CN207160352U - Curtain wall dried hanging structure and building curtain wall - Google Patents
Curtain wall dried hanging structure and building curtain wall Download PDFInfo
- Publication number
- CN207160352U CN207160352U CN201721035099.4U CN201721035099U CN207160352U CN 207160352 U CN207160352 U CN 207160352U CN 201721035099 U CN201721035099 U CN 201721035099U CN 207160352 U CN207160352 U CN 207160352U
- Authority
- CN
- China
- Prior art keywords
- curtain wall
- connector
- panel
- angle steel
- dried hanging
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Load-Bearing And Curtain Walls (AREA)
Abstract
It the utility model is related to curtain wall construction field, it is intended to which panel can not be fixed on accurate position by solving existing dry-hang attachment structure, the problem of influenceing curtain wall overall appearance, there is provided curtain wall dried hanging structure and building curtain wall.Curtain wall dried hanging structure is used to panel support being connected to Curtain wall frame.The top of back side of panel is connected to Curtain wall frame by the first attachment structure.The bottom of back side of panel is connected in Curtain wall frame by the second attachment structure.Second attachment structure includes the first connector and the second connector.First connector limits mating groove by bottom plate and the side plate of the relative hook portion of the band of both sides.Second connector one end is connected to Curtain wall frame, and the both sides of the other end offer slot respectively, is slidably matched with realizing.The beneficial effects of the utility model be can adapt to the attachment structures caused by reason such as the processing dimension due to each connection member, in-site installation precision can not normally Matching installation connection situation.
Description
Technical field
Curtain wall construction field is the utility model is related to, in particular to curtain wall dried hanging structure and building curtain wall.
Background technology
Dry-hang attachment structure is a kind of conventional curtain wall panel attachment structure.Existing dry-hang attachment structure is being installed
When, it is more because each connector manufacture size, installation accuracy etc. are difficult to lead to not panel being fixed on accurately the reason for control
Position, influence curtain wall overall appearance other performances.
Utility model content
The utility model aims to provide a kind of curtain wall dried hanging structure, to solve the above problems.
Another object of the present utility model is to provide a kind of building curtain wall for possessing above-mentioned curtain wall dried hanging structure.
The utility model also provides a kind of curtain wall installation method.
What embodiment of the present utility model was realized in:
The utility model embodiment provides a kind of curtain wall dried hanging structure, for panel support to be connected into Curtain wall frame.Face
The top of back is connected to Curtain wall frame by the first attachment structure.The bottom of back side of panel is coordinated by the second attachment structure
It is connected to Curtain wall frame.Second attachment structure includes the first connector and the second connector.First connector is by bottom plate and connection
Vertically extending mating groove is limited between the side plate of the band hook portion relatively of bottom plate both sides, two side plates.Second connector one
End is connected to Curtain wall frame, and the both sides of the other end offer slot respectively.First connector is with the hook portion pair of two side plate
The mode that should be caught in the slot of two second connecting portions realizes can slide relatively between the first connector and the second connector
It is dynamic to coordinate.
In an embodiment of the present embodiment:
First connector shares two, and the second connector shares two.Two the first connectors and two the second connectors
The rectangular back side for being connected to panel.
In an embodiment of the present embodiment:
Second connector is connected by the first adjusting part with being connected to the first angle steel of Curtain wall frame, and for adjusting
The horizontal spacing of panel and Curtain wall frame.
In an embodiment of the present embodiment:
The another side of first angle steel is connected to Curtain wall frame by the second adjusting part, for realizing that vertical position is adjusted.
In an embodiment of the present embodiment:
Curtain wall frame includes along longitudinal vertical grid beam and is vertically connected at the horizontal grid beam of vertical grid beam.
The horizontal grid beam of institute is rectangular frame structure, and the second angle steel is connected with the outside of horizontal grid beam.Second angle steel is while pass through bolt
Connect horizontal grid beam.The another side of second angle steel connects the longitudinal edge of the first angle steel by the second adjusting part.Second connector is
Platy structure, and the widthwise edge of the first angle steel is superimposed on, and pass through the adjustable connection of the first regulating part.
In an embodiment of the present embodiment:
First adjusting part and the second adjusting part are by bolt, nut, the adjustment sheet and and adjustment sheet with alveolar surface
Alveolar surface engagement positioning mesh tooth face.
Widthwise edge, the second connector and the regulation of first angle steel of the screw bolt passes overlapping of the first adjusting part
Piece, and three is compressed by nut, realize the restriction of the relative position of the widthwise edge of the second connector and the first angle steel.
The bolt of second regulating part passes through one side of the second angle steel, the longitudinal edge of the first angle steel and the regulation overlapped successively
Piece, and three is compressed by nut, realize the restriction of the relative position of the longitudinal edge of the second angle steel and the widthwise edge of the first angle steel.
In an embodiment of the present embodiment:
The back side of panel is connected with crab-bolt.
The attaching nut that the bottom plate of first connector is connected through a screw thread crab-bolt presses connection panel.
In an embodiment of the present embodiment:
Curtain wall dried hanging structure also includes pad and locking nut, and pad is arranged in locking nut and compressed by locking nut
In the back side of panel.
In an embodiment of the present embodiment:
First attachment structure is buckle-type attachment structure.
The utility model embodiment also provides a kind of building curtain wall, and it includes multiple foregoing curtain wall dried hanging structures.It is multiple
The panel of curtain wall dried hanging structure complements each other to form the alien invasion of building curtain wall.
The utility model embodiment also provides a kind of curtain wall panel installation method, and it is based on foregoing curtain wall dried hanging structure.
Curtain wall panel installation method comprises the following steps:
The top of panel is connected to by Curtain wall frame using the first attachment structure;
First connector is connected to the bottom at the back side of panel, two slots of second connector one end is coordinated card
Enter two hook portions of the first connector, and the second connector is slided into suitable position with respect to the first connector, then by
The other end of two connectors is connected to Curtain wall frame.
To sum up, the curtain wall dried hanging structure in the utility model embodiment and corresponding curtain wall panel installation method have bigger
Vertical adjustment scope, can adapt to connect caused by the reasons such as the processing dimension due to each connection member, in-site installation precision
Binding structure can not normally Matching installation connection situation;Building curtain wall in the utility model embodiment is done using foregoing curtain wall
Hanging hang structure, also having tightly split can form the alien invasion of required regular building curtain wall.
Brief description of the drawings
, below will be to required use in embodiment in order to illustrate more clearly of the technical scheme of the utility model embodiment
Accompanying drawing be briefly described, it will be appreciated that the following drawings illustrate only some embodiments of the present utility model, therefore should not be by
Regard the restriction to scope as, for those of ordinary skill in the art, on the premise of not paying creative work, may be used also
To obtain other related accompanying drawings according to these accompanying drawings.
The structural representation of the curtain wall dried hanging structure in the utility model embodiment one is shown in Fig. 1;
Fig. 2 is enlarged drawing at Fig. 1 A;
Fig. 3 is Fig. 2 C direction views;
Fig. 4 is Fig. 1 B direction views;
Fig. 5 is the structural representation of the building curtain wall in the utility model embodiment two.
Icon:001- building curtain walls;010- curtain wall dried hanging structures;The attachment structures of 100- first;The attachment structures of 200- second;
300- panels;310- crab-bolts;320- attaching nut;330- pads;340- locking nuts;400- Curtain wall frames;410- indulges grid beam;
420- cross supporting frames;The connectors of 10- first;11- bottom plates;12- side plates;13- hook portions;The connectors of 20- second;The angle steel of 30- first;
The angle steel of 40- second;C1- mating grooves;C2- slots;L1- bolts;L2- nuts;L3- adjustment sheets;L4- alveolar surfaces;L5- engaging tooths
Face;The adjusting parts of Z1- first;The adjusting parts of Z2- second.
Embodiment
It is new below in conjunction with this practicality to make the purpose, technical scheme and advantage of the utility model embodiment clearer
Accompanying drawing in type embodiment, the technical scheme in the embodiment of the utility model is clearly and completely described, it is clear that is retouched
The embodiment stated is the utility model part of the embodiment, rather than whole embodiments.Generally here described in accompanying drawing and
The component of the utility model embodiment shown can be configured to arrange and design with a variety of.
Therefore, the detailed description of the embodiment of the present utility model to providing in the accompanying drawings is not intended to limit requirement below
The scope of the utility model of protection, but it is merely representative of selected embodiment of the present utility model.Based in the utility model
Embodiment, the every other embodiment that those of ordinary skill in the art are obtained under the premise of creative work is not made, all
Belong to the scope of the utility model protection.
It should be noted that:Similar label and letter represents similar terms in following accompanying drawing, therefore, once a certain Xiang Yi
It is defined, then it further need not be defined and explained in subsequent accompanying drawing in individual accompanying drawing.
, it is necessary to explanation in description of the present utility model, if occur term " " center ", " on ", " under ", " left side ",
The orientation or position relationship of the instruction such as " right side ", " vertical ", " level ", " interior ", " outer " are based on orientation shown in the drawings or position
Relation, or the utility model product using when the orientation usually put or position relationship, be for only for ease of and describe this reality
With new and simplify description, rather than instruction or imply that signified device or element there must be specific orientation, with specific
Azimuth configuration and operation, therefore it is not intended that to limitation of the present utility model.If in addition, occur in description of the present utility model
Term " first ", " second " etc. are only used for distinguishing description, and it is not intended that instruction or hint relative importance.
If it is not offered as requiring part in addition, occurring the term such as term " level ", " vertical " in description of the present utility model
Abswolute level or pendency, but can be slightly tilted.Such as " level " only refers to that its direction is more horizontal with respect to for " vertical ",
It is not to represent that the structure must be fully horizontal, but can be slightly tilted.
In description of the present utility model, it is also necessary to explanation, unless otherwise clearly defined and limited, if there is art
Language " setting ", " installation ", " connected ", " connection " should be interpreted broadly, for example, it may be being fixedly connected or detachably
Connection, or be integrally connected;Can be mechanical connection or electrical connection;Can be joined directly together, centre can also be passed through
Medium is indirectly connected, and can be the connection of two element internals.For the ordinary skill in the art, can specific feelings
Condition understands concrete meaning of the above-mentioned term in the utility model.
Embodiment one
The structural representation of the curtain wall dried hanging structure 010 in the utility model embodiment one is shown in Fig. 1;Fig. 2 is Fig. 1
A at enlarged drawing;Fig. 3 is Fig. 2 C direction views.It refer to Fig. 1 (coordinating referring to Fig. 2, Fig. 3), the curtain wall dried hanging in the present embodiment
Structure 010 is used to the support of panel 300 being connected to Curtain wall frame 400.The top at the back side of panel 300 passes through the first attachment structure
100 are connected to Curtain wall frame 400.The bottom at the back side of panel 300 is connected in Curtain wall frame by the second attachment structure 200
400.Second attachment structure 200 includes the first connector 10 and the second connector 20.First connector 10 is by bottom plate 11 and connection
Vertically extending mating groove C1 is limited between the side plate 12 of the band hook portion 13 relatively of the both sides of bottom plate 11, two side plates 12.The
The one end of two connector 20 is connected to Curtain wall frame 400, and the both sides of the other end offer slot C2 respectively.First connector 10 with
The corresponding mode being caught in the slot C2 of two the second connectors 20 of the hook portion 13 of two side plate 12 realizes the first connector
10 and second relative can be slidably matched between connector 20.Generally, each panel 300 is by way of 4 points are fixed
Installation, two, top, bottom two, four rectangular distributions of mount point.Referring to Fig. 4, the curtain wall dried hanging in corresponding the present embodiment
Structure 010, the first connector 10 share two, and the second connector 20 shares two.Two the first connectors 10 and two second
The rectangular back side for being connected to panel 300 of connector 20.First attachment structure 100 is buckle-type attachment structure, can be used existing
Conventional suspension member.
The utility model embodiment also provides a kind of curtain wall panel installation method, and it is based on foregoing curtain wall dried hanging structure
010.Curtain wall panel installation method comprises the following steps:
The top of panel 300 is connected to by Curtain wall frame 400 using the first attachment structure 100;
First connector 10 is connected to the bottom at the back side of panel 300, makes two of the one end of the second connector 20 to engage
Groove C2 coordinates two hook portions 13 for being caught in the first connector 10, and 20 relative first connector 10 of the second connector is slided into conjunction
Suitable position, the other end of the second connector 20 is then connected to Curtain wall frame 400.
In curtain wall dried hanging structure 010 and corresponding curtain wall panel installation method in the present embodiment, due to second can be made
Connector 20 slides into suitable position with respect to the first connector 10, so as to have bigger vertical adjustment scope, can adapt to
Because the attachment structure caused by reason such as the processing dimension of each connection member, in-site installation precision normally Matching installation can not connect
The problem of connecing.In actual use, sufficiently long first connector 10 can be set to obtain sufficiently large adjusting range on demand
Structure.
In an embodiment of the present embodiment, alternatively, the second connector 20 passes through the first adjusting part Z1 and company
The first angle steel 30 for being connected to Curtain wall frame 400 is connected, and for adjusting the horizontal spacing of panel 300 and Curtain wall frame 400.The
The another side of one angle steel 30 is connected to Curtain wall frame 400 by the second adjusting part Z2, for realizing that vertical position is adjusted.
In an embodiment of the present embodiment, Curtain wall frame 400 includes the vertical grid beam 410 and vertical connection along longitudinal direction
In the cross supporting frame 420 of vertical grid beam 410.The outside of cross supporting frame 420 is connected with the second angle steel 40.The one side of second angle steel 40 passes through
Bolt L1 connections cross supporting frame 420.The another side of second angle steel 40 passes through the vertical of second the first angle steel of adjusting part Z2 connections 30
Xiang Bian.Second connector 20 is platy structure, and is superimposed on the widthwise edge of the first angle steel 30, and be can adjust by the first regulating part
Connection.
In an embodiment of the present embodiment, the first adjusting part Z1 and the second adjusting part Z2 by bolt L1,
Nut L2, the adjustment sheet L3 with alveolar surface L4 and the mesh tooth face L5 that positioning is engaged with adjustment sheet L3 alveolar surface L4.First
Adjusting part Z1 bolt L1 sequentially passes through the widthwise edge, the second connector 20 and adjustment sheet L3 of the first angle steel 30 of overlapping,
And three is compressed by nut L2, realize the restriction of the relative position of the widthwise edge of the second connector 20 and the first angle steel 30.The
Two adjusting part Z2 bolt L1 passes through one side of the second angle steel 40, the longitudinal edge of the first angle steel 30 and the regulation overlapped successively
Piece L3, and three is compressed by nut L2, realize the relative position of the longitudinal edge of the second angle steel 40 and the widthwise edge of the first angle steel 30
The restriction put.
In an embodiment of the present embodiment, the back side of panel 300 is connected with crab-bolt 310.First connector 10
The attaching nut 320 that bottom plate 11 is connected through a screw thread crab-bolt 310 presses connection panel 300.Curtain wall dried hanging structure 010 also includes pad
Piece 330 and locking nut 340, pad 330 are arranged in locking nut 340 and the back of the body of panel 300 are pressed in by locking nut 340
Face.
In summary, in the present embodiment in curtain wall dried hanging structure 010 and corresponding curtain wall panel installation method, due to
20 relative first connector 10 of the second connector can be made to slide into suitable position, so as to have bigger vertical adjustment scope,
Can adapt to the attachment structures caused by reason such as the processing dimension due to each connection member, in-site installation precision can not be normal
The problem of being connected with installation.In actual use, sufficiently long first connector 10 can be set to obtain sufficiently large tune on demand
The structure of whole scope.
Embodiment two
Refer to Fig. 5 the present embodiment and a kind of building curtain wall 001 is provided, it includes the curtain wall dried hanging knot in multiple embodiments one
Structure 010.The panel 300 of multiple curtain wall dried hanging structures 010 complements each other to form the alien invasion of building curtain wall 001.Shown in Fig. 5
The split structure of four curtain wall dried hanging structures 010 therein.
The building curtain wall 001 formed using the curtain wall dried hanging structure 010 in embodiment one, it is big with adjustable range, can
Ensure that each panel 300 tightly split can form required rule on the basis of curtain wall dried hanging structure 010 normally connection
Building curtain wall 001 alien invasion.
In summary embodiment, curtain wall dried hanging structure 010 and corresponding curtain wall panel peace in the utility model embodiment
Dress method has bigger vertical adjustment scope, can adapt to the processing dimension due to each connection member, in-site installation precision
Etc. attachment structure caused by reason can not normally Matching installation connection situation.
Preferred embodiment of the present utility model is the foregoing is only, is not limited to the utility model, for this
For the technical staff in field, the utility model can have various modifications and variations.It is all in the spirit and principles of the utility model
Within, any modification, equivalent substitution and improvements made etc., it should be included within the scope of protection of the utility model.
Claims (10)
- A kind of 1. curtain wall dried hanging structure, for panel support to be connected into Curtain wall frame, it is characterised in that:The top of the back side of panel is connected to the Curtain wall frame by the first attachment structure;The bottom of the back side of panel is connected in the Curtain wall frame by the second attachment structure;Second attachment structure includes the first connector and the second connector;First connector is by bottom plate and is connected to the side plate of the bands of the bottom plate both sides with respect to hook portion, two side plates it Between limit vertically extending mating groove;Described second connector one end is connected to the Curtain wall frame, and the both sides of the other end offer slot respectively;First connector is correspondingly caught in the hook portion of side plate two described in the slot of two second connectors Mode realize relative can be slidably matched between first connector and second connector.
- 2. curtain wall dried hanging structure according to claim 1, it is characterised in that:First connector shares two, and second connector shares two;Two first connectors and two rectangular back sides for being connected to the panel of the second connector.
- 3. curtain wall dried hanging structure according to claim 1, it is characterised in that:Second connector is connected by the first adjusting part with being connected to the first angle steel of the Curtain wall frame, and is used for Adjust the horizontal spacing of the panel and the Curtain wall frame.
- 4. curtain wall dried hanging structure according to claim 3, it is characterised in that:The another side of first angle steel is connected to the Curtain wall frame by the second adjusting part, for realizing that vertical position is adjusted Section.
- 5. curtain wall dried hanging structure according to claim 4, it is characterised in that:The Curtain wall frame includes along longitudinal vertical grid beam and is vertically connected at the horizontal grid beam of the vertical grid beam;The horizontal grid beam of institute is rectangular frame structure, and the second angle steel is connected with the outside of the horizontal grid beam;Second angle steel is while pass through Horizontal grid beam described in bolt connection;The another side of second angle steel connects first angle steel by second adjusting part Longitudinal edge;Second connector is platy structure, and is superimposed on the widthwise edge of first angle steel, and is adjusted by described first Save the adjustable connection of component.
- 6. curtain wall dried hanging structure according to claim 5, it is characterised in that:First adjusting part and second adjusting part by bolt, nut, the adjustment sheet with alveolar surface and with institute State the mesh tooth face of the alveolar surface engagement positioning of adjustment sheet;The widthwise edge of first angle steel of the screw bolt passes overlapping of first adjusting part, second connector with And the adjustment sheet, and three is compressed by the nut, realize the widthwise edge of second connector and first angle steel Relative position restriction;The bolt of second adjusting part passes through one side, the longitudinal direction of first angle steel of second angle steel overlapped successively Side and the adjustment sheet, and three is compressed by the nut, realize the longitudinal edge of second angle steel and described first jiao The restriction of the relative position of the widthwise edge of steel.
- 7. curtain wall dried hanging structure according to claim 1, it is characterised in that:The back side of the panel is connected with crab-bolt;The attaching nut that the bottom plate of first connector is connected through a screw thread the crab-bolt presses the connection panel.
- 8. curtain wall dried hanging structure according to claim 7, it is characterised in that:The curtain wall dried hanging structure also includes pad and locking nut, and the pad is arranged in the locking nut and passes through locking Nut is pressed in the back side of the panel.
- 9. curtain wall dried hanging structure according to claim 1, it is characterised in that:First attachment structure is buckle-type attachment structure.
- A kind of 10. building curtain wall, it is characterised in that:The building curtain wall includes multiple curtain wall dried hanging structures as described in claim any one of 1-9;The panel of multiple curtain wall dried hanging structures complements each other to form the alien invasion of the building curtain wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721035099.4U CN207160352U (en) | 2017-08-17 | 2017-08-17 | Curtain wall dried hanging structure and building curtain wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721035099.4U CN207160352U (en) | 2017-08-17 | 2017-08-17 | Curtain wall dried hanging structure and building curtain wall |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207160352U true CN207160352U (en) | 2018-03-30 |
Family
ID=61717825
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721035099.4U Expired - Fee Related CN207160352U (en) | 2017-08-17 | 2017-08-17 | Curtain wall dried hanging structure and building curtain wall |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207160352U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107268850A (en) * | 2017-08-17 | 2017-10-20 | 四川盛邦建设股份有限公司 | Curtain wall dried hanging structure, building curtain wall and curtain wall panel installation method |
-
2017
- 2017-08-17 CN CN201721035099.4U patent/CN207160352U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107268850A (en) * | 2017-08-17 | 2017-10-20 | 四川盛邦建设股份有限公司 | Curtain wall dried hanging structure, building curtain wall and curtain wall panel installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208235841U (en) | External corner module | |
CN207160352U (en) | Curtain wall dried hanging structure and building curtain wall | |
CN104975667B (en) | A kind of hyperboloid metal plate curtain wall installing structure and its installation method | |
CN107268850A (en) | Curtain wall dried hanging structure, building curtain wall and curtain wall panel installation method | |
CN207426108U (en) | Antenna system and its antenna mounting device | |
CN203569748U (en) | Inserting connection type aluminum plate curtain wall structure | |
CN102182246A (en) | Adjustable member connecting plate | |
CN206779344U (en) | Coalignment | |
CN208486546U (en) | A kind of adjustable gang form | |
US10565902B2 (en) | Display panel support and support assembly | |
CN207717655U (en) | A kind of installing mechanism of strain clamp detection device | |
CN207974406U (en) | Outer corner component | |
CN206641675U (en) | A kind of screen square column attachment means | |
CN207974436U (en) | External corner connecting piece and outer corner component | |
CN209398170U (en) | A kind of profile fixinig plate and the connection structure using it | |
CN208056634U (en) | A kind of back cord that convenience is connected in corner | |
CN207678150U (en) | A kind of limit adjustable guide rail | |
CN205225965U (en) | Stand crossbeam connection structure | |
CN207717085U (en) | A kind of telescopic auxiliary device for coordinating level meter | |
CN214364732U (en) | Aluminum wallboard edging connecting structure | |
CN207673125U (en) | A kind of connecting piece for rail | |
CN206625539U (en) | The formwork structure of special-shaped component | |
CN208086322U (en) | A kind of adjustable how arc-shaped electrolysis steel plate connection component of tightness | |
CN211903970U (en) | Compressor stator winding quality detection tool | |
CN205005381U (en) | How online electric cabinet of frequency conversion |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||