CN207232382U - Electric energy metering secondary overall operation situation on-Line Monitor Device - Google Patents

Electric energy metering secondary overall operation situation on-Line Monitor Device Download PDF

Info

Publication number
CN207232382U
CN207232382U CN201721206110.9U CN201721206110U CN207232382U CN 207232382 U CN207232382 U CN 207232382U CN 201721206110 U CN201721206110 U CN 201721206110U CN 207232382 U CN207232382 U CN 207232382U
Authority
CN
China
Prior art keywords
electric energy
module
acquisition
terminal
voltage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721206110.9U
Other languages
Chinese (zh)
Inventor
王海元
胡军华
杨茂涛
杨帅
熊德智
李恺
黄红桥
卜文彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hunan Electric Power Co Ltd
Metering Center of State Grid Hunan Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hunan Electric Power Co Ltd
Metering Center of State Grid Hunan Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hunan Electric Power Co Ltd, Metering Center of State Grid Hunan Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201721206110.9U priority Critical patent/CN207232382U/en
Application granted granted Critical
Publication of CN207232382U publication Critical patent/CN207232382U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The utility model discloses a kind of electric energy metering secondary overall operation situation on-Line Monitor Device, including main website side unit and terminal unit, main website side unit includes main website computer and metering device on-line monitoring equipment, terminal unit includes electric energy metering secondary, PT voltage acquisition modules, CT current acquisition modules, table voltage acquisition module and table current acquisition module, electric energy metering secondary includes voltage transformer pt, Current Transmit, electric energy meter and electric energy acquisition terminal, and electric energy acquisition terminal is connected with metering device on-line monitoring equipment.The utility model can save a large amount of manpower and materials costs, security risk caused by live live detection, while the secondary overall operation situation of monitoring and metering device in real time be reduced, to finding there is remarkable effect phenomena such as measurement loop and device exception and stealing in time.

Description

Electric energy metering secondary overall operation situation on-Line Monitor Device
Technical field
It the utility model is related to electrical energy measurement field, and in particular to a kind of electric energy metering secondary overall operation situation exists Line monitoring device, can supervise the operating condition of the electric energy metering device of the responsible consumer such as substation and big industrial customer online Survey.
Background technology
In recent years, with the propulsion of the power system reforms such as factory's net separation, power plant closes electric energy metering device closely Note, particularly National Development and Reform Committee, National Energy Board in 2015 formally announces《State Council of the Central Committee of the Communist Party of China is on further in-depth electric power Some opinions of system reform》Afterwards, " electricity " is more and more obvious as the market life circle of commodity, and electricity is as measurement electricity consumption/power generation Quantity directly concern the economic interests of power plant and big power consumer.The electric energy metering device device how many as metering electricity, Nowadays also increasingly paid attention to be subject to power plant, power grid enterprises and power customer.For power grid enterprises, electricity transaction is enterprise Where the economic lifeline of industry development, and metering points of electric energy quantity is more, and geographical distribution is wide, it is difficult to carry out efficient field management, The technology of economical rationality is taken to be monitored regional electric energy metering device, it is ensured that electrical energy measurement failure or stealing occur It can be found in time during phenomenon, tool is of great significance.
Power industry regulatory requirements, should all be in specific round of visits, to electric energy for all kinds of electric energy metering devices The equipment such as table, metered voltage secondary circuit voltage drop and circuit carry out live periodic inspection.On the one hand, since electrical energy measurement is counted Measure numerous, geographical distribution is wide, and it is by only carrying out that electric energy meter field, which is examined, and metered voltage secondary circuit voltage drop is also to press group Carry out, workflow is cumbersome, complicated, need to expend a large amount of manpower and materials and time;On the other hand, this kind of field test project all must Must be operated in the case of powered, during field test repeatedly, frequently operation be easy to cause the wire connection terminal production to equipment Raw damage, be easy to cause measurement loop open circuit, possesses certain security risk, careless slightly to bring larger safety hidden to system Suffer from.
Utility model content
The technical problems to be solved in the utility model:For the above problem of the prior art, there is provided one kind can save largely Manpower and materials cost, reduces security risk caused by live live detection, while the secondary overall fortune of monitoring and metering device in real time Market condition, to finding electric energy metering secondary of phenomena such as measurement loop and device exception and stealing with remarkable effect in time Overall operation situation on-Line Monitor Device.
In order to solve the above-mentioned technical problem, the technical solution adopted in the utility model is:
A kind of electric energy metering secondary overall operation situation on-Line Monitor Device, including main website side unit and at least one Terminal unit, the main website side unit include main website computer and the metering device on-line monitoring equipment being connected with each other, the terminal Unit includes electric energy metering secondary, PT voltage acquisition modules, CT current acquisition modules, table voltage acquisition module and table electric current Acquisition module, the electric energy metering secondary include voltage transformer pt, Current Transmit, electric energy meter and generated energy acquisition Terminal, the voltage transformer pt, Current Transmit, electric energy acquisition terminal are connected with electric energy meter respectively, the PT voltages Acquisition module is connected with the output terminal of voltage transformer pt, the CT current acquisition modules and the output terminal phase of Current Transmit Even, the table voltage acquisition module, table current acquisition module are connected with the table wire connection terminal of electric energy meter respectively, and the PT voltages are adopted Collect module, CT current acquisition modules, table voltage acquisition module and table current acquisition module output terminal respectively with generated energy acquisition Terminal is connected, and the electric energy acquisition terminal is connected by network with metering device on-line monitoring equipment.
Preferably, the electric energy acquisition terminal is connected by GPRS network with metering device on-line monitoring equipment.
Preferably, the metering device on-line monitoring equipment includes signal processing interface module, multichannel A/D moduluss of conversion Block, active pulse collection module, counter, dsp processor, microprocessor and communication module, the signal processing interface module, Active pulse collection module is connected with electric energy acquisition terminal respectively, and the signal processing interface module is turned by multichannel A/D Mold changing block is connected with dsp processor, and the active pulse collection module is connected by counter with dsp processor, at the DSP Reason device, be connected with each other between microprocessor, and the microprocessor is connected by communication module with main website computer.
Preferably, the communication module is RS485 serial communication modulars.
Preferably, liquid crystal display mode, key-press module and history data repository are also associated with the microprocessor.
The utility model electric energy metering secondary overall operation situation on-Line Monitor Device tool has the advantage that:
1st, the utility model includes main website side unit and at least one terminal unit, and main website side unit includes what is be connected with each other Main website computer and metering device on-line monitoring equipment, main website is placed in by the metering device on-line monitoring equipment with standard table function Side, realizes the structure of standard scale postposition, and whole electric energy metering secondary overall operation situation on-line monitoring system need to only match somebody with somebody Put a standard electric energy meter (metering device on-line monitoring equipment), you can meet regulatory requirements, while ensure standard electric energy meter Output data is accurately and reliably.Control is sent when to needing to carry out the tested electric energy meter of error-detecting by main website side unit to refer to Order, then after corresponding electric energy acquisition terminal receives instruction, the voltage of tested electric energy meter, current signal and active pulse are passed through Wireless public network is transmitted to metering device on-line monitoring equipment, and the error of checklist is calculated by metering device on-line monitoring equipment.
2nd, existing electric energy metering device secondary circuit and its on-Line Monitor Device, need to be in each substation and with per family One standard electric energy meter is installed, on the one hand significantly increases project investment, on the other hand, is installed on the standard electric energy meter at scene Need every three months to carry out a laboratory verification according to regulatory requirements, do not possess real dissemination.The utility model is for existing Electric energy metering device secondary circuit and its on-Line Monitor Device, monitor generated energy acquisition function and metering device on-line function Separation, generated energy acquisition function is realized by existing electric energy metering secondary, on the basis of existing electric energy metering secondary Upper increase PT voltage acquisition modules, CT current acquisition modules, table voltage acquisition module and table current acquisition module, then utilize master The metering device on-line monitoring equipment of side unit of standing receives the electric energy data that transmits of electric energy acquisition terminal, can be very big Ground reduces equipment cost, and has very positive dissemination, is particularly suitable for the weight such as substation and big industrial customer The operating condition of the electric energy metering device of user is wanted to be monitored on-line.
Brief description of the drawings
Fig. 1 is the structure diagram of the utility model embodiment device.
Fig. 2 is the structure diagram of the utility model embodiment metering device on-line monitoring equipment.
Marginal data:1st, main website side unit;11st, main website computer;12nd, metering device on-line monitoring equipment;121st, at signal Manage interface module;122nd, multichannel A/D modular converters;123rd, active pulse collection module;124th, counter;125th, DSP processing Device;126th, microprocessor;127th, communication module;2nd, terminal unit;21st, electric energy metering secondary;211st, electric energy meter;212nd, it is electric Energy acquisition terminal;22nd, PT voltage acquisition modules;23rd, CT current acquisition modules;24th, table voltage acquisition module;25th, table electric current Acquisition module.
Embodiment
As shown in Figure 1, the electric energy metering secondary overall operation situation on-Line Monitor Device of the present embodiment includes main website Side unit 1 and at least one terminal unit 2, main website side unit 1 includes the main website computer 11 being connected with each other and metering device is online Monitoring device 12, terminal unit 2 include electric energy metering secondary 21, PT voltage acquisition modules 22, CT current acquisition modules 23, Table voltage acquisition module 24 and table current acquisition module 25, it is mutual that electric energy metering secondary 21 includes voltage transformer pt, electric current Sensor CT, electric energy meter 211 and electric energy acquisition terminal 212, voltage transformer pt, Current Transmit, electric energy acquisition terminal 212 are connected with electric energy meter 211 respectively, and PT voltage acquisition modules 22 are connected with the output terminal of voltage transformer pt, CT current acquisitions Module 23 is connected with the output terminal of Current Transmit, table voltage acquisition module 24, table current acquisition module 25 respectively with electric energy The table wire connection terminal of table 211 is connected, PT voltage acquisition modules 22, CT current acquisition modules 23, table voltage acquisition module 24 and table The output terminal of current acquisition module 25 is connected with electric energy acquisition terminal 212 respectively, and electric energy acquisition terminal 212 passes through network It is connected with metering device on-line monitoring equipment 12.Electric energy metering secondary 21 be existing electric energy meter metering circuit, this implementation In example on the basis of electric energy metering secondary 21, in the PT terminal boxs installation PT voltage acquisition modules 22 of voltage transformer pt To gather this side measure winding secondary voltage of three-phase PT, CT current acquisition modules are installed in the CT terminal boxs of Current Transmit 23 to gather this side measure winding secondary current of three-phase CT, in 24 He of screen cabinet installation table voltage acquisition module of electric energy meter 211 Table current acquisition module 25, for gathering electric power meter end three-phase voltage and electric power meter end three-phase voltage, the voltage/current collected Data are by RS485 port transmissions to electric energy acquisition terminal 212, while the active pulse signal of electric energy meter 211 then passes through electricity Amount pulse output interface, which is exported to electric energy acquisition terminal 212, voltage, the electric current of 211 Internal Gauge of electric energy meter, passes through electric energy meter On RS485 interfaces be transmitted to electric energy acquisition terminal 212.Electric energy acquisition terminal 212 passes through the electric parameter data of reception Network transmission to main website side unit 1 metering device on-line monitoring equipment 12, metering device on-line monitoring equipment 12 to data into Row processing, obtains electric energy metering secondary overall operation situation and exports to main website computer 11.
In the present embodiment, electric energy acquisition terminal 212 is connected by GPRS network with metering device on-line monitoring equipment 12, GPRS network has the advantages that wide coverage, equipment cost are low, disclosure satisfy that the electric energy metering secondary of the present embodiment is whole The data volume and data rate requirement of running body situation on-line monitoring.
As shown in Fig. 2, metering device on-line monitoring equipment 12 includes signal processing interface module 121, multichannel A/D is changed Module 122, active pulse collection module 123, counter 124, dsp processor 125, microprocessor 126 and communication module 127, Signal processing interface module 121, active pulse collection module 123 are connected with electric energy acquisition terminal 212 respectively, and signal processing connects Mouth mold block 121 is connected by multichannel A/D modular converters 122 with dsp processor 125, and active pulse collection module 123 passes through meter Number device 124 is connected with dsp processor 125, is connected with each other between dsp processor 125, microprocessor 126, and microprocessor 126 It is connected by communication module 127 with main website computer 11.Metering device on-line monitoring equipment 12 is with arm processor+DSP data processings Unit is core, has a powerful digital processing capabilities, metering device on-line monitoring equipment 12 receive from voltage acquisition equipment, The voltage U and electric current I of current acquisition equipment output, and the active pulse of electric energy meter output, turn through Signal-regulated kinase and A/D DSP operation is sent into after parallel operation, electric energy metering device secondary circuit global error, electric energy meter kinematic error, metered voltage can be obtained Secondary circuit voltage drops.
In the present embodiment, signal processing interface module 121 specifically uses GPRS wireless communication modules, and dsp processor 125 has Body uses the dsp chip of model tms320f28335, and microprocessor 126 specifically uses ARM946E-STMProcessor.This implementation In example, communication module 127 is RS485 serial communication modulars.As shown in Fig. 2, it is also associated with liquid crystal display mode on microprocessor 126 The peripheral circuits such as formula, key-press module, history data repository, JTAG emulation interface (being omitted in figure), composition one are complete micro- Machine processing system.In the present embodiment, history data repository specifically uses massive store SD card.
Metering device on-line monitoring equipment 12 is used as DC power supply using the conversion of linear power frequency, and electrically mutual with two The DC conversion power of isolation, wherein+5V (maximum output 3A) is used as supplying digital circuits, ± 12V (maximum output 0.2A) makees Power for analog circuit.DC conversion power be used for by the 220V power supplys (L, N) of input be converted to+5V, positive and negative 12V to signal at Manage interface module 121, multichannel A/D modular converters 122, active pulse collection module 123, counter 124, dsp processor 125th, microprocessor 126, and power to RS485 serial communication modulars.The main performance of metering device on-line monitoring equipment 12 Parameter is:Input analog voltage 42~120V of scope, error≤0.2%;Input analog current 0~6A of scope, error≤ 0.2%, working power (180~260) V, 50Hz.
The standard electric energy meter examined for electric energy meter reality load error, according to power industry regulatory requirements, needs every three months Carry out a laboratory verification.Current existing correlation theory has development that standard electric energy meter is placed in scene, and to carry out metering device remote The method introduction of journey monitoring, such method need to be mounted on a standard electric energy meter, this method in each substation and user Be limited in that be difficult to be installed on scene standard electric energy meter every three months carry out a laboratory verification, can not ensure mark Quasi- electric energy meter is accurately and reliably.The present embodiment electric energy metering secondary overall operation situation on-Line Monitor Device uses standard scale Postposition method, system main website side is installed on as main website side unit using the metering device on-line monitoring equipment 12 with standard table function 1 component, whole secondary circuit overall operation situation on-line monitoring system need to only configure a metering device on-line monitoring equipment 12, metering device on-line monitoring equipment 12 has the function of standard electric energy meter, in practical application, metering device on-line monitoring is set Standby standard electric energy meter function module every three months carries out a laboratory verification, can meet regulatory requirements, while ensure standard Electric energy meter output data is accurately and reliably.The present embodiment electric energy metering secondary overall operation situation on-Line Monitor Device can be right Metering secondary global error is monitored on-line, can monitoring and metering circuit operation it is whether normal, for electric current secondary loop The abnormal conditions such as two points ground fault or voltage secondary circuit pressure drop are excessive, can find in time, reduce electricity mistake.Meanwhile for meter The excessive phenomenon of secondary circuit global error is measured, exceptional instructions can be sent in time and inform power grid and user, guarantee supplies electricity consumption both sides Economic interests.The present embodiment electric energy metering secondary overall operation situation on-Line Monitor Device can be in some province or area A wide range of installation, monitors the electric energy metering device operating status and error of substation in area or large user on-line.Tool Body embodiment is:Electric energy acquisition terminal stores the voltage of collection, electric current and active pulse data, and monitoring main website needs When gathering the metering device running state data of wherein some stoichiometric point, data test introduction is sent by main website, via metering Device on-line monitoring equipment carries out data to the corresponding electric energy acquisition terminal of the stoichiometric point and calls survey together, and electric energy acquisition terminal should Voltage, electric current and the active burst data transfers of stoichiometric point are to metering device on-line monitoring equipment, and on-line monitoring equipment is to data Handled to obtain the information such as error and secondary voltage drop and be transmitted to main website, main station system judges metering by preset threshold value Whether device operation is normal, and sends corresponding condition indicative signal and inform administrative staff.
The present embodiment electric energy metering secondary overall operation situation on-Line Monitor Device can be realized to electric energy metering device Secondary circuit electric information carries out long-range monitoring function, obtains metering device and secondary circuit real time execution situation, can be to area The electric energy metering device of interior all substations and large user realize electric energy metering device secondary circuit global error, electric energy meter operation The on-line monitoring of the parameter such as error, metered voltage secondary circuit voltage drop, and then to the real-time running state of electric energy metering device Remotely monitor and judge.The application process of the present embodiment electric energy metering secondary overall operation situation on-Line Monitor Device Implementation steps include:
1) the main website computer 11 of main website side unit 1 passes through metering device on-line monitoring equipment 12 and each terminal unit 2 Electric energy acquisition terminal 212 to gather this side of the voltage transformer of voltage transformer pt in each terminal unit 2 respectively secondary Voltage uben, the current transformer of Current Transmit this side secondary current iben, electric energy meter 211 table side secondary voltage ubiao, electric energy meter 211 table side secondary current ibiaoAnd the active pulse that the unit interval T inside counting device of electric energy meter 211 obtains Quantity N;
2) it is based on this side of voltage transformer secondary voltage uben, this side of current transformer secondary current iben, table side two Secondary voltage ubiao, table side secondary current ibiaoAnd the active number of pulses N that unit interval T inside counting device obtains carries out electric energy meter Amount monitoring data are calculated and exported;The electrical energy measurement monitoring data include this side active-power P of mutual inductorben, electric energy table side Active-power Pbiao, electric energy meter active-power P itself0, secondary circuit overall operation error η1, electric energy meter kinematic error η2, voltage At least one of transformer secondary circuit voltage drop e.
In the present embodiment, this side active-power P of mutual inductor in step 2)benCalculating function expression such as formula (1) institute Show, electric energy table side active-power PbiaoCalculating function expression such as formula (2) shown in, electric energy meter active-power P itself0Calculating Shown in function expression such as formula (3);
In formula (1)~formula (3), uben(i) it is this side of voltage transformer secondary voltage ubenSampling window M in i-th A voltage sample value, iben(i) it is this side of current transformer secondary current ibenSampling window M in i-th of current sample Value, M are sampling window size, and N is the active number of pulses that unit time T inside countings device obtains, and C is normal for the active pulse of electric energy meter Number.
In the present embodiment, secondary circuit overall operation error η in step 2)1Calculating function expression such as formula (4) shown in, Electric energy meter kinematic error η2Calculating function expression such as formula (5) shown in;
In formula (4) and formula (5), PbenFor this side active power of mutual inductor, PbiaoFor electric energy table side active power, P0For electricity Can table active power itself.
In the present embodiment, calculating function expression such as formula (6) institute of Voltage Transformer Secondary Circuit Voltage Drop e in step 2) Show;
In formula (6), ubenFor this side secondary voltage of voltage transformer, ubiaoFor table side secondary voltage, δ is secondary circuit Voltage drop angular difference component,The power-factor angle of load is measured for electric energy meter.
In the present embodiment, shown in the calculating function expression such as formula (7) of secondary circuit voltage drop angular difference component δ, electric energy meter Measure the power-factor angle of loadCalculating function expression such as formula (8) shown in;
The π Δs t (7) of δ=2
In formula (7) and formula (8), Δ t is this side of voltage transformer secondary voltage uben, table side secondary voltage ubiaoBetween Adjacent zero crossing time difference, Δ t1 are table side secondary voltage ubiao, table side secondary current ibiaoBetween the adjacent zero crossing time difference.
In addition, the application process of the present embodiment electric energy metering secondary overall operation situation on-Line Monitor Device can also root According to the voltage difference and phase difference for needing to calculate metered voltage secondary circuit head and the tail both ends, when error exceeds regulatory requirements, then Alarm signal is sent by main website computer 11, to remind operating personnel to pay attention to.
The above is only the preferred embodiment of the utility model, and the scope of protection of the utility model is not limited merely to Above-described embodiment, all technical solutions belonged under the utility model thinking belong to the scope of protection of the utility model.It should refer to Go out, for those skilled in the art, some improvement under the premise of the utility model principle is not departed from and Retouching, these improvements and modifications also should be regarded as the scope of protection of the utility model.

Claims (5)

  1. A kind of 1. electric energy metering secondary overall operation situation on-Line Monitor Device, it is characterised in that:Including main website side unit (1) and at least one terminal unit (2), the main website side unit (1) include the main website computer (11) being connected with each other and metering dress On-line monitoring equipment (12) is put, the terminal unit (2) includes electric energy metering secondary (21), PT voltage acquisition modules (22), CT current acquisition modules (23), table voltage acquisition module (24) and table current acquisition module (25), the electrical energy measurement two Minor loop (21) includes voltage transformer pt, Current Transmit, electric energy meter (211) and electric energy acquisition terminal (212), described Voltage transformer pt, Current Transmit, electric energy acquisition terminal (212) are connected with electric energy meter (211) respectively, the PT voltages Acquisition module (22) is connected with the output terminal of voltage transformer pt, the CT current acquisition modules (23) and Current Transmit Output terminal is connected, the table wiring with electric energy meter (211) respectively of the table voltage acquisition module (24), table current acquisition module (25) Terminal is connected, the PT voltage acquisition modules (22), CT current acquisition modules (23), table voltage acquisition module (24) and table electric current The output terminal of acquisition module (25) is connected with electric energy acquisition terminal (212) respectively, and the electric energy acquisition terminal (212) is logical Network is crossed with metering device on-line monitoring equipment (12) to be connected.
  2. 2. electric energy metering secondary overall operation situation on-Line Monitor Device according to claim 1, it is characterised in that: The electric energy acquisition terminal (212) is connected by GPRS network with metering device on-line monitoring equipment (12).
  3. 3. electric energy metering secondary overall operation situation on-Line Monitor Device according to claim 2, it is characterised in that: The metering device on-line monitoring equipment (12) include signal processing interface module (121), multichannel A/D modular converters (122), Active pulse collection module (123), counter (124), dsp processor (125), microprocessor (126) and communication module (127), the signal processing interface module (121), active pulse collection module (123) respectively with electric energy acquisition terminal (212) it is connected, the signal processing interface module (121) passes through multichannel A/D modular converters (122) and dsp processor (125) It is connected, the active pulse collection module (123) is connected by counter (124) with dsp processor (125), the DSP processing Device (125), microprocessor are connected with each other between (126), and the microprocessor (126) passes through communication module (127) and main website Computer (11) is connected.
  4. 4. electric energy metering secondary overall operation situation on-Line Monitor Device according to claim 3, it is characterised in that: The communication module (127) is RS485 serial communication modulars.
  5. 5. electric energy metering secondary overall operation situation on-Line Monitor Device according to claim 3, it is characterised in that: Liquid crystal display mode, key-press module and history data repository are also associated with the microprocessor (126).
CN201721206110.9U 2017-09-20 2017-09-20 Electric energy metering secondary overall operation situation on-Line Monitor Device Active CN207232382U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721206110.9U CN207232382U (en) 2017-09-20 2017-09-20 Electric energy metering secondary overall operation situation on-Line Monitor Device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721206110.9U CN207232382U (en) 2017-09-20 2017-09-20 Electric energy metering secondary overall operation situation on-Line Monitor Device

Publications (1)

Publication Number Publication Date
CN207232382U true CN207232382U (en) 2018-04-13

Family

ID=61863146

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721206110.9U Active CN207232382U (en) 2017-09-20 2017-09-20 Electric energy metering secondary overall operation situation on-Line Monitor Device

Country Status (1)

Country Link
CN (1) CN207232382U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110456146A (en) * 2019-09-04 2019-11-15 深圳宝龙达信创科技股份有限公司 Power detection device and power detecting method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110456146A (en) * 2019-09-04 2019-11-15 深圳宝龙达信创科技股份有限公司 Power detection device and power detecting method

Similar Documents

Publication Publication Date Title
CN107462864A (en) Electric energy metering secondary overall operation situation on-Line Monitor Device and application process
CN102621516B (en) Electric energy meter operational abnormity judging method based on large-scale data application background
CN201732120U (en) Power consumption information collecting and monitoring system in base station
CN104635198B (en) Remote monitoring and diagnosing method for electric energy metering device with timely fault finding function
CN104165660B (en) A kind of distribution transforming intelligent monitoring terminal calculating winding temperature
CN108521172A (en) A kind of wisdom formula safety utilization of electric power hidden danger cloud supervisory systems
CN104678348A (en) Remote monitoring and diagnosing method for electric energy metering device with high efficiency
CN107832946A (en) A kind of power energy monitoring and controlling for workshop and management method and system
CN103439546A (en) Electric energy measuring system and method for low-voltage user photovoltaic power generation
CN104714206B (en) Remote monitoring and diagnosing method for electric energy metering device capable of finding faults timely
CN110736957B (en) Online detection system and method for electric energy metering device based on clock synchronization
CN107748283A (en) A kind of micro energy lose electric energy meter metered voltage current monitoring alarm device and its monitoring method
CN204719225U (en) A kind of Watthour meter remote monitors check system automatically
CN104655926B (en) A kind of built-in terminal and its monitoring method that can monitor power information and electricity charge data
CN202475013U (en) Intelligent power distribution device
CN207232382U (en) Electric energy metering secondary overall operation situation on-Line Monitor Device
CN203479855U (en) Photovoltaic generating electric energy metering system for low-voltage users
CN203350356U (en) High-voltage user photovoltaic power generation energy metering system
CN104656050B (en) Manpower-saving remote monitoring and diagnosing method for electric energy metering device
CN104614700B (en) Remote monitoring and diagnosing method for electric energy metering device with good real-time performance
CN201434887Y (en) On-line monitoring unit for secondary loop voltage drop
CN104656052B (en) Remote monitoring and diagnosing method for loss-reducing and efficiency-improving electric energy metering device
CN104656051B (en) Remote monitoring and diagnosing method for electric energy metering device with good real-time performance
CN102645581A (en) Low-tension electricity metering device
CN202524168U (en) Power quality data monitoring device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant