CN207231256U - A kind of high aluminium melting furnace of hot melt - Google Patents

A kind of high aluminium melting furnace of hot melt Download PDF

Info

Publication number
CN207231256U
CN207231256U CN201721269874.2U CN201721269874U CN207231256U CN 207231256 U CN207231256 U CN 207231256U CN 201721269874 U CN201721269874 U CN 201721269874U CN 207231256 U CN207231256 U CN 207231256U
Authority
CN
China
Prior art keywords
melting furnace
furnace body
combustion chamber
aluminum melting
aluminum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721269874.2U
Other languages
Chinese (zh)
Inventor
尹庆炜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hantman Light Metal Casting (tianjin) Co Ltd
Original Assignee
Hantman Light Metal Casting (tianjin) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hantman Light Metal Casting (tianjin) Co Ltd filed Critical Hantman Light Metal Casting (tianjin) Co Ltd
Priority to CN201721269874.2U priority Critical patent/CN207231256U/en
Application granted granted Critical
Publication of CN207231256U publication Critical patent/CN207231256U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of high aluminium melting furnace of hot melt, including the first combustion chamber, aluminum melting furnace body and the second combustion chamber, first combustion chamber is arranged at the top of aluminum melting furnace body one side, first bottom of combustion chamber extends the first hot blast pipe, first gas valve is installed on the first hot blast pipe, the first combustor side face is provided with the first air hose, extend the first burner close to the one side of aluminum melting furnace body in the first combustion chamber, the aluminum melting furnace body top end face is provided with flue gas recirculation pipe, second combustion chamber is arranged at the bottom of aluminum melting furnace body another side, second top of combustion chamber extends the second hot blast pipe, second gas valve is installed on the second hot blast pipe, second combustor side face is provided with the second air hose, extend the second burner close to the one side of aluminum melting furnace body in the second combustion chamber.The utility model, integrates preheating, heat recovery and insulation and avoids heat dissipation, can effectively improve hot melt.

Description

A kind of high aluminium melting furnace of hot melt
Technical field
Aluminium melting furnace equipment technical field is the utility model is related to, is specially a kind of high aluminium melting furnace of hot melt.
Background technology
Aluminium stove is a kind of novel high-efficiency and energy-saving stove developed according to aluminium smelting technology, it can meet aluminium smelter well In skill:Alloy composition requirement is tight, and production is discontinuous, and larger wait of single heat size requires, and has reached reduction consumption, has reduced scaling loss, carry High yield quality, reduces labor intensity, the effect of improving working conditions and improve production efficiency, suitable for batch operation, coordinates Melting more than gold and foundry returns.
It is several that aluminium melting furnace according to combustion system is segmented into biomass fuel type, gas-fuelled models and electromagnetic heating type, presses It can be divided into according to shape square, circular etc., burner formula, pre-heating heat accumulation type are segmented into according to working method, from going out for burner formula Hair, its principle are that the aluminium blocks such as the aluminium ingot inside aluminium melting furnace are carried out heating burning to reach molten using indoor high temperature burner of burning The purpose of aluminium, in existing aluminum melting furnace apparatus, hot melt rate does not reach maximization, so, if it is possible to improve aluminium melting furnace Hot melt, can reach more efficient, resource more saves and more environmentally-friendly purpose.
Utility model content
The purpose of this utility model is to provide a kind of high aluminium melting furnace of hot melt, possess flue gas recirculation heating, aluminum melting Furnace body heat conduction from outside to inside solves so as to carry out the advantages of just section burning of insulation and combustion chamber preheats aluminum melting furnace body Traditional aluminium melting furnace is relatively low using heat energy efficiency, has only done fume afterheat circulation, improves the problem of hot melt means are single.
To achieve the above object, the utility model provides following technical solution:A kind of high aluminium melting furnace of hot melt, including First combustion chamber, aluminum melting furnace body and the second combustion chamber, first combustion chamber are arranged at the top of aluminum melting furnace body one side, the One bottom of combustion chamber extends the first hot blast pipe, and the first hot blast pipe extends to aluminium melting furnace body interior and connects the first preheating Manage, first gas valve is installed on the first hot blast pipe, the first combustor side face is provided with the first air hose, the first air Pressure fan is installed, the first burner is extended in the first combustion chamber close to the one side of aluminum melting furnace body, and the first burner prolongs on pipe Aluminium melting furnace body interior is extended, the aluminum melting furnace body is double layer design, and internal layer is stove inner casing, stove made of stainless steel material Insulating layer is provided with gap between inner casing and aluminium melting furnace body housing, the aluminum melting furnace body top end face is provided with flue gas and follows Endless tube, and flue gas recirculation pipe is extended in insulating layer, fixation is close by flue gas ash screen, flue gas recirculation pipe inside flue gas recirculation pipe Its bottom position is provided with air-introduced machine, and second combustion chamber is arranged at the bottom of aluminum melting furnace body another side, the second combustion Burn ceiling portion and extend the second hot blast pipe, and the second hot blast pipe extends to aluminium melting furnace body interior and connects the second economizer bank, the Second gas valve is installed on two hot blast pipes, the second combustor side face is provided with the second air hose, and on the second air hose Pressure fan is installed, the second burner is extended in the second combustion chamber close to the one side of aluminum melting furnace body, and the second burner extends to Aluminium melting furnace body interior.
Preferably, the insulating layer forms for carborundum and the filling of steel scrap.
Preferably, one layer of carbofrax material is coated with the aluminium melting furnace inner body wall.
Preferably, filler door, the seam between filler door and aluminum melting furnace body are hinged with the aluminum melting furnace body front surface Metallic gasket is provided with gap.
Preferably, the aluminium melting furnace body bottom portion centre position offers molten aluminum mouth, and molten aluminum mouth connection rest chamber into Liquid pipe.
Preferably, second economizer bank and the first economizer bank are in the opposed setting of aluminium melting furnace body interior, and second is pre- Heat pipe and the first preheating pipe surface are all evenly arranged with through hole.
Preferably, first combustion chamber is consistent with the second combustion chamber surface structure, and the first combustion chamber and the second burning Ceiling portion is both provided with fuel hopper, and fuel hopper is supporting is provided with metallic sealed cover.
Compared with prior art, the beneficial effects of the utility model are as follows:
1st, the utility model is by setting flue gas recirculation pipe, it is possible to achieve what the waste heat in flue gas can be recycled Effect, and set flue gas ash screen tentatively to be filtered to the dust in flue gas in flue gas recirculation pipe, it helps after Continuous fume centralized discharge.
2nd, the utility model is provided with the first combustion chamber and the second combustion chamber is heated at high temperature from upper and lower two diagonal angles Burning, can accelerate the aluminium ingot burn-off rate in aluminium melting furnace.
3rd, the utility model is provided with the first hot blast pipe and the second hot blast pipe can be when starting aluminum melting work by two combustions The hot wind for burning room is delivered in aluminum melting furnace body, be have also been made the pre-heat treatment equivalent to aluminium melting furnace body interior, can be reached molten The effect of aluminium furnace body quick heat-collector.
4th, the utility model is provided with aluminium melting furnace body outer wall, insulating layer and stove inner casing, and the thermal conductivity of material used Step up from the inside to the outside, can effectively avoid the heat of aluminium melting furnace body outer wall from being all dispersed among air, can subtract Few heat distributes.
Brief description of the drawings
Fig. 1 is the overall structure diagram of the utility model;
Fig. 2 is the aluminum melting furnace body outside drawing of the utility model;
Fig. 3 is the first combustion chamber outside drawing of the utility model.
In figure:1- molten aluminum mouths;The first economizer banks of 2-;3- first gas valves;The first hot blast pipes of 4-;5- pressure fan;6- first Air hose;The first combustion chambers of 7-;The first burners of 8-;9- aluminum melting furnace bodies;10- flue gas ash screens;11- flue gas recirculation pipes;12- draws Wind turbine;The second economizer banks of 13-;14- second gas valves;The second hot blast pipes of 15-;The second burners of 16-;The second air hoses of 17-;18- Second combustion chamber;19- stove inner casings;20- metallic gaskets;21- filler doors;22- insulating layers;23- metallic sealed covers;24- fuel Bucket.
Embodiment
The following is a combination of the drawings in the embodiments of the present utility model, and the technical scheme in the embodiment of the utility model is carried out Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are without making creative work All other embodiments obtained, shall fall within the protection scope of the present invention.
Please refer to Fig.1 to 3, a kind of embodiment provided by the utility model:A kind of high aluminium melting furnace of hot melt, including the One combustion chamber 7,9 and second combustion chamber 18 of aluminum melting furnace body, the first combustion chamber 7 are arranged at the top of 9 one side of aluminum melting furnace body, the The first hot blast pipe 4 is extended in one combustion chamber, 7 bottom, and the first hot blast pipe 4 extends to the inside of aluminum melting furnace body 9 and connection first is pre- Heat pipe 2, the first hot blast pipe 4 play start the hot wind in the first combustion chamber 7 is delivered to first during burning in the first combustion chamber 7 it is pre- In heat pipe 2, and it is discharged into by the first economizer bank 2 inside aluminum melting furnace body 9, plays the role of preheating aluminum melting furnace body 9, the first hot wind First gas valve 3 is installed, first gas valve 3 plays the role of control, the first combustion chamber 7 in hot wind course of conveying on pipe 4 One side is provided with the first air hose 6, and pressure fan 5 is provided with the first air hose 6, and pressure fan 5 plays the sky of accelerated combustion Gas enters the effect of the first combustion chamber 7 by the first air hose 6, and the first combustion chamber 7 extends close to the one side of aluminum melting furnace body 9 Go out the first burner 8, and the first burner 8 is extended to inside aluminum melting furnace body 9, the first burner 8 plays the role of combustion heating aluminium ingot, Aluminum melting furnace body 9 is double layer design, and internal layer is stove inner casing 19 made of stainless steel material, stove inner casing 19 and aluminum melting furnace body 9 Insulating layer 22 is provided with gap between shell, insulating layer 22 forms for carborundum and the filling of steel scrap, aluminum melting furnace body 9 Be coated with one layer of carbofrax material on inner wall, the heat conductivility of 9 shell of aluminum melting furnace body, insulating layer 22 and stove inner casing 19 progressively under Drop so that 9 shell of aluminum melting furnace body when with heat exchange with outside also can heat conduction to stove inner casing 19 get on, while also so that stove inner casing Heat transfer on 19 can play insulation effect, 9 top end face of aluminum melting furnace body to relatively fewer on 9 shell of aluminum melting furnace body Flue gas recirculation pipe 11 is provided with, and flue gas recirculation pipe 11 is extended in insulating layer 22, the inside of flue gas recirculation pipe 11 is fixed by flue gas Ash screen 10, flue gas recirculation pipe 11 are provided with air-introduced machine 12 close to its bottom position, and flue gas recirculation pipe 11 is substantially carried out flue gas The effect of circulation so that the heat carried secretly in flue gas can be reentered in insulating layer 22, play the role of residual heat collection, flue gas Ash screen 10 can carry out preliminary leaching to flue gas and work, and air-introduced machine 12 plays the role of accelerating flue gas recirculation, aluminium melting furnace sheet Filler door 21 is hinged with 9 front surface of body, metallic gasket is provided with the gap between filler door 21 and aluminum melting furnace body 9 20,9 bottom centre position of aluminum melting furnace body offers molten aluminum mouth 1, and molten aluminum mouth 1 connects the inlet tube of rest chamber, and molten aluminum mouth 1 makes The molten aluminum that must be melted, which enters in rest chamber, to be stood, and helps to improve the quality of molten aluminum, the second combustion chamber 18 is arranged on aluminum melting At 9 another side bottom of furnace body, the second hot blast pipe 15 is extended at the top of the second combustion chamber 18, and the second hot blast pipe 15 extends to The inside of aluminum melting furnace body 9 simultaneously connects the second economizer bank 13, and the second economizer bank 13 and the first economizer bank 2 are inside aluminum melting furnace body 9 Opposed setting, and the second economizer bank 13 and 2 surface of the first economizer bank are all evenly arranged with through hole, are installed on the second hot blast pipe 15 There is second gas valve 14,18 one side of the second combustion chamber is provided with the second air hose 17, and is also provided with the second air hose 17 Pressure fan 5, the second burner 16 is extended in the second combustion chamber 18 close to the one side of aluminum melting furnace body 9, and the second burner 16 extends To aluminum melting furnace body 9, the second economizer bank 13, second gas valve 14, the second hot blast pipe 15, the second burner 16 and the second air Pipe 17 play it is above-mentioned in the first economizer bank 2, first gas valve 3,7 class of the first hot blast pipe 4, the first burner 8 and the first air hose As effect, can achieve the purpose that the first combustion chamber 7 and the second combustion chamber about 18 fully heating burning, the first combustion chamber 7 It is consistent with 18 surface structure of the second combustion chamber, and the first combustion chamber 7 and the top of the second combustion chamber 18 are both provided with fuel hopper 24, and Fuel hopper 24 is supporting to be provided with metallic sealed cover 23.
Specifically used mode:In utility model works, by fuel hopper 24 to the first combustion chamber 7 and the second combustion chamber 18 Middle addition biomass dyestuff, opens first gas valve 3 and second gas valve 14, opens filler door 21 and adds the aluminum feedstocks such as aluminium ingot Inside aluminum melting furnace body 9, start work of burning, the first combustion chamber 7 and 18 internal temperature of the second combustion chamber start to raise, and first burns 8 and second burner 16 of mouth starts to be internally heated burning work to aluminum melting furnace body 9, in the first combustion chamber 7 and the second burning While burning, the gas needed for 5 accelerated combustion of pressure fan enters first from the first air hose 6 and the second air hose 17 for room 18 In 7 and second combustion chamber 18 of combustion chamber, 9 internal-combustion of aluminum melting furnace body produce flue gas by flue gas recirculation pipe 11 again into Enter in the insulating layer 22 in aluminum melting furnace body 9, carry out the work of heat recovery, in combustion, in aluminum melting furnace body 9 Heat from the inside to the outside successively pass through stove inner casing 19, insulating layer 22 and aluminum melting furnace body 9 shell, due to stove inner casing 19, insulation The difference using material of layer 22 and aluminum melting furnace body 9, the heat conductivility of three progressively declines, so insulating layer 22 can be with Effective to carry out heat insulation work, the molten aluminum of hot melt molding is escaped and enter in rest chamber by molten aluminum mouth 1.
It is obvious to a person skilled in the art that the utility model is not limited to the details of above-mentioned one exemplary embodiment, and And in the case of the spirit or essential attributes without departing substantially from the utility model, it can realize that this practicality is new in other specific forms Type.Therefore, in all respects, the present embodiments are to be considered as illustrative and not restrictive, this practicality is new The scope of type is indicated by the appended claims rather than the foregoing description, it is intended that the equivalency fallen in claim is contained All changes in justice and scope are embraced therein.Any reference numeral in claim should not be considered as limitation Involved claim.

Claims (7)

1. a kind of high aluminium melting furnace of hot melt, including the first combustion chamber (7), aluminum melting furnace body (9) and the second combustion chamber (18), It is characterized in that:First combustion chamber (7) is arranged at the top of aluminum melting furnace body (9) one side, and the first combustion chamber (7) bottom is prolonged The first hot blast pipe (4) is stretched out, and the first hot blast pipe (4) extends to aluminum melting furnace body (9) inside and connects the first economizer bank (2), First gas valve (3) is installed, the first combustion chamber (7) one side is provided with the first air hose on the first hot blast pipe (4) (6), pressure fan (5) is installed, the first combustion chamber (7) extend close to the one side of aluminum melting furnace body (9) on the first air hose (6) Go out the first burner (8), and the first burner (8) extends to aluminum melting furnace body (9) inside, the aluminum melting furnace body (9) sets for bilayer Meter, and internal layer is stove inner casing (19) made of stainless steel material, the gap between stove inner casing (19) and aluminum melting furnace body (9) shell In be provided with insulating layer (22), aluminum melting furnace body (9) top end face is provided with flue gas recirculation pipe (11), and flue gas recirculation pipe (11) extend in insulating layer (22), it is fixed by flue gas ash screen (10), flue gas recirculation pipe (11) inside flue gas recirculation pipe (11) Air-introduced machine (12) is installed close to its bottom position, second combustion chamber (18) is arranged on aluminum melting furnace body (9) opposite side At the bottom of face, extend the second hot blast pipe (15) at the top of the second combustion chamber (18), and the second hot blast pipe (15) extends to aluminium melting furnace Body (9) is internal and connects the second economizer bank (13), and second gas valve (14), the second burning are provided with the second hot blast pipe (15) Room (18) one side is provided with the second air hose (17), and pressure fan (5) is also provided with the second air hose (17), the second burning The second burner (16) is extended in room (18) close to the one side of aluminum melting furnace body (9), and the second burner (16) extends to aluminium melting furnace Body (9) is internal.
A kind of 2. high aluminium melting furnace of hot melt according to claim 1, it is characterised in that:The insulating layer (22) is carbon SiClx and the filling of steel scrap form.
A kind of 3. high aluminium melting furnace of hot melt according to claim 1, it is characterised in that:The aluminum melting furnace body (9) One layer of carbofrax material is coated with inner wall.
A kind of 4. high aluminium melting furnace of hot melt according to claim 1, it is characterised in that:The aluminum melting furnace body (9) Filler door (21) is hinged with front surface, metal sealing is provided with the gap between filler door (21) and aluminum melting furnace body (9) Pad (20).
A kind of 5. high aluminium melting furnace of hot melt according to claim 1, it is characterised in that:The aluminum melting furnace body (9) Bottom centre position offers molten aluminum mouth (1), and the inlet tube of molten aluminum mouth (1) connection rest chamber.
A kind of 6. high aluminium melting furnace of hot melt according to claim 1, it is characterised in that:Second economizer bank (13) The opposed setting inside aluminum melting furnace body (9) with the first economizer bank (2), and the second economizer bank (13) and the first economizer bank (2) Surface is all evenly arranged with through hole.
A kind of 7. high aluminium melting furnace of hot melt according to claim 1, it is characterised in that:First combustion chamber (7) It is consistent with the second combustion chamber (18) surface structure, and it is both provided with fuel at the top of the first combustion chamber (7) and the second combustion chamber (18) Struggle against (24), and fuel hopper (24) is supporting is provided with metallic sealed cover (23).
CN201721269874.2U 2017-09-29 2017-09-29 A kind of high aluminium melting furnace of hot melt Expired - Fee Related CN207231256U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721269874.2U CN207231256U (en) 2017-09-29 2017-09-29 A kind of high aluminium melting furnace of hot melt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721269874.2U CN207231256U (en) 2017-09-29 2017-09-29 A kind of high aluminium melting furnace of hot melt

Publications (1)

Publication Number Publication Date
CN207231256U true CN207231256U (en) 2018-04-13

Family

ID=61850971

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721269874.2U Expired - Fee Related CN207231256U (en) 2017-09-29 2017-09-29 A kind of high aluminium melting furnace of hot melt

Country Status (1)

Country Link
CN (1) CN207231256U (en)

Similar Documents

Publication Publication Date Title
CN106766891A (en) A kind of aluminium melting furnace burning and EGR
CN206583290U (en) A kind of aluminium melting furnace burning and EGR
CN209021229U (en) A kind of vertical ladle baking facility
CN101457305B (en) Double-burning and double thermal heat storing type energy-saving high efficiency furnace and tank integrated reducing furnace system
CN206146182U (en) Energy -saving aluminum alloy melting device
CN207231256U (en) A kind of high aluminium melting furnace of hot melt
CN105858649B (en) Graphite high temperature puffing stove
CN102676849A (en) Reduction tank and magnesium reduction furnace
CN208733163U (en) A kind of annealing furnace exhaust uptake of the flat cold-rolled sheet with air preheat function
CN106766890A (en) A kind of new-type burning of aluminium melting furnace and the circulatory system
CN106225479A (en) A kind of heating rate has the smelting equipment of waste gas purification function soon
CN206930159U (en) A kind of heat accumulating type crucible furnace
CN204346098U (en) Energy-saving living beings melt aluminium stove
CN209470357U (en) Novel coil forced circulation skid hot-water boiler
CN209524751U (en) A kind of novel energy-saving environment-friendly aluminum melting equipment
CN207702506U (en) Small-sized air heating furnace deashing device
CN208238578U (en) Cupola furnace residual heat using device
CN103017330B (en) Airtight automatic-oxygen-supply, twinbridge-smoke and smoke-drum energy-saving hot blast stove
CN207372467U (en) A kind of energy-saving gas soldering oven
CN207402080U (en) A kind of magnesium alloy gas furnace
CN201363890Y (en) Horizontal boiler
CN206338935U (en) Top blast bottom ignition boiler
CN205505708U (en) Energy -saving pair of segmentation tunnel cave with ventilation cooling device
CN206160478U (en) Double -hearth violently manages shell and tube high -efficiency biological matter hot -blast furnace
CN212123674U (en) Baking device for producing air brick

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180413

CF01 Termination of patent right due to non-payment of annual fee