055U (en) Water air conditioner
CN210624778U (en) Energy storage power generation direct evaporative cooling air conditioning unit
CN207622209U (en) A kind of air cleaning unit
CN102980261A (en) Method for regulating city temperature through utilizing karst cave air and assort system of method for regulating city temperature through utilizing karst cave air
CN206347635U (en) One kind coupling energy-storage system
CN202660667U (en) Centralized air conditioning device using cold energy of liquefied natural gas (LNG)
CN201126281Y (en) High-efficiency controllable solar air heat collectors
CN201126280Y (en) Ladder bed structure solar air heat collectors
CN207247370U (en) A kind of energy-saving clean workshop system
CN203478561U (en) Condensate water recycling system of large central air conditioner unit
CN204373023U (en) Straight pipe type air-to-air energy recovery device
CN218511056U (en) Kitchen waste heat, PV/T and ground source heat pump integrated system
CN203571924U (en) Earth energy central air conditioner provided with Venturi tubes
CN208504541U (en) A kind of solar energy and air energy combining heating system
CN108105997A (en) A kind of indoor solar heating system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant