- CN107268850A CN107268850A CN201710704901.2A CN201710704901A CN107268850A CN 107268850 A CN107268850 A CN 107268850A CN 201710704901 A CN201710704901 A CN 201710704901A CN 107268850 A CN107268850 A CN 107268850A
- Authority
- CN
- China
- Prior art keywords
- curtain wall
- connector
- panel
- angle steel
- dried hanging
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000009434 installation Methods 0.000 title claims abstract description 25
- 238000000034 method Methods 0.000 title claims abstract description 15
- 230000013011 mating Effects 0.000 claims abstract description 5
- 229910000831 Steel Inorganic materials 0.000 claims description 41
- 239000010959 steel Substances 0.000 claims description 41
- 230000009545 invasion Effects 0.000 claims description 5
- 241000276425 Xiphophorus maculatus Species 0.000 claims description 3
- 238000003825 pressing Methods 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 2
- 230000009286 beneficial effect Effects 0.000 abstract 1
- 230000001105 regulatory effect Effects 0.000 description 3
- 210000000515 tooth Anatomy 0.000 description 3
- 238000009826 distribution Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
- E04B2/96—Curtain walls comprising panels attached to the structure through mullions or transoms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/88—Curtain walls
- E04B2/96—Curtain walls comprising panels attached to the structure through mullions or transoms
- E04B2/965—Connections of mullions and transoms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Abstract
The present invention relates to curtain wall construction field, it is intended to which solving the problem of panel can not be fixed on accurate position, influence curtain wall overall appearance by existing dry-hang attachment structure, there is provided curtain wall dried hanging structure, building curtain wall and curtain wall panel installation method.Curtain wall dried hanging structure is used to panel support being connected to Curtain wall frame.The top of back side of panel is connected to Curtain wall frame by the first attachment structure.The bottom of back side of panel is connected in Curtain wall frame by the second attachment structure.Second attachment structure includes the first connector and the second connector.The side plate of the relative hook portion of band of first connector by bottom plate and both sides, and limit mating groove.Second connector one end is connected to Curtain wall frame, and the both sides of the other end offer slot respectively, is slidably matched with realizing.The attachment structure caused the beneficial effects of the invention are as follows reasons such as the processing dimension that can adapt to due to each connection member, in-site installation precision can not normal Matching installation connection situation.
Description
Technical field
The present invention relates to curtain wall construction field, pacify in particular to curtain wall dried hanging structure, building curtain wall and curtain wall panel
Dress method.
Background technology
Dry-hang attachment structure is a kind of conventional curtain wall panel attachment structure.Existing dry-hang attachment structure is being installed
When, it is many because each connector manufacture size, installation accuracy etc. are difficult to lead to not panel being fixed on accurately the reason for control
Position, other performances of influence curtain wall overall appearance.
The content of the invention
The present invention is intended to provide a kind of curtain wall dried hanging structure, to solve the above problems.
Another object of the present invention is to provide a kind of building curtain wall for possessing above-mentioned curtain wall dried hanging structure.
The present invention also provides a kind of curtain wall installation method.
What embodiments of the invention were realized in:
The embodiment of the present invention provides a kind of curtain wall dried hanging structure, for panel support to be connected into Curtain wall frame.Panel is carried on the back
The top in face is connected to Curtain wall frame by the first attachment structure.The bottom of back side of panel is connected by the second attachment structure
In Curtain wall frame.Second attachment structure includes the first connector and the second connector.First connector is by bottom plate and is connected to bottom
The band of plate both sides limits vertically extending mating groove between two side plates with respect to the side plate of hook portion.Second connector one end connects
Curtain wall frame is connected to, the both sides of the other end offer slot respectively.First connector is blocked with the hook portion correspondence of two side plate
Enter the mode in the slot of two second connecting portions and realize that relative can slide between the first connector and the second connector is matched somebody with somebody
Close.
In an embodiment of the present embodiment:
First connector has two, and the second connector has two.Two the first connectors and two the second connectors
The rectangular back side for being connected to panel.
In an embodiment of the present embodiment:
Second connector is connected by the first adjusting part with being connected to the first angle steel of Curtain wall frame, and for adjusting
The horizontal spacing of panel and Curtain wall frame.
In an embodiment of the present embodiment:
The another side of first angle steel is connected to Curtain wall frame by the second adjusting part, for realizing that vertical position is adjusted.
In an embodiment of the present embodiment:
Curtain wall frame includes the vertical grid beam and the horizontal grid beam for being vertically connected at vertical grid beam along longitudinal direction.
The horizontal grid beam of institute is to be connected with the second angle steel on the outside of rectangle mount structure, horizontal grid beam.Second angle steel is while pass through bolt
Connect horizontal grid beam.The another side of second angle steel connects the longitudinal edge of the first angle steel by the second adjusting part.Second connector is
Platy structure, and the widthwise edge of the first angle steel is superimposed on, and pass through the adjustable connection of the first regulating part.
In an embodiment of the present embodiment:
First adjusting part and the second adjusting part are by bolt, nut, the adjustment sheet with alveolar surface and and adjustment sheet
Alveolar surface engagement positioning mesh tooth face.
Widthwise edge, the second connector and the regulation of first angle steel of the screw bolt passes overlapping of the first adjusting part
Piece, and three is compressed by nut, realize the restriction of the relative position of the widthwise edge of the second connector and the first angle steel.
The bolt of second regulating part passes through one side, the longitudinal edge of the first angle steel and the regulation of the second angle steel overlapped successively
Piece, and three is compressed by nut, realize the restriction of the relative position of the longitudinal edge of the second angle steel and the widthwise edge of the first angle steel.
In an embodiment of the present embodiment:
The back side of panel is connected with crab-bolt.
The bottom plate of first connector is connected through a screw thread attaching nut's pressing connection panel of crab-bolt.
In an embodiment of the present embodiment:
Curtain wall dried hanging structure also includes pad and locking nut, and pad is arranged in locking nut and compressed by locking nut
In the back side of panel.
The embodiment of the present invention also provides a kind of building curtain wall, and it includes multiple foregoing curtain wall dried hanging structures.Multiple curtain walls
The panel of dried hanging hang structure complements each other to form the alien invasion of building curtain wall.
The embodiment of the present invention also provides a kind of curtain wall panel installation method, and it is based on foregoing curtain wall dried hanging structure.Curtain wall
Panel installation techniques comprise the following steps:
The top of panel is connected to by Curtain wall frame using the first attachment structure;
First connector is connected to the bottom at the back side of panel, two slots of second connector one end is coordinated card
Enter two hook portions of the first connector, and the second connector is slided into suitable position with respect to the first connector, then by
The other end of two connectors is connected to Curtain wall frame.
To sum up, in the embodiment of the present invention curtain wall dried hanging structure and corresponding curtain wall panel installation method has bigger erect
To adjustable range, the connection knot that the reasons such as the processing dimension due to each connection member, in-site installation precision are caused can adapt to
Structure can not normally Matching installation connection situation;Building curtain wall in the embodiment of the present invention uses foregoing curtain wall dried hanging structure,
Also having tightly split can form the alien invasion of required regular building curtain wall.
Brief description of the drawings
In order to illustrate the technical solution of the embodiments of the present invention more clearly, below will be attached to what is used required in embodiment
Figure is briefly described, it will be appreciated that the following drawings illustrate only certain embodiments of the present invention, therefore is not construed as pair
The restriction of scope, for those of ordinary skill in the art, on the premise of not paying creative work, can also be according to this
A little accompanying drawings obtain other related accompanying drawings.
The structural representation of the curtain wall dried hanging structure in the embodiment of the present invention one is shown in Fig. 1;
Fig. 2 is enlarged drawing at Fig. 1 A;
Fig. 3 is Fig. 2 C direction views;
Fig. 4 is Fig. 1 B direction views;
Fig. 5 be the embodiment of the present invention two in building curtain wall structural representation.
Icon:001- building curtain walls;010- curtain wall dried hanging structures;The attachment structures of 100- first;The attachment structures of 200- second;
300- panels;310- crab-bolts;320- attaching nut;330- pads;340- locking nuts;400- Curtain wall frames;410- indulges grid beam;
420- cross supporting frames;The connectors of 10- first;11- bottom plates;12- side plates;13- hook portions;The connectors of 20- second;The angle steel of 30- first;
The angle steel of 40- second;C1- mating grooves;C2- slots;L1- bolts;L2- nuts;L3- adjustment sheets;L4- alveolar surfaces;L5- engaging tooths
Face;The adjusting parts of Z1- first;The adjusting parts of Z2- second.
Embodiment
To make the purpose, technical scheme and advantage of the embodiment of the present invention clearer, below in conjunction with the embodiment of the present invention
In accompanying drawing, the technical scheme in the embodiment of the present invention is clearly and completely described, it is clear that described embodiment is
A part of embodiment of the present invention, rather than whole embodiments.The present invention implementation being generally described and illustrated herein in the accompanying drawings
The component of example can be arranged and designed with a variety of configurations.
Therefore, the detailed description of embodiments of the invention below to providing in the accompanying drawings is not intended to limit claimed
The scope of the present invention, but be merely representative of the present invention selected embodiment.Based on the embodiment in the present invention, this area is common
The every other embodiment that technical staff is obtained under the premise of creative work is not made, belongs to the model that the present invention is protected
Enclose.
It should be noted that:Similar label and letter represents similar terms in following accompanying drawing, therefore, once a certain Xiang Yi
It is defined in individual accompanying drawing, then it further need not be defined and explained in subsequent accompanying drawing.
In the description of the invention, it is necessary to explanation, if occur term " " center ", " on ", " under ", "left", "right",
The orientation or position relationship of the instruction such as " vertical ", " level ", " interior ", " outer " be based on orientation shown in the drawings or position relationship,
The orientation or position relationship usually put when either the invention product is used, are for only for ease of the description present invention and simplification is retouched
State, rather than indicate or imply that the device or element of meaning there must be specific orientation, with specific azimuth configuration and operation,
Therefore it is not considered as limiting the invention.If only being used in addition, occurring term " first ", " second " etc. in description of the invention
Described in distinguishing, and it is not intended that indicating or implying relative importance.
If being not offered as requiring that part is absolute in addition, occurring the term such as term " level ", " vertical " in description of the invention
Level or pendency, but can be slightly tilted.As " level " only refers to its direction with respect to more level for " vertical ", not
It is to represent that the structure must be fully horizontal, but can be slightly tilted.
In the description of the invention, in addition it is also necessary to explanation, unless otherwise clearly defined and limited, if there is term
" setting ", " installation ", " connected ", " connection " should be interpreted broadly, for example, it may be being fixedly connected or detachably connecting
Connect, or be integrally connected;Can be mechanical connection or electrical connection;Can be joined directly together, middle matchmaker can also be passed through
Jie is indirectly connected to, and can be the connection of two element internals.For the ordinary skill in the art, can be with concrete condition
Understand the concrete meaning of above-mentioned term in the present invention.
Embodiment one
The structural representation of the curtain wall dried hanging structure 010 in the embodiment of the present invention one is shown in Fig. 1;Fig. 2 is Fig. 1 A
Locate enlarged drawing;Fig. 3 is Fig. 2 C direction views.It refer to the curtain wall dried hanging knot in Fig. 1 (coordinating referring to Fig. 2, Fig. 3), the present embodiment
Structure 010 is used to the support of panel 300 being connected to Curtain wall frame 400.The top at the back side of panel 300 passes through the first attachment structure 100
It is connected to Curtain wall frame 400.The bottom at the back side of panel 300 is connected in Curtain wall frame 400 by the second attachment structure 200.
Second attachment structure 200 includes the first connector 10 and the second connector 20.First connector 10 is by bottom plate 11 and is connected to bottom
The band of the both sides of plate 11 limits vertically extending mating groove C1 between two side plates 12 with respect to the side plate 12 of hook portion 13.Second connects
The one end of fitting 20 is connected to Curtain wall frame 400, and the both sides of the other end offer slot C2 respectively.First connector 10 with its two
The mode that the correspondence of hook portion 13 of individual side plate 12 is caught in the slot C2 of two the second connectors 20 realizes the He of the first connector 10
Relative can be slidably matched between the second connector 20.Generally, each panel 300 is pacified by way of 4 points are fixed
Dress, two, top, bottom two, the rectangular distribution of four mount points.Referring to Fig. 4, the curtain wall dried hanging knot in the present embodiment is corresponded to
Structure 010, the first connector 10 has two, and the second connector 20 has two.Two the first connectors 10 and two second companies
The rectangular back side for being connected to panel 300 of fitting 20.First attachment structure 100 is buckle-type attachment structure, can be used existing
Conventional suspension member.
The embodiment of the present invention also provides a kind of curtain wall panel installation method, and it is based on foregoing curtain wall dried hanging structure 010.Curtain
Metope method of plate installation comprises the following steps:
The top of panel 300 is connected to by Curtain wall frame 400 using the first attachment structure 100;
First connector 10 is connected to the bottom at the back side of panel 300, makes two of the one end of the second connector 20 to engage
Groove C2 coordinates two hook portions 13 for being caught in the first connector 10, and relative first connector 10 of the second connector 20 is slided into conjunction
Suitable position, is then connected to Curtain wall frame 400 by the other end of the second connector 20.
In curtain wall dried hanging structure 010 and corresponding curtain wall panel installation method in the present embodiment, due to second can be made
Connector 20 slides into suitable position with respect to the first connector 10, so as to bigger vertical adjustment scope, can adapt to
The attachment structure that the reasons such as processing dimension, in-site installation precision due to each connection member are caused normally Matching installation can not connect
The problem of connecing.In actual use, sufficiently long first connector 10 can be set to obtain sufficiently large adjusting range on demand
Structure.
In an embodiment of the present embodiment, alternatively, the second connector 20 passes through the first adjusting part Z1 and company
The first angle steel 30 for being connected to Curtain wall frame 400 is connected, and for adjusting the horizontal spacing of panel 300 and Curtain wall frame 400.The
The another side of one angle steel 30 is connected to Curtain wall frame 400 by the second adjusting part Z2, for realizing that vertical position is adjusted.
In an embodiment of the present embodiment, Curtain wall frame 400 includes the vertical grid beam 410 and vertical connection along longitudinal direction
In the cross supporting frame 420 of vertical grid beam 410.The outside of cross supporting frame 420 is connected with the second angle steel 40.The one side of second angle steel 40 passes through
Bolt L1 connections cross supporting frame 420.The another side of second angle steel 40 passes through the vertical of second the first angle steel of adjusting part Z2 connections 30
Xiang Bian.Second connector 20 is platy structure, and is superimposed on the widthwise edge of the first angle steel 30, and adjustable by the first regulating part
Connection.
In an embodiment of the present embodiment, the first adjusting part Z1 and the second adjusting part Z2 by bolt L1,
Nut L2, the adjustment sheet L3 with alveolar surface L4 and the mesh tooth face L5 that positioning is engaged with adjustment sheet L3 alveolar surface L4.First
Adjusting part Z1 bolt L1 sequentially passes through the widthwise edge, the second connector 20 and adjustment sheet L3 of the first angle steel 30 of overlapping,
And three is compressed by nut L2, realize the restriction of the relative position of the widthwise edge of the second connector 20 and the first angle steel 30.The
Two adjusting part Z2 bolt L1 passes through one side, the longitudinal edge of the first angle steel 30 and the regulation of the second angle steel 40 overlapped successively
Piece L3, and three is compressed by nut L2, realize the relative position of the longitudinal edge of the second angle steel 40 and the widthwise edge of the first angle steel 30
The restriction put.
In an embodiment of the present embodiment, the back side of panel 300 is connected with crab-bolt 310.First connector 10
Bottom plate 11 is connected through a screw thread the pressing connection panel 300 of attaching nut 320 of crab-bolt 310.Curtain wall dried hanging structure 010 also includes pad
Piece 330 and locking nut 340, pad 330 are arranged in locking nut 340 and the back of the body of panel 300 are pressed in by locking nut 340
Face.
In summary, in the present embodiment in curtain wall dried hanging structure 010 and corresponding curtain wall panel installation method, due to
Relative first connector 10 of the second connector 20 can be made to slide into suitable position, so that with bigger vertical adjustment scope,
Can adapt to attachment structure that the reasons such as the processing dimension due to each connection member, in-site installation precision cause can not be normal
The problem of with connection is installed.In actual use, sufficiently long first connector 10 can be set to obtain sufficiently large tune on demand
The structure of whole scope.
Embodiment two
Refer to Fig. 5 the present embodiment and a kind of building curtain wall 001 is provided, it includes the curtain wall dried hanging knot in multiple embodiments one
Structure 010.The panel 300 of multiple curtain wall dried hanging structures 010 complements each other to form the alien invasion of building curtain wall 001.Shown in Fig. 5
The split structure of four curtain wall dried hanging structures 010 therein.
The building curtain wall 001 constituted using the curtain wall dried hanging structure 010 in embodiment one, it is big with adjustable range, can
Ensure that each panel 300 tightly split can form required rule on the basis of curtain wall dried hanging structure 010 normally connection
Building curtain wall 001 alien invasion.
In summary curtain wall dried hanging structure 010 and corresponding curtain wall panel installation side in embodiment, the embodiment of the present invention
Method has bigger vertical adjustment scope, can adapt to the originals such as processing dimension, in-site installation precision due to each connection member
Attachment structure caused by can not normal Matching installation connection situation.
The preferred embodiments of the present invention are the foregoing is only, are not intended to limit the invention, for the skill of this area
For art personnel, the present invention can have various modifications and variations.Within the spirit and principles of the invention, that is made any repaiies
Change, equivalent substitution, improvement etc., should be included in the scope of the protection.
Claims (10)
1. a kind of curtain wall dried hanging structure, for panel support to be connected into Curtain wall frame, it is characterised in that:
The top of the back side of panel is connected to the Curtain wall frame by the first attachment structure;
The bottom of the back side of panel is connected in the Curtain wall frame by the second attachment structure;
Second attachment structure includes the first connector and the second connector;
First connector is by bottom plate and is connected to the side plate of the bands of the bottom plate both sides with respect to hook portion, two side plates it
Between limit vertically extending mating groove;
Described second connector one end is connected to the Curtain wall frame, and the both sides of the other end offer slot respectively;
First connector is caught in the slot of two second connectors with the hook portion correspondence of side plate two described
Mode realize relative can be slidably matched between first connector and second connector.
2. curtain wall dried hanging structure according to claim 1, it is characterised in that:
First connector has two, and second connector has two;
Two first connectors and two rectangular back sides for being connected to the panel of the second connector.
3. curtain wall dried hanging structure according to claim 1, it is characterised in that:
Second connector is connected by the first adjusting part with being connected to the first angle steel of the Curtain wall frame, and is used for
Adjust the horizontal spacing of the panel and the Curtain wall frame.
4. curtain wall dried hanging structure according to claim 3, it is characterised in that:
The another side of first angle steel is connected to the Curtain wall frame by the second adjusting part, for realizing that vertical position is adjusted
Section.
5. curtain wall dried hanging structure according to claim 4, it is characterised in that:
The Curtain wall frame includes the vertical grid beam and the horizontal grid beam for being vertically connected at the vertical grid beam along longitudinal direction;
The horizontal grid beam of institute is to be connected with the second angle steel on the outside of rectangle mount structure, the horizontal grid beam;Second angle steel is while pass through
Horizontal grid beam described in bolt connection;The another side of second angle steel connects first angle steel by second adjusting part
Longitudinal edge;Second connector is platy structure, and is superimposed on the widthwise edge of first angle steel, and is adjusted by described first
Save the adjustable connection of component.
6. curtain wall dried hanging structure according to claim 5, it is characterised in that:
First adjusting part and second adjusting part by bolt, nut, the adjustment sheet with alveolar surface and with institute
State the mesh tooth face of the alveolar surface engagement positioning of adjustment sheet;
The widthwise edge of first angle steel of the screw bolt passes overlapping of first adjusting part, second connector with
And the adjustment sheet, and three is compressed by the nut, realize the widthwise edge of second connector and first angle steel
Relative position restriction;
The bolt of second adjusting part passes through one side, the longitudinal direction of first angle steel of second angle steel overlapped successively
Side and the adjustment sheet, and three is compressed by the nut, realize the longitudinal edge of second angle steel and described first jiao
The restriction of the relative position of the widthwise edge of steel.
7. curtain wall dried hanging structure according to claim 1, it is characterised in that:
The back side of the panel is connected with crab-bolt;
The bottom plate of first connector is connected through a screw thread attaching nut's pressing connection panel of the crab-bolt.
8. curtain wall dried hanging structure according to claim 7, it is characterised in that:
The curtain wall dried hanging structure also includes pad and locking nut, and the pad is arranged in the locking nut and by locking
Nut is pressed in the back side of the panel.
9. a kind of building curtain wall, it is characterised in that:
The building curtain wall includes multiple curtain wall dried hanging structures as described in claim any one of 1-8;
The panel of multiple curtain wall dried hanging structures complements each other to form the alien invasion of the building curtain wall.
10. a kind of curtain wall panel installation method, it is characterised in that:Based on the curtain wall dried hanging knot described in claim any one of 1-8
Structure;The curtain wall panel installation method comprises the following steps:
The top of the panel is connected to by the Curtain wall frame using first attachment structure;
First connector is connected to the bottom at the back side of the panel, makes two of described second connector one end to engage
Groove coordinates two hook portions for being caught in first connector, and slides into relatively described first connector of second connector
Suitable position, is then connected to the Curtain wall frame by the other end of second connector.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710704901.2A CN107268850A (en) | 2017-08-17 | 2017-08-17 | Curtain wall dried hanging structure, building curtain wall and curtain wall panel installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710704901.2A CN107268850A (en) | 2017-08-17 | 2017-08-17 | Curtain wall dried hanging structure, building curtain wall and curtain wall panel installation method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107268850A true CN107268850A (en) | 2017-10-20 |
Family
ID=60077430
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710704901.2A Pending CN107268850A (en) | 2017-08-17 | 2017-08-17 | Curtain wall dried hanging structure, building curtain wall and curtain wall panel installation method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107268850A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111648508A (en) * | 2020-06-11 | 2020-09-11 | 正兴建设集团股份有限公司 | Quick detach fast-assembling type curtain connection structure and curtain system |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201292587Y (en) * | 2008-11-19 | 2009-08-19 | 江苏省江建集团有限公司 | Connecting piece for tall building combined stone curtain wall |
CN101956438A (en) * | 2010-10-22 | 2011-01-26 | 泛华建设集团有限公司 | Three-dimensionally adjustable disconnectable curtain wall connecting device and construction method thereof |
DE102009040319A1 (en) * | 2009-09-05 | 2011-03-10 | LängleGlas GmbH | Shed holder for quick assembly of plates and glass panels as well as procedures for mounting a shed holder |
CN202440970U (en) * | 2012-02-17 | 2012-09-19 | 广东贝克洛幕墙门窗系统有限公司 | Curtain-wall hooking and connecting assembly |
CN203066307U (en) * | 2012-10-24 | 2013-07-17 | 江苏朗景幕墙科技有限公司 | Hanging system of building stone curtain wall |
CN103669663A (en) * | 2013-12-10 | 2014-03-26 | 苏州苏明装饰股份有限公司 | Back-bolt type dry-hang curtain wall system |
CN104975667A (en) * | 2015-04-07 | 2015-10-14 | 浙江亚厦幕墙有限公司 | Double-curved-surface metal plate curtain wall installing structure and double-curved-surface metal plate curtain wall installing method |
CN205116494U (en) * | 2015-10-17 | 2016-03-30 | 山西颐顺鑫科技有限公司 | Subassembly is hung futilely to curtain panel |
CN106223518A (en) * | 2016-07-22 | 2016-12-14 | 广东古帆装饰工程有限公司 | A kind of suspension assembly for curtain wall |
CN106703265A (en) * | 2016-11-18 | 2017-05-24 | 广州铝质装饰工程有限公司 | Stone and glass mixed curtain wall construction method |
CN207160352U (en) * | 2017-08-17 | 2018-03-30 | 四川盛邦建设股份有限公司 | Curtain wall dried hanging structure and building curtain wall |
-
2017
- 2017-08-17 CN CN201710704901.2A patent/CN107268850A/en active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201292587Y (en) * | 2008-11-19 | 2009-08-19 | 江苏省江建集团有限公司 | Connecting piece for tall building combined stone curtain wall |
DE102009040319A1 (en) * | 2009-09-05 | 2011-03-10 | LängleGlas GmbH | Shed holder for quick assembly of plates and glass panels as well as procedures for mounting a shed holder |
CN101956438A (en) * | 2010-10-22 | 2011-01-26 | 泛华建设集团有限公司 | Three-dimensionally adjustable disconnectable curtain wall connecting device and construction method thereof |
CN202440970U (en) * | 2012-02-17 | 2012-09-19 | 广东贝克洛幕墙门窗系统有限公司 | Curtain-wall hooking and connecting assembly |
CN203066307U (en) * | 2012-10-24 | 2013-07-17 | 江苏朗景幕墙科技有限公司 | Hanging system of building stone curtain wall |
CN103669663A (en) * | 2013-12-10 | 2014-03-26 | 苏州苏明装饰股份有限公司 | Back-bolt type dry-hang curtain wall system |
CN104975667A (en) * | 2015-04-07 | 2015-10-14 | 浙江亚厦幕墙有限公司 | Double-curved-surface metal plate curtain wall installing structure and double-curved-surface metal plate curtain wall installing method |
CN205116494U (en) * | 2015-10-17 | 2016-03-30 | 山西颐顺鑫科技有限公司 | Subassembly is hung futilely to curtain panel |
CN106223518A (en) * | 2016-07-22 | 2016-12-14 | 广东古帆装饰工程有限公司 | A kind of suspension assembly for curtain wall |
CN106703265A (en) * | 2016-11-18 | 2017-05-24 | 广州铝质装饰工程有限公司 | Stone and glass mixed curtain wall construction method |
CN207160352U (en) * | 2017-08-17 | 2018-03-30 | 四川盛邦建设股份有限公司 | Curtain wall dried hanging structure and building curtain wall |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111648508A (en) * | 2020-06-11 | 2020-09-11 | 正兴建设集团股份有限公司 | Quick detach fast-assembling type curtain connection structure and curtain system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107131409B (en) | display panel bracket | |
CN107268850A (en) | Curtain wall dried hanging structure, building curtain wall and curtain wall panel installation method | |
CN207160352U (en) | Curtain wall dried hanging structure and building curtain wall | |
CN104975667B (en) | A kind of hyperboloid metal plate curtain wall installing structure and its installation method | |
CN106141533B (en) | A kind of pipe arrangement frock | |
CN211974141U (en) | Assembled wallboard structure of inserting | |
CN219087030U (en) | Profile casting die, profile and photovoltaic system | |
CN207556430U (en) | A kind of lug spacing detection tool in soft-package battery production | |
CN208235841U (en) | External corner module | |
CN109916064A (en) | A kind of assembling structure of air conditioner indoor unit electric-controlled box | |
CN215166992U (en) | Self-adaptive three-dimensional six-degree-of-freedom adjusting curved curtain wall | |
CN208401378U (en) | A kind of spliced L shape photovoltaic U.S. structure changes | |
CN212926645U (en) | Integrated suspended ceiling connecting piece | |
CN211817630U (en) | Dry-hanging wallboard structure with hooks on back surface of keel | |
CN208219963U (en) | Connector for house integrated ceiling | |
CN209129501U (en) | A kind of window bucket mounting structure peculiar to vessel | |
CN207526833U (en) | A kind of Novel cabinet connector and cabinet connection structure | |
CN207043619U (en) | Mounting blocks welding tooling component and welding equipment | |
CN108471094A (en) | A kind of data center's crane span structure | |
CN205830192U (en) | A kind of guard shield for controller | |
US20140127951A1 (en) | Connecting device for solar panel | |
CN207299415U (en) | Lifting lug and air-conditioning device assembly are installed | |
CN208105622U (en) | A kind of profile structure of curtain wall aluminium plate installation | |
CN205005381U (en) | How online electric cabinet of frequency conversion | |
CN214364732U (en) | Aluminum wallboard edging connecting structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
AD01 | Patent right deemed abandoned |
Effective date of abandoning: 20240329 |
|
AD01 | Patent right deemed abandoned |