CN207213651U - A kind of high-pressure natural gas long distance pipeline hydrate inhibitor fills skid-mounted unit - Google Patents

A kind of high-pressure natural gas long distance pipeline hydrate inhibitor fills skid-mounted unit Download PDF

Info

Publication number
CN207213651U
CN207213651U CN201721193843.3U CN201721193843U CN207213651U CN 207213651 U CN207213651 U CN 207213651U CN 201721193843 U CN201721193843 U CN 201721193843U CN 207213651 U CN207213651 U CN 207213651U
Authority
CN
China
Prior art keywords
pipeline
storage tank
pump
dispenser pump
long distance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721193843.3U
Other languages
Chinese (zh)
Inventor
王雁冰
曹建国
丁宁
李积明
艾国
吴瑶晗
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Chemical Corp
China Oil and Gas Pipeline Network Corp
National Pipeline Network Group Sichuan to East Natural Gas Pipeline Co Ltd
Original Assignee
Sinopec Sichuan East Gas Pipeline Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinopec Sichuan East Gas Pipeline Co Ltd filed Critical Sinopec Sichuan East Gas Pipeline Co Ltd
Priority to CN201721193843.3U priority Critical patent/CN207213651U/en
Application granted granted Critical
Publication of CN207213651U publication Critical patent/CN207213651U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

It the utility model is related to a kind of high-pressure natural gas long distance pipeline hydrate inhibitor filling skid-mounted unit, including the storage tank for laying in inhibitor, the dispenser pump of two a preparation and a use and control cabinet and integrated sledge dress, tank bottom is connected by pipeline and the inlet communication of dispenser pump, the outlet of dispenser pump by pipeline with natural-gas transfer pipeline;Storage tank is provided with liquid level gauge, and storage tank connects with inhibitor feeding line, and inhibitor feeding line is provided with dosing pump;Each dispenser pump is provided with flow calibrator and the buffer for steadily filling pump discharge, and dispenser pump is connected with flow calibrator and buffer respectively by pipeline, and electric cabinet electrically connects respectively at dosing pump and dispenser pump.The beneficial effects of the utility model are that each part sledge dressization is integrated, compact-sized, are occupied little space, and installation and debugging are convenient, service life length, efficiency high, securely and reliably.

Description

A kind of high-pressure natural gas long distance pipeline hydrate inhibitor fills skid-mounted unit
Technical field
It the utility model is related to a kind of anti-frozen block note alcohol device, more particularly to a kind of high-pressure natural gas long distance pipeline hydrate Inhibitor fills skid-mounted unit.
Background technology
The natural gas gone out from exploitation of oil-gas field inevitably carries stratum water, general Long-distance Transmission Pipeline source of the gas water Dew point index is up to standard.But because pipeline is low-lying, the special pipeline section such as big that rises and falls causes the remaining of aqueous water so that pipeline gas water Dew point value is higher or occupy zone of saturation.Concentrating conveying on natural gas during the broiling summer influences not being very big, but in the winter time It is particularly in production in the case of pole cold air time, will form gas hydrates in the pipeline section that partly cannot get ground temperature protection causes Ice blocks up, or in the presence of the pipeline section to throttle, can also form hydrate, not only influence the normal conveying of natural gas, serious meeting is blocked up Dead pipeline, and the potential safety hazard such as cause to build the pressure.
For this above-mentioned present situation, solved at present using the method that hydrate inhibitor is injected to pipeline.Defect is filling It is cumbersome, and the adding amount of the inhibitor of filling can not effectively be controlled.
Utility model content
Technical problem to be solved in the utility model is to provide a kind of high-pressure natural gas long distance pipeline hydrate inhibitor Skid-mounted unit is filled, simple in construction, installation and debugging are convenient, can regulate and control the adding amount of inhibitor, efficiency high, securely and reliably.
The technical scheme that the utility model solves above-mentioned technical problem is as follows
A kind of high-pressure natural gas long distance pipeline hydrate inhibitor fills skid-mounted unit, including for laying in the storage of inhibitor Tank, the dispenser pump of two a preparation and a use and control cabinet and integrated sledge dress, the tank bottom pass through pipeline and the dispenser pump Inlet communication, the outlet of the dispenser pump is connected by pipeline with natural-gas transfer pipeline;The storage tank, which is provided with, to be used to survey The liquid level gauge of inhibitor amount of storage in the storage tank is measured, storage tank connects with inhibitor feeding line, is set on inhibitor feeding line There is dosing pump;Each dispenser pump is provided with flow calibrator and the buffer for the steady filling pump discharge, described Dispenser pump is connected with the flow calibrator and buffer respectively by the pipeline, and the electric cabinet is respectively at the dosing pump Connected with dispenser pump.
The beneficial effects of the utility model are:Using two dispenser pumps of a preparation and a use, reliable, the efficiency high of filling, The service life of equipment is also extended simultaneously.Further, dispenser pump is additionally provided with flow calibrator, can adjust the adding amount of inhibitor, Realize the adjustable controllable of adding amount.In addition, storage tank, dispenser pump and control cabinet integrate sledge dress, structure is tightly raised, space-consuming Small, installation and debugging are convenient, securely and reliably.
On the basis of above-mentioned technical proposal, the utility model can also do following improvement.
Further, the dispenser pump uses plunger pump, and each plunger pump discharge is adjustable.
Use it is above-mentioned further scheme beneficial effect be the dispenser pump used for plunger pump, it is simple in construction, can bear compared with Big pressure, reliable, cost is relatively low.
Further, the top of the storage tank is provided with the fire-retardant breather valve for adjusting the tank inner pressure, the storage tank tank body It is additionally provided with thermometer.
Beneficial effect using above-mentioned further scheme is the real time temperature that thermometer can measure tank inside;Use Fire-retardant breather valve has drainage function, can adjust the pressure of tank inside, plays a part of protection to storage tank.
Further, the bottom of the storage tank is connected with blowdown tank, and the blowdown tank is used to store discharge in the storage tank Dirt.
Beneficial effect using above-mentioned further scheme is that the dirt in storage tank is collected using blowdown tank, in order to avoid directly discharge Pollute environment.
Further, the pipeline between the storage tank and the dispenser pump is provided with filter.
Beneficial effect using above-mentioned further scheme is that the inhibitor of filling is filtered using filter, prevents it In impurity blocking pipeline, damage dispenser pump.
Further, in addition on each dispenser pump and between the dispenser pump and natural-gas transfer pipeline manage Pressure gauge on line.
Further, in addition to located at each safety valve on the dispenser pump.
Further, in addition to located at the check-valves between the dispenser pump and natural-gas transfer pipeline on pipeline.
Further, in addition to located between the dosing pump and the storage tank on pipeline and the storage tank and the filling Ball valve between pump on pipeline.
Further, in addition to located between the dosing pump and the storage tank on pipeline and the dispenser pump and natural gas Flange between conveyance conduit on pipeline.
Brief description of the drawings
Fig. 1 is the utility model part and pipeline connection diagram.
In accompanying drawing, the list of parts representated by each label is as follows:
1st, storage tank, 2, liquid level gauge, 3, inhibitor feeding line, 4, dosing pump, 5, dispenser pump, 6, buffer, 7, flux scale Determine device, 8, fire-retardant breather valve, 9, blowdown tank, 10, filter, 11, pressure gauge, 12, safety valve, 13, check-valves, 14, ball valve, 15th, flange.
Embodiment
Principle of the present utility model and feature are described below in conjunction with accompanying drawing, example is served only for explaining this practicality It is new, it is not intended to limit the scope of the utility model.
As shown in figure 1, the utility model provides a kind of high-pressure natural gas long distance pipeline hydrate inhibitor filling sledge dress dress Put, including the dispenser pump 5 and control cabinet of 1, two a preparation and a use of storage tank for laying in inhibitor and integrated sledge dress, storage tank 1 By pipeline and the inlet communication of dispenser pump 5, the outlet of dispenser pump 5 is connected by pipeline with natural-gas transfer pipeline 16 for bottom; Storage tank 1 is provided with the liquid level gauge 2 for being used for measuring inhibitor amount of storage in storage tank 1, and storage tank 1 connects with inhibitor feeding line 3, presses down Preparation feeding line 3 is provided with dosing pump 4, and the tank body of storage tank 1 is additionally provided with thermometer, can measure the real time temperature in storage tank 1, storage The top of tank 1 is provided with fire-retardant breather valve 8, and fire-retardant breather valve 8 has drainage function, and the pressure inside storage tank 1 can be adjusted Section, play a part of protecting storage tank 1;Dispenser pump 5 uses plunger pump, and each plunger pump discharge is adjustable, is set on each dispenser pump 5 Have a flow calibrator 7 and the buffer 6 for the steady flow of dispenser pump 5, dispenser pump 5 by pipeline respectively with flow calibrator 7 Connected with buffer 6, electric cabinet connects respectively at dosing pump 4 and dispenser pump 5.
In the present embodiment, the bottom of storage tank 1 is connected with blowdown tank 9, and blowdown tank 9, which is used to store in inhibitor storage tank 1, discharges Dirt, can prevent the pollution of the environment;Meanwhile the pipeline between storage tank 1 and dispenser pump 5 is provided with filter 10, filter 10 Inhibitor in pipeline can be filtered, prevent impurity blocking pipeline therein, damage dispenser pump.
In the present embodiment, note alcohol device also includes on each dispenser pump 5 and dispenser pump 5 and natural-gas transfer pipeline Pressure gauge 11 between 16 on pipeline, the safety valve 12 on each dispenser pump 5, located at dispenser pump 5 and gas delivering pipe Check-valves 13 between road 16 on pipeline, managed between dosing pump 4 and storage tank 1 on pipeline and between storage tank 1 and dispenser pump 5 Ball valve 14 on line and managed between dosing pump 4 and storage tank 1 on pipeline and between dispenser pump 5 and natural-gas transfer pipeline 16 Flange 15 on line, corresponding pressure table 11 are used for the pressure observed in the outlet of dispenser pump 5 and natural-gas transfer pipeline 16, safety valve 12 are used to limit the outlet pressure of dispenser pump 5, and check-valves 13 is used to prevent that medium to flow backwards in pipeline, and ball valve 14 then plays the work of shut-off With.
Preferred embodiment of the present utility model is the foregoing is only, it is all in this practicality not to limit the utility model Within new spirit and principle, any modification, equivalent substitution and improvements made etc., guarantor of the present utility model should be included in Within the scope of shield.

Claims (10)

1. a kind of high-pressure natural gas long distance pipeline hydrate inhibitor fills skid-mounted unit, it is characterised in that:Including for laying in The storage tank (1) of inhibitor, the dispenser pump (5) of two a preparation and a use and control cabinet and integrated sledge dress, storage tank (1) bottom leads to The inlet communication of pipeline and the dispenser pump (5) is crossed, the outlet of the dispenser pump (5) passes through pipeline and natural-gas transfer pipeline (16) connect;The storage tank (1) is provided with the liquid level gauge (2) for being used for measuring the interior inhibitor amount of storage of the storage tank (1), the storage Tank (1) connects with inhibitor feeding line (3), and the inhibitor feeding line (3) is provided with dosing pump (4);Add described in each Note pump (5) and be provided with flow calibrator (7) and the buffer (6) for steady dispenser pump (5) flow, the dispenser pump (5) connected respectively with the flow calibrator (7) and the buffer (6) by the pipeline, electric cabinet adds respectively at described Teat pipette (4) and dispenser pump (5) electrical connection.
2. a kind of high-pressure natural gas long distance pipeline hydrate inhibitor filling skid-mounted unit according to claim 1, it is special Sign is:The dispenser pump (5) uses plunger pump, and each plunger pump discharge is adjustable.
3. a kind of high-pressure natural gas long distance pipeline hydrate inhibitor filling skid-mounted unit according to claim 1, it is special Sign is:The top of the storage tank (1) is provided with the fire-retardant breather valve (8) of the regulation interior pressure of the storage tank (1), the storage tank (1) Tank body is additionally provided with thermometer.
4. a kind of high-pressure natural gas long distance pipeline hydrate inhibitor filling skid-mounted unit according to claim 1, it is special Sign is:The bottom of the storage tank (1) is connected with blowdown tank (9), and the blowdown tank (9), which is used to store in the storage tank (1), arranges The dirt gone out.
5. a kind of high-pressure natural gas long distance pipeline hydrate inhibitor filling skid-mounted unit according to claim 1, it is special Sign is:The pipeline between the storage tank (1) and the dispenser pump (5) is provided with filter (10).
6. a kind of high-pressure natural gas long distance pipeline hydrate inhibitor filling skid-mounted unit according to claim 1, it is special Sign is:Also include on each dispenser pump (5) and between the dispenser pump (5) and natural-gas transfer pipeline (16) Pressure gauge (11) on pipeline.
7. a kind of high-pressure natural gas long distance pipeline hydrate inhibitor filling skid-mounted unit according to claim 1, it is special Sign is:Also include the safety valve (12) on each dispenser pump (5).
8. a kind of high-pressure natural gas long distance pipeline hydrate inhibitor filling skid-mounted unit according to claim 1, it is special Sign is:Also include located at the check-valves (13) between the dispenser pump (5) and natural-gas transfer pipeline (16) on pipeline.
9. a kind of high-pressure natural gas long distance pipeline hydrate inhibitor filling skid-mounted unit according to claim 1, it is special Sign is:Also include being located between the dosing pump (4) and the storage tank (1) on pipeline and the storage tank (1) adds with described Ball valve (14) between note pump (5) on pipeline.
10. a kind of high-pressure natural gas long distance pipeline hydrate inhibitor filling skid-mounted unit according to claim 1, it is special Sign is:Also include be located between the dosing pump (4) and the storage tank (1) on pipeline and the dispenser pump (5) with naturally Flange (15) between letter shoot road (16) on pipeline.
CN201721193843.3U 2017-09-18 2017-09-18 A kind of high-pressure natural gas long distance pipeline hydrate inhibitor fills skid-mounted unit Active CN207213651U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721193843.3U CN207213651U (en) 2017-09-18 2017-09-18 A kind of high-pressure natural gas long distance pipeline hydrate inhibitor fills skid-mounted unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721193843.3U CN207213651U (en) 2017-09-18 2017-09-18 A kind of high-pressure natural gas long distance pipeline hydrate inhibitor fills skid-mounted unit

Publications (1)

Publication Number Publication Date
CN207213651U true CN207213651U (en) 2018-04-10

Family

ID=61821621

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721193843.3U Active CN207213651U (en) 2017-09-18 2017-09-18 A kind of high-pressure natural gas long distance pipeline hydrate inhibitor fills skid-mounted unit

Country Status (1)

Country Link
CN (1) CN207213651U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108894762A (en) * 2018-08-30 2018-11-27 西安长庆科技工程有限责任公司 A kind of gas well well site note alcohol device and its application method
CN110242860A (en) * 2019-07-01 2019-09-17 西安热工研究院有限公司 The ice protection system and method fast and safely discharged for supercritical CO 2 electricity generation system
CN110511801A (en) * 2019-09-17 2019-11-29 青岛华友恒新能源材料技术研究院有限公司 A kind of natural gas mercury-removing agent chemicals dosing plant

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108894762A (en) * 2018-08-30 2018-11-27 西安长庆科技工程有限责任公司 A kind of gas well well site note alcohol device and its application method
CN110242860A (en) * 2019-07-01 2019-09-17 西安热工研究院有限公司 The ice protection system and method fast and safely discharged for supercritical CO 2 electricity generation system
CN110242860B (en) * 2019-07-01 2024-04-05 西安热工研究院有限公司 Anti-icing system and method for rapid and safe emission of supercritical CO2 power generation system
CN110511801A (en) * 2019-09-17 2019-11-29 青岛华友恒新能源材料技术研究院有限公司 A kind of natural gas mercury-removing agent chemicals dosing plant

Similar Documents

Publication Publication Date Title
CN207213651U (en) A kind of high-pressure natural gas long distance pipeline hydrate inhibitor fills skid-mounted unit
CN204755435U (en) Subsea production system's hydraulic power unit
CN202363006U (en) Experimental physical model for low-permeability bottom water oil pool exploitation
CN103968252A (en) Alcohol injection process method for medium and low pressure natural gas collection
CN203230404U (en) Gathering and transportation pry device for gas injection-production of salt-cavern gas storage
US7874381B2 (en) Pneumatic line deicing system
CN205196305U (en) Irrigation device for garden
CN209330811U (en) A kind of park maintenance automatic irrigation device
CN204023717U (en) A kind of pot type non-negative pressure water-supply installation of many pumps multifrequency
CN103470235A (en) High-pressure nitrogen foam generation measuring and control device
CN201218093Y (en) Thick oil borehole viscosity-reduction oil-extraction heating apparatus
CN207048738U (en) A kind of ground coal bed gas well mining device
CN206955627U (en) A kind of skid-mounted oil filling device
CN203559889U (en) Automatic adjustable water distributor
CN204609856U (en) The online acidizing device of portable water injection well
CN103643987A (en) Gas collection, slag removal and drainage device for drill hole
CN204026157U (en) Integration note alcohol injecting device
CN203223195U (en) Gas drilling anti-dust device
CN105089567B (en) Deep-well is adjustable low density flow quick fluid-discharge formation testing device and its operational method
CN104006285A (en) Drainage system for gas turbine
CN203704962U (en) Metering tank
CN103527179B (en) A kind of HIGH-PRESSURE INJECTION EXPERIMENT loading system
CN202730606U (en) Spreading device
CN202547188U (en) Automatic switching system for ground source heat pump groundwater exploitation and recharging wells
CN208224012U (en) A kind of condensate saturation measuring device in rock core

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200908

Address after: 100728 Beijing, Chaoyangmen, North Street, No. 22, No.

Co-patentee after: SINOPEC CHUANQI DONGSONG NATURAL GAS PIPELINE Co.,Ltd.

Patentee after: China Petroleum & Chemical Corp.

Address before: 430223 Hubei Wuhan City, Wuhan City, East Lake New Technology Development Zone Optics Valley Avenue No. 126 Sichuan Gas East pipeline project, the 1-5 layer of the Wuhan control center

Patentee before: SINOPEC CHUANQI DONGSONG NATURAL GAS PIPELINE Co.,Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100728 No. 22 North Main Street, Chaoyang District, Beijing, Chaoyangmen

Patentee after: CHINA PETROLEUM & CHEMICAL Corp.

Patentee after: Sichuan East Natural Gas Pipeline Co.,Ltd.

Address before: 100728 No. 22 North Main Street, Chaoyang District, Beijing, Chaoyangmen

Patentee before: CHINA PETROLEUM & CHEMICAL Corp.

Patentee before: SINOPEC CHUANQI DONGSONG NATURAL GAS PIPELINE Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20211116

Address after: Room 08-10, 6 / F, building a, No. 5, Dongtucheng Road, Chaoyang District, Beijing 100728

Patentee after: National Petroleum and natural gas pipeline network Group Co.,Ltd.

Patentee after: Sichuan East Natural Gas Pipeline Co.,Ltd.

Address before: 100728 No. 22 North Main Street, Chaoyang District, Beijing, Chaoyangmen

Patentee before: CHINA PETROLEUM & CHEMICAL Corp.

Patentee before: Sichuan East Natural Gas Pipeline Co.,Ltd.